CUSTOMER PENDING WORK DETAIL

All piping support insert plate required. Dea. Storage tank grouting required. Initial heating & steam inlet, Condensate water inlet and make up water inlet piping connection required.

VWHA 054 boiler , Blow down tank orientation modification req.

VWHO 052 BOILER BLOW DOWN TANK GROUTING REQUIRED.\ALL BOILER HP dosing grouting required.

VWTA 020 BLOW DOWN TANK GROUTING REQUIRED.

ALL BOILER BALANCE, COLUMN GROUTING REQUIRED.

OIL FIRING SYSTEM GROUTING REQUIRED.

CHIMNEY PLATE BENDING WORK IS UNDER PROCESSING NOW.CHIMNEY REQUIRED. ID FAN CHIMNEY DUCT SUPPORT INSERT PLATE REQUIRED.

ALL FEED PUMP FULL GROUTING REQUIRED.

FEED WATER COMMON HEADER SUPPORT FOUNDATION MODIFICATION REQUIRED.

AUTO MINIMUM RECIRCULATION & BALANCE LEAK OFF PIPING SUPPORT INSERT PLATE REQUIRED.