Top Banner
CSSE 372 Software Project Management: Earned Value Analysis (EVA) Exercises Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected]
24

CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

May 17, 2018

Download

Documents

vuongkhuong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

CSSE 372 Software Project Management:

Earned Value Analysis (EVA) Exercises

Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected]

Page 2: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner
Page 3: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Learning Outcomes: Plan (verb)

Create a plan for an intermediate size software project and manage to the plan. Maintain a software project schedule. n  Do some Earned Value

Analysis n  Examine Estimated to

Complete Values n  Determine good and bad

Trends in the progress

Page 4: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

You have the WBS and have identified the activities. Where do you start with Earned Value Analysis? n  Think for 15.11 seconds… n  Turn to a neighbor and

discuss it for a minute n  Then can we tawlk?

Page 5: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Earned Value Exercise (PV, AC, EV) Task – Develop and install ten printer drivers.

•  Budget - $100,000 ($10K per printer driver) •  Time – 10 weeks (1 printer driver per week)

At week 5:

•  4 printer drivers developed and installed •  $47,500 spent to date

PV = $???

AC = $???

EV = $??? Q1, 2, 3

Page 6: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Derived EVA Metrics: CV and SV

Schedule Variance n  Comparison of work

performed during a period of time to what was scheduled to be performed

n  Negative SV means the project is behind schedule

Cost Variance n  Comparison of the

budgeted cost of work performed with actual cost

n  Negative CV means the project is over budget

Q4

CV = EV–AC SV = EV–PV

Page 7: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Cost Variance (CV)

CV = EV - AC

= $???

Good News: If CV value is positive, the project is currently under budget (spending less than planned for the work)

Bad News: If CV value is negative, the project is currently over budget (spending more than planned for the work)

Earned Value Exercise (CV)

Page 8: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Cost Performance Index (CPI)

CPI = EV / AC

= ???

Good News: If CPI value is >1 or =1, the project cost trend is currently under or at planned budget

Bad News: If CPI value <1, the project cost trend is currently over budget

Earned Value Exercise (CPI)

Q5

Page 9: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Cost Variance % (CV%)

CV% = CV / EV

= ???%

Good News: If CV% value is positive, the project is currently under budget by the CV%

Bad News: If CV% value is negative, the project is currently over budget by the CV%

Earned Value Exercise (CV%)

Page 10: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Awkward!!!

Page 11: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Schedule Variance (SV)

SV = EV - PV

= ???

Good News: If SV value is positive, the project is currently ahead of schedule

Bad News: If SV value is negative, the project is currently behind schedule

Earned Value Exercise (SV)

Page 12: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Earned Value Exercise (SPI)

Schedule Performance Index (SPI)

SPI = EV / PV

= ???

Good News: If SPI value is >1 or =1, the project schedule trend is currently ahead or on planned schedule

Bad News: If SPI value <1, the project schedule trend is currently behind schedule

Q6

Page 13: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Earned Value Exercise (SV%)

Schedule Variance % (SV%)

SV% = SV / PV

= ???%

Good News: If SV value is positive, the project is currently ahead of schedule

Bad News: If SV value is negative, the project is currently behind schedule

Q7

Page 14: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Earned Value Exercise

PV = $50,000

AC = $47,500

EV = $40,000

CV = -$7,500

CPI = 0.84

CV% = -19%

SV = -$10,000

SPI = 0.80

SV% = -20%

Task – Develop and install ten printer drivers.

•  Budget - $100,000 ($10K per printer driver) •  Time – 10 weeks (1 printer driver per week) At week 5:

•  4 printer drivers developed and installed •  $47,500 spent to date

Page 15: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

But, when will we complete?

Estimate at Completion (EAC)

Actual costs to date plus a new estimate for all remaining work (original plan no longer valid)

EAC = AC + ETC

(ETC Estimate to Complete)

Q8

Page 16: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Well, it’s a little involved…

Estimate at Completion (EAC)

Actual costs to date plus remaining budget (current variances viewed as atypical of future variances)

Actual costs to date plus remaining budget modified by a performance factor (CPI) (current variances are viewed as typical of future variances)

EAC = AC + [(BAC - EV) / CPI]

~EAC = BAC / CPI Q8

Page 17: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Project: Alpha

C C C

C C C S S S S S S C

S S C

Under budget Ahead of schedule

Over budget Behind schedule

1.0 0.8 0.6 0.4

1.2 1.4 1.6

Project Week

8 7 6 5 4 9 3 2 1

Earned Value – Performance Indices

Good Progress

Page 18: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Project Week

8 7 6 5 4 9 3 2 1

1.0 0.8 0.6 0.4

1.2 1.4 1.6

C C C

C C C S S S

S S

S

Under budget Ahead of schedule

Over budget Behind schedule

Project: Beta

Earned Value – Performance Indices

Divergent Progress

Page 19: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Project: Charlie

C C C

C C C

S S S

S S

S C S

Under budget Ahead of schedule

Over budget Behind schedule

1.0 0.8 0.6 0.4

1.2 1.4 1.6

Project Week

8 7 6 5 4 9 3 2 1

Earned Value – Performance Indices

Losing Ground

Q9

Page 20: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Recall: PV, EV and AC Curves

Page 21: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Cost and Schedule Variance

Page 22: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Another View of Cost and Schedule Variance

Schedule Variance

Cost Variance

PV

AC

EV

Time

Progress

Page 23: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner
Page 24: CSSE 372 Software Project Management: Earned Value ... Homework 6 – Earned Value Analysis " Due by 11:55pm, Tuesday, October 16th, 2012 ! Have a great Fall break! Author: bohner

Homework and Reading Reminders n  Read ahead with Chapter 9 of text for Monday n  Complete Homework 5 – Software Schedule

¨ Due by 11:55pm, Tuesday, October 9th, 2012 n  Final Project – SW Proj. Mgt. Plan (SPMP)

¨ Completed by team… ¨ Due by 11:55pm, Friday, November 2nd, 2012. ¨ No late days –review swap with another team

Complete Homework 6 – Earned Value Analysis ¨ Due by 11:55pm, Tuesday, October 16th, 2012

n  Have a great Fall break!