Project Management - Topics
Schedules And Gantt Charts
Project Milestones
How to Organize Your Team Surgical or Democratic Team?
Drexel University
Schedules And Gantt Charts
3
Drexel University 4
Schedules And Gantt Charts
What is a schedule? A schedule is:
A listing of planned events Properties:
Ordered by time Shows dependencies between tasks Might show assignment of tasks to personnel
Planned events tied to milestones
Drexel University 5
How To Make A Project Schedule Identify the individual component tasks for each
phase or spiral Estimate the size of tasks and amount of time
required Identify dependencies between tasks:
What inputs are required for each task? In what previous task are these inputs created?
Define milestones: High-level milestones Intermediate milestones Low-level milestones (separate personal schedule
document)
Drexel University 6
Gantt Charts A tabular notation to document schedule Rows represent task ids and names (listed in
order). Columns—many variations and many optional
notations: Start-date column, end-date column Task duration column (how long? Hours, days, etc.) Task assignment column (who is doing this?) Task completion: percentage-complete column, or a
line through the task bar
Drexel University 7
Drexel University 8
Gantt Charts Columns—many variations and many optional
notations (continued): Timeline—may be in terms of days, weeks, months,
quarters, etc. In the timeline, a task bar indicates duration of task. Milestones (aka checkpoints) shown like a task and a
task bar, but with a special symbol. Summary “tasks” and bars: higher-level name showing
a collection of related tasks (e.g. requirements analysis, or any “phase” or spiral)
Vertical line showing today's date
Drexel University 9
Comments On Example Chart Two “summary” tasks: requirements analysis
and requirements specification (note the yellow triangles on the ends of the bars)
Timeline: days in a month Duration column: in days, hours Purple-lines in task bars indicate how much is
completed Vertical line shows today's date (task 3 is late!)
Drexel University 10
Comments On Example Chart Milestones: black diamonds, duration of zero “Who” column shows personnel assignments Task dependencies: arrows from one task to
another: First task must be completed before the second
starts Milestones depend on preceding task(s) Tool automatically adjusts chart according to
durations, dependencies
Drexel University 11
Tool Support For Gantt Charts
Microsoft Project: Data file standard: MPX Files (“Ms Project
eXchange”) Visio:
Known As “Project Timeline” Diagram Can Import/export Data In Mpx Format
Drexel University
Project Milestones
12
Drexel University 13
Advice On Milestones For team projects Milestones often tied to sign-off (after review) of major
work-products, such as: Project management plan document Software requirements specification (SRS) document Design document Stage 1 code released (stage 2,...) Final product released
Milestones Must Be Visible To Management, Possibly Customer
Drexel University 14
Milestones
Part of top-down approach Break large project into small problems, each of
which can be estimated and planned A milestone is:
An objectively identifiable point in a project Good checkpoints are:
Clear, unambiguous, crisp, verifiable Binary: done or not done
Drexel University 15
Milestones
“Coding is 90% complete”: In terms of time, or loc? How do you know?
“Program is designed”: What’s this mean? In your head, or on paper? Has it been reviewed, agreed upon?
Drexel University 16
Milestones—Good Examples
Design document reviewed Design document signed-off by management System software successfully passes integration
test data suite Specification document approved by customer All risks determined at last process review
addressed and resolved
Drexel University
How to Organize Your Team
17
Drexel University 18
Group/Team Structure Differences between programmers:
Productivity: 10:1 Program Speed: 5:1
What if we only hire top people?
Efficiency + Conceptual Integrity vs. Large System
Drexel University 19
Group/Team Structure Democratic Team or Surgical Team? A Surgical Team
The Surgeon –-Chief architect, Design and Impl The Copilot ---Impl, Testing, etc The Administrator ---Version control, plan, testing The Program clerk The Editor Two Secretaries The Tool Smith The Tester The language Laywer
Drexel University
Summary How to plan your project using a Gantt Chart
The concept of milestone
Surgical Team vs. Democratic Team
20
Drexel University
Reminder: Reading Homework:
"No Silver Bullet: Essence and Accidents of Software Engineering", by Frederick P. Brooks.
"The Mythical Man Month" by Frederick P. Brooks. Next Tuesday Quiz on papers Term project presentation
21
Drexel University
Term Project Presentation Project description
List all the functions of the project What are the input/output How will the user interact with it Web based? Standalone App? Mobile App?
Team member roles The Surgeon –-Chief architect, Design, Document and Impl The Copilot ---Impl, Testing, Document, etc The Administrator ---Version control, plan, testing The Tester
Project plan in a Gantt Chart with at least 4 milestones