Top Banner
Cryogenic Experts Meeting (19 ~ Cryogenic Experts Meeting (19 ~ 20.09.2007) 20.09.2007) Cooling scheme discussion for 300 Tm High Energy Beam Transfer line (HEBT) with large inclination MT/FAIR – Cryogenics Y. Xiang, M. Kauschke
11

Cryogenic Experts Meeting (19 ~ 20.09.2007)

Jan 27, 2016

Download

Documents

Cindy

Cryogenic Experts Meeting (19 ~ 20.09.2007). Cooling scheme discussion for 300 Tm High Energy Beam Transfer line (HEBT) with large inclination. MT/FAIR – Cryogenics Y. Xiang, M. Kauschke. Cryogenic Experts Meeting (19 ~ 20.09.2007). Outline. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Cryogenic Experts Meeting (19 ~ 20.09.2007)Cryogenic Experts Meeting (19 ~ 20.09.2007)

Cooling scheme discussion for 300 Tm High Energy Beam Transfer line

(HEBT) with large inclination

MT/FAIR – Cryogenics

Y. Xiang, M. Kauschke

Page 2: Cryogenic Experts Meeting (19 ~ 20.09.2007)

• Design constraints to helium flow in 300 Tm HEBT due to the tunnel with large inclinations;

• Simulation results on flow pattern analysis of two-phase helium flow in 300 Tm HEBT as the baseline design in FBTR;

• The single phase helium cooling scheme is to be presented together with one of the current feeding concepts;

• Conclusions

Outline

Cryogenic Experts Meeting (19 ~ 20.09.2007)Cryogenic Experts Meeting (19 ~ 20.09.2007)

Page 3: Cryogenic Experts Meeting (19 ~ 20.09.2007)

300 Tm HEBT layout

HERA type quadrupole

HERA / UNK type dipole

Page 4: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Constraints given by the inclined tunnel for extractionConstraints given by the inclined tunnel for extraction

One of the major constrains for magnet string design and layout;

• Inclination up to 6.6 (11.5%, 115 mrad ) for 300 Tm HEBT from SIS 300 to beam dump and CBM

No such a big slope has ever been considered as constraints in the superconduting magnet baseline design for the existing large machines, e.g.,

HERA ring (6.3 km) --- 0.5 (1 %, max 10 mrad)

LHC ring (27 km) --- 0.8 (1.4 %, 14 mrad)

Tevatron (6.0 km), RHIC (3.8 km), Nuclotron (251.5 m) --- nearly horizontal

Upper limit for using wheeled-vehicles for magnet installation --- 4 % (2.3 , statement from Fermilab, "Design Study for a Staged Very Large Hadron Collider", 2001)

Page 5: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Design constrains to helium flow in magnet string with large inclinations

One of the design experiences for two-phase helium flow in HERA proton ring:

The JT expansion is done at the lowest point of each octant of HERA so that the two-phase flow in HERA magnets is always directed uphill to avoid the capture of bubbles.

One-phase and two-phase helium flow arrangement (baseline design in FAIR Baseline Technical Report 2006)

Page 6: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Two-phase helium flow pattern in the inclined part of 300 Tm HEBT from SIS 300 to Beam Dump

Too close to the transition boundary which means high risk of changing into unstable flow pattern

We need another concept of cooling scheme!

Page 7: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Studies at CERN in 2006 --- A Possible Upgrade of the LHC Injection Lines (450 GeV) to 900 GeV using HERA Dipoles

Injection lines between SPS and LHC are,

TI2 (2.9 km with up-hill and down-hill slopes) --- steepest slope is 2.6%;

TI8 (2.7 km) --- steepest slope is 3.77%

One statement of the study,

"The lines are characterized by a strong inclination (7.2% max slope) ... The distribution to the magnets of liquid helium in strongly inclined channels and over a distance of several hundred meters represents a considerable cryogenic challenge."

Such a study lets people to trace back another study which was done at CERN in earlier 1993 :

Page 8: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Single phase cooling scheme Alternative two-phase cooling scheme

Studies at CERN in 1993 --- Design Criteria of the cryogenic system for the CERN LHC injection lines

The authors proposed two cooling schemes for the inclined injection lines:

Only the gaseous stream flows into a pipe thermally insulated from the existing channel

Two single phase streams flow in a thermally insulated pipe inside the existing two channels to prevent possible heat transfer between forward and return streams

Statements of the Study at CERN in 1993 :

"The single phase cooling scheme adopts a cooling method different from that already operated in HERA. The alternative two-phase cooling scheme offers the possibility of developing a new challenging cooling scheme for SC magnets with two-phase flow over very long distances in strongly inclined channels. However, since it introduces several unknowns and “its feasibility is still doubtful”. Further tests are required before the solution can be seriously pursued."

Page 9: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Single phase helium cooling scheme for 300 Tm HEBT

Page 10: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Flow scheme of current feedbox for superconducting links (DFBL) for LHC

• If the concept that the current feedboxes are located close to the feeding points of the magnet string (LHC mode) inside the extraction tunnel is not a favourite solution for the power supply requirement at GSI, the recooler has to be integrated in the magnet cryostat design.

• No clear picture on this point at GSI up to now because of the uncertainty of cold link design.

Page 11: Cryogenic Experts Meeting (19 ~ 20.09.2007)

Conclusions

• The numerical simulation shows the baseline of two-phase cooling flow scheme specified in FBTR for the 300 Tm HEBT magnet strings with strong inclinations has high uncertainty.

• The single phase cooling scheme which is based on the concept initiated at CERN for LHC injection lines has been presented for the 300 Tm HEBT magnet string.

• To start the recooler design, one needs the final decision of current feeding concept.

Cryogenic Experts Meeting (19 ~ 20.09.2007)Cryogenic Experts Meeting (19 ~ 20.09.2007)