Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA
15

Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

Dec 23, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

Cross Border Rail PassengerProgress Report

Transportation Border Working GroupApril 17, 2012 – Seattle, WA

Page 2: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

2

Presented by Amtrak and VIA Rail Canada also on behalf of:

New York State DOT

Page 3: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

3

Presentation Outline

• Summary Review of November Presentation

• Montreal Central Station Current Operations Potential Future Preclearance Concept

• Niagara Falls Whirlpool Bridge Niagara Falls NY Station and Customs Facilities

• Vancouver Current Operations Potential Future Preclearance Concept

• Requirements for Preclearance Canada / U.S. Treaty Completion of Facility Improvements in Montreal Staff and Other Resources for USCBP and CBSA Operations

Page 4: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

4

Summary Review of November Presentation

• Lack of Process for Border Security

• Agency Issues with On-Board Inspection

• Amtrak Issues with Enroute Off-Board Inspection

• Characteristics of Two Route Types Single Canadian Station Multiple Stops on Both Sides of the Border

• Current International Rail Passenger Services New York – Montreal “Adirondack” New York – Toronto “Maple Leaf” with VIA Rail Canada Portland – Seattle – Vancouver “Amtrak Cascades”

• Potential Future International Services Northeast Corridor – Vermont – Montreal Chicago – Michigan – Ontario - Quebec

Page 5: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

5

Montreal

• Montreal Central Station Serves Amtrak’s New York – Montreal “Adirondack” VIA Rail Canada intercity hub – Halifax, Quebec, Ottawa, Toronto, etc. Agence Metropolitaine de Transport commuter train system Expect to add NEC – Vermont – Montreal “Vermonter” perhaps late 2014

• The partners intend to build a joint customs and immigration facility in Central Station for both CBSA and USCBP Replace CBSA facility at Lacolle and USCBP facility at Rouses Point Discontinue Amtrak service at St. Lambert and operate non-stop, closed-

door between Central Station and the border Serve the New York – Montreal “Adirondack” initially Be available to Vermont to serve an extended “Vermonter” although not at

the times the “Adirondack” is in the station

• Plans follow: Concourse level Track level

Page 6: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

6

Montreal Central Station Proposed Concourse Level

Page 7: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

7

Montreal Central Station Proposed Track Level

Page 8: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

8

Montreal

• Progress to date Amtrak Engineering has developed a conceptual plan CBSA and USCBP have concurred in the concept subject to further

review as the project advances Quebec, New York and Vermont have committed to share the $250,000

cost of a Canadian architect’s review Agence Metropolitaine de Transport (AMT) and Amtrak have signed a

memorandum of understanding whereby AMT will act on behalf of Amtrak to retain the architect

• Next phase through September 2012 Retain and task the architect Conclude the architect’s review, hopefully by September Conduct a September “all partners” meeting to evaluate the architect’s

recommendations Determine the probable lease cost for the required space in the station Make a joint partners’ go / no go decision to proceed subject to treaty

Page 9: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

9

Montreal

• Post September Work Plan, assuming a decision to proceed Quebec, New York and Vermont to determine funding sources for

construction, lease and operating costs Monitor progress towards the attainment of a Canada / U.S. surface

transportation preclearance treaty currently targeted for December Inform federal authorities of the resource requirements for CBSA and

USCBP to staff and operate the facility if built Once the above steps are complete, suspend effort until the surface

transportation preclearance treaty has been enacted in both countries

• Once (and if) the treaty is enacted Lease required space on both levels in Central Station Advertise for bids and select the designer of the facility Obtain approval of the final design by USCBP and CBSA Advertise for bids to construct the facility Outfit and staff the facility Commence operations no earlier than the last half of 2014

Page 10: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

10

Niagara Falls – Whirlpool Bridge

• Owned by Niagara Falls Bridge Commission (NFBC).

• CNR has filed for abandonment of rail service on the Canadian side

• CNR will file for abandonment of rail service on the U.S. side. The delay was for environmental reasons

• The NFBC, Amtrak and VIA have a verbal agreement in principal on a future bridge agreement including a per train fee

• CNR is drafting proposed agreements for VIA and Amtrak to acquire CNR’s assets at a nominal price

• Three agreements must take effect simultaneously upon CNR’s actual abandonment of track on both sides of the border

• Roughly $2.0 million more will be needed for track, tie and drainage replacement on the bridge

• New York State DOT has been kept advised but has not participated in the negotiations

Page 11: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

11

Niagara Falls – Customs and Stations Facilities

• A preclearance operation is not currently feasible because there need to be multiple stops on both sides of the border

• Passengers are now cleared at the border In Ontario screening is entirely off board in VIA’s Niagara Falls, ON,

station In New York primary inspection is on the train at Amtrak’s Niagara Falls,

NY, station with secondary screening in the station

• City of Niagara Falls is building a new station and USCBP facility including the former Customs House plus a major expansion Amtrak will relocate to the new facility USCBP will screen passengers entirely off board as now done in Canada Facility will have a high level platform alleviating safety concerns but not

train delays or passenger inconvenience

Page 12: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

12

Vancouver

• Pacific Central Station is owned by VIA Rail Canada and serves Toronto – Vancouver “Canadian” Portland – Seattle – Vancouver “Amtrak Cascades” Intercity bus carriers

• Most advanced of the three border crossings Full customs and immigration processing by CBSA for inbound

passengers to Canada Immigration pre-inspection and agriculture inspection for passengers to

the U.S. are done in PCS although customs inspections remain on board at Blaine, WA

• The post – treaty goal is to have Vancouver and Montreal function similarly with full customs and immigration plus preclearance in the station

• Photographs of customs and immigration facility at Pacific Central Station follow

Page 13: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

13

Vancouver Pacific Central Station Facility

• Track and sterile compound • Approach to customs facility

Page 14: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

14

Additional Developments – Detroit - Windsor

• Regular international rail service is years in the future Connect the Amtrak Michigan Corridor with the VIA Rail Canada Quebec

– Windsor Corridor Requires construction of the new Continental Rail Gateway Tunnel Released capacity in existing tunnel potentially then to be made available

for intercity rail passenger service

• Michigan Department of Transportation has requested a one time demonstration round trip – Toronto – Ann Arbor and return January 1, 2013 For the “Winter Classic” game in Ann Arbor hosted by the Detroit Red

Wings for the Toronto Maple Leafs Requires cooperation and assistance by: MDOT, Amtrak. VIA Rail

Canada, Canadian Pacific, Norfolk Southern, CBSA, USCBP, the two teams, and others

Amtrak and VIA are studying the feasibility of this potential operation

Page 15: Cross Border Rail Passenger Progress Report Transportation Border Working Group April 17, 2012 – Seattle, WA.

15

Questions and Discussion