Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4, 2012 Hilbert Robinson, Senior Program Manager Mike Hannan, VP, Public Sector
27

Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Dec 15, 2015

Download

Documents

Quintin Groom
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Critical Chain Project ManagementCritical Chain Project ManagementSolving the 3 Biggest Problems in Project Management

Prepared for PMI Montgomery ChapterApril Chapter dinner

April 4, 2012

Hilbert Robinson, Senior Program ManagerMike Hannan, VP, Public Sector

Page 2: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Common Project Stakeholder ComplaintsCommon Project Stakeholder Complaints

2

Low

Org

aniz

atio

nal

prod

uctiv

ity

Long lead timesDe-scoped or

cancelled projects

Cost/budget overruns

Unhappy stakeholders

Poor due date reliability

Missed opportunities

Page 3: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Common Project Management ComplaintsCommon Project Management Complaints

3

Rework

Errors

Unpleasant Surprises

Scope creep & spec changes

Overloaded resources

Frequent “fire drills”

Unclear/competingPriorities

High stress

Frustration Low

morale

Burnout/

turnover Low

productivity

More reporting Meetings

Poor coordination

Severe and chronic

multitasking

Severe and chronic

multitasking

Page 4: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Productive effort

Unrecoverable losses

Cu

rren

t P

ote

nti

al

Recoverable losses

Other

High Rework

Many Open Issues

Poor Coordination

Severe Multitasking

Missing Inputs

PE

RF

OR

MA

NC

EOperational Gap (1)Operational Gap (1)

4

Other

High Rework

Many Open Issues

Poor Coordination

Severe Multitasking

Missing Inputs

Missing Inputs, Severe Multitasking, Poor Coordination, Many Open Issues,

High Rework, Other

MurphyMurphy

CurrentEffectiveCapacity

FUTURECURRENT

Future gains from reducing losses

IncreasedEffective Capacity

Murphy

IncreasedEffective Capacity

%

Page 5: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Old Rule #1Old Rule #1

5

Old RuleProblem

1 Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

Page 6: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Estimate vs. CommitmentEstimate vs. Commitment

6

If we treat task-level estimates as commitments, Task Owners will build in hidden schedule buffers, and then have little incentive to finish early.

If we treat task-level estimates as estimates, and pool schedule risk at the project level, we can allocate project-level schedule buffer to those tasks that need it, and only those tasks that need it.

10 Days 10 Days 10 Days 10 Days 10 Days

15 Days10 Days 15 Days10 Days15 Days10 Days 15 Days10 Days 10 Days

Set of task-level estimates = 50 days

Set of task-level commitments = 125 days

10 Days 10 Days 10 Days 10 Days 10 Days

2 Days Work : 1 Day Protection

Project Buffer

15 Days

Page 7: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

New Rule #1New Rule #1

7

1

New Rule Advantage

Buffer Projects, Not Tasks

Highly reliableproject commitment.

Old RuleProblem

Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

Page 8: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Old Rule #2Old Rule #2

8

1

New Rule Advantage

Buffer Projects, Not Tasks

Highly reliableproject commitment.

Old RuleProblem

Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

2Assign staff to multiple

tasks, and start all projectsas early as possible.

Focusing staff on 1 taskat a time results in low resource utilization, andholds up other projects.

Page 9: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

9

The Overcommitted / Overloaded OrganizationThe Overcommitted / Overloaded Organization

Simple Example:

Three person team: A – DesignerB – BuilderC – Tester

The sooner we start ….

Three hot projects

Seven weeks each

Page 10: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

10

The Illusion of ProgressThe Illusion of Progress

Delay Delay Delay

High resource utilization

Delay

Page 11: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Reasons to MultitaskReasons to Multitask

11

Be responsive to demands/needs of others Appease customers, stakeholders, PM, boss, etc. Avoid idle time while waiting for input Be efficient Be busy Impress others with how many projects you can juggle …and many others.

Page 12: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

The Hidden Cost of MultitaskingThe Hidden Cost of Multitasking

Loss of focus / more mistakes / rework More open / unresolved issues / expediting Disguises other process failures Destroys the smooth flow of work Increases need for (burden of) tracking and reporting Wastes capacity [need for more overtime] Longer project cycle time/lead time Increases per unit cost Fewer completions / higher burnout / lower morale Dilutes managements attention and focus – Loss of control

12

Some negative effects of multi-tasking includes:

Page 13: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Simultaneous vs. Staggered ProjectsSimultaneous vs. Staggered Projects

P4

13

8

6

4

Simultaneous Projects

Staggered Projects

Page 14: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

New Rule #2New Rule #2

14

1

New Rule Advantage

Buffer Projects, Not Tasks

Highly reliableproject commitment.

Old RuleProblem

Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

2Assign staff to multiple

tasks, and start all projectsas early as possible.

Focusing staff on 1 taskat a time results in low resource utilization, andholds up other projects.

Stagger ProjectsMaximize project completion rate

and resource utilization.

Page 15: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Old Rule #3Old Rule #3

15

1

New Rule Advantage

Buffer Projects, Not Tasks

Highly reliableproject commitment.

Old RuleProblem

Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

2Assign staff to multiple

tasks, and start all projectsas early as possible.

Focusing staff on 1 taskat a time results in low resource utilization, andholds up other projects.

Stagger ProjectsMaximize project completion rate

and resource utilization.

3Each PM lobbies the PMO

for critical resources.

Priorities across projectsshift, resulting in persistent conflicts over resources.

Page 16: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

To Which Project Should I Assign the Critical Staff Resource?To Which Project Should I Assign the Critical Staff Resource?

16

15 Days10 Days 15 Days10 Days25 Days 25 Days

15 Days10 Days 15 Days10 Days 15 Days10 Days25 Days 25 Days 25 Days

Project A

Project B

Today

Two identical tasks, only one person with the required skill

Page 17: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Urgent Field Problem

versus a New Design

Engineering Congress

Regulators

Irate Customer

Project Manager

Golf Partner

Executive Sponsor

Respond to Whomever Shouts the Loudest?Respond to Whomever Shouts the Loudest?

17

Page 18: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

To Which Project Should I Assign the Critical Staff Resource?To Which Project Should I Assign the Critical Staff Resource?

18

15 Days10 Days 15 Days10 Days25 Days 25 Days

15 Days10 Days 15 Days10 Days 15 Days10 Days25 Days 25 Days 25 Days

Project A

Project B

Today

Two identical tasks, only one person with the required skill

Project Buffer

Project Buffer

To Project B, because it is further from completion than Project A, and because it has less project

buffer remaining.

Page 19: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

19

10% 20% 30% 40% 50% 60% 70% 80% 90% 100%0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Series1; 60%

40%

Percent Project Buffer Consumed Versus Chain Completed

% of Chain Completed

% P

roje

ct

Bu

ffe

r C

on

su

me

d

D

C

BPI Based Prioritization MetricBPI Based Prioritization Metric

All projects and tasks are prioritized according to

their current BPI

Page 20: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Single Project Buffer Trend ChartSingle Project Buffer Trend Chart

20

Watch

Plan

Recover

Page 21: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

21

Portfolio Dashboard Real Time Organization-wide Prioritization

Portfolio Dashboard Real Time Organization-wide Prioritization

All decisions are evaluated according to their predicted

impact on BPI

Watch

Plan

Recover

Page 22: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

New Rule #3New Rule #3

22

1

New Rule Advantage

Buffer Projects, Not Tasks

Highly reliableproject commitment.

Old RuleProblem

Plan each task as a highly reliable commitment.

Task variability preventsreliable project commitments.

2Assign staff to multiple

tasks, and start all projectsas early as possible.

Focusing staff on 1 taskat a time results in low resource utilization, andholds up other projects.

Stagger ProjectsMaximize project completion rate

and resource utilization.

3Each PM lobbies the PMO

for critical resources.

Priorities across projectsshift, resulting in persistent conflicts over resources.

Protect ProjectBuffers ThatNeed It Most

Clarity, commonly agreedpriorities, stronger

cooperation among PMs

Page 23: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Cu

rren

t P

ote

nti

al

Productive effort

Fu

ture

Po

ten

tial

Unrecoverable losses

Recoverable losses

Other

High Rework

Many Open Issues

Poor Coordination

Severe Multitasking

Missing Inputs

The Whole is Greater…The Whole is Greater…

23

Other

High Rework

Many Open Issues

Poor Coordination

Severe Multitasking

Missing Inputs

Missing Inputs, Severe Multitasking, Poor Coordination, Many Open Issues,

High Rework, Other

Murphy

More Effective Teamwork, Reduced Learning Curve, etc.

Murphy

Gains from reducing losses

PE

RF

OR

MA

NC

E

FUTURECURRENT

Page 24: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Expected Stakeholder BenefitsExpected Stakeholder Benefits

24

Long lead timesDe-scoped or

cancelled projects

Cost/budget overruns

Unhappy stakeholders

Poor due date reliability

Missed opportunities

Shorter lead times

More stable scope fewer

cancelled projects

Effective cost/budget

controls

Happier / satisfied

stakeholders

Fewer missed opportunities

Highly reliable due dates

Much higher organizational

productivityLow

Org

aniz

atio

nal

Produ

ctiv

ity

Strong Foundation for Growth

Page 25: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Documented Benefits of Critical ChainDocumented Benefits of Critical Chain

25

Page 26: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

Sample ResultsSample Results

18 months vs. 60 months,

IT department first then drug development – CEO: “100% due date performance”

Warner Robbins – Iraq War – Expanded C-5 air lift capacity by 8 million ton-miles

Iraq War – One extra submarine in steaming days

Satellite Division – Turned around the business

Engine Division – partially funded Northwest acquisition

Software delivered 5 months early, 33% cost reduction

26

Sometimes Speed and Reliability Are Mission Critical.

Sometimes Speed and Reliability Are Mission Critical.

Page 27: Critical Chain Project Management Solving the 3 Biggest Problems in Project Management Prepared for PMI Montgomery Chapter April Chapter dinner April 4,

What if We’re Not an Advanced Project Management Organization?What if We’re Not an Advanced Project Management Organization?

27

CCPM is simple in concept—it turns common sense into common practice.

Introducing CCPM will help any project right away, regardless of how sophisticated and disciplined your project-management practices are (or aren’t).

Some “high-discipline” PM organizations take longer to realize CCPM benefits, because they have a harder time letting go of the “Old Rules.”

Many “low-discipline” PM organizations have an easier time adopting CCPM, because the “Old Rules” are not as deeply embedded.