Page 1: Critical Chain Long

Critical ChainCritical ChainTheory of Constraints in Project Management

Theory of Constraints in Project Management

Page 2: Critical Chain Long

FF

CC DD

AA BB EE GG

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

Student Syndrome: “I have sufficient time”

Parkinson’s Law: Work will take all available time

Murphy’s Law: Failure at the first step

Bad multitasking: “I do more in... more time”

Problems in projects

Page 3: Critical Chain Long

Task 1 Task 2 Task 3

Bad Multi-tasking

Tasks 1 and 2 are delayed

Page 4: Critical Chain Long

Task 1 Task 2 Task 3

No task was completed on time

Bad Multi-tasking

Page 5: Critical Chain Long

50% 80%probability

Estimating

Page 6: Critical Chain Long

50% 80%probability

50%

80%

Estimating

Page 7: Critical Chain Long

probability50%

80%

Estimating

Page 8: Critical Chain Long

FF

CC

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

DD

Project according to estimation

Step 1 – Identify the restriction

Page 9: Critical Chain Long

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

săptămâni

17 18 19 20 21

BB EE GG

50%

The project after moving the contingency

Step 2 – Exploit the restriction

Page 10: Critical Chain Long

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

25% 25%

The project after cutting the contingency in half

Step 2 – Exploit the restriction

Page 11: Critical Chain Long

The project with non-critical tasks

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

săptămâni

17 18 19 20 21

BB EE GG

25% 25%FF

CC DD

Step 3 – Subordinating to the restriction

Page 12: Critical Chain Long

FF

CC

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

DD

Feeding-buffer not consumed

Page 13: Critical Chain Long

FF

CC

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

DD

Feending buffer consumed

Page 14: Critical Chain Long

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

35%

15%

Monitoring the project

Page 15: Critical Chain Long

AA

161 2 3 4 5 6 7 8 9 10 11 12 13 14 15

weeks

17 18 19 20 21

BB EE GG

35%

60%

Monitoring the project

Page 16: Critical Chain Long

Good luckGood luck!!