Top Banner
Cracks in Building Er Gurudev Singh, IDSE SE Director (Design) ADG (D&C) Pune
51
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cracks

Cracks in Building

Er Gurudev Singh, IDSE

SE

Director (Design)

ADG (D&C) Pune

Page 2: Cracks

INTRODUCTION

• Cracks in building are the common building defects.

• A building component develops cracks whenever stress in a building component exceeds its strength.

• Cracks

Structural - affects strength

Non-Structural - affects beauty/ appearance

• Thin cracks, even though closely spaced & greater in number are less damaging to the structure as compared to fewer Nos. of wide cracks.

Page 3: Cracks

Causes of cracks(a) Moisture changes(b) Thermal variations(c) Elastic deformation(d) Creep(e) Chemical reaction(f) Foundation movement & settlement of soil(g) Vegetation(h) Future extention (Horizontal/Vertical)

Page 4: Cracks

Flexural tension cracks in wall masonry

Page 5: Cracks

Shear crack in masonry wall

Page 6: Cracks

Cracking due to expansion of brickwork

Page 7: Cracks

Cracks in wall

Settlement Crack

Shear Crack

Shrinkage Crack

Page 8: Cracks

Measures for controlling cracks due to shrinkage

(a) Use of bricks after 2-3 weeks on receipt from kiln

(b) Avoid use of rich cement and very fine sand

(c) Delay plaster; till masonry dries and after curing

(d) Use of precast components

(e) Laying floor in small panels

(f) Use of temp reinforcement in concrete

Page 9: Cracks

(a) Moisture changes

Most of the building materials are porous in their structure. That’s why they expand on absorbing moisture & shrink on drying. These reversible movement (cyclic in nature) causes cracks in building component/material.

Page 10: Cracks

(b) Thermal variations

All materials, more or less, expand on heating & contract on cooling. Magnitude of movement varies for different materials. When there is some restraint to movement of a component of a structure, internal stresses are set up in the component, resulting in cracks due to tensile or shear stresses.

Page 11: Cracks

Daily changes which are rapid, have much greater damaging effect on account of movement than seasonal changes, which are gradual.

Thermal movement depends upon :

(i) Colour, Surface characteristics and Dimensions

(ii) Thermal conductivity/Co-eff. Of expansion and Temperature variation

(iii) Insulation and protective layer

(iv) Internally generated heat

(v) 1 m wide strip of slab of 100 mm thick heated through 22 deg C requires force of 500 kN to restain.

Page 12: Cracks
Page 13: Cracks
Page 14: Cracks

Horizontal crack at the base of brick masonry parapet supported on a projecting RCC slab

Page 15: Cracks

Vertical cracks at corners in the side walls of a

long bldg due to thermal movement

Page 16: Cracks

(c) Elastic deformation

(i) Unevenly loaded walls have wide variation in stress. Excessive shear strain develops cracks in walls.

(ii) When a beam or slab of large span undergoes excessive deflection & there

is not much vertical load above the supports, end of beam/slab curl up causing cracks in supporting masonry.

Page 17: Cracks

(iii) When two materials, having widely different elastic properties, are built side by side, under the effect of load ,

shear stress is set up at the interface of the two materials, resulting in cracks at the junction.

Page 18: Cracks

Diagonal cracks in cross walls of Multi-storied

Load Bearing Structures

Page 19: Cracks

Vertical cracks in Multi-storied Load Bearing Structures

having window openings in load bearing wall

Page 20: Cracks

Horizontal cracks in a wall at supports due to excessive deflection of a slab of large span

Page 21: Cracks

Horizontal cracks above the RCC slab in top most storey due to arching and expansion of slab

Page 22: Cracks

(d) CreepCreepDue to creep in concrete, there is substantial increase in

deformation of structural members,which may be 2 to 3 times the initial elastic deformation. This deformation sometimes results in formation of crack in brick masonry of framed & load bearing structures.

– Creep increases with increase with increase in water & cement content, w/c ratio & temperature.

– Decreases with increase in humidity & age of bldg

– Use of admixtures & pozzolona increases creep.

– High surface to volume ratio of concrete increases creep

Page 23: Cracks

Horizontal cracks in brick panels of a framed structure

Page 24: Cracks

Vertical cracks in brick panel wall of framed Structures due to expansion of brickwork

Page 25: Cracks

Cracking of a partition wall supported on RCC slab/beam. When length to height ratio of partition wall

is large and there is no door opening

Page 26: Cracks

Cracking of a partition wall supported on RCC slab/beam. When length to height ratio of partition

wall is large and there is central door opening

Page 27: Cracks

(e) Chemical reaction (i) Corrosion of reinforcement in concrete

(ii) Alkali-Aggregate reaction

i.e. Alkali-Silica expansion

(iii) Sulphate attack

Sulphate reacts with C A in presence of moisture & form products of much bigger volume

(iv) Carbonation

3

Page 28: Cracks

(f) Foundation movement & settlement of soil

Differential settlement

- unequal bearing pressure

- bearing pressure excess of safe bearing capacity

Cracks that occur due to foundation movement of a corner on an end of a building are usually diagonal in shape (wide at top & decreases in width downwards).

Page 29: Cracks

(g) Vegetation

(i) Dehydrating action of growing root which causes soil to shrink & cause foundation settlement. (crack wide at top & narrow at bottom).

Page 30: Cracks

(ii) Cracks in wall due to expansive action of root growing under the foundation.

(iii) Upward thrust on a portion of the building, when old trees are cut off and the soil that had been dehydrated earlier by roots, swells up on getting moisture from some source, such as rain.

These crack (ii & iii) are wide at the base & narrow down as they pass upwards.

Page 31: Cracks

Cracking of a compound wall due to growing roots under the foundation

Page 32: Cracks

Roots of fast growing tree under the foundation of compound wall may topple down the wall

Page 33: Cracks

Trees growing close to a building on shrinkable soil may cause cracks in the walls

Page 34: Cracks

Cracking due to expansion of soil, if construction is taken up soon after removal of trees

Page 35: Cracks

(h) Future extension

Horizontal extension

Foundation of a old building undergoes some settlement as load comes on the foundation & the new building is constructed without giving any separation joint.

Page 36: Cracks

Vertical extension In case of framed construction, all frame-

work should be completed before taking up masonry work of cladding & partitions, which should be started from top storey downwards.

If we follow this principle, then where is the scope for vertical extension of building!

But, still it is being catered & done.

Page 37: Cracks

Prevention of CracksPrevention of Cracks

Page 38: Cracks

(i) Time lag between removal of brick from kilns & their use in masonry should be 2 to 3 weeks.

(ii) Avoid using rich cement and very fine sand.

(iii) As far as possible try to use weak mortar for masonry work. Plaster work should be delayed till masonry has dried after proper curing & has undergone most of its initial shrinkage.

(iv) Slip joint should be introduced between slab & its supporting wall. Ceiling plaster should be made discontinuous by a groove about 10 mm in width.

Page 39: Cracks

(v) Provision of vertical expansion joint, if the block of building longer than 20 m (in hot & dry regions).

(vi) Provision of horizontal expansion joint of 10 mm depth between the top of wall panel & soffit of beam. This gap may be filled with mastic compound, finished with some sealant or filled with weak mortar. If structurally necessary, lateral restraint to the panel at the top should be provided by using telescoping anchorages.

Page 40: Cracks

Elevation

Schematic sketch of telescopic anchorages for panel walls

Page 41: Cracks
Page 42: Cracks

Schematic sketch of telescopic anchorages for panel walls

Page 43: Cracks

(vii) The subgrade below the entire area of the building shall preferably be of the same type of the soil. Wherever this is not possible, a suitably located separation or crumple section shall be provided.

(viii) Stair halls shall preferably be separated from the rest of the building by means of separation or crumple sections to eliminate the bracing effect on the floors.

(ix) Temperature reinf. should be increased by 50 to 100 % of the min amount for the member which are exposed to sun (sun-shades, fins, facia, railings, canopies, balconies etc.)

(x) Over flat roof slab, a layer of insulating material along with a high reflectivity finish should be provided so as to reduce heat load.

m

Page 44: Cracks

(xi) Try to avoid very fast pace of construction. Allow a time interval of atleast 2 weeks between

removal of centering & construction of partition or panel wall over it.

(xii) Removal of centering & imposition of load should be deferred as much as possible (at least one month) so that concrete attains sufficient strength before it bears the load (for cantilever beam/slab).

(xiii) All frame-work should be completed before taking up masonry work of cladding & partitions which should be started from top storey downwards.

Page 45: Cracks

(xiv) Provide upward camber in floor slab/beam so as to counteract deflection.

(xv) Concrete grade should be of min M25 to match with the strength of Fe 415.

(xvi) Concreting should be commenced from the point, loading upon which results max deflection.

Simply supported/ continuous -center towards end

Cantilever - free end towards fixed end

(xvii) Provision of horizontal extension should be made , as per fig. shown :-

m

Page 46: Cracks

Structural provision of horizontal extension with an expansion joint, for RCC framed structure

Page 47: Cracks

(xviii) Na O & K O content of cement should be less than 0.6% & should be less than 3 kg per cubic metre of concrete. If it is unavoidable then mix a suitable proportion of pozzolanic material (especially silica fume) for making concrete.

(xix) Do not let trees grow too close to building.

(xx) If some large trees exist close to a building (within a distance of the ht. of the tree) & these are not causing any problem, as far as possible, do not disturb these trees if soil under the foundation happen to be shrinkable clay.

2 2

Page 48: Cracks

(xxi) If, from any site intended for new construction, vegetation including trees is removed & the soil is shrinkable clay, do not commence construction activity on that soil until it has undergone expansion after absorbing moisture & has stabilized.

(xxii) Length of return wall should not be less than the length of 3 bricks.

(xxiii) Use of precast components.

(xxiv) Laying of floor in small panels.

Page 49: Cracks

Corrosion of steel

- Use CRS bar, Fusion bonded epoxy coated bar, TMT bar.

- MCI (Migratory corrosion inhibitors)

Page 50: Cracks

M C I

MCI are vapour phase inhibitors which by virtue of their very high vapour pressure & their affinity for steel, penetrate through concrete to the steel. It provides a monomolecular layer of inhibitor protection which reduces or stops the corrosion, electrochemically, thus areas of steel not exposed or deeply embedded are also provided protection. Further the MCI systems are effective even in the presence of high percentage of chlorides within the concrete.

Page 51: Cracks