29 th March 2012 Yeo Kim Hock Code of Practice on Safe Lifting Operations at Workplaces LIFTING PLAN PERMIT TO WORK RISK ASSESSMENT Formulating a Lifting Plan Fundamental Contents- Key Factors of a Lifting Plan Introduction-Objectives of Lifting Plan/ PTW/ RA Review of the Lifting Plan Conclusion Objectives of a Lifting Plan Facilitate common understanding amongst the lifting crews •Conduct Risk Assessment •Eliminate Risks •Mitigate Risks •PTW •LP Safe Outcomes & Compliance to Regulations Fundamental Contents Key Factors of a Lifting Plan Detail of the Load Detail of the Lifting Equipment Means of Communication Personnel Involved in the lifting operation Physical & Environmental Considerations Not nec essary in sequenc e Description of the load/s Load Configurations Overall dimensions Weight Centre of Gravity. Type of Lifting Equipment Maxi SWL Max boom/Jib length Intended Load Radius Visual-Standard Hand Signal Audio-Radio Within sight and view of load and all personnel Lifting Supervisor Crane Operator Rigger Signalman Site Supervisor/ others Acronym ‘GOLDEN’ Fundamental Contents Key Factors of a Lifting Plan Other Considerations based on the 5M Model Critical Document and Information Method of Rigging Not nec essary in sequenc e Machine Material Medium Man Method Load Capacity Chart/ Range Diagram Operations Manual/ Logbook Appointment of Competent Personnel Valid Test Certificate Checklists Choker Hitch Basket Hitch Direct Rigging Sling Angle Sequence/ Special Precautions Sketch of the Lifting Zone Public Safety/ Tandem Ops Initial and Final location of the load Path of the load Load Radius Obstructions Type of LGs Chain Sling Fibre Sling Wire Sling General Formulating a Lifting Plan
6
Embed
CP 0n SLO in the Workplace-Lifting Plan_6 Slides Per Page_R2
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
29th March 2012
Yeo Kim Hock
Code of Practice
on Safe Lifting Operations at Workplaces
LIFTING PLAN
PERMIT TO WORKRISK ASSESSMENT
Formulating a Lifting Plan
Fundamental Contents- Key Factors of a Lifting Plan
Introduction-Objectives of Lifting Plan/ PTW/ RA
Review of the Lifting Plan
Conclusion
Objectives of a Lifting Plan
Facilitate common
understanding
amongst the lifting
crews
•Conduct Risk Assessment
•Eliminate Risks
•Mitigate Risks
•PTW
•LP
Safe Outcomes
&
Compliance to
Regulations
Fundamental ContentsKey Factors of a Lifting Plan
Detail of the Load
Detail of the Lifting
Equipment
Means of Communication
Personnel Involved in the
lifting operation
Physical & Environmental Considerations
Not necessary
in s
equence
Description of the load/sLoad ConfigurationsOverall dimensionsWeightCentre of Gravity.
Type of Lifting EquipmentMaxi SWLMax boom/Jib lengthIntended Load Radius
Visual-Standard Hand SignalAudio-RadioWithin sight and view of load and all personnel