Top Banner
Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology, Bombay Submitted by :- Deepak Garg (05329015) Priyesh Wadhwa (05329011) Saurabh P. Singh (05329037) Mukesh S. Rawat (05329020)
18

Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Mar 28, 2015

Download

Documents

Zakary Flavell
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Cost Estimation in a Construction Company

Under the guidance of Prof. K. Narayanan

Department of Humanities and Social Science Indian Institute of Technology, Bombay

Submitted by :- Deepak Garg (05329015) Priyesh Wadhwa (05329011) Saurabh P. Singh (05329037) Mukesh S. Rawat (05329020)

Page 2: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Road Map• Introduction

• Types of Construction Cost Estimates

• Approaches to Cost Estimation

• Unit Cost Method of Estimation

• Other Methods

Page 3: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Introduction• Cost Estimation

– Cost estimation is one of the most important steps in project management.

– Why• Feasibility study.• Profit measures.

– How• Advanced software packages are available.

Page 4: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Costs in Construction Firm• Initial Capital cost

– Land acquisition– Planning and feasibility studies– Architectural and engineering design– Construction, including materials, equipment and labor– Insurance and taxes during construction

• Operation and maintenance cost– Operating staff– Labor and material for maintenance and repairs– Utilities– Periodic renovations– Insurance and taxes

• Unexpected cost during construction– Design development changes– Schedule adjustments– General administration changes

Page 5: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Types of Construction Cost Estimates• Design Estimates

– Screening estimates (or order of magnitude estimates)– Preliminary estimates (or conceptual estimates)– Detailed estimates (or definitive estimates)– Engineer's estimates based on plans and specifications

• Bid Estimates– As a contractor, a bid estimate is submitted to the owner

either for competitive bidding or negotiation.

• Control Estimates– Budget estimate for financing– Budgeted cost after contracting but prior to construction– Estimated cost to completion during the progress of

construction.

Page 6: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Approaches to Cost Estimation

• Production function

Q = P(I1,I2,….. In)

• Empirical cost inference

• Unit costs for bill of quantities

• Allocation of joint costs

Page 7: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Unit Cost Method of Estimation

Simple Unit Cost Formula

Formula Based on Labor, Material and Equipment

Page 8: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Example

• Cost estimate using labor, material and equipment rates.

Page 9: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Other Methods• Allocation of joint costs

- Difficult causal relationship b/w element and associated costs

- Joint costs are prorated in proportion of basic costs of elements

For example : F being overhead associated with different elements

Fi = F * yi/y

Then total cost can be written as :-

Li = yi + Fi

• Historical cost data- Widely used for forecasting / estimation future costs

- Collected and organized for future use

- Continuous updates

- May effect cost substantially if relative prices change

Page 10: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Other Methods contd.• Cost indices

- Reflect price level changes for inputs and outputs

- Weighted aggregate average of different components of selected element

- Can be used for cost forecasting with historic data

- General price indices are provided by govt.

- Construction specific price indices are collected from industry sources

- Screening estimates are generally made on single factor like constructed area, no. of rooms etc

- Adjustments are made to these using

- Inflation indices

- Construction specific indices

of detailed factors

Page 11: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Other Methods contd.•Based on Engineer's List of Quantities

- based on a list of items and the associated quantities

- list is provided to contractor

- costs for winning bidder is taken as starting estimates

- progress payments are made to contractor depending upon the units of work done and unit prices listed

- each unit defined the level of detail of measure

- ex. Sample entries in bid table for engineer’s list-

Item Unit Quantity Unit price Item cost

Tiling sf 1000 12 12000

Water Proofing

sf 1000 7 7000

.

.

.

.

.

.

.

.

.

.

Rs.19000

Page 12: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Computer Aided Cost Estimation • Types:

– Simple spreadsheet calculation software.– Integrated systems.

• Features:– Databases for unit cost items.– Databases of expected productivity for

different components types, equipments, and process.

– Version control, Flexible reporting formats, import and export utilities, archive of past projects.

• Advantages: Rapid cost estimation and with less efforts.

• Example : as will be shown

Page 13: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Estimation of Operating Costs • Depends upon: maintenance

policies and facility use.• Minimized by: periodic repairs

and rehabilitation at periodic intervals.

• Example: Maintenance cost on a roadway– C = 596 + 0.0019 V + 21.7 A – Where, C is the annual cost of

routine maintenance per lane-mile.

– V is the volume of traffic on the roadway measured in ESAL (equivalent standard axle loads)

– A is the age of the roadway in years since the last resurfacing.

Page 14: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Case study• Raheja builders

• Estd. in 1952

• Uses simple unit cost estimation method

• Uses simple accounting tools

• In process of configuring ERP

Page 15: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Thanks

Questions?

Page 16: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Allocation of Construction Cost over time

• Rate of work done during various time periods expressed in percentage of project cost per unit time.

• The value of work completed at a given time expressed as a cumulative percentage of project cost

Page 17: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Example

• Decomposition of a building foundation into design and construction elements.

Page 18: Cost Estimation in a Construction Company Under the guidance of Prof. K. Narayanan Department of Humanities and Social Science Indian Institute of Technology,

Price indices in subsequent years show a proportionate changes due to price changes. Percent change in price indices for year t+1-

jt+1=((It+1-It) / It )* (100%)

- Measure price level changes