Top Banner
Cost Control
60

Cost Control. Do project managers control costs, monitor costs or both?

Dec 22, 2015

Download

Documents

Elijah Anthony
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cost Control. Do project managers control costs, monitor costs or both?

Cost ControlCost Control

Page 2: Cost Control. Do project managers control costs, monitor costs or both?

Do project managers control costs, monitor costs or both?

Page 3: Cost Control. Do project managers control costs, monitor costs or both?

Cost ManagementCost Management

Cost estimating Cost accounting Project cash flow Company cash flow Direct labor costing Overhead rate costing Others, such as incentives, penalties, and

profit-sharing

Cost estimating Cost accounting Project cash flow Company cash flow Direct labor costing Overhead rate costing Others, such as incentives, penalties, and

profit-sharing

Page 4: Cost Control. Do project managers control costs, monitor costs or both?

Cost And Control SystemCost And Control System

PLANNING

WORK

AUTHORIZATION

AND RELEASE

DATA

COLLECTION

AND REPORTING

COST

ACCOUNTING

CUSTOMER AND

MANAGEMENT

REPORTING

PHASE I PHASE II PHASE III PHASE IV PHASE V

OPERATING CYCLE CYCLE

PLANNING

Page 5: Cost Control. Do project managers control costs, monitor costs or both?

Cost Control RequirementsCost Control Requirements

Measure resources consumed Measure status and accomplishments Compare measurements to projections

and standards Provide the basis for diagnosis and re-

planning

Measure resources consumed Measure status and accomplishments Compare measurements to projections

and standards Provide the basis for diagnosis and re-

planning

Page 6: Cost Control. Do project managers control costs, monitor costs or both?

Cost Control RequirementsCost Control Requirements

Thorough planning of the work to be performed to complete the project

Good estimating of time, labor, and costs Clear communication of the scope of

required tasks A disciplined budget and authorizations

of expenditures Timely accounting of physical progress

and cost expenditures Periodic re-estimation of time and cost to

complete remaining work

Thorough planning of the work to be performed to complete the project

Good estimating of time, labor, and costs Clear communication of the scope of

required tasks A disciplined budget and authorizations

of expenditures Timely accounting of physical progress

and cost expenditures Periodic re-estimation of time and cost to

complete remaining work

Page 7: Cost Control. Do project managers control costs, monitor costs or both?

Cost Control Requirements (Continued)

Cost Control Requirements (Continued)

Frequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion

Frequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion

Page 8: Cost Control. Do project managers control costs, monitor costs or both?

WHEN TO IMPLEMENT A COST MANAGEMENT SYSTEM

CONCLUSION

A cost management system should be implemented right at the beginning of the life cycle of the project.

Possible costreductions

Cost of change

PROJECTCOSTS

PROJECT LIFE CYCLE PHASES

Page 9: Cost Control. Do project managers control costs, monitor costs or both?

Partitioning The Budget

Page 10: Cost Control. Do project managers control costs, monitor costs or both?

The Work Authorization Form

Page 11: Cost Control. Do project managers control costs, monitor costs or both?

Work Authorization Form

Description Cost Work WorkCenters Hours Cost Starts Ends

- Test Material 2400 150 R4500 1 Aug 15 Sept - Processing 2610 160 R7500- Final inspection 2621 140 R3500- Packaging 2623 46 R 750- Delivery 2624 R 350

Project office authorization signature:________________

WBS: 31.03.02 Work order no: D1385

Date of original release: 03 Feb 97 Date of revision: 18 March 97 Revision number: C

Page 12: Cost Control. Do project managers control costs, monitor costs or both?

PLANNING AND BUDGETING

Work packages

WBS Element

MGR

Org

Org

Org

Work Package

WP______ORG_______Description of task_________________________Sched: Start____Stop__Budget:______________

Page 13: Cost Control. Do project managers control costs, monitor costs or both?

CACN No. _____________ Revision to Cost Account No. ____________ Date ___________

DESCRIPTION OF CHANGE:________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

REASON FOR CHANGE:______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Requested Budget Authorized BudgetLabor Hours _________________ _________________ Period of performanceMaterials _________________ _________________ From _____________ODCS _________________ _________________ To _____________

BUDGET SOURCE: Funded Contract Change Management Reserve Undistributed Budget Other _________________INITIATED BY: ____________________________ APPROVALS: Program Mgr. ________ Prog. Control ________

COST ACCOUNT CHANGE NOTICE (CACN)

Page 14: Cost Control. Do project managers control costs, monitor costs or both?

Sources Of Additional FundingSources Of Additional Funding

Funded contract change

Management reserve

Undistributed budget

Other (e.g. profits)

Funded contract change

Management reserve

Undistributed budget

Other (e.g. profits)

Page 15: Cost Control. Do project managers control costs, monitor costs or both?

Cost data collation and reporting flow chart

Actuals

Labor

ACWP

InventoryAccounts

BCWP

Computer

BCWS

Monthly TotalProgram Effort

Weekly Labor Reports

MCCS Comparisonreports To All Execs

Variance Report

Page 16: Cost Control. Do project managers control costs, monitor costs or both?

Cost DataCost Data

Labor Material Other direct charges Overhead

Labor Material Other direct charges Overhead

Page 17: Cost Control. Do project managers control costs, monitor costs or both?

Types of BudgetsTypes of Budgets

Distributed budget Management budget Undistributed budget Contract changes

Distributed budget Management budget Undistributed budget Contract changes

Page 18: Cost Control. Do project managers control costs, monitor costs or both?

Variance Analyses

Page 19: Cost Control. Do project managers control costs, monitor costs or both?

VARIABLES FOR VARIANCE ANALYSIS BUDGETED COST FOR WORKED SCHEDULED (BCWS) IS THE BUDGETED

AMOUNT OF COST FOR WORD SCHEDULED TO BE ACCOMPLISHED PLUS THE AMOUNT OF LEVEL OF EFFORT OR APPORTIONED EFFORT SCHEDULED TO BE ACCOMPLISHED IN A GIVEN TIME PERIOD.

BUDGETED COST FOR WORK PERFORMED (BCWP) IS THE BUDGETED AMOUNT OF COST FOR COMPLETED WORD, PLUS BUDGETED FOR LEVEL OF EFFORT OR APPORTIONED EFFORT ACTIVITY COMPLETED WITHIN A GIVEN TIME PERIOD. THIS IS SOMETIMES REFERRED TO AS AN “EARNED VALUE.”

ACTUAL COST FOR WORK PERFORMED (ACWP) IS THE AMOUNT REPORTED AS ACTUALLY EXPENDED IN COMPLETING THE WORK ACCOMPLISHED WITHIN A GIVEN TIME PERIOD.

COST VARIANCE = BCWP – ACWP

SCHEDULE/PERFORMANCE VARIANCE = BCWP - BCWS

Page 20: Cost Control. Do project managers control costs, monitor costs or both?

VariancesVariances

The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.

The scheduling variance provides a comparison between planned and actual performance but does not include costs.

The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.

The scheduling variance provides a comparison between planned and actual performance but does not include costs.

Page 21: Cost Control. Do project managers control costs, monitor costs or both?

Measurements Measurements

Measurable efforts: discrete increments of work with a definable schedule for accomplishment, whose completion produces tangible results.

Level of effort: work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support and project control.

Measurable efforts: discrete increments of work with a definable schedule for accomplishment, whose completion produces tangible results.

Level of effort: work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support and project control.

Page 22: Cost Control. Do project managers control costs, monitor costs or both?

COST VARIANCE CALCULATION

A NEGATIVE VARIANCE INDICATES A COST OVERRUN

CV = BCWP - ACWP

Page 23: Cost Control. Do project managers control costs, monitor costs or both?

SCHEDULE VARIANCE CALCULATION

SV = BCWP - BCWS

A NEGATIVE VARIANCE INDICATESA BEHIND SCHEDULE CONDITION

Page 24: Cost Control. Do project managers control costs, monitor costs or both?

VARIANCE PERCENTS

SCHEDULE VARIANCE % = (SVP)

COST VARIANCE % = (CVP)

SVBCWS X 100

CVBCWP X 100

Page 25: Cost Control. Do project managers control costs, monitor costs or both?

Project Variance AnalysisProject Variance Analysis

R&D QUALIFICATION DEVELOPMENTPHASE I PHASE II PHASE III

VARIANCE LOWER BOUNDARY

ACTUAL COST VARIANCE

PROJECTED COST

VARIANCE UPPER BOUNDARY

TIME

$

Page 26: Cost Control. Do project managers control costs, monitor costs or both?

Trend Analyses

Page 27: Cost Control. Do project managers control costs, monitor costs or both?

Management ReserveManagement Reserve

CONTRACTED COST

RELEASED BUDGET

ACTUAL COST

TIME

MANAGEMENTRESERVE

$

Page 28: Cost Control. Do project managers control costs, monitor costs or both?

Information RequirementsInformation Requirements

Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability

Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability

Page 29: Cost Control. Do project managers control costs, monitor costs or both?

Variance Analysis QuestionsVariance Analysis Questions What is the problem causing the

variance? What is the impact on time, cost, and

performance? What is the impact on other efforts, if

any? What corrective action is planned or

under way? What are the expected results of the

corrective action?

What is the problem causing the variance?

What is the impact on time, cost, and performance?

What is the impact on other efforts, if any?

What corrective action is planned or under way?

What are the expected results of the corrective action?

Page 30: Cost Control. Do project managers control costs, monitor costs or both?

VARIANCE REPORTING

Variance reporting is accomplished at each reporting interval. However, the variance threshold reports are exception reports and occur only when the variances exceed the upper and lower boundaries of the project variances envelope.

Page 31: Cost Control. Do project managers control costs, monitor costs or both?

REPORTING INTERVALS

Depends on the type of organization and characteristics of the projects.

Project-driven organization - weekly. Non-project-driven organization - monthly

Page 32: Cost Control. Do project managers control costs, monitor costs or both?

Cost Account Variance Analysis ReportCost account no/camWBS/Description

Cost performance data Variance

Reporting levelAs of

At completionBudget EAC Var. BCWS BCWP ACWP SCHED COST

Month to date ($)Contract to date ($k)

Problem cause and impact

Corrective action (including expected recovery date)

Cost account Date Cost center Date WBS element Date DateMgr. Mgr. Mgr.

Page 33: Cost Control. Do project managers control costs, monitor costs or both?

The 50/50 rule

HALF OF THE BUDGET FOR EACH ELEMENT IS RECORDED AT THE TIME THAT THE WORK IS SCHEDULED TO BEGIN AND THE OTHER HALF AT THE TIME THE WORK IS SCHEDULED TO BE COMPLETED.

FOR A PROJECT WITH A LARGE NUMBER OF ELEMENTS THE AMOUNT OF DISTORTION FROM SUCH A PROCEDURE IS MINIMAL.

Page 34: Cost Control. Do project managers control costs, monitor costs or both?

J F M A M J J A S O N D

ANALYSISBudgeted cost for work Scheduled (BCWS)

Performed (BCWP)

Budget - 6

8 14

12

10

12

8

12

10

8

Work packages

Cost account budget = 100 (thousands)

BCWS = 38BCWP = 49SCHED. VARIANCE = +11

50-50 rule used for work in process

Page 35: Cost Control. Do project managers control costs, monitor costs or both?

Using The 50-50 RuleUsing The 50-50 Rule

4,000

10,000

12,000

4,000

6,000

6,000

10,000

TIME

TIME LINE

COMPLETED

NOT COMPLETED

LEGEND

BCWS = 34,000BCWP = 33,000 BAC = 52,000

Page 36: Cost Control. Do project managers control costs, monitor costs or both?

Earned Value Status ReportingEarned Value Status Reporting

SV

CV

BCWS

BCWP

ACWP

TIME LINE

CU

MM

UL

AT

IVE

CO

ST

, $

TIME

Page 37: Cost Control. Do project managers control costs, monitor costs or both?

Estimated Cost At Completion

Page 38: Cost Control. Do project managers control costs, monitor costs or both?

ESTIMATE AT COMPLETION (EAC)

EAC = ACWPBCWP

X Budget at completion

The estimate at completion is the best estimate of the total cost at the completion of the project.

The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.

(BAC)

Page 39: Cost Control. Do project managers control costs, monitor costs or both?

PROGRESS REPORTING Progress reporting needs to answer four fundamental

questions:

1. Where are we today (time and cost)?

2. Where will we end up (time and cost)?

3. What are the present and future risks?

4. Are there any special problems that need to be

addressed and what can management do to help?

Page 40: Cost Control. Do project managers control costs, monitor costs or both?

Monthly Project Report 1. VARIANCE ANALYSIS (Cost in Thousands) 1 June 1997

Budgeted Budgeted Cost

Milestone Cost Work Work Actual Variance, %

Subtask Status Scheduled Performed Cost Schedule Cost

1 Completed 100 100 100 0 0

2 Completed 50 50 55 0 -10

3 Completed 50 50 40 0 20

4 Not Started 70 0 0 -100 --

5 Completed 90 90 140 0 -55.5

6 Not started 40 0 0 -100 --

7 Started 50 50 25 0 50

8 Not started 0 0 0 -- --

Total 450 340 360 -24.4 -5.9

Page 41: Cost Control. Do project managers control costs, monitor costs or both?

2. ESTIMATE AT COMPLETION (EAC)EAC = (360/340) X 579,000 = $613,059Overrun = 613,059 - 579,000 = $34,059

3. COST SUMMARYCosts are running approximately 5.9% over budget due to higher salaried labor.

4. SCHEDULE SUMMARYThe 24.4% behind schedule condition is due to subtasks 4 and 6 which have not yet begun due to lack of raw materials and the 50/50 method for booking costs. Overtime will get us back on schedule but at an additional cost of 2.5% of direct labor costs.

Page 42: Cost Control. Do project managers control costs, monitor costs or both?

5. MILESTONE REPORT

Milestone/ Scheduled Projected Actual

Subtask Completion Completion Completion

1 4/1/97 4/1/97

2 5/1/97 5/1/97

3 5/1/97 4/23/97

4 7/1/97 7/1/97

5 6/1/97 6/1/97

6 8/1/97 8/1/97

7 9/1/97 9/1/97

8 10/1/97 10/1/97

Page 43: Cost Control. Do project managers control costs, monitor costs or both?

6. ACTIVITY REPORT

Current Potential Corrective

Problem Impact Action

(a) Lack of raw Cost overruns and Overtime is scheduled.

materials. behind schedule We will try to use lower

condition. salaried staff. Raw

materials are expected

to be on dock next week.

(b) Customer un- May need add- Customer will provide

happy with test itional planning. us with revised statement

results. of work on 6/15/97.

Page 44: Cost Control. Do project managers control costs, monitor costs or both?

Status Reporting Is More Than Just A Computer Printout.

Page 45: Cost Control. Do project managers control costs, monitor costs or both?

Intranet Status Reporting

Page 46: Cost Control. Do project managers control costs, monitor costs or both?

Reporting Favorable Status

Page 47: Cost Control. Do project managers control costs, monitor costs or both?

Reporting Unfavorable Status

Page 48: Cost Control. Do project managers control costs, monitor costs or both?

DATA ACCUMULATION

WBS

Org

aniz

atio

n

BCWS

BCWP

ACWP

BudgetSCHED

VAR

COST VAR

Page 49: Cost Control. Do project managers control costs, monitor costs or both?

Cutting The BudgetCutting The Budget

Page 50: Cost Control. Do project managers control costs, monitor costs or both?

Financial Close-OutFinancial Close-Out

Page 51: Cost Control. Do project managers control costs, monitor costs or both?

Cost ProblemsCost Problems Poor estimating techniques and/or

standards, resulting in unrealistic budgets Out-of-sequence starting and completion

of activities and events Inadequate work breakdown structure No management policy on reporting and

control practices Poor work definition at the lower levels of

the organization

Poor estimating techniques and/or standards, resulting in unrealistic budgets

Out-of-sequence starting and completion of activities and events

Inadequate work breakdown structure No management policy on reporting and

control practices Poor work definition at the lower levels of

the organization

Page 52: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems (Continued)Cost Problems (Continued)

Management reducing budgets or bids to be competitive or to eliminate “fat”

Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort

Poor comparison of actual and planned costs

Comparison of actual and planned costs at the wrong level of management

Unforeseen technical problems

Management reducing budgets or bids to be competitive or to eliminate “fat”

Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort

Poor comparison of actual and planned costs

Comparison of actual and planned costs at the wrong level of management

Unforeseen technical problems

Page 53: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems (Continued)Cost Problems (Continued)

Schedule delays that require overtime or idle time costing

Material escalation factors that are unrealistic

Schedule delays that require overtime or idle time costing

Material escalation factors that are unrealistic

Page 54: Cost Control. Do project managers control costs, monitor costs or both?

Problem Areas in Cost Control Organization:

- Inadequate Work Breakdown Structure

- Poor work definition at working levels- Lack of formal system procedures

Planning and budgeting:

- Inadequate forward planning- Over-allocation of budget- Poor integration of budget, schedule, work authorization

Accounting:

- Inability to account for cost of material on applied basis Analysis:

- Determination of status not based on work package completion- Comparison of actual vs. planned costs at improper level

Revisions:- Failure to maintain valid measurement baseline

Page 55: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Proposal Phase– Failure to understand customer requirements– Unrealistic appraisal of in-house capabilities– Underestimating time requirements

Proposal Phase– Failure to understand customer requirements– Unrealistic appraisal of in-house capabilities– Underestimating time requirements

Page 56: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Planning phase– Omissions– Inaccuracy of the work breakdown structure– Misinterpretation of information– Use of wrong estimating techniques– Failure to identify and concentrate on major

cost elements– Failure to assess and provide for risks

Planning phase– Omissions– Inaccuracy of the work breakdown structure– Misinterpretation of information– Use of wrong estimating techniques– Failure to identify and concentrate on major

cost elements– Failure to assess and provide for risks

Page 57: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Negotiation phase– Forcing a speedy compromise– Procurement ceiling costs– Negotiation team that must “win this one”

Negotiation phase– Forcing a speedy compromise– Procurement ceiling costs– Negotiation team that must “win this one”

Page 58: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Contractual phase– Contractual discrepancies– SOW different from RFP requirements– Proposal team different from project team

Contractual phase– Contractual discrepancies– SOW different from RFP requirements– Proposal team different from project team

Page 59: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Design phase– Accepting customer requests without

management approval – Problems in customer communications

channels and data items– Problems in design review meetings

Design phase– Accepting customer requests without

management approval – Problems in customer communications

channels and data items– Problems in design review meetings

Page 60: Cost Control. Do project managers control costs, monitor costs or both?

Cost Problems Per PhaseCost Problems Per Phase

Production phase– Excessive material costs – Specifications that are not acceptable– Manufacturing and engineering disagreement

Production phase– Excessive material costs – Specifications that are not acceptable– Manufacturing and engineering disagreement