Cost Analysis of Energy Usage at Shepherd University Final Presentation Omed Amin Chris Hardy Kathleen Yan 11 May 2018 1
Cost Analysis of Energy Usage
at Shepherd University
Final Presentation
Omed Amin
Chris Hardy
Kathleen Yan
11 May 2018
1
Project Background
• Shepherd University
• Founded in 1871
• Shepherdstown, West Virginia
• 49 buildings varied in size, age, function,
and construction material
• Motivation
• High utility costs
• Not enough studies and strategic plans on campus wide energy conservation
• Interested in campus wide initiatives to reduce the total cost of energy usage
• Inspired by local county public K-12 schools
2
Problem Statement
Shepherd University currently has high utility costs totaling nearly $2 million a
year due to old buildings with outdated utility systems. Therefore, there is a need
for modern, more energy efficient utility systems to reduce annual utility costs.
The Operation & Facilities Department asked the team to perform a cost
analysis on various energy usage domains and recommend a solution. The
recommended solution must pay for its implementation cost and have the
greatest annual utility savings.
3
Project Objective and Scope
Objective: Study various energy conservation solutions and recommend
a solution to reduce the total cost of energy usage to Shepherd University,
including a cost analysis for each solution, detailing their implementation
costs, annual and long-term cost savings, and payback periods.
Scope: East Campus, 21 Buildings
Research Domains:
• Heating, Ventilation, and Air Conditioning (HVAC)
• Building Envelope (Windows, Air Sealings, Insulations)
• Lighting Loads
4
East Campus
Technical Approach 5
Phase 1
Data Collection: Compiled an overview of existing energy
solutions related to the 3 research domains. Identified
parameters to be used in the cost analysis.
Phase 2Cost Analysis: Examined each solution within the domains to
calculate initial implementation costs, annual utility savings, 20-
year cost savings, and simple payback periods.
Phase 3Decision Analysis: Compared solutions based on different
attributes to determine the best recommendation to Shepherd
University.
HVAC Cost Analysis Summary
• Only 4 buildings on East Campus need HVAC unit replacements.
• The analysis is based on replacing the existing HVAC units with 16 Seasonal Energy
Efficiency Ratio (SEER)1 rated units reducing utility costs by 50% annually.
6
1The SEER rating of a unit is the cooling output during a typical cooling-season divided by the total electric energy input during
the same period. The higher the unit's SEER rating the more energy efficient it is.
Implementation Costs ($):
• $13,200 per building, a fixed cost based on building
size
Annual Savings ($):
• Cost per 1 M British Thermal Units (BTUs) =
($0.11/Kwh * 293)
• BTUs required per building per month =
(Gross Area * 3,000) + 500,000
• Annual cost = 12 * Cost per 1 M BTUs * BTUs
required /1,000,000
• Savings = Annual cost - (Annual cost * % Saving)
Payback Period (yrs.):
Implementation Cost ($)
Annual Savings ($)
20-Year Cost Savings ($):
• Net cost saving in present
value using 2.02% real
interest rate
Building Envelope Summary
• White Roofs
o Painting roofs with reflective paint to save on
cooling costs
• Energy Efficient Windows
o Energy efficient windows are better at reflecting
sun and keeping conditioned air inside
• Air Sealing
o Using weather-stripping and caulking to close
holes where air leaks in and out of the building
• Insulation
o Increasing the thermal resistance of wall areas to
prevent heat and cold air from moving through
7
Calculating Cost Savings – Windows8
Assumptions:
• Electricity percent usage
breakdown
• Number of windows
Market Research:
• Window size
• Window area relative to building
size
• Parameter cost estimates
o Window price
o Labor cost per window
• Percentage savings
Provided Data:
• FY17 electricity costs per building
• Building gross area
Annual Savings ($):
• FY17 electricity cost($) * %
Usage of heating & AC *
%Savings
Implementation Costs ($):
• (Window Price ($) + Labor
Cost($)) * # of Windows
Payback Period (yrs.):
• Implementation Cost ($)
Annual Savings ($)
20-Year Cost Savings ($):
• Net cost saving in
present value using
2.02% real interest rate
Building Envelope Cost Summary
Solution
Total
Implementation
Cost ($)
Total Payback
Period (yrs.)
Total Annual
Utility Savings
($)
Total 20-year
Cost Saving ($)
Product Lifetime
(yrs.)
White Roof $853,821 26.79 $31,867 -$323,250 30
Energy Efficient
Windows$2,190,115 46.04 $47,573 -$1,398,049 25
Air Sealing:
Weather-Stripping$542,804 12.55 $43,248 $177,256 20
Air Sealing:
Caulking$286,811 8.84 $32,436 -$33,577 10
9
• Very costly. Payback period is more than
product lifetime.
• Best implemented when a building is under
construction for incremental cost savings.
Implementation
cost is counted
twice
The negative
value is due to
net present
value
Building Envelope: Insulation10
Wall
Area
(ft2)
Heating
Degree
Days (HDD)
Current Insulation
Thermal
Resistance
Future Insulation
Thermal
Resistance
$ per MBTUBTUs Saved
(Millions)
Annual
Savings
5000 5293 22 40 $32.23 12.99 $418.69
Diminishing returns due to not being
able to completely reduce heat flow
through a wall.
Adding insulation to areas where none
exists has greater cost and energy
savings than adding insulation to
already insulated areas.
Heat Flow = 1/R * Area * HDD * 24
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
0 5 10 15 20 25 30 35 40 45
HEAT FLOW
OVER A
HEATING
SEASON
(MBTUS)
THERMAL RESISTANCE, R
Lighting Analysis Summary
Analysis Area
• Replacing LED lightbulbs only and fixtures
• Interior lights and exterior lights
• Occupation sensors for traditional lights and LED lights
Analysis Focus
• 18 types of lightbulbs
• LED wattage equivalence and savings for each old lightbulb type
• Number of lightbulbs only and fixture + lightbulbs for each building by type
• Part and labor costs for LED lightbulbs and traditional lightbulbs
11
LED Total
Installment
Cost
LED Annual
Energy
Savings
LED Payback
Period (yrs.)
LED Life
Cycle (yrs.)
Old Life
Cycle
20-yr Old
Replacement
Cost
LED
Replacement
Cost
20-yr LED
Replacement
Cost
20 yr. Cost
Saving
$70,009 $8,156 6.80 10.20 1.28 $311,715 $67,740 $137,749 $309,762
Example of LED Cost Analysis 12
Marketing Research
Sponsor provided
$0.11/kwh 40,000 hrs.
lifetime
5,000 hrs.
lifetime
Present value using 2.02%
real interest rate.
Subtract diff. in LED and old
replacement cost
Cost Analysis Summary – East Campus13
Combined analysis for a
few promising solutions
The total annual savings of all individual solutions is 15% of current
annual utility cost of $2M.
Decision Analysis – Attributes and Weights14
Attribute Range Preferred Value Rank Weight
Implementation Cost (IC) $53,000 – $2,190,000 Lower 2 0.19
Payback Period (PP) 1 – 46 yrs. Lower 4 0.10
Annual Utility Savings (AS) $32,000 – $127,000 Higher 1 0.39
20-year Cost Savings (CS) $-1,398,000 – $3,684,000 Higher 3 0.13
Environment Benefits (EB) Low, Medium, High Higher 6 0.06
Ease of Implementation (EI) Easy, Medium, Hard Lower 5 0.08
Product Lifetime (PL) 10 – 30 yrs. Higher 7 0.06
Weights are calculated using rank reciprocal method: Consult with
Sponsor𝑊 =
1
𝑅𝑖
𝑖=1
71
𝑅𝑖
Decision Analysis – Ranked Solution
Solution Utility Score
LED + HVAC 0.82
LED + Occupation Sensors 0.73
HVAC + Occupation Sensors 0.71
LED 0.60
HVAC 0.51
Occupation Sensors 0.49
Air Sealing with Weatherstripping 0.41
Air Sealing with Caulking 0.38
Reflective Roof Painting 0.32
Energy Efficient Windows 0.15
15
Utility Score = 𝑊𝐼𝐶∗ 𝑈𝐼𝐶 +𝑊𝑃𝑃 ∗ 𝑈𝑃𝑃 +𝑊𝐴𝑆 ∗ 𝑈𝐴𝑆 +𝑊𝐶𝑆 ∗ 𝑈𝐶𝑆 +𝑊𝑃𝐿 ∗ 𝑈𝑃𝐿 +𝑊𝐸𝐵 ∗ 𝑈𝐸𝐵 +𝑊𝐸𝐼 ∗ 𝑈𝐸𝐼
Recommended
solution
𝑈(𝑥) =𝐻𝑖𝑔ℎ − 𝑥
𝐻𝑖𝑔ℎ − 𝐿𝑜𝑤
𝑈(𝑥) =𝑥 − 𝐿𝑜𝑤
𝐻𝑖𝑔ℎ − 𝐿𝑜𝑤
where High represents the maximum
value, Low represents the minimum
value, and x represents the value that
is being assessed for a given attribute.
Sensitivity Analysis – Weights 16
AttributesOriginal
Rank
New
Rank
Implementation Cost (IC) 2 2
Payback Period (PP) 4 4
Annual Utility Savings (AS) 1 3
20-year Cost Savings (CS) 3 1
Environment Benefits (EB) 6 4
Ease of Implementation
(EI)5 4
Product Lifetime (PL) 7 4
• LED + HVAC and LED + Sensor are tied in
utility score
• LED has a higher utility score than Sensor +
HVAC
Solution Utility Score
LED + HVAC 0.79
LED + Occupation Sensors 0.79
HVAC + Occupation Sensors 0.64
LED 0.68
HVAC 0.57
Occupation Sensors 0.53
Air Sealing with Weatherstripping 0.47
Air Sealing with Caulking 0.46
Reflective Roof Painting 0.40
Energy Efficient Windows 0.13
Sensitivity Analysis – Cost
Increase / decrease costs by 20% for each solution while others remain constant
17
Solution Cost Change Results
HVAC Increase/decrease implementation cost by 20% No change on any solution ranking
LED Increase/ decrease parts + labor cost by 20% No change on any solution ranking
Sensor Increase/ decrease parts + labor cost by 20% No change on any solution ranking
Electricity
Rate Increase by 20% No change on any solution ranking
Electricity
Rate
Decease by 20% Solution ranking of HVAC + Occupation
Sensors overtook LED + Occupation Sensors
Solution ranking is not sensitive to varying implementation cost by ± 20% since the
annual utility savings has the highest weight.
Recommendations
• A combination of replacing traditional lights with LED lighting and upgrading HVAC
units provides the best overall benefits based on our cost and decision analysis.
o It satisfies all requirements of the University.
o It requires a total implementation cost of $893,000 with payback period of 7 years.
o It has the highest annual utility savings of $127,000.
o It is expected to yield $3.6 million cost savings in a 20-year period measured in
present value.
o LED lights are expected to last for 13 years and HVAC for 20 years.
o It is robust to sensitivity analysis.
18
Assumptions and Limitations
• Extrapolation based on building size and type was used to allocate
electricity cost to buildings with missing data.
• Only open source information was used for cost analysis parameters.
• Savings estimates did not take into account all characteristics of each
individual building.
19
Future Work / Improvement
• More accurate assessment on light usage (hours of usage per day, days of
year, percent of lights in use, etc.) and building conditions
• More market research on labor and part costs
o Getting estimates from local contractors
• Including maintenance cost in the cost analysis
• Research additional energy conservation solutions
o Renewable energy (e.g. wind, solar, etc.)
o Plug loads and better user policies
20
Deliverables
• A final report documenting results, analysis details, and all supporting data.
• A single spreadsheet with linked sheets and cells
o A brief user manual
o Areas to change attribute rankings
o A single sheet to change all calculation parameters including assumptions, parts
and labor costs
o A summary of all solutions
o A building-wide summary of each solution
o Supporting calculation sheets
• A website available for external access, describing the project and providing
to project proposal, final report, and final presentation.
21
Acknowledgement
Special Thank You!
Sponsor - Shepherd University
• Mr. Eric Shuler
• Mr. Dustin Robins
George Mason University - SEOR Department
• Dr. Kathryn Laskey
22
Questions
23
Backup Slides
24
Management Information – Roles
Omed Amin
• Project Management (Schedule)
• Data Analysis
• HVAC Cost Analysis
• Decision Analysis
Chris Hardy
• Communications Management
• Data Analysis
• Building Envelope Cost Analysis
• Website Development
Kathleen Yan
• Project Management (Deliverables)
• Data Analysis
• Lighting Cost Analysis
• Decision Analysis
25
Management Information – Schedule 26
Management Information – EVM Chart27
Overall, we are on scheduled as planned.
Calculating LED Cost Savings28
Provided Data:
• East campus building profile
• Lightbulb type, wattage
usage, counts, LED
replacements in each
building
Marketing Research:
• Parts & labor cost for each
lightbulb type
• LED and old lightbulb
lifecycle
• Electricity Cost
• Long term interest discount
rate
Assumptions:
• Building operational hours per
day, days per year
• Percent of lightbulbs in each
building
Old & LED lightbulb
wattage usage per
building by type
LED annual
energy savings
per building
Old & LED lightbulbs
installation &
replacement cost per
building by type
Old & LED lifecycle
per building based on
usage 20-yr LED cost
savings on East
Campus
LED initial
installation cost
LED & Old 20-yr
replacement cost
Payback period
20-yr net cost
saving in present
value per building
Cost Analysis – LED29
Building NameImplementation
Cost ($)
Payback
Period (yr.)
Annual Utility
Savings ($)
20-year Cost
Saving ($)
Product
Lifetime (yr.)
Boone Field House $28,198 15.45 $1,261 $45,082 23.81
Byrd Center $147,669 8.63 $11,926 $404,475 14.17
Dining Hall $31,912 8.21 $2,609 $138,853 10.20
Entler Weltheimer House $15,695 6.49 $1,588 $77,154 10.20
Erma Ora Byrd Hall $73,097 13.14 $4,118 $167,444 12.15
Facilities Management $13,044 5.55 $1,577 $64,988 10.20
Gardiner Hall $45,032 5.23 $6,266 $164,715 12.96
Human Resources $9,965 8.16 $816 $30,112 13.89
Ikenberry Hall $43,959 8.16 $3,600 $132,831 13.89
Kenamond Hall $38,895 4.04 $6,847 $172,270 12.96
Knutti Boiler House $1,620 6.42 $211 $4,858 10.20
Knutti Hall $66,458 7.54 $6,051 $241,539 12.15
McMurran Hall $10,237 8.16 $838 $30,934 13.89
Reynolds Hall $9,194 7.43 $852 $33,350 12.15
Scarborough Library $70,009 6.04 $8,156 $309,762 10.20
Synder Hall $30,879 8.55 $2,470 $109,985 12.15
Student Center $52,680 6.43 $5,547 $245,145 10.20
Stutzman-Slonaker Hall $51,965 7.94 $4,360 $198,749 12.15
Turner Hall $49,176 8.28 $4,328 $138,419 12.96
White Hall $50,270 7.60 $4,333 $200,928 12.15
Total/Average $839,955 10.80 $77,754 $2,911,594 13
Cost Analysis – Occupation Sensors30
Cost Analysis – LED + Sensors31
Cost Analysis – HVAC 32
Building NameImplementation
Cost ($)
Payback
Period (yr.)
Annual Utility
Savings ($)
20-year Cost
Saving ($)
Product
Lifetime (yr.)
Boone Field House
Byrd Center
Dining Hall $13,200 0.49 $13,537 $212,192 20
Entler Weltheimer House
Erma Ora Byrd Hall
Facilities Management
Gardiner Hall $13,200 0.34 $19,412 $310,009 20
Human Resources
Ikenberry Hall $13,200 0.49 $13,399 $209,893 20
Kenamond Hall
Knutti Boiler House
Knutti Hall
McMurran Hall $13,200 2.07 $3,195 $39,989 20
Reynolds Hall
Scarborough Library
Synder Hall
Student Center
Stutzman-Slonaker Hall
Turner Hall
White Hall
Total/Average $52,800 1.07 $49,544 $772,083 20
Cost Analysis – Reflective Roof Painting33
Building NameImplementation
Cost ($)
Payback
Period (yr.)
Annual Utility
Savings ($)
20-year Cost
Saving ($)
Product
Lifetime (yr.)
Boone Field House $24,965 26.11 $956 -$9,046 30
Byrd Center $78,400 8.50 $9,218 $75,083 30
Dining Hall $100,800 102.86 $980 -$84,483 30
Entler Weltheimer House
Erma Ora Byrd Hall $48,082 15.32 $3,138 $4,163 30
Facilities Management $27,440 163.31 $168 -$24,642 30
Gardiner Hall $46,614 27.75 $1,680 -$18,643 30
Human Resources $14,560 110.67 $132 -$12,370 30
Ikenberry Hall $33,600 86.04 $391 -$27,098 30
Kenamond Hall
Knutti Boiler House
Knutti Hall $78,400 44.30 $1,770 -$48,934 30
McMurran Hall $15,120 27.02 $560 -$5,804 30
Reynolds Hall $10,640 20.96 $508 -$2,187 30
Scarborough Library $128,800 102.75 $1,254 -$107,930 30
Synder Hall $44,800 13.02 $3,442 $12,504 30
Student Center $89,600 19.69 $4,550 -$13,837 30
Stutzman-Slonaker Hall $56,000 133.18 $420 -$48,999 30
Turner Hall
White Hall $56,000 20.73 $2,701 -$11,027 30
Total/Average $853,821 26.79 $31,867 -$323,250 30
Cost Analysis – Energy Efficient Windows34
Building NameImplementation
Cost ($)
Payback
Period (yr.)
Annual Utility
Savings ($)
20-year Cost
Saving ($)
Product
Lifetime (yr.)
Boone Field House $44,580 31.23 $1,427 -$20,816 25
Byrd Center $280,185 20.36 $13,762 -$51,057 25
Dining Hall $115,840 79.18 $1,463 -$91,482 25
Entler Weltheimer House
Erma Ora Byrd Hall $171,725 36.66 $4,684 -$93,731 25
Facilities Management $49,330 196.66 $251 -$45,154 25
Gardiner Hall $166,475 66.38 $2,508 -$124,718 25
Human Resources $25,990 132.33 $196 -$22,720 25
Ikenberry Hall $114,650 196.66 $583 -$104,943 25
Kenamond Hall
Knutti Boiler House
Knutti Hall $177,495 67.18 $2,642 -$133,507 25
McMurran Hall $26,700 31.96 $835 -$12,792 25
Reynolds Hall $24,225 31.96 $758 -$11,606 25
Scarborough Library $368,005 196.66 $1,871 -$336,849 25
Synder Hall $104,610 20.36 $5,138 -$19,063 25
Student Center $249,030 36.66 $6,793 -$135,926 25
Stutzman-Slonaker Hall $123,450 196.66 $628 -$112,998 25
Turner Hall
White Hall $147,825 36.66 $4,032 -$80,686 25
Total/Average $2,190,115 46.04 $47,573 -$1,398,049 25
Cost Analysis - Air Sealing with Caulking35
Cost Analysis – Air Sealing with Weatherstripping36