COST ANALYSIS COST MANAGEMENT BASICS
Feb 25, 2016
COST ANALYSISCOST MANAGEMENT BASICS
Agenda
• Cost Estimating• Types of Cost• Normalization and Inflation• Risk Assessment• Cost Estimating Methods• Labor Costing• Optimization• Statistical Analysis• Tools
2
Cost Estimating
3
Cost:• The monetary representation of resources used or sacrificed, and
liabilities incurred to achieve an objective– Example:
The resources expended in acquiring or producing a good The resources expended in performing an activity or service
Cost Estimating: • The process of collecting and analyzing data and applying quantitative
models, techniques, tools, and databases to estimate the future cost of an item, product, program, or task
Cost and Cost Estimating Definition
4
Cost estimating is thought by some to be difficult, but the skills and knowledge are logical and straightforward.
• Enable managers to:– Make resource-informed decisions– Develop and defend budgets– Identify specific cost drivers– Improve cost controls
• Translate system/functional needs associated with programs, projects, proposals, or processes into costs
• Determine and communicate a realistic view of the probable costs, which will be used to inform the decision-making process.
Purpose of Cost Estimating
5
• Well documented – Includes source data and its significance– Clear and detailed calculations and results– Contains explanations for choosing a particular method or reference
• Comprehensive – Ensures a level of detail where cost elements are neither omitted nor
double counted
• Accurate – Avoids bias and overly conservative or optimistic estimates– Bases its assessments on most likely scenarios and assumptions
• Credible– Discusses any limitations of the analysis deriving from the uncertainty/bias
of the data or assumptions
Characteristics of a Good Cost Estimate
6
• Sunk Costs• Opportunity Costs• Marginal Costs• Average Costs
Types of Cost
7
Example: Paul is assembling his new home theatre system. He has spent 5 hours thus far and estimates he will complete the assembly in 2 more hours. Joan informs him he is doing it the hard way and describes a simpler approach which will take one hour to undo his
work and re-assemble the system.
7
Sunk Costs
• Costs that have already been incurred and cannot be changed no matter what action is taken in the future are called Sunk Costs
Opportunity Costs
Example: The opportunity cost of accepting a job is forgoing the opportunity to do something else with
our time If our best alternative to working is playing golf the
opportunity cost of working is the forgone opportunity of playing golf
If the opportunity to play golf has a value greater than the benefits of working we will choose to play golf
8
• The size of a foregone opportunity of using a resource is the Opportunity Cost
Marginal Costs
10
• Marginal Costs are the costs to produce one more additional unit or output
• The slope of the ‘Total Cost Curve’ at any given level of production is the marginal cost for one more unit
• Marginal costs are highest at very low output rates and at output rates near capacity
Marginal Costs
Output
Total (£)
Total cost
High marginal costs
A
CHigh marginal costs
BLowest marginal costs
10
Average Costs
• Average Cost is calculated by dividing the total cost by the total units produced
• Average Cost is very high at low levels of output
13
Definition: Factors, activities, or events that cause costs to be incurred Usually can be quantified/measured - e.g., number of hours spent on a
task, supported population Analyst should identify and focus on the primary cost drivers that affect
total cost Helps to ensure the accuracy and reliability of the cost estimate Makes it easier to control costs within the organization
Examples: The labor cost associated with assembling a HMMWV at a the factory would
be driven by the quantity of vehicles produced Energy consumption at the PX is driven by the square footage of the
building and the operating hours The cost of printing budget documents for the Office of Management and
Budget is driven by the number of pages in each set and the number of sets needed
Cost DriversOrganizations perform work activities to
deliver products/services to a stakeholder
Types of Analyses Used in Army Decision-Making
14
EA Economic Analysis
AoA Analysis of Alternatives
BCA Business
Case Analysis
CBA Cost Benefit
Analysis
Comparative Analyses Supporting Resource Informed Decision
AoA is an OSD MDAP required analysis in support of acquisition requirement decision at early program concept phase MS-A with an update at MS-B decision.
AoA is a formal and elaborate study that in addition to the program life cycle, often includes an operational model done by TRADOC for the Army ASARC and OSD DAB decisions.
EA is an OSD MAIS required analysis in support of investment decision at early IT/ERP program concept phase MS-A with an update at MS-B decision.
EA is also required by the Army CoE in support of Military construction decision.
CBA is an Army required analysis for all new and existing initiatives at resource decision forums with cost of $10M or more.
CBA for Army HQ decision is developed by the initiative advocate and reviewed by the CBA-RB . AMC and TRADOC also have similar process for their internal resource decisions.
BCA is an OSD MDAP required analysis at post production phase in support of Performance Based Logistics (PBL) Contractor Logistic Support (CLS) vs. organic O&S decision. Risk analysis is an essential component of BCA.
BCA term is often synonymous with CBA for non-PBL analysis.
(MDAP) Major Defense Acquisition Programs
(MAIS) Major Automated Information System programs
15
Break-Even Point:• Used when a given alternative has a significant investment
cost but is expected to experience cost reduction in future years
Break-Even Point
16
This is also where (in current dollars):savings = investment
Cost Reduction = Upfront Investment
Summary of Break-Even Point:- It’s the year where the savings become positive.- Using inflation indices, constant dollars are converted into current dollars.- Savings are the difference between cumulative costs.
Example - Break-Even Point
17
Internal Rate of Return (IRR)• The annualized effective compounded return rate • Rate where the present value of cash inflows is equal to the present value of cash outflows• IRR = (FV/PV)1/N -1
18
Net Present Value (NPV):• The difference between the present value of cash inflows
and the present value of cash outflows– Used to analyze the profitability of an investment
• This works only if values, costs (outflows), and benefits (inflows) are quantified into monetary terms
Net Present Value
19
Net Present Value Formula
Net Present Value (NPV):• The amount of dollars that would have to be invested
during the base year at the assumed discount (interest) rate to cover the costs, match the revenues, or match the savings at a specific point in the future
20
NPV = PV (benefits) – PV (costs)
Cost Estimating in EA
Must consider the “Economic Life”• Period of time over which the benefits to be
gained from a project may reasonably be expected to accrue. Benefits are limited by the equipment or facility’s physical and technological life
• Measured against a stipulated level of threat, or represent a period during which a given mission or function is required or can be supported
21
Total Life Cycle Cost (LCC)• The sum of all costs required to research, develop, test, procure, field, operate, sustain, and dispose a system • A planning number that often differs from the sum of budgeted amounts allocated towards or in support of a particular system
22
Investment Multiples/Ratios• Ratios compare the profits or savings of an investment cost to illustrate the relativity of cost and savings• S/IR = OPERATING COST SAVINGS
COST OF INVESTMENT• If S/IR > 1, then positive investment
23
Business Cases Analysis (BCA): Key Questions
Is the proposed solution:
1. Financially Viable (Make Economic Sense)
2. Optimal (Best Value or Increased
Effectiveness)
3. Feasible (Assessing Constraints)
4. Implementable (Risks & 2nd/3rd Order Effects)
24
Within the Department of the Army, one major process which incorporates cost analysis is Cost Benefit Analysis (CBA)
Cost Benefit Analysis (CBA)
25
Cost-Benefit Analysis:• Is a structured methodology used to identify alternative
solutions to a problem, determine the costs and benefits of each alternative, define the appropriate decision criteria, and select the best alternative
• Produces a strong value proposition – a clear statement that the benefits outweigh the costs and risks.
• In Basic Terms:1. Define a problem or opportunity2. Identify alternatives3. Determine their costs and benefits4. Evaluate and select the best alternative
What is a CBA?
26
Purpose:• Supplement (but not replace) professional experience,
subject matter expertise, and military judgment with rigorous analytical techniques
• Make best possible use of constrained resources• When making resource decisions:
– Ensure that all decisions are resource-informed– Treat cost as a consideration from the outset, not as an
afterthought– Understand how much benefit will be derived– Identify billpayers– Consider second- and third-order effects
Why Do We Need CBAs?
27
• In any organization, “culture” is the beliefs and principles that guide the behavior of the people in that organization.
– Example: The Army’s military culture is based on mission accomplishment, selfless service, valor, and dedication. These concepts establish the foundation for how Soldiers and Civilians go about their duties.
• In a cost culture:– Cost is an integral part of every decision– Soldiers and Civilians strive to find better and more cost effective ways to operate the
Army enterprise– Leaders at all levels engage in cost control and management activities, which are
supported by talented cost staffs
CBA and the “Cost Culture”
28
CBA is part of a high-priority initiative to inculcatea cost culture throughout the Army.
BENEFITS The total of
quantifiable and non-quantifiable benefits
Quantifiable benefits Cost Savings Cost Avoidances
Non-Quantifiable benefits Greater capability Faster availability Better quality Improved morale Other?
CBA – Using analysis to make the case for a project or proposal:
Weighing the total expected costs against the total expected benefitsover the near, far, and lifecycle timeframes from an Army enterprise perspective
BENEFITS MUST BALANCE OR OUTWEIGH COSTS
Cost Benefit Analysis
COSTS Quantifiable costs
Direct Indirect Initial/Start up Sustainment Procurement
Non-Quantifiable costs Life/Safety/Health Perception/Image Opportunity Risk/Uncertainty Political 8. Report Results and Recommendations
7. Compare Alternatives
6. Define Alternative Selection Criteria
5. Identify Quantifiable and Non- Quantifiable Benefits
4. Develop Cost Estimate for each Alternative
3. Define Alternatives
2. Define the Scope; Formulate Facts and Assumptions
1. Define the Problem/Opportunity
29
CBA is NOT a Linear Process
30
Objective
Assumptions
Alternatives
SelectionCriteria
CompareAlternatives
Recommendation
Cost EstimatesBenefits
Estimate
Sensitivity Analysis
• At any step in the process, the team’s findings and analysis might make it necessary to revisit previous steps
• Significant findings might require asking the decision maker for revised guidance
Normalization and Inflation
31
• Adjusting for inflation is a specific form of normalization, an adjustment intended to make a given data set consistent and comparable with other data sets
• A frequent use of simple normalization is to adjust based on quantities. For example:– In a manufacturing process, COA 1 produces 17,000 widgets per
year at a total cost of $33,765 and COA 2 produces 14,500 widgets at a total cost of $28,725. It’s difficult to evaluate these COAs unless we normalize by computing a unit cost, which shows us that COA 2, with a unit cost of $1.95 per widget, is preferable to COA 1, which has a unit cost of $1.99.
Normalization and Inflation
32
What is Inflation?
33
Of all the topics discussed in cost analysis, none will be encountered more frequently than inflation
Definition• A rise in the general level of prices• Measure of change in the dollars’ purchasing power• In other words:
• A given dollar amount will have less buying power next year than it does this year
• To maintain consistent buying power, we must adjust this year’s dollars with the inflation factor from year to year
Common methods for normalization:• Discounting• Constant (Base) Year
• Basic calculations:– (Constant Dollars) * (Inflation Factor) = Current (Dollars)– Inflation is compounded from year to year (i.e., multiplied, not
added).• Example: A loaf of bread in 1950 cost $0.25. Today, in 2012, it costs
$3.00.
Inflation Calculation and Examples
34
• Data: We’ve calculated the annual cost for a given COA in FY12 constant dollars:– Civilian personnel: $145,000– Contract support: $100,000 (paid by OMA appropriation)
• Applicable inflation factors:– Civilian personnel: 2% per year– OMA appropriation: 3% per year
• Calculation for the first three years of the life-cycle:
Example—Current Dollar Calculation
35
Cost Element
Const. Dollar Cost
Infl. Factor
Current- Dollar Calculation Current-Dollar Cost
FY12 FY13 FY14 FY12 FY13 FY14
Civ per 145,000 2% 145,000 145,000 * 1.02
145 * 1.02^2
145,000 147,900 150,858
Contract 100,000 3% 100,000 100,000 * 1.03
100,000 * 1.02^2
100,000 103,000
Total cost
245,000 245,000 250,900 256,948
Risk Assessment
36
The goal of risk assessment is to answer questions like:• What risks may occur? • What is the likelihood that risks will occur? • Are the source of these risks internal or external? • What causes these risks? • What are the consequences if the risks go unresolved?
– What assets, operations, activities, functions, etc. will be affected as a result?
• How much risk is tolerable? • What should be done to anticipate and limit risks?
Risk Assessment and Mitigation
37
Always measure the risk by the potential adverse impacts on alternatives.
Business/Programmatic Risk:• Affects the budget and viability of a programOperational Risk:• Affects the ability to perform a missionProcess Risk:• Associated with failing to meet standards and performance benchmarks in a
newly established processTechnical Risk:• Associated with failing to develop or implement technologySchedule Risk:• Associated with allocating time to perform and manage tasksOrganizational Risk:• Associated with management changes
Types of Risks
38
• Methods of measuring and/or addressing risk include, but are not limited to:
– Effective Mean– Cost of Risk Mitigation
Ways to Measure/Address Risk
39
• The effective mean, or expected value, of a measurable quantity is the sum of all possible outcomes multiplied by their corresponding probabilities
• Example: if the cost of a new ground combat vehicle is judged to be $1.4M with 50% probability, $2M with 25% probability, and $1.2M with 25% probability, then the effective mean (expected cost) is $1.4M x 0.5 + $2M x 0.25 + $1.2M x 0.25 = $1.5M.
• Example: if inter-theater transit time for a sustainment brigade is projected to be 5 days with 90% probability and 4 days with 10% probability, then the expected transit time is 5 x 0.9 + 4 x 0.1 = 4.9 days.
Effective Mean (Expected Value)
40
Cost of Risk Mitigation
41
If a cost can be associated with reducing risk, then risk can be measured by that monetary value.
Example: If for $22K extra, the risk of a schedule over-run can be reduced from 15% to 3%, then $22K can be a measure for the difference in risk.
• Use authoritative data sources• Ensure that cost estimates support “apples-to-apples”
comparison among COAs• Ensure the cost estimate is well-documented,
comprehensive, accurate, and credible• Constant vs. current dollars
– Use constant (un-inflated) dollars for even comparison for COAs in CBAs
– Convert estimate to current (inflated) dollars to determine POM/budget resourcing requirements
Cost Estimating Principles and Rules
42
43
Cost Estimating Methods
Available methods:• Analogy
• Parametric
• Engineering
• Actual Cost
• Expert Opinion
• Learning Curves
Available Cost Estimating Methods
44
Most CBAs utilize all cost estimating methods
Cost Estimating Methods
Parametric
Analogy
Actual Costs
Engineering
GROSS ESTIMATES DETAILED ESTIMATES
45
The use of each method is based on the information available to support it.
Figure 1: A summary of the usual application of each technique.
Analogy Method
46
• Estimates the cost, based on historical data, of an analogous system or subsystem
• Utilizes a current fielded system that is similarly designed to the proposed system
• Adjusts historical cost of the current system to account for differences– Adjustments should be made through parameters/scaling
factors based on quantitative data These adjustments should show validity of comparison
When is it used?• When an analogous case (that can be applied to a
subsystem or component level) exists
Attribute Old System New SystemEngine: F-100 F-200Thrust: 12,000 lbs 16,000 lbsCost: $5.2M ?
Q: What is the unit cost of the F-200?
A: $5.2M * (16,000/12,000) = $6.9M
Warning 2: An adjusted analogy is, by definition, estimating outside the
range of the data.
Warning 1: An adjusted analogy is
like a regression, but the slope is just a
guess.
47
Analogy Method Example
Parametric Method
• Uses regression or other statistical methods to develop a cost estimating relationship based on observed patterns of how specific parameters influence total cost
• Utilizes:• High-level ‘Work Breakdown Structure’ (top down approach)• A database from elements of one or more systems
When is it used?• Historical data is available but not detailed• In earlier stages of the system or project life cycle
48
Parametric Method Example
49
Cost of Gross Curb Cubic Ft Net Vehicle First Unit Weight Weight Shipping Horsepower M274 $ 9,585 1,770 970 81.6 12.5M561 50,002 8,363 5,363 732.3 93M656 93,262 24,785 14,785 1,227 183 M520 147,889 36,590 10,500 2,368 176
High Mobility Wheeled Vehicles Database
Is ‘Cubic Ft Shipping’ a good predictor of cost?
Parametric Method Example (Cont’d)
0
50000
100000
150000
200000
0 500 1000 1500 2000 2500
Cost
of F
irst U
nit (
$K)
Cubic Feet of Shipping
Cost of First Unit vs. Shipping Capacity
We can estimate the cost of any vehicle given the shipping capacity using the above equation.
50
Cost of First Unit = 60.992 * (Cubic Shipping Feet) + 7,957.2
Engineering Method
51
• Breaks down the system of interest into lower level components, each of which is estimated separately– Work Breakdown Structure
• Uses algebraic equations (bottom up approach)– Most detailed of all techniques
• Requires extensive knowledge of a system’s characteristics and the respective detailed data
• Is expensive and time consumingWhen is it used?• All potential costs can be assumed or estimated
Types of Army data sources (AMCOS Lite, MILCON, SRM, historical ,execution, travel, etc.)
• What the WBS does:– Ensures that all component elements are identified so that all costs are
counted only once– Provides a systematic, standardized way to collect data
• Decompose to as many levels as needed• Example: The airplane cockpit can be decomposed into its
subelements:– Instrument panel
• Primary flight instruments– Directional gyro– Turn and bank indicator– Altimeter– Airspeed indicator
• Avionics controls– Communications– Navigation– Radar
Developing the WBS
52
– Flight control systems• Rudder pedals• Steering yoke• Trim tab controls
– Seats• Seat and shoulder belts• Cushions• Head rest
… and so on
A well-decomposed process flowchart that defines/describesthe COA is a useful tool in developing the WBS
WBS – Another Example
53
Actual Cost Method
54
• If historical costs from experience or trends from prototypes, engineering development models, and early production items are available, they can be used to cost current goods or services
• Extracts costs that were actually incurred on same system during an earlier period– Obtaining access to these actual costs may be difficult
When is it used?• The actual data from the same system is present
Actual Cost Method Example
a. The development process is nearing completionb. The materials have all been procured at a cost of
$20Mc. The labor cost to date is $30Md. According to earned value cost performance
reports (CPRs), the estimated cost at completion for the remainder of the labor is another $20M
55
Cost = $20M + $30M + $20M = $70M
Expert Opinion Method
56
• Obtains opinions from experienced individuals or a group– Documents the source of opinions– Lists attributes of the sources
When is it used?• When availability of data is limited.
Delphi Technique1. Query expert opinion from group
2. Seek expert opinion from each group, and then summarize results to send in reports
3. Gather another opinion and summarize those results
4. Continue process until experts reach a consensus
1. You hold interviews to explain the Stakeholders’ needs, sizing level, and development process for your new system
2. Each member of the group submits his/her opinion of the final cost
3. If all expert opinions converge to, or hover around the same figure, that may be taken as a good cost estimate
Expert Opinion Method Example
57
Scenario: Three software engineers are recognized experts in ERP software
development
Forecasting: What is Forecasting?
• Process of predicting a future event
• Underlying basis of all business decisions
• Production• Inventory• Personnel• Facilities
??
62
Personnel Costing
59
Personnel Costing
• Labor is expensive and typically accounts for the majority of costs incurred
• Example: when you get your car repaired, labor typically accounts for 70-85% of the bill
60
AMCOS
• AMCOS is the principal tool cost analysts use for labor costing and it can be found at:
https://www.osmisweb.army.mil/amcos/app/home.aspx• Costs are shown for military, government
civilian, and private sector civilian workers• Costs are most detailed for military, and the least
detailed for private sector civilians
61
AMCOS
62
AMCOS
63AMCOS ApplicationsAMCOS lite
GFEBS Payroll vs. Labor
64
Optimization
65
What is optimization?
• Optimization is about achieving the maximum or minimum possible result
• Example: If you have 20ft of fence to make a rectangular garden, what is the maximum sized garden you can make? The answer is a square with each length measuring 5ft.
66
• U.S. Army Central Command has secured $198M for the procurement of two different models of the “HIMARS 2” multiple rocket launcher—class X and class Y—for deployment to Afghanistan.
• The class Y HIMARS 2 costs $9M each and weighs 27,000 pounds.
• The class X HIMARS 2 costs $11M and weighs 12,000 pounds.
• After procurement, all the HIMARS 2 will be transported to Afghanistan by a fleet of C-130 Hercules aircraft, each with a total maximum payload of 405,000 pounds.
Example: Finding Optimal Solutions
67
1. How do you maximize the total number of HIMARS procured?
2. If you buy only Class X, you can afford 18.3. If you buy only Class Y, you can carry 15.4. So is “buy 18 Class X HIMARS” the optimal
solution?
Example: Finding Optimal Solutions
68
Example: Finding Optimal Solutions
69
COA 1 (Status Quo)
COA 2
COA 3
COA 4
• You can procure 9 Class X and 11 Class Y HIMARS, for a total of 20.
• Moral of the exercise: analysis is sometimes necessary to determine the optimal solution.
Example: Finding Optimal Solutions
70
Statistical Analysis
71
Statistical Analysis
a m bMeanTime
Beta distribution
a m bMeanTime
3σ 3σ
Area under curve between a and b is 99.74%
Normal distribution
78
Statistic Analysis Applications
• Statistics is the study of the collection, organization, analysis, interpretation and presentation of data
• One application of statistics is the U.S. Census. It seeks to understand some details (such as income, gender, marital status) of people living in the country
73
Statistical Analysis Standard Terms
• Probability: likelihood of an event occurring (expressed as a value between 0 and 1, e.g. 0.63)
• Average/mean: the sum of a list of numbers divided by the size (amount of numbers) of the list
• Mode: the most frequent appearing or most likely to be drawn quantity
• Variance: (1/N)*∑(xi-average)2
• Standard deviation: square root of variance
80
Statistical Analysis Example
• A data set consists of the values 6.5, 6.5, 0.2, 4.0
• The mean is (6.5+6.5+0.2+4.0)/4=4.3• The mode is 6.5• The variance is (1/4)*((4.3-6.5)2+ (4.3-6.5)2+
(4.3-0.2)2+ (4.3-4.0)2)=6.6• The standard deviation is sqrt (6.6)=2.6
81
Understanding likelihood of occurrence
• How likely an event is to occur is expressed in probability– Example: if you roll a fair die, you have a 1/6 chance of
getting a particular number since the die is 6-sided• In the case of dice, there are 6 possible outcomes (which
is finite). Sometimes there may be infinite outcomes • What is the likelihood of leaving work at exactly 5pm?
(not being even one billionth of a second over or under)• For cases like this in which there are infinite outcomes
(i.e. you may leave one millisecond over, two milliseconds over, 5 microseconds under, etc.) you need to use probability densities
82
Quantifying Cost Risk
• Statistics can be used to quantify risk associated with costs
• We may ask, what are the odds of the costs being significantly under or above the target?
77
Cost Risk and Schedule Example
• Example: Let’s say the cost to construct a building is expected to be approximately $3,000,000 if completed on time and every month delay in completion adds $23,000 to the cost, and every month the building is completed in advance saves $23,000.
• There is a 20% chance the building is completed on time, a 20% chance of being one month late, a 20% chance being two months late, a 20% chance being one month early, and a 20% chance being two months early.
• What is the likelihood of paying no more than $2,977,000 for the building?
78
Solution to Example
• $2,977,000 is the amount paid if the building is one month early. Thus, if we seek to pay no more than this, we must finish the building one month ahead of schedule (at the latest). In other words, we can finish one or two months early.
• There is a 20% chance of being one month ahead of schedule, and another 20% chance of being two months ahead of schedule, so the answer is 20%+20%=40%
79
The “normal/Gaussian/bell-curve” distribution
• A probability density function shows the likelihood of an event occurring.
• The height of the curve corresponds to the likelihood of an event occurring.
• Perhaps the most commonly used probability distribution is the normal distribution.
• Given two points on the x-axis, the area under the curve bounded by these points is equal to the probability that a value within those bounds will occur
• The average and mode are given by the x-coordinate corresponding to the curve’s peak.
Probability of meeting the schedule is 0.8078
Normal distribution:Mean = 69 weeks;σ = 3.45 weeks
Probability of exceeding 72 weeks is 0.1922
Project duration (weeks)69 72
• Consider the normal curve below:– The x-axis shows project duration in weeks. – The peak of the curve occurs at week 69. Week 69 is also the average project duration (which is
intuitive due to the symmetry of the curve). – The purple shaded area represents the probability of having project duration of at least 72 weeks.– The blue shaded area represent the probability of having a project duration less than 72 weeks.
• Probability distributions, especially probability densities, are often used to quantify risk in cost estimating and in other fields
86
Variances
• Statistically, how far a set of numbers is spread out or distributed
• In the context of budgeting or cost estimation, a variance is the difference between an actual and an expected (budgeted) amount.
87
Variances
• Further analysis decomposes (breaks down) the variance analysis into progressively smaller components answers: “How much were we off?”
• Examination of variance into progressively more-detailed levels of analysis answers: “Where and why were we off?”
90
Variances Basic Concepts
• Static-Budget Variance (Level 0): the difference between the actual result and the corresponding static budget amount
• Favorable Variance (F): has the effect of increasing operating income relative to the budget amount
• Unfavorable Variance (U): has the effect of decreasing operating income relative to the budget amount
88
Variance Analysis
• VAR (X) = E [(X - µ)2]• Continuous random variable
• Discrete random variable
• Normal distribution
89
85
Tools
Available Tools and Models for Cost Data
Tool/Model URL PurposeFORCES Cost Models https://www.osmisweb.army.mil/forces/login.aspx Suite of models that provides quick
and reasonable unit cost estimates to a wide variety of users
Army Military-Civilian Cost System (AMCOS)
https://www.osmisweb.army.mil/amcos/app/home.aspx
Personnel costs for military, civilian, and/or contractor
ASA(FM&C) Website http://asafm.army.mil/Documents/OfficeDocuments/CostEconomics/rates/indices.xls
Inflation indices
Capabilities Knowledge Base
http://asafm.army.mil/Documents/officedocuments/costeconomics/guidances/ckb-ui.pdfhttp://asafm.army.mil/offices/CE/Ckb.aspx?OfficeCode=1400
Research, development, and acquisition costing for major weapon/material systems
Operating and Support Management
Information System (OSMIS)
https://www.osmisweb.army.mil/osmisrdb/login.aspx
Operating and support information for major weapon/material systems
Some of the websites listed here require user accounts. In most cases, anyone with a dot mil address can obtain an account. You are encouraged to scan these sites and request an account to any site that you think will be useful to you. This will save time when you need to use any sites to support a CBA or other
projects.
86
Access links through the “Resources” tab in the CBA Portal at:https://cpp.army.mil
Conclusion
87
88
Overhead Variances
• Overhead is the most difficult cost to manage, and is the least understood
• Overhead variances involve taking differences between equations as the analysis moves back and forth between actual results and budgeted amounts