Page 1: Core-CT Assessment Final Report

Final Report – February 2, 2007

State of ConnecticutCore-CT Assessment Final Report

February 2, 2007

Page 2: Core-CT Assessment Final Report

2© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Table of Contents

Executive Summary- Project Background page 4- Core-CT Assessment Findings Summary page 9- Recommendations Summary page 13

Core-CT Assessment Recommendation Details- ERP Competency Center page 21- Expanded Steering Committee page 41- Position Classifications page 45- Critical Line Agency Enhancement Requests page 74- Training page 92- Management Reporting page 112

Appendix A - Core-CT Functionality Gaps page 120Appendix B - Core-CT Detailed Staffing Gaps page 126Appendix C - Detailed Initiative Roadmap Timeline page 144

Page 3: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentExecutive Summary

Page 4: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentProject Background

Page 5: Core-CT Assessment Final Report

5© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Objectives

The focus of this study was to provide a high level historical and forward-looking perspective of the Core-CT ERP implementation

Historical Perspective– Where has the State received value?

– Where is the State not receiving full value?

– What key functionality is missing?

– Was the implementation performed efficiently and effectively?

Forward-Looking Perspective– Is there an effective plan in place with adequate

resources for the future use, administration and maintenance of the system?

– What additional steps should the State take to protect its future investments in the system?

Page 6: Core-CT Assessment Final Report

6© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Project Status Draft report delivered electronically on 12/20/06 and was reviewed by

selected State of CT stakeholders. Final report discussed with Executive Steering Committee on 1/29/07. Revised Final report, including results of roadmap exercise conducted on

1/30/07, was delivered electronically on 2/2/07.

Kickoff Data Gathering Analysis

Summary & Recommendation

Development

Summary & Recommendation

Delivery

Reviews

12/6 12/13

Deliver ReportDraft12/20

FinalJan

11/6 11/6 – 11/16 11/13 – 12/6

Page 7: Core-CT Assessment Final Report

7© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Interview Session Participants

Core-CT Team Directors James Shumway (OSC), Cathy Daly

(DAS), Jean Skellett (DOIT), Gale Mattison (OPM)

HRMS Team Leads: Anne North (OSC) & Sue Martin (DOIT)

Financial Team Lead: John Harnick (OSC) Technical Team Leads: Deb Miggins (DOIT),

Angelo Romano (OSC) EPM & Security Team Lead: Mary Yabrosky

OPM Robert Genuario, Secretary Anne Gnazzo, Deputy Secretary John Bacewicz, Executive Budget Officer Barry Sullivan, Assistant EBO

DAS Linda Yelmini, Commissioner Carol Wilson, Director Procurement Services Pam Libby, Human Resources

State Comptroller Nancy Wyman, Comptroller Martha Carlson, Chief of Staff John Clarke, Director Budget and Financial Analysis Mark Aronowitz, Director Accounts Payable Division Gary Reardon, Director Payroll Services Division Dr. Thomas Woodruff, Director Retirement & Benefit

Services Division

Accenture Rick Hegwood & Mark Raymond, Project Directors

Interview participants included Core-CT stakeholders from the State of Connecticut central agencies, line agencies, the Core-CT implementation team members, and executive steering committee members.

Page 8: Core-CT Assessment Final Report

8© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Interview Session Participants (cont)

DOIT Diane Wallace, CIO Eric Linquist, Director Network and Distributed

Systems Suzanne Niedzielska, Director Business

Development

Department of Correction Theresa Lantz, Commissioner, Carol Salsbury,

Deputy Commissioner

Department of Transportation Ralph Carpenter, Commissioner Reanne Curtis, Deputy Commissioner

Department of Education Brian Mahoney, Chief Financial Officer Eugene Croce, Director Karen Chilone, Human Resources

Department of Revenue Services Pamela Law, Commissioner

Department of Mental Retardation Peter O’Meara, Commissioner Vincent O’Connell, Chief Fiscal Officer Karen Davies, Human Resources

Page 9: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentFindings Summary

Page 10: Core-CT Assessment Final Report

10© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Findings SummaryIs the State receiving full value for its investment?

The State of Connecticut has received foundational value from its Core-CT investment,but is not currently receiving full value.

Achieved value is difficult to quantify because no cost baseline or targeted improvement metrics were developed.

The primary stakeholder group for Core-CT was the central agencies. The Core-CT business case focused on: replacing legacy/unsupported applications; creating a single source of consistent and more granular state-wide data; increasing central agency efficiency; and, implementing a standard solution with minimal customizations. The intended goals were achieved. Only approximately 30% or organizations that deploy enterprise applications

achieve their original goals. However, the magnitude of the investment requires additional value to be delivered Enhancement of Core-CT organization, along with selected, incremental investments, will help the State realize full

value On a summary level, the State has not been able to fully leverage Core-CT’s potential benefit because:

the initial implementation was driven almost entirely by milestone dates and limited solution scope the early retirement package/state-wide layoffs of 2003 negatively impacted Core-CT go-live consistent, closed loop communication of decisions, and their impacts, did not occur between the Core-CT team and

the agencies the project under-invested in the areas of organizational change management and process change education the Core-CT team lacks key personnel with some required vital skills

The decision to go live with Core-CT after the layoffs in 2003 increased the risk of the implementation, and impacted the effectiveness of the application that was delivered to the state employees, but was ultimately a positive decision.

Page 11: Core-CT Assessment Final Report

11© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Since the foundation now exists, the State has an opportunity to realize more substantial benefits from a much smaller future investment.

Core-CT Assessment – Findings SummaryIs the State receiving full value for its investment?

Past Implementation Investment

Future Incremental Investment

Received Benefit

Future Benefit

Realized Benefits Improved state-wide Information Central agencies are more effective Common business solutions and practices now exist across the central agencies Service levels to State stakeholders (citizens, State leadership, auditors, etc) have increased Technical risk mitigated

Potential Future Benefits Agency-specific training for more accurate and efficient transaction handling All critical line and central agency functions enabled by Core-CT Improved line and central agency effectiveness and risk management More efficient data access and more effective decision-making through improved analytic

capabilities

Page 12: Core-CT Assessment Final Report

12© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

1 2 3 4 5 6

1: Core-CT team is not a distinct entity. It lacks its own employees, distinct services, efficient support and development processes, and effective governance.

3: Core-CT position classifications do not accurately convey the competencies, qualifications, and responsibilities necessary to support the Core-CT application.

4: Key line agency functionality gaps exist. Interim plans, supported by Core-CT, have not been developed. With no known release strategy, agencies will develop their own solutions.

5: Training effectiveness has been limited and has reduced user ability to benefit from Core-CT functionality.

6: Management reporting has not been a strategic focus. Central and line agencies are not effectively able to access and analyze the data that exists within Core-CT.

2: Line agencies do not have formal representation within the Core-CT steering committee, despite having a vested interest in the success and future direction of Core-CT. Governance processes are ad-hoc and inconsistent.

1: Define a formal and distinct Core-CT ERP Competency Center (CC), within the State agency structure, complete with its own employees, service catalog, reporting structure and efficient processes.

2: Expand the Core-CT steering committee and improve the Core-CT governance processes through expanded line agency involvement.

3: Create new and distinct Core-CT position classifications that effectively outline the unique team-member skill-sets, abilities, compensation, and career path.

4: Prioritize the critical line agency enhancement requests, and enhance the development/ deployment and config/release management capabilities of the Core-CT team.

5: Create State specific training material, develop training technology (computer based training), use business/ technology experts to deliver training within the context of the State agency processes.

6: Implement Enterprise Performance Mgmt (EPM) Analytical functionality & expand EPM team to allow a more strategic focus. Build mgmt reports & queries and make effective training an immediate focus.

Key Findings

Core-CT Assessment – Findings SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 13: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendations Summary

Page 14: Core-CT Assessment Final Report

14© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The Core-CT team is not a distinct unit, with its own employees, that formally belongs to one agency.

The current Core-CT team is comprised of multiple agency personnel who have been pulled from their existing jobs, in many cases with the understanding that they would return once the project was complete.

Managing staff is difficult due to multiple-agency assignments and varying department policies and supervisory rules. Core-CT personnel do not operate under a formal service level agreement framework with their customers and stakeholders. Core-CT team member compensation, goals, and incentives are not tied to Core-CT performance.

Reorganize the Core-CT team into an ERP Competency Center (CC) reporting to OSC with a dotted line to DAS. The Competency Center should be an independent Division or Unit within OSC or an independent agency attached for administrative purposes to OSC.

Eliminate the Director group and establish a clear Director in charge of the CC. Create a clear ERP CC service catalog as the foundation for service level

agreements that will evolve. Create a PMO within the CC to support governance, administrative, and

communications activities Develop and continuously improve governance processes in support of the

ERP CC (see slide later in this document)

Finding: Core-CT team is not a distinct entity. It lacks its own employees, distinct services, efficient support and development processes, and effective governance.

Recommendation: Define a formal and distinct Core-CT ERP Competency Center (CC), within the State agency structure, complete with its own employees, service catalog, reporting structure, and efficient processes.

Core-CT Assessment – Recommendations SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 15: Core-CT Assessment Final Report

15© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The Core-CT project is emerging from an ‘implementation’ phase and is entering a ‘support and enhancement’ phase. The objective of this new phase should be to optimize the foundation.

The existing Core-CT steering committee structure was appropriate for overseeing an aggressive implementation and ensuring that project scope, funding/budgets, and third party partners were effectively managed.

Since Core-CT go-live, line agencies have relied on Core-CT to perform many of their key functions. These line agency stakeholders are disconnected from the governance processes that will dictate how Core-CT supports the agencies in the future.

It has been stated that the existing vision for Core-CT must be revised so that agencies can align their processes more efficiently to the solution.

The purpose and goals of the steering committee must evolve as the Core-CT services shift from milestone driven implementation to enhanced service delivery to all agencies.

The steering committee should be expanded to include additional major stakeholders of the Core-CT application. Line agencies have a vested interest in the evolution of Core-CT and should be formally incorporated into Core-CT governance processes.

Line agencies should play a central role in the following decisions:- Functionality enhancement demand and prioritization; release

management- Funding for desired services- Business process standardization- Training delivery

Finding: Line agencies do not have formal representation within the Core-CT steering committee, despite having a vested interest in the success and future direction of Core-CT. Governance processes are ad-hoc and inconsistent.

Recommendation: Expand the Core-CT steering committee and improve the Core-CT governance processes through expanded line agency involvement.

Core-CT Assessment – Recommendations SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 16: Core-CT Assessment Final Report

16© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

It was stated that: It is difficult to recruit qualified functional/technical staff. Finding IT candidates

with PeopleSoft or ERP skills has been a challenge. Current Core-CT position classifications are outdated. They do not

communicate the required Peoplesoft integrated module knowledge, agency business process understanding, consultative/collaborative skills, or combination of technical and functional analysis skills.

IT compensation plans are inflexible – It is difficult to attract and reward highly valued employees appropriately with respect to the marketplace.

IT work schedules are limited to 35 hours a week. No formal Core-CT career development and succession planning strategy

exists.

Create accurate and meaningful new position classifications, rather than re-classifying existing positions.

Consider creating legislation that would define the Core-CT competency center as an independent unit or division reporting to OSC, paving the way for new job classifications.

Make the Core-CT position salaries competitive in the marketplace. Create a ‘barrier to entry’ for these positions so that only qualified people will

be accepted and those who do not qualify will clearly understand why they don’t qualify.

Solicit union input for any new position classifications.

Finding: Position classifications do not accurately convey the competencies, qualifications, and responsibilities necessary to support the Core-CT application.

Recommendation: Create new and distinct Core-CT position classifications that effectively outline the unique team-member skill-sets, abilities, compensation, and career path.

What additional steps should the State take to protect its future investments in the system?

Core-CT Assessment – Recommendations Summary

Page 17: Core-CT Assessment Final Report

17© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

At the time of go-live, the Core-CT solution did not support key and mandatory line agency functions. (e.g., Federal billing support, 24x7 scheduling).

Line agencies are currently being forced to create manual workarounds or seek other solutions for some key functions that are not supported within Core-CT.

It was stated that success in the past was defined as, “Deploy an application that works”. The future vision of Core-CT must ensure that all agencies are more fully supported by the application or that an alternative solution is deployed.

The Core-CT team has indicated that it lacks the proper resources to implement enhancements in a timely manner.

Leverage an expanded steering committee that has line agency representation to define the long term Core-CT vision.

Prioritize the enhancements that will evolve the current state Core-CT application to meet the future state needs of the agencies.

- Focused effort to deal with areas that have not been a good fit (time & labor, purchasing, federal billing, inventory mgmt, 24x7 scheduling)

Define an acceptable release schedule to meet the needs of the agencies. Reduce maintenance complexity by stabilizing modules on the same release.

Staff the Core-CT team with the appropriate number of qualified full time staff, supplementing with 3rd party resources in the short term if needed.

Demonstrate ability to address line agency concerns – need some “wins” here.

Finding: Key line agency functionality gaps exist. Interim plans, supported by Core-CT, have not been developed. With no known release strategy, agencies will develop their own solutions.

Recommendation: Prioritize the critical line agency enhancement requests, and enhance the development/deployment and config/release management capabilities of the Core-CT team.

Core-CT Assessment – Recommendations SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 18: Core-CT Assessment Final Report

18© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Training material was generic and not specific to agency processes. Application experts delivered the training - not ‘power users’ who understood

how the application did/did not support the State’s business processes. Training technology (i.e. computer based training, help functions within the

Core-CT application) were not effectively developed and/or deployed. The organizational change management effort was reduced and was not a

strategic or consistent focus during the implementation. Change resistance has not been revisited in a meaningful way since Core-CT was deployed.

Inexperienced line agency personnel have struggled to accurately enter increased amounts of data into an application that demands a higher level of business understanding on the part of the user.

Assign a training owner within the ERP CC to focus on a common, but effective way to develop and deliver Core-CT training going forward.

Develop a training strategy that addresses all key training gaps and provides a training solution that will support both existing and new users.

Develop a communication strategy that educates and informs users and keeps them up to date on the most recent training and best practices developments.

Identify super users who have a good understanding of both the agencies’ business processes and the Core-CT application along with the required skills to effectively deliver training. Integrate power users into selected ERP CC governance processes.

Redeploy focused, refresher training to all Core-CT users.

Finding: Training effectiveness has been limited and has reduced user ability to benefit from Core-CT functionality.

Recommendation: Create State-specific training material, develop training technology (computer based training), and use business/technology experts to deliver training within the context of the State agency processes.

Core-CT Assessment – Recommendations SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 19: Core-CT Assessment Final Report

19© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT users do not have the required knowledge to use the Core-CT Enterprise Performance Management (EPM) module for management reporting.

The Core-CT team has not developed, or distributed, canned reports that meet agency needs. There is no consistent and easy process to re-use valuable reports by one agency across all other agencies.

EPM analytical functionality has not been implemented, and is therefore not presently available to end users. Analysis needs to be done outside of the Core-CT solution.

Make EPM a strategic asset, rather than a tactical tool, by heightening its visibility. Re-position the EPM lead position as a strategic, cross-agency role.

Expand and enhance the EPM team by staffing it with qualified technical resources, effective training staff, and business relationship managers whose goal is to understand and communicate agency requirements.

Implement EPM Analytical functionality. Build and deploy management reports and queries and a process to re-use

them across agencies. Communicate new functionality effectively and constantly seek improvement feedback.

Make effective training an immediate focus in order to allow agencies to receive full benefit from the valuable Core-CT data that exists today.

Finding: Management reporting has not been a strategic focus. Core and line agencies are not effectively able to access and analyze the data that exists within Core-CT.

Recommendation: Implement EPM Analytical functionality and expand EPM team to allow a more strategic focus. Build management reports/queries and make effective training an immediate focus.

Core-CT Assessment – Recommendations SummaryWhat additional steps should the State take to protect its future investments in the system?

Page 20: Core-CT Assessment Final Report

20© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Recommendations SummaryRecommendation Roadmap

The Recommendation Details sections describe each of these initiatives in more depth and Appendix A provides a more detailed schedule regarding the activities of each initiative.

2007 2008 2009 2010 2011

Page 21: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsERP Competency Center

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 22: Core-CT Assessment Final Report

22© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Apps Arch &Ops

Support

BusinessProcess

Enablement

InfraSupport

Apps Dev & Integration

Support

End Users

AgencySuper Users

ERPCompetency

CenterProblem

Solution

IT Help DeskORACLEProductSupport

Agency Leadership (Chaired by Comptroller)

Infrastructure• Business process skills• User Group mgmt• Liaison to ERP CC

• CoreCT solution skills• Demand vs. Supply• Standardization/Trng• Release Mgmt

• Level 1

• Business process ownership• Business change leadership• Prioritization of system changes• Funding resolution SLA

Support Development

IT Process Optimization

Business Process Optimization

ERP Environment Optimization

AppsFunctional

Support

UserInterfaceSupport

DOITSLA

SLASLA

StrategicDemand Mgmt

Tactical Demand

Mgmt

Training

Support procedures SLA management and monitoring Application & systems management Configuration management Release management Portfolio management Resource (Supply) management Vendor management and influence

Demand management and prioritization Solution standardization Information management Integration and workflow Best practice knowledge management

Infrastructure optimization Architecture standards and rationalization Master data management Instance strategy Upgrade management Security management Disaster Recovery/Business Continuity Planning

ERP Competency Center (CC)

Core-CT Assessment – Detailed RecommendationTransition to an ERP Competency Center (CC) as a best practices support organization

Page 23: Core-CT Assessment Final Report

23© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

CC

Mat

urity

Time

Initial ERP CC

ERP Product centric & technology focused

Enhanced ERP CC

ERP business solution focused

Enterprise CC

Business process focused

Core-CT Assessment – Detailed RecommendationState of CT Competency Center Evolution Path

Migration Path

The State of CT should evolve from its current product and technology focus to one that provides business solutions in support of agency business processes.

Page 24: Core-CT Assessment Final Report

24© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationState of CT Competency Center Evolution Path

Initial ERP CC

Application functional support

Application development

Application operations

Enhanced ERP CC

Business process enablementand functional support

Application developmentand integration

Application architectureand operations

User education

Page 25: Core-CT Assessment Final Report

25© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationThe value of an ERP Competency Center

10

203040

5060

708090

100% 1st Project

2nd Project

3rd Project

4th Project

5th Project

010

203040

5060

708090

100% 1st Project

2nd Project

3rd Project

4th Project

5th Project

0

Companies with ERP CCs have shown dramatic decreases in external consulting costs as a % of overall project costs.

Those without ERP CCs continue to run in the 40-50% range.

A project could be an upgrade, an implementation of a new module, a need to create a new instance to handle an acquired business, etc.

Support Staff vs Concurrent Users

y = 0.0613x + 5.1754

y = 0.0188x + 20.221

0

50

100

150

200

250

0 1000 2000 3000 4000 5000 6000 7000

Concurrent Users

Supp

ort F

TE's

Without Competence Center

With Competence Center

Companies with ERP CCs have the ability to support many more concurrent users per support full-time equivalent (FTE)

This difference is even more significant as the number of users grows.

Without ERP CC 500 users – 36 FTEs 1000 users – 66 FTEs 2000 users – 128 FTEs 3000 users – 189 FTEs

With ERP CC 500 users – 30 FTEs 1000 users – 39 FTEs 2000 users – 58 FTEs 3000 users – 77 FTEs

Source: Gartner Research 2002

Source: Gartner Research 2002

Page 26: Core-CT Assessment Final Report

26© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

ERP Competency Center Critical Success Factors A strong team with the right skill set

– Balance between business process knowledge, technical knowledge and business interaction

– Must understand and speak with the agencies in their own language People retention Human capital development plan Clear governance Strong process orientation Market the vision and mission of the ERP CC Ability to demonstrate credibility and deliver value

– A service mentality– Gain agency’s trust and support

Core-CT Assessment – Detailed RecommendationERP Competency Center critical success factors - focus on people and process

Source: The SAP Competency CenterGartner Best Practices EXP Research 2006

Page 27: Core-CT Assessment Final Report

27© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

ERP CC Governance Process Input Rights Decision Rights Governance Process Owner

Demand Management – determining which tactical and strategic enhancements to consider.

Agency Leadership Super Users CC Team Leaders

CC Steering Comm. CC Director

CC Team Leaders

Prioritization – determining the priorities of the demand under consideration. Agency Leadership Super Users CC Team Leaders

CC Steering Comm. CC Director

CC Director

Supply Management – determining how to hire, retain, and allocate CC resources to meet prioritized demand.

CC Director CC Team Leaders DAS

CC Director CC Team Leaders

CC Team Leaders

Service Level Monitoring and Measurement – determining services, SLAs and monitoring/measurement processes.

Agency Leadership Super Users CC Team Leaders DOIT

CC Steering Comm. CC Director

CC PMO

Portfolio Management – determining the risk and value of application and project inventories and investments to drive funding decisions.

Super Users CC Team Leaders

Agency Leadership CC Director

CC PMO

Funding – determining how to allocate ongoing and investment dollars within budget constraints.

Agency Leadership CC Team Leaders

CC Steering Comm. CC Director

CC PMO

Vendor Management – determining how and when to engage product and service vendors in the best interests of the State.

CC Director CC Team Leaders Super Users

CC Director CC Team Leaders

CC Director

Knowledge Management – capturing and making accessible key internal and external knowledge objects regarding the ERP solution and its optimal use and evolution.

Super Users CC Team Leaders CC Director

Super Users CC Team Leaders

CC Team Leaders

Release Management – determining how and when to release solution enhancements to benefit the State

Super Users CC Team Leaders CC Director Oracle DOIT

CC Team Leaders CC Director

CC Director

Communications Management – determining how and when to communicate status, plans, and events regarding the ERP solution to manage expectations and enable optimal usage.

CC Director CC Team Leaders

CC PMO CC Director

CC PMO

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Page 28: Core-CT Assessment Final Report

28© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Demand Management governance process

Super Users

CC Team Leaders

What enhance

-ment demand should

we consider

?

Agency Leadership

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Strategic enhancement input from process areas within the CC team leader’s domain

Tactical enhancement requests

Organizes strategic and tactical demand into bundled, logical requests with high level costs and benefits

Ongoing list of requests under consideration

Disposition and rationale communicated for requests not being considered

CC S

teerin

g

Comm

ittee

(Stra

tegic

Req

uests

)

CC Director

Process Owner:CC Team Leaders

Input Rights Decision Rights

Page 29: Core-CT Assessment Final Report

29© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Prioritization governance process

Super Users

CC Team Leaders

What are the

priorities for the

demand being

considered ?

Agency Leadership

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Provides strategic input on bundled demand priorities

Provides operational input on bundled demand priorities

Provides solution feasibility and cost input on bundled demand priorities

Ongoing list of prioritized, tactical enhancements and fixes handled through normal maintenance staff

Prioritized inventory of investment projects across all process areas supported by ERP solution. Typically coincides with planning and budgeting process.

CC Ste

ering

Comm

ittee

CC Director

Process Owner:CC Director

Input Rights Decision Rights

Page 30: Core-CT Assessment Final Report

30© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Supply Management governance process

CC Team Leaders

DAS

How to hire,

retain, and

allocate CC

resources to meet

demand ?

CC Director

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Provides budget, organization/career goals, service level metrics, compensation requirements, and sourcing strategy input

Input on team capacity & skill gaps as well as team member goals and performance

Input on bargaining unit, job classification, compensation guidelines, hiring strategy, retention strategy

CC Tea

mLe

ader

s

CC Director

Process Owner:CC Team Leaders

Input Rights Decision Rights

Hiring decisions Promotion decisions Compensation decisions Re-organization decisions Team member

assignments Preferred 3rd party

partners

Page 31: Core-CT Assessment Final Report

31© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Service Level Monitoring & Metrics governance process

Super Users

DOIT

What services,

SLAs, and

monitoring

processes ?

Agency Leadership

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Desired Services Desired SLAs*

CC Director

Process Owner:CC PMO

Input Rights Decision Rights

DOIT infrastructure services and SLA with ERP CC

ERP CC application services (service catalog) and SLA with agencies

SLA monitoring & measurement processes

CC Team Leaders

Proposed ERP application services, processes, & SLAs*

Desired DOIT services and SLAs

Proposed infrastructure services, processes & SLAs*

* SLA = Service Level Agreement

CC Ste

ering

Comm

ittee

Page 32: Core-CT Assessment Final Report

32© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Portfolio Management governance process

CC Team Leaders

How should we

change our

portfolio of application

s and related

investments ?

Super Users

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Value of existing applications Value of existing investments

to improve apps

Value, risk, cost, and complexity of existing apps

Value, risk, cost, and complexity of investments to improve apps

CC Director

Process Owner:CC PMO

Input Rights Decision Rights

Application migration strategy- Retire- Replace- Upgrade/Enhance

Application investment decisions

- Approve- Reject- Defer- Cancel

Investment Portfolio View- Strategic- Enhancement- Utility- Infrastructure

Agen

cyLe

ader

ship

Page 33: Core-CT Assessment Final Report

33© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Funding governance process

CC Team Leaders

How to allocate ongoing

and investme

nt dollars ?

Agency Leadership

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Budget available for ongoing ERP maintenance

Budget available for ERP investments

Baseline costs for ongoing support

Investment costs for prioritized enhancements

Approved ERP CC maintenance (operating expense) budget

Approved ERP CC investment (capital expense) budget

Typically coincides with planning and budgeting process.

CC Ste

ering

Comm

ittee

CC Director

Process Owner:CC PMO

Input Rights Decision Rights

Page 34: Core-CT Assessment Final Report

34© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Vendor Management governance process

CC Team Leaders

Super Users

How and when to engage product

and service

vendors ?

CC Director

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Requirements Desired SLAs* Preferred 3rd party partners

Requirements Desired SLAs*

Requirements

CC Tea

mLe

ader

s

CC Director

Process Owner:CC Director

Input Rights Decision Rights

3rd Party Sourcing Decisions

Master License and Service contracts

Software orders Service SOWs and orders Product SLAs* Service SLAs*

Page 35: Core-CT Assessment Final Report

35© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Knowledge Management governance process

CC Team Leaders

CC Director

What knowledge should

be captured and how should it

be classified

?

Super Users

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Agency best practices inputs

Improvement suggestions

Solution best practices inputs

Work products and deliverables

Improvement suggestions

Knowledge re-use opportunities

CC Tea

mLe

ader

s

Super Users

Process Owner:CC Team Leaders

Input Rights Decision Rights

ERP best practices ERP work products and

deliverables

Page 36: Core-CT Assessment Final Report

36© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Release Management governance process

CC Team Leaders

DOIT

How and when to release solution

enhance-ments ?

Super Users

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Operational desires & constraints

CC Director

Process Owner:CC Director

Input Rights Decision Rights

ERP release schedule

CC Director

Vendor release schedule

* SLA = Service Level Agreement

CC Tea

mLe

ader

s

Oracle

Solution rqmnts & constraints

Planning

Infrastructure rqmnts & constraints

Page 37: Core-CT Assessment Final Report

37© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Implement Communications Management governance process

CC Team Leaders

How and when to

communicate about and market the ERP CC ?

CC Director

Core-CT Assessment – Detailed RecommendationBuilding governance between the ERP CC and key stakeholders

Status Overall strategy Decisions Events Value messages CC Director

Process Owner:CC PMO

Input Rights Decision Rights

Communications

CC PMO

Status Training Tactical plan Decisions Events Value messages

Page 38: Core-CT Assessment Final Report

38© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Selecting the ideal ERP CC Director

Strong interpersonal skills for communication and presentation

A track record of managing across organizational structures

Experience in managing diverse skill sets

The ability to overcome barriers and handle internal politics

Proven leadership ability

Strong planning skills

Core-CT Assessment – Detailed RecommendationLeading the ERP Competency Center

Source: The SAP Competency CenterGartner Best Practices EXP Research 2006

Page 39: Core-CT Assessment Final Report

39© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Super User Responsibilities Act as first point of contact for end-users within respective agency

departments Act as experts and departmental trainer in relation to agency (master) data,

business ways of working and departmental use of Core-CT solution Communicate with users on “best practices” for use of Core-CT solution Raise functional incident reports as “authorized caller” and serve as contact

person for related follow-up, particularly in relation to emergencies (“severity 1” problems)

Specify user requirements for application changes, as well as participate in design, testing and implementation of such changes

Raise, evaluate and participate in the implementation of proposals on organizational and process changes

Act, when required and requested, as member of the local governance board in representation of the corresponding agency/department and perform other duties as locally agreed

Core-CT Assessment – Detailed RecommendationThe ERP CC needs to leverage a key business stakeholder – the Super User

Page 40: Core-CT Assessment Final Report

40© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationERP Competency Center - Recommendation Action Plan

Define a formal and distinct Core-CT ERP Competency Center (CC), within the State agency structure, complete with its own employees, service catalog, reporting structure, and efficient IT and governance processes.

Benefits

Q1 2007 - Q2 2008 Sponsors: Comptroller, Steering Committee

Execution: Director Group, CC Director

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Hire/Assign CC Director; accountable for CC going forward; create formal CC organization (Who – Nancy/Gale/Steering Committee; When - M1-M6); dependent on legislative action

Build PMO – hire/assign resources (2) and accountability (Who – Directors; When - M1-M3 if hire from within; not until M7-M8 if external)

Create and communicate org chart (Who – CC Director/Directors; When - M3-M6)

Create and communicate role descriptions (Who – CC Director/Directors; When - M3-M6)

Create and communicate governance processes (Who – CC Director/Directors; When - M4-M8)

Assemble ERP CC Charter and gain approval (Who – CC Director/Directors/Steering Committee; When - M6-M9)

Primary Activities

TBD by Service Catalog and SLAs

Dependency on Other Initiatives Ultimate success of CC is highly dependent on ability to

create new and distinct Core-CT position classifications.

Dis-assemble Director Group (Who – Directors; When - M9) Create CC Service Catalog and potential SLA descriptions and metrics

(Who – PMO; When - M7-M9) Document/refine CC processes to support CC services; ensure

alignment with governance processes (Who – PMO/CC Team Leads; When - M10-M15)

Integrate with Core-CT position classifications and transition team members into new classifications (Who - CC Director/DAS) ;When - M9)

- Create clear career paths aligned with new positions

Clear accountability to customer of desired services and metrics. Focused ERP process support efficiencies Lower ERP total cost of ownership (TCO); less reliance on external services Higher business process value delivered. Gain procurement economies of scale with key vendors

Page 41: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsExpanded Steering Committee

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 42: Core-CT Assessment Final Report

42© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The implementation was served well by a Core-CT Steering Committee that was comprised of central agency leadership.

However, lack of line agency representation has created a perspective that Core-CT is a central agency solution whose priorities are driven by central agency demand.

There are two primary reasons that this cannot continue:- The Core-CT solution and supporting information is integrated across all agencies, so the

efficiency and effectiveness of the entire user community is dependent on one another.- The investment in Core-CT will be significantly diluted as line agencies seek control and

features not adequately provided by the Core-CT solution on their own.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 43: Core-CT Assessment Final Report

43© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Expand the steering committee for the ERP Competency Center to include line agency representation, especially where an agency has a significant user base and unique requirements because of their inherent services model that must be supported. Examples would include:

- DOT: projects and federal billing needs must be met better than the current solution- 24x7 Agency representation (e.g., DOC): scheduling and unique labor rules must be met

better than the current solution- Rotating large agency representation: focusing on core field transaction entry and reporting

efficiencies and improvements Implement improved governance processes where the steering committee can play a

value-added role. These processes are supported by the ERP CC and the Enhancement Request recommendations. Key governance processes would include:

- Demand Management- Prioritization- Service Level Monitoring and Metrics- Funding

With well-run governance processes, who the ERP CC reports to and the involvement of line agencies become non-issues.

Core-CT Assessment – Detailed RecommendationSummary Recommendations

Page 44: Core-CT Assessment Final Report

44© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationExpanded Steering Committee- Recommendation Action Plan

Expand the steering committee for the ERP Competency Center to include line agency representation. Implement improved governance processes where the steering committee can play a value-added and necessary role.

Benefits

Q2 2007 – Q1 2008 Sponsors: Comptroller, Steering Committee

Execution: Director Group, CC Director

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Expand the steering committee for the ERP Competency Center to include line agency representation, especially where an agency has a significant user base and unique requirements because of their inherent services model that must be supported. (Who – Nancy/Directors; When – M5-M8)

Consider the following steering committee organization:- DAS, OPM, DOITT, and OSC representing central agencies- DOT, DOC, MHA, DMR, Tax representing some unique agencies- 1-2 other agencies representing remainder of agency needs serving

on a rotating basis

Primary Activities

Formal input mechanisms for all stakeholder agencies, central and line.

Improved central/line agency ability to more effectively execute all key business functions within the Core-CT application

Dependency on Other Initiatives Success is dependent on implementing the ERP CC

structure and clearly defined governance processes.

Implement and execute improved governance processes in the following key areas (Who – CC Director, Steering Committee, PMO; When – M9-M12 and ongoing):

- Demand Management- Prioritization- Service Level Monitoring & Metrics- Funding

More effective decisions that are made using complete data and input from all relevant stakeholder agencies

More relevant Core-CT vision based on the needs of both central and line agency, especially those agencies with unique needs

Page 45: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsPosition Classifications

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 46: Core-CT Assessment Final Report

46© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

It was stated during Gartner interview sessions that: It is difficult to recruit qualified functional/technical staff. Finding IT candidates with

PeopleSoft or ERP skills has been a challenge. Current Core-CT position classifications are outdated. They do not communicate the

required Peoplesoft integrated module knowledge, agency business process understanding, consultative/collaborative skills, or combination of technical and functional analysis skills.

IT compensation plans are inflexible – It is difficult to attract and reward highly valued employees appropriately with respect to the marketplace.

IT work schedules are limited to 35 hours a week. No formal Core-CT career development and succession planning strategy exists.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 47: Core-CT Assessment Final Report

47© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Review the team organization and position classification data that has been provided by the Core-CT team. The team was asked to describe an ideal ‘future state’ for the Core-CT team size and skill-set. This information is captured on the remaining slides in this section.

Taking into consideration the current team’s input, and using it as a foundation, create accurate and meaningful new position classifications (rather than re-classifying existing positions).

Consider creating legislation that would define the ERP competency center as a division reporting to OSC, paving the way for new job classifications.

Make the Core-CT positions competitive in the marketplace, from a salary perspective. Create a ‘barrier to entry’ for these positions so that only qualified people will be

accepted, and those who do not qualify will clearly understand why they don’t qualify. Solicit union input for any new position classifications.

Core-CT Assessment – Detailed RecommendationSummary Recommendations

Page 48: Core-CT Assessment Final Report

48© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationSummary Staffing Gaps

Functional Area PositionCore-CT EPM System Developer - one resource required

HRMS EPM Query Specialist - one resource required EPM Support Specialist - one resource required

Core-CT Security Technical Specialist - one resource required Cross Team Support for HR - one resource required Cross Team Support for FIN - one resource required

Core-CT HR Functional Team Benefits Team Lead - one resource required (which should report to Core, not Central

Bens) SME Position - one Payroll resource and one Benefits resource required.Development Team Developer - one resource required Support Developer - one resource required Training Support - two resources required

Core-CT Finance Trainer – two resources are required Helpdesk Agent – one resource is required Implementation Developer – one resource is required Supply Chain Position - one resource is required Financial Development Position – re-class an existing position to management

Page 49: Core-CT Assessment Final Report

49© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

EPM Team Lead

1 1 Planning & Project Management Manage Workload Prioritize Communications Networking Negotiating Understand Business

Process Cross Team Awareness Implement Change Identify Product

Enhancements Team Building Recruit / Retain / Train Reward

It is difficult to plan under State structure – leadership changing every 4 years or so;

It is difficult to recruit qualified IT Staff; Managing staff is difficult due to different

agency assignments and varying department policies and leadership.

It is difficult to reward highly valued employees appropriately.

Career Paths for CoreCT are non-existent

Page 50: Core-CT Assessment Final Report

50© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Technical Support – System Developer

3 4 System development of Peoplesoft Enterprise Performance Warehouse (EPM)

Write SQL for views and data transformations

On-line PS Enterprise Warehouse Processing

Informatica ETL Skills Strong Oracle/SQL Data Modeling & design Query Security Trees On-Call batch process support PS Query Skills Strong problem solving skills OLAP Reporting tools Strong analytical and testing

skills Strong writing & documentation

skills

Finding IT candidates with PeopleSoft or enterprise skills is difficult, and ultimately have to be trained.

Specialized training is not always readily available to tech staff.

Current IT job classifications are outdated.

IT Compensation plans are inflexible – compensation should be negotiable for highly skilled IT SMEs that are not managers.

IT work schedules are limited at 35 hours a week.

Documenting procedures inconsistent across teams

Page 51: Core-CT Assessment Final Report

51© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

DBA 0 .5 Build & maintain EPM Dbase Objects

Build Fast/Full refreshable Materialized Views (dbase ETLs)

Performance Tune Partition Tables Troubleshoot dbase issues Monitor jobs and batch

processes Run traces Import/Export data when

needed Maintain dbase security

Rely heavily on DBA to perform tasks that directly support EPM.

The DBA resources reside on another Core Team and are shared across CORE.

Would estimate that .5 FTE is required to support EPM.

Page 52: Core-CT Assessment Final Report

52© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Financial EPM Query Specialist

1 1 Understand Business Process and reporting Needs

Understanding Govt. Accounting and Data

Networking Collaborating Communication Customer Services Multi-tasking Cross Team Awareness Training Reporting Help Desk Support EPM PS Query PTools PL SQL

The Team Lead and the FIN Query specialist work together to fulfill the reporting needs of FIN and HR users statewide.

Page 53: Core-CT Assessment Final Report

53© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

HRMS EPM Query Specialist

0 1 Same as FIN Query Specialist KSAs with HR focus.

Understand HR Business Rules, Policies and HR Data.

Currently use the FIN specialist and Team Lead for all EPM training and support.

EPM Support specialist

0 1 Support / Assist Lead, HR & FIN functional specialists in:

Curriculum development and Training; maintain

Website Content & Job Aids Maintain Query Designs Create Maintain catalog of

reports or EPM Maintenance of WLA Help Desk Support

Creation, documentation and management of EPM Public Queries is not consistent.

EPM needs to have the WLA content updated and maintained.

Better deployment and maintenance of current job aids reference materials is desired.

Page 54: Core-CT Assessment Final Report

54© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Security Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Security Team Lead

1 1 Planning & Project Management

Coordinate cross team security needs

Prioritize Communications Networking Negotiating Understand PS Security Cross Team Awareness Implement Change Identify Enhancements in

Security Reporting Team Building Recruit / Retain / Train Reward

It is difficult to plan under State structure – leadership changing every 4 years or so

There is a great need for additional PS Security technical expertise

It is difficult to recruit qualified IT Staff

Managing staff is difficult due to different agency assignments and varying department policies and leadership.

It is difficult to reward highly valued employees appropriately.

IT Compensation plans are inflexible – compensation should be negotiable for highly skilled IT SMEs that are not managers.

Page 55: Core-CT Assessment Final Report

55© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Security Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Technical Support – Technical Analyst

Technical Specialist

2

1

2

2

Understand elements of PS Internet Architecture

Understand Data Structures of PS application

Familiarity with securing enterprise-level applications

PTools & PS Application Designer

Configure and Maintain Fin, HRMS and EPM user profiles

Maintain Query Security Trees

Implement /Maintain Developer Security

Implement application and data permission security

Implement security for batch processing and reporting

Administer portal and sign-in security

Until December 2005, only 1 analyst was assigned to Security Product Support Team.

Security requests are received, monitored and processed through an email / fax process which is very cumbersome and non streamline.

Not currently using any of the automated features or full functionality of security, which adds time to the management and maintenance.

Do not have the PS Security Engineering expertise in place to lead efforts on researching solutions and implementing change to improve security configuration and procedures.

Large projects relating to new module or agency implementation can monopolize the security team in setting up new users, causing a large backlog in daily user security requests, enhancement requests and production support.

Page 56: Core-CT Assessment Final Report

56© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Security Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Technical Support – Technical Analyst

Technical Specialist

2

1

2

2

Test Security Strong problem solving

skills Strong analytical and testing

skills Strong writing &

documentation skills Perform an array of security

tasks at a lower level under the direction of the Technical Analysts.

Beginning to decentralize to the functional teams security tasks related to upgrades/ implementation in environments other than production.

Currently, no Security Migration Procedures exist for upgrades and implementation. It is difficult to ensure synchronization of security in all environments.

Core-CT Security Standards need to be reviewed and updated.

Security Documentation is not up to date. Finding IT candidates with PeopleSoft or

enterprise skills is difficult, and ultimately have to be trained.

Specialized training is not always readily available to tech staff.

Current IT job classifications are outdated. IT work schedules are limited at 35

hours/week.

Page 57: Core-CT Assessment Final Report

57© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Security Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/Comments

Cross Team Support – Financial and HR System Developer

1 2 See KSAs for Analyst Position.

In environments relating to Upgrade or Implementation:

Configure and develop all elements of security impacted by upgrade or implementationFollow Core Security

StandardsMeet regularly with

Production Security Team Members on progressTest SecurityCreate Migration

ProjectsPerform as back-up for

Production team when necessary.

The goal is to have 2 staff members trained per functional team when needed. The FTE on Upgrade/Imp. efforts (per year) average 1 FTE / team.

Working closely with Fin & HR Team to standardize upgrade and implementation security procedures and migrations.

Two functional team IT staff have been id’d on the FIN team and 1 on the HR team.

Page 58: Core-CT Assessment Final Report

58© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT HR Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

HRMS Lead Position

1 1 Planning, organizational skills, written and verbal communication skills, the ability to view things at high level as well as detailed, staffing, setting priorities.

Functional Team Position

1 lead for each of the 4 modules.

Management skills, identify priorities within their module, the ability to recognize changes in the business processes and be able to identify the impact on the Peoplesoft application.

Expert within the business and application side of their module.

Need to the liaison between the correct team and the business, need a high awareness of the integration points within the Core-CT application.

Creative problem solving skills, communication and collaboration, responsiveness to the changing business environment, detail oriented and customer service oriented.

Need to report directly to Core-CT while representing the interests of the business.

Page 59: Core-CT Assessment Final Report

59© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT HR Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Function Team – Subject Matter Expert Position

2 positions for Time and Labour

2 positions for Payroll

1 position for Benefits

4 positions for HR

Need to be responsive to changing business requirements, ability to recognize changes in the business process and recommend changes in the application as a result, need to be expert within their business processes, as well as in Peoplesoft.

Need a high awareness of integration points across the application

Creative problem solving, communication, collaboration skills

The ability to multitask, detail oriented and customer service oriented.

The positions should report to Core-CT , while representing the business.

Support Level Position

4 positions for HR,

1 position for Time/Labour,

0 for Benefits/ Payroll

Skilled within their business processes, detail oriented and customer oriented.

Positions should report to Core-CT , while representing the business.

Page 60: Core-CT Assessment Final Report

60© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT HR Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Develop-ment TeamManager Position

1 1 Knowledgeable in Peoplesoft application and the toolset.

Knowledgeable in State business processes. Coordination, organization, communication,

prioritization skills.

Develop-ment Team Developer

10 Knowledgeable in the Peoplesoft application and toolset

Familiar with the state business processes Capable of supporting the batch process Problem solving and analytical skills. 40 hours+ workweek is the expectation.

Develop-ment Team Contract Developer (Tech Specialist)

2 Knowledgeable in the Peoplesoft application and toolset

Willing to learn the state business processes Capable of supporting the batch process Problem solving and analytical skills. 40 hours+ workweek is the expectation.

Page 61: Core-CT Assessment Final Report

61© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT HR Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Develop-ment Team Contract Developer

2 Manages interfaces and migrations

Develop-ment Team Training Support / Communi-cations Position

2 Strong communication skills, strong organizational skills, ability to organize and publish materials on the website

General knowledge of HRMS, experience in curriculum development

Extensive experience in the use with development of training tools for use in the classroom

Extensive experience with delivering training

Page 62: Core-CT Assessment Final Report

62© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Training 0 2 Two positions are needed to increase the training team staffing to meet the demands of the user community.

The training delivery must be a blend of instructor led and web-based training.

The State of Connecticut must invest in new tools (i.e. UPK-User Productivity Kit) to leverage the use of technology for rolling training out to over 5,000 financial users.

Helpdesk 2 One position to support the implementation of the Projects & Contracts Modules.

With the addition of DOT to full utilization of the production system, it is anticipated that the volume of calls to the helpdesk will increase significantly.

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Page 63: Core-CT Assessment Final Report

63© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Implement-ation

The Core-CT team has a constant need to stay current with technology to position ourselves to take advantage of new opportunities.

Inherent in this system is the need to constantly apply maintenance packs to the code-line in order to apply new fixes, tax upgrades, etc.

This position will also support adding configuration updates to the production system.

Supply Chain

A position is needed to implement and support electronic purchasing commonly referred to as either punch-out or direct connect.

This functionality needs to be implemented within the next year.

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Page 64: Core-CT Assessment Final Report

64© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Financial Develop-ment

Re-class an existing position to management an assistant to the development lead is needed to effectively manager the large number of developers and contactors assigned to that unit.

The current structure has too many direct reports to the lead position, which detracts from his ability to focus on higher level assignments.

Contract Staff

The Financial Development Team has an ongoing need for developers that must continue to be included in the Core-CT funding.

Two highly skilled PeopleSoft developers must continue to be part of this team to triage production related issues and develop complex system fixes.

The current salary structure precludes us from attracting this unique skill set. It would be very risky to not have this level of expertise readily available and our ability to respond quickly to production issues would be greatly diminished.

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Page 65: Core-CT Assessment Final Report

65© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Major Initiative

A need exists to develop a strategy to archive existing system data.

My opinion is that funding should be budgeted to hire consultants to develop, test and implement an archiving program.

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Page 66: Core-CT Assessment Final Report

66© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

Technical Team Leads

2 Management skills Review, plan and set priorities Capacity and resource planning Recommend & implement software, hardware and

configuration changes as needed Communication, coordination, collaboration skills Organizational Skills and Facilitation skills Broad understanding of different technologies and

business impacts Review changing technology direction; coordinate

with broader initiatives. Broad understanding of highly available distributive system architecture.

Assist with defining architecture & technology standards

In-depth knowledge of PeopleSoft Internet Technology

Assist with development of IT budget, hardware and software procurement, maintenance

Staff recruiting / training

Report directly to Core-CT manage-ment

Page 67: Core-CT Assessment Final Report

67© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Technical Team Leads

2

One responsible for day to day coordination and planning activities One focused on strategic planning and performance testing.

Advanced or expert level PeopleSoft technical experience supporting multiple PeopleSoft product lines

Management skills Communication skills Analysis and design skills Coordination skills; with

functional and technical teams Collaboration skills Define and prioritize Ensure capacity and resource

planning are performed to specifications

Develop project plans and schedules

Report directly to Core-CT technical team management

6 key support areas; PeopleSoft Administration, Stat Administration, Database Administration, Windows Administration, AIX Administration, Rapid Recovery SAN Administration

Page 68: Core-CT Assessment Final Report

68© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE

KSAs and/or Duties required

Issues/ Comments

PeopleSoft Administrator - Lead

1 Coordinate with Environment Managers and other technical team leads

Strong understanding and implementation of PeopleSoft 8.x PIA and technical components

Management skills Analysis and design skills Participate in planning sessions Provide in-depth troubleshooting Provide technical input in review and analysis of

current/future direction; recommend new tools. Collaboration skills Input to strategic planning

Page 69: Core-CT Assessment Final Report

69© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

PeopleSoft Administrator - Support

7

HRMS, Financials, EPM, PortalCustom components/integration, cross-support/strategic

PeopleSoft 8.x technical architecture, PIA, PeopleTools and third party software

Development and Administration Tools

Analytical skills Monitoring Debugging Shell scripting Intermediate SQL Apply patches/fixes/updates Perform code migrations / compares Change management/control Maintenance / tuning Participate in disaster recovery

Page 70: Core-CT Assessment Final Report

70© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Stat Administrator

1 Coordinate with Environment Managers and technical team leads

AIX, Windows 2002/2003 operating systems

PeopleSoft 8.x environment experience

Analysis and design skills Configuration and software support Monitoring

Page 71: Core-CT Assessment Final Report

71© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Database Administrator - Lead

1 Coordinate with Environment Managers and other technical team leads

Strong understanding and implementation of Oracle 9i+

Management skills Analysis and design skills Expertise in integration between

application and database Expertise in performance tuning

PeopleSoft dynamically generated SQL

Participate in planning sessions Provide in-depth troubleshooting Provide technical input in review and

analysis of current/future direction; recommend new tools.

Collaboration skills Input to strategic planning

Page 72: Core-CT Assessment Final Report

72© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Technical Team Staffing Requirements

Position Current FTE

Sufficient FTE KSAs and/or Duties required

Issues/ Comments

Database Administrator - Lead

5

HRMS, Financials, EPMSoftware management, cross-support/strategic

Oracle 9i+ database administration

Understanding of the PeopleSoft data model

Apply patches/fixes/updates Configuration Maintenance Performance database

monitoring, analysis, tuning, sizing

Database backup, exports, restores

Security Participate in Disaster

Recovery

Page 73: Core-CT Assessment Final Report

73© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationPosition Classifications- Recommendation Action Plan

Review the ‘future state’ Core-CT team organization, and position classification data, that is included in this report. Create and institute accurate and meaningful new position classifications, in a timely manner, to ensure that the Core-CT application is supported by qualified personnel who have a defined career. Staff the Core-CT adequately to fully leverage functionality.

Benefits

Q4 2007 – Q4 2009 Sponsors: Comptroller, Steering Committee

Execution: DAS, CC Director, Team Leads

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Determine if gaps need to be filled and fill with contractors or new employees (Who – CC Director/Team Leads; When - M7-M8)

Review the team organization and position classification data that has been provided by the Core-CT team. The team was asked to describe an ideal ‘future state’ for the Core-CT team size and skill-set. This information is captured on the remaining slides in this section. (Who – CC Director/Team Leads; When - M8-M9)

Primary Activities

Core-CT team capability to perform all of their critical functions within Core-CT

Core-CT turnover and retention metrics Core-CT job satisfaction

Dependency on Other Initiatives Dependent on formal creation of ERP CC and approval of charter Success is highly dependent on accurate and meaningful position

classifications being defined and instituted. Salaries, especially technical team salaries, must be more competitive

with the marketplace.

DAS classification unit; review/re-write specs and career path – (Who – DAS; When – begin in M10 and go on for 2 years duration)

- Taking into consideration the current team’s input, and using it as a foundation, create accurate and meaningful new position classifications (rather than re-classifying existing positions).

- Make the Core-CT positions competitive in the marketplace, from a salary perspective.

- Create a ‘barrier to entry’ for these positions so that only qualified people will be accepted, and those who do not qualify will clearly understand why they don’t qualify.

- Solicit union input for any new position classifications.

More effective and efficient Core-CT support function Improved central and line agency service delivery Improved employee morale Lower employee turnover

Page 74: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsCritical Line Agency Enhancement Requests

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 75: Core-CT Assessment Final Report

75© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

At the time of go-live, the Core-CT solution did not support key and mandatory line agency functions. (e.g., Federal billing support, 24x7 scheduling).

Line agencies are currently being forced to create manual workarounds or seek other solutions for some key functions that are not supported within Core-CT.

It was stated that success in the past was defined as, “Deploy an application that works”. The future vision of Core-CT must ensure that all agencies are more fully supported by the application or that an alternative solution is deployed.

The Core-CT team has indicated that it lacks the proper resources to implement enhancements in a timely manner.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 76: Core-CT Assessment Final Report

76© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Priority Functional Area DescriptionHigh EPM and Reporting The Core-CT application currently lacks useable EPM functionality and a sufficient

number of canned reports. It was indicated that the following should be created: a basic data warehouse; analytical intelligence and usage; and, divisional and scorecard capabilities (dimensional reporting).

High 24/7 Scheduling, Leave Accruals

Rotating averaging schedule functions cannot be performed at the Dept of Corrections. Regular hours are not paid correctly. Leave accruals within Core-CT are not aligned with State leave accruals; employees are paid bi-weekly but their leave accrues monthly.

High Employee Benefit Eligibility

Core-CT is not successfully enabling the maintenance of accurate and up to date employee benefit lists; agencies are not tracking employee eligibility to carriers and employees are losing coverage that they should have, as a result.

High Purchasing/ Inventory

It was indicated that not all goods should be tracked within the inventory module, given the tight integration between the Core-CT inventory and purchasing modules, and the need to include inventoried items within internal catalogs.

High Catalog Management

Punchout catalogs (vendor maintained catalogs) cannot be leveraged, and as a result, the Core-CT team is devoting a great deal of time/effort maintaining all internal catalogs.

High Commitment Control

Inconsistent in functionality. Occasionally allows a document to pass when there are insufficient funds in the impacted budget, and the process to reverse purchase orders and release unexpended encumbrances is very cumbersome for agency users.

High Field Level Edits and Validation

It was stated that Core-CT provides the users with a great deal of flexibility; much more so than the legacy applications. The legacy applications had ‘hard edits’. The Core-CT team tried to address the increased flexibility with training, but mistakes still occur. (E.g. The previous system would not let you move off of the screen until the appropriate fields have been entered.) They’ve lost these real-time edits.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 77: Core-CT Assessment Final Report

77© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Leverage an expanded steering committee that has line agency representation to define the long term Core-CT vision.

Utilize an IT Investment Management (ITIM) framework to prioritize the enhancements that will evolve the current state Core-CT application to meet the future state needs of the agencies. (The ITIM framework will be described in the following slides. This framework provides even more details regarding demand management, prioritization, portfolio management and funding governance processes described in the ERP CC recommendation).

- The Core-CT team should focus on correcting critical functional gaps that have are hindering the line agencies from properly serving their employees and other stakeholders (time & labor, purchasing, federal billing, inventory management, 24x7 scheduling)

Define an acceptable release schedule that will meet the needs of the agencies. Eliminate maintenance complexity by stabilizing all modules on the same release. Release management governance was described earlier in the ERP CC recommendation.

Staff the Core-CT team with the appropriate number of qualified full time staff, supplementing with 3rd party resources in the short term if needed.

Demonstrate ability to address line agency concerns – Core-CT needs some “wins” here.

Core-CT Assessment – Detailed RecommendationSummary Recommendations

Page 78: Core-CT Assessment Final Report

78© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

To establish a comprehensive, collaborative framework that: Provides for a formal and effective decision making process for new Core-CT

investments (This is demonstrated by the SELECT phase on the next slide). Provides for a program review cycle for all new, under-development and on-going

(legacy) Core-CT investments (This is demonstrated by the CONTROL phase on the next slide)

Provides for a program evaluation cycle for all “completed” or on-going Core-CT operations and maintenance investments (This is demonstrated by the EVALUATE phase on the next slide).

Additionally, it will: Enable effective continuous improvement that will ensure the Core-CT application

performs all critical line and central agency functions. Agency buy-in will increase because their critical needs will be recognized Shadow systems (‘one-off’ applications built and funded by agencies that

compensate for functions that cannot be performed within Core-CT) will not be built within agency environments, thereby diluting the single source of data that the State has currently achieved. Shadow systems are typically a source of significant “IT” costs embedded in the business that can be reduced.

Core-CT Assessment – Detailed RecommendationInformation Technology Investment Management (ITIM)

Page 79: Core-CT Assessment Final Report

79© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Additionally, it will: Institutionalize the ITIM process so that it is formally integrated into the Core-CT

budget and strategic planning processes Establish a balanced Core-CT investment portfolio for enhancements, additional

module implementation, and application upgrades.

Core-CT Assessment – Detailed RecommendationInformation Technology Investment Management (ITIM)

Page 80: Core-CT Assessment Final Report

80© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Results: Alignment of Core-CT

investments and State strategy

Better investment decisions

Governance principles for Core-CT management

SelectHow do you

know you have selected the

best Core-CT enhancements

?

EvaluateBased on your evaluation, did

Core-CT deliver the expected results?

ControlWhat are you

doing to ensure

enhancements will deliver

benefits?

Conduct reviews Make

adjustments Apply lessons

learned

Monitor progress Take corrective action

Screen Rank Score

Core-CT Assessment – Detailed RecommendationInformation Technology Investment Management (ITIM)

Page 81: Core-CT Assessment Final Report

81© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Expanded Core-CT steering committee conducts post-implementation reviews for key enhancements

Successes and failures (lessons learned) are incorporated into Core-CT processes—continuous improvement is achieved

Core-CT steering committee monitors key enhancements

Proactive Core-CT management, by exception Earned value Scope Schedule

Select Phase Enhancements are assembled into an Investment

Portfolio for a cross-agency enterprise perspective Expanded Core-CT steering committee and Core-CT

team leaders align enhancement requests with business strategies

Expanded Core-CT steering committee and Core-CT team leaders select enhancements based on predefined criteria

Control Phase

Evaluate Phase

Life-cycle approach to selecting, controlling and evaluating Core-CT enhancement requests in a consistent and repeatable fashion.

Core-CT Assessment – Detailed RecommendationInformation Technology Investment Management (ITIM)

SelectHow do you

know you have selected the

best Core-CT enhancements

?

EvaluateBased on your evaluation, did

Core-CT deliver the expected results?

ControlWhat are you

doing to ensure

enhancements will deliver

benefits?

Conduct reviews Make

adjustments Apply lessons

learned

Monitor progress Take corrective action

Screen Rank Score

Page 82: Core-CT Assessment Final Report

82© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Simply put, portfolios describe, in table form, the complete set of Core-CT technologies, application modules and services managed by the ERP

Competency Center. The set of portfolios represents 100 percent of the ERP CC resources.

Business and Core-CTStrategicPlanning

Processes

PerformanceManagement &Measurement

Annual Core-CTInvestments &

Budgeting

Short-TermPlanning

USES

PORTFOLIOINFORMATION

Demographics

Stakeholders/Users

Resources Consumed

Development Planning

Requirements

ApplicationManagement

Management

ServicesManagement

InfrastructureManagement

ApplicationDevelopment

ManagementDevelopment

ServicesDevelopment

InfrastructureDevelopment

CORE-CT PORTFOLIO AREAS

Investment Portfolio

Current State Portfolio

Core-CT Assessment – Detailed RecommendationInformation Technology Investment Management (ITIM)

Page 83: Core-CT Assessment Final Report

83© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

FY ’XX Budget

Agency or ERP CC Idea

Concept Paper

Business Case

Analysis

Go/No-Go Decisio

n

Line or Central AgencyStaff

ERP CCPeople

Process

Tools

Agency Staff Agency Management Core-CT Technical

Reviewers Core-CT Leadership

Oversight Reviewers

Executive Tier Agency Staff Agency

Management Core-CT Leadership

Project Oversight Reviewers

Concept Paper Template Architectural Standards Agency Mission, Vision,

Objectives Project Ranking Criteria

Business Case Agency Mission,

Vision, Objectives Project Ranking

Criteria

Executive Tier

Briefing Materials Project Selection Criteria

Core-CT Assessment – Detailed RecommendationEnhancement Identification/Evaluation Process

Page 84: Core-CT Assessment Final Report

84© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Key Concept: People still make decisions.

Enhancement Name/Alias

Short DescriptionEnhance-

ment NumberAgency Sponsor

FY __ BudgetRequest

($'s)

Estimated Life-Cycle

Costs Man

date

t Req

uire

men

t?

With

Fun

ding

?

Fund

ing

Sour

ce

Proj

ect R

isk

Fina

ncia

l Ris

k

Tech

nica

l/ Ar

chite

ctur

e Ri

sk

Secu

rity

Risk

Mis

sion

Fit

(Tot

al W

eigh

ted

Scor

e fr

om P

roje

ct S

corin

g W

orks

heet

)

Ran

king

1. Commitment Control 123-ABC John Doe / OPM

2007$150K

Thru 2008$300K

Y,Y Grantxyz

3 2 4 4 450 2

2. EPM Analytics module Implementation

456-DEF Jane Doe / ALL

2007 $750K

Thru 2009$2.2M

N,N 4 3 3 3 350 33. 24/7 Scheduling. Leave Accrual Functionality

789-GHI Mary Smith / DOC

2007$350K

Thru 2008$550k

N,N 3 3 2 4 470 1

Engagement SELECT ScoresExample for illustrative purposes

Core-CT Assessment – Detailed RecommendationProfile Each Enhancement in an Investment Portfolio

Page 85: Core-CT Assessment Final Report

85© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Example for illustrative purposes

Core-CT Assessment – Detailed RecommendationKnow “what you spend” and “what you should spend” by investment category

Make Decisions: Where do you want to spend your limited dollars?

Legal Mandate

Infrastructure

Enhancement

Utility

StrategicSalesforce.com $0K

Oracle Mfg/Lean Trans $597K

eProcurement $0K

Oracle ADP/ATP $274K

Oracle WH/Transp Mgmt $K

EDW/Orders DWH $812K

Oracle/COM Integration $1.2M

Sales/Mktg Enhancements $432K

Factory/Rooftop Consol $275K

PDM Infrastructure $0KInfrastructure $31.2MInstance Multi-Org $350K

Matrix 1 $0KLCC/Brno Factory $0K

Hyperion/OFA $160K

O&M $3.702M

Legal Mandate $ 0 M 0%Enhancement $ 3.590 M 9.2%Strategic $ 0 M 0%Infrastructure $ 31.550 M 80.9%Utility $ 3.862 M 9.9%Total $ 39.002 M 100.0%

Legal Mandate $ 0 M 0%Enhancement $ 3.590 M 9.2%Strategic $ 0 M 0%Infrastructure $ 31.550 M 80.9%Utility $ 3.862 M 9.9%Total $ 39.002 M 100.0%

Complexity Status Count Total

High Complexity (Red) 3Medium Complexity (Yellow) 7Low Complexity (Green) 7

Complexity Status Count Total

High Complexity (Red) 3Medium Complexity (Yellow) 7Low Complexity (Green) 7

Total Value $Total Value $xMxM / y%/ y%

Legend: Legal Mandate—A project or initiative mandated by legislation,

executive direction, legal requirement or policy/guidelines Enhancement—Adding new functions, features or capabilities.

Usually associated with cost reduction and/or productivity benefits Strategic—Assessing/developing new or future capabilities.

Usually associated with growth, revenue, and/or significant costreduction

Infrastructure—Maintenance, technical refresh, and enabling foundations for existing systems, programs, etc.

Utility—Administrative and commodity capabilities required to manage core business processes. Usually associated with, at most, minor productivity benefits

Legend: Legal Mandate—A project or initiative mandated by legislation,

executive direction, legal requirement or policy/guidelines Enhancement—Adding new functions, features or capabilities.

Usually associated with cost reduction and/or productivity benefits Strategic—Assessing/developing new or future capabilities.

Usually associated with growth, revenue, and/or significant costreduction

Infrastructure—Maintenance, technical refresh, and enabling foundations for existing systems, programs, etc.

Utility—Administrative and commodity capabilities required to manage core business processes. Usually associated with, at most, minor productivity benefits

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Balance Sheet Carve-out $0K

Page 86: Core-CT Assessment Final Report

86© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

New Product Development(Idea to Product)

Purchasing(Req-to-Check)

Sales and Marketing(Contract-to-Order)

Manufacturing(Rqmnt-to-Product)

Order Management(Order-to-Cust Use)

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

New Prod Development $ 0M 0%Sales and Marketing $ 0.432M 11.5%Order Management $ 1.686M 45.0%Purchasing $ 0.070M 1.9%Manufacturing $ 0.777M 20.7%Distribution $ 0.625M 16.7%Finance $ 0.160M 4.3%Total $ 3.750M 100.0%

New Prod Development $ 0M 0%Sales and Marketing $ 0.432M 11.5%Order Management $ 1.686M 45.0%Purchasing $ 0.070M 1.9%Manufacturing $ 0.777M 20.7%Distribution $ 0.625M 16.7%Finance $ 0.160M 4.3%Total $ 3.750M 100.0%

Distribution(Req-to-Dist Inventory)

Finance

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Salesforce.com $0K

Sales/Mktg Enhancements $432K

PDM Infrastructure $0KMatrix 1 $0K

LCC/Brno Factory $0KOracle Mfg/Lean Trans $502KFactory/Rooftop Consol $275K

Balance Sheet Carve-out $0KHyperion/OFA $160K

Oracle ADP/ATP $274K

EDW/Orders DWH $812K

Oracle/COM Integration $600K

Oracle/COM Integration $600K

Oracle WH/Transp Mgmt $0K

Oracle Mfg/Lean Trans $25K

eProcurement $0K

OracleMfg/Lean Trans $70K

Example for illustrative purposes

Make Decisions: Where do you want to spend your limited dollars?

Core-CT Assessment – Detailed RecommendationKnow “what you spend” and “what you should spend” by business process

Page 87: Core-CT Assessment Final Report

87© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

$

Department/Agency

Enhancements/Utility

Infrastructure/Foundation

Strategic/Frontier

Legal/Pet RockCore-CT Technical Review/ Core-CT Executive Leadership Team

Enhancements/Utility

Infrastructure/Foundation

Strategic/Frontier

Legal/Pet Rock

Central Agencies

Enhancements/Utility

Infrastructure/Foundation

Strategic/Frontier

Legal/Pet Rock

Line Agencies

Enhancements/Utility

Infrastructure/Foundation

Strategic/Frontier

Legal/Pet Rock

Budget Office/ Finance Department

Document business strategy

Establish weights on strategic priorities

Evaluate each new enhancement against its contribution to the strategy

Balance the portfolio

Submit portfolio to Core-CT Steering Committee

2

1

3

4

5

Core-CT Assessment – Detailed RecommendationHow It Really Works

Page 88: Core-CT Assessment Final Report

88© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Phase 1Pilot

Process

Phase 2Rollout

Phase 3Measure & Improve

Introduce the framework Pilot with manageable amount of content Post-pilot review and tuning

Rollout the process; pilot full portfolio

Full content; focus on data accuracy Post-pilot review and tuning

Measure the process performance and output results

Modify processes at root cause Execute improved processes

Phases are sequential and must proceed in order. However, you can be in different phases for each of the strategic areas (planning, investment management, enterprise architecture) at the same time.

Core-CT GovernanceIT Governance & Principles

STR

ATE

GY

ITIM EA

Portfolio Management

Level 1Level 2

Level 3

Level 4

Level 5

Performance Measurement

Matur

ity

Core-CT Assessment – Detailed RecommendationHow to Get There

Page 89: Core-CT Assessment Final Report

89© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Currently, the Core-CT team lacks:

- Effective line agency enhancement input mechanisms

- Formal Core-CT enhancement evaluation processes

- Distinct Core-CT Competency Center operating budget

- A detailed understanding of requested Core-CT application enhancements

- Formal and communicated Core-CT enhancement roadmap, complete with implementation timelines, funding commitments, and assigned resources.

The Core-CT steering committee and team can leverage the ITIM framework to define and mature key processes

ITIM summary charts and tables should be used as project ‘dashboards’. Dashboards are effective summary evaluation tools and should be an important measurement component, and executive communication platform.

Enhancement Name/Alias

Short DescriptionEnhance-

ment NumberAgency Sponsor

FY __ BudgetRequest

($'s)

Estimated Life-Cycle

Costs Man

datet R

equiremen

t?

With

Fun

ding

?

Fund

ing So

urce

Projec

t Risk

Fina

ncial R

isk

Tech

nica

l/ Ar

chite

ctur

e Risk

Secu

rity Ri

sk

Mission

Fit (Total W

eigh

ted

Scor

e from

Pro

ject Sco

ring

Wor

kshe

et )

Ran

king

1. Commitment Control 123-ABC John Doe / OPM

2007$150K

Thru 2008$300K

Y,Y Grantxyz

3 2 4 4 450 2

2. EPM Analytics module Implementation

456-DEF Jane Doe / ALL

2007 $750K

Thru 2009$2.2M

N,N 4 3 3 3 350 33. 24/7 Scheduling. Leave Accrual Functionality

789-GHI Mary Smith / DOC

2007$350K

Thru 2008$550k

N,N 3 3 2 4 470 1

Engagement SELECT Scores

Core-CT Assessment – Detailed RecommendationCurrent Gaps

Legal Mandate

Infrastructure

Enhancement

Utility

StrategicSalesforce.com $0K

Oracle Mfg/Lean Trans $597K

eProcurement $0K

Oracle ADP/ATP $274K

Oracle WH/Transp Mgmt $K

EDW/Orders DWH $812K

Oracle/COM Integration $1.2M

Sales/Mktg Enhancements $432K

Factory/Rooftop Consol $275K

PDM Infrastructure $0KInfrastructure $31.2MInstance Multi-Org $350K

Matrix 1 $0KLCC/Brno Factory $0K

Hyperion/OFA $160K

O&M $3.702M

Legal Mandate $ 0 M 0%Enhancement $ 3.590 M 9.2%Strategic $ 0 M 0%Infrastructure $ 31.550 M 80.9%Utility $ 3.862 M 9.9%Total $ 39.002 M 100.0%

Legal Mandate $ 0 M 0%Enhancement $ 3.590 M 9.2%Strategic $ 0 M 0%Infrastructure $ 31.550 M 80.9%Utility $ 3.862 M 9.9%Total $ 39.002 M 100.0%

Risk Status Count Total

High Risk (Red) 3Medium Risk (Yellow) 7Low Risk (Green) 7

Risk Status Count Total

High Risk (Red) 3Medium Risk (Yellow) 7Low Risk (Green) 7

Total Value $Total Value $xMxM / y%/ y%

Legend: Legal Mandate—A project or initiative mandated by legislation,

executive direction, legal requirement or policy/guidelines Enhancement—Adding new functions, features or capabilities.

Usually associated with cost reduction and/or productivity benefits Strategic—Assessing/developing new or future capabilities.

Usually associated with growth, revenue, and/or significant costreduction

Infrastructure—Maintenance, technical refresh, and enabling foundations for existing systems, programs, etc.

Utility—Administrative and commodity capabilities required to manage core business processes. Usually associated with, at most, minor productivity benefits

Legend: Legal Mandate—A project or initiative mandated by legislation,

executive direction, legal requirement or policy/guidelines Enhancement—Adding new functions, features or capabilities.

Usually associated with cost reduction and/or productivity benefits Strategic—Assessing/developing new or future capabilities.

Usually associated with growth, revenue, and/or significant costreduction

Infrastructure—Maintenance, technical refresh, and enabling foundations for existing systems, programs, etc.

Utility—Administrative and commodity capabilities required to manage core business processes. Usually associated with, at most, minor productivity benefits

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Total Value $Total Value $xMxM / y%/ y% Total Value $Total Value $xMxM / y%/ y%

Balance Sheet Carve-out $0K

Page 90: Core-CT Assessment Final Report

90© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core- CT Governance

IT Governance & Principles

STR

ATEG

Y

ITIM EA

Portfolio Management

Level 1Level 2

Level 3

Level 4

Level 5

Performance Measurement

Maturity

Core- CT Governance

IT Governance & Principles

STR

ATEG

Y

ITIM EA

Portfolio Management

Level 1Level 2

Level 3

Level 4

Level 5

Performance Measurement

Maturity

Maturing the Core-CT strategic planning process will enable the State to effectively enhance the application to successfully enable all line and central agencies.

It will also minimize wasted dollars on poorly conceived, or low-impact initiatives.

The Core-CT steering committee should recognize that the ITIM process must be coupled with adequate budget allocations, and a suitable Core-CT team (size and capability) , in order to ensure success.

Core-CT Assessment – Detailed RecommendationBottom Line

Page 91: Core-CT Assessment Final Report

91© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationCritical Line Agency Enhancements - Recommendation Action Plan

Implement critical line agency enhancements in a timely manner; enable effective continuous improvement that will ensure the Core-CT application performs all critical line and central agency functions. Implement request intake and investment portfolio management processes to better communicate operating and investment spending status and priorities.

Benefits

Q2 2007 – Q1 2008 Implementation

timeframes TBD

Sponsors: Comptroller, Steering Committee

Execution: CC Director, Team Leads, PMO

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Gather, consolidate, rationalize, and prioritize SIRs and Enhancement Requests. Determine and communicate clear disposition to requestors (Who – Team Leads/PMO; When – M4-M7)

Create improved, consistent, and repeatable process for request intake process across all teams (Who – Team Leads/PMO; When – M7-M9)

Review and leverage IT Investment Mgmt (ITIM) framework to refine and optimize Demand, Prioritization, and Portfolio Mgmt governance processes (Who – PMO/CC Director; When – M9-M12)

Primary Activities

Line agency capability to perform critical functions within Core-CT

Project investment alignment with agency needs Improved communications to agencies

Dependency on Other Initiatives Dependent on implementation of ERP CC structure and governance

processes. Dependent on an expanded steering committee that includes line agencies Dependent on adequate staffing/funding of the team in order to implement

enhancement projects in a timely manner

Develop project charters and set clear expectations for key investment initiatives, including (Who – Directors/PMO; When – M7-M8)

- EPM and Reporting, 24/7 Scheduling, DOT Inventory Pilot, Catalog Management Develop and implement project portfolio management process to do the following (Who -

CC Director/PMO; When – M9-M12)- Review charter and necessary investment requirements and business case- Assist with staffing and sourcing/supply management- Establish project-related governance regarding status and progress reporting- Establish project portfolio dashboard reporting for ERP CC projects- Monitor and measure effectiveness of enhancements

Enhanced Core-CT functionality More effective use of Core-CT investment spend More effective and efficient line agency processes utilizing the

Core-CT solution

Page 92: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsTraining

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 93: Core-CT Assessment Final Report

93© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The training recommendation section of this report includes a large amount of content. By using dedicated, and qualified, training resources, the Core-CT team can successfully undertake all of them.

Organizations typically under-invest in training, and that leads to a very large missed opportunity. Training can provide significant value in reducing the costs of using technology to run business processes effectively. One can derive large savings from good training delivery.

The Core-CT team has created a training foundation that can be leveraged.

Core-CT Assessment – Detailed RecommendationKey Messages

Page 94: Core-CT Assessment Final Report

94© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT training material was generic and not specific to agency processes. Application experts delivered the training - not ‘power users’ who understood how the

application did/did not support the State’s business processes. Training technology (i.e. computer based training, help functions within the Core-CT

application) were not effectively developed and/or deployed. The organizational change management effort was reduced and was not a strategic or

consistent focus during the implementation. Change resistance has not been revisited in a meaningful way since Core-CT was deployed.

Inexperienced line agency personnel have struggled to accurately enter increased amounts of data into an application that demands a higher level of business understanding on the part of the user.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 95: Core-CT Assessment Final Report

95© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

General Observations Poorly trained users prevent the acceptance of ERP within the user community, and limit

the realization of full benefits. Training budgets are typically grossly underestimated. They usually contain some form

of "train the trainer" effort; this type of training can fail if poor trainers are selected. Many organizations perform only one round of training and overlook the need for

ongoing training. Organizations often overlook the formal software vendor IT workforce training needs

associated with ERP implementations. After an ERP implementation, almost all organizations state that, during future

implementations, they would: increase employee participation earlier in the implementation process; make greater investments in end-user training programs; and, focus more on change management.

Ongoing communication has enhanced training and change management initiatives through such mechanisms as: project Web sites; newsletters and "road shows" regarding the project's direction; changes; progress; accomplishments; and, benefits

Key Success Factors Place a high priority on quality and ‘agency relevant’ end-user training. Core-CT training

must be a strategic focus that will enable all agency end users.

Core-CT Assessment – Detailed RecommendationGeneral Observations and Key Success Factors

Page 96: Core-CT Assessment Final Report

96© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Key Success Factors (cont) Education and training programs must embrace multiple methods and delivery vehicles,

such as: one-on-one training; classroom training; computer-based training; and, learning management systems (LMS) to meet the needs of the line and central agency user community.

Adequate investment in formal software vendor training is important to the success of Core-CT, given that the enterprise solution will be supported and maintained in-house.

Core-CT Assessment – Detailed RecommendationGeneral Observations and Key Success Factors

Page 97: Core-CT Assessment Final Report

97© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Training is a key deliverable of any change management program, and must become a strategic component of the ongoing Core-CT support/enhancement program.

Make a major commitment to training; sustain and evolve the Core-CT training program. Given the issues with the original Core-CT training effort, and the state of the current

training program, the Core-CT leadership team should re-assess the entire training effort. The Core-CT team should ‘start from scratch’ and create a new training strategy, leveraging any/all existing training material where appropriate. (The following slides will outline a complete training approach.)

Assign a training owner within the ERP CC who will be accountable for: - Coordinating all training stakeholders- Gathering all existing key training gaps- Developing a training strategy- Managing the delivery of Core-CT training going forward- Developing a communication strategy that educates and informs users, and keeps them

up to date on the most recent training and best practice developments.- Monitoring and measuring the success of the training program

Ongoing training for new hires or staff-switching roles should form part of Core-CT’s annual maintenance budget. Consistent, high-quality education and training is vital to success, and for full Core-CT adoption by the user community.

Core-CT Assessment – Detailed RecommendationSummary Recommendations

Page 98: Core-CT Assessment Final Report

98© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Training should be evaluated through the use of feedback questionnaires to determine its effectiveness and how the courses can be improved.

Identify super users who have a good understanding of both the agencies’ business processes and the Core-CT application along with the required skills to effectively deliver training. Integrate super users into selected ERP CC governance processes.

- An effective super user community can act as a very efficient level 1 source of help, especially in the areas of training. This can have significant positive impacts in keeping help desk costs down by preventing training calls from ever entering the problem ticket process.

Redeploy focused, refresher training to all Core-CT users on an ongoing basis.

Core-CT Assessment – Detailed RecommendationSummary Recommendations

Page 99: Core-CT Assessment Final Report

99© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Define Learning Vision and Obtain Leadership Buy-In Agency leadership must understand the value of defining a learning vision, and should

‘buy-in’ to the concept publicly. A critical aspect of implementing a learning vision is establishing a plan for staff

development. An established training team leader should be appointed within the ERP CC. This

person should be dedicated to overseeing the development of training programs that are applicable to all agency stakeholders.

The training team leaders should be empowered to liaise with central and line agencies, DOIT professionals, and should have the visibility and/or influence to lobby for training budget, communicating needs, and identifying opportunities for continuous improvement.

Training has not been a strategic focus for the Core-CT leadership team, and adequate funding has not been provided. The Core-CT team should leverage an expanded steering committee, define a training vision and high level goals, and identify qualified personnel to execute the vision.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 100: Core-CT Assessment Final Report

100© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Link Core-CT Training to State Objectives

Increased agency effectiveness - recognize agency requests for effective, efficient training so as to enable the agencies to perform their mission critical functions successfully; staff and fund training appropriately.

Increase service delivery to State stakeholders - address poor service delivery, low agency morale, and the increased cost that is caused by the data reconciliation that results from improper data entry at the line and central agency level. Employees cannot learn "on the fly“ when utilizing a complex application while performing time sensitive responsibilities.

Career development - training must become a strategic investment in order to incent state employees

The ability for the State of Connecticut to receive full benefit from its Core-CT investment depends directly on its capability to enable all state Core-CT users so that all line and central agencies perform critical functionality as effectively and efficiently as possible.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 101: Core-CT Assessment Final Report

101© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Perform Audience Analysis In order to effectively bridge the knowledge gap that has been created by the

deployment of the Core-CT application, the need exists to assess the current skill level of the audience to be trained.

It is important to understand the types of users, grouped by business function and level of Core-CT involvement, in order to determine the breakdown of processes and functions per user group.

Understand the magnitude of business process change stemming from the Core-CT effort, in order to understand high level training requirements.

Conduct audience analysis/skills assessment by creating a detailed survey to assess user computer skills and awareness of Core-CT.

The Core-CT team should be prepared to make a sizable investment in terms of time in this area. Leveraging existing documentation is unlikely given the time that has passed since the original Core-CT go-live date.. Understanding the training audience is a cornerstone of successful training delivery.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 102: Core-CT Assessment Final Report

102© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Develop Instructional Training Strategy Assess results of audience analysis - Understand application skill gaps across the

different categories of end users to identify how many users require basic training, advanced training, etc. Assessing these results also drives the content and format of the training materials.

Determine breakdown of groups - This is done by grouping like categories of users by skill and job functions. Certain groups can be trained collectively, while others will require specialized training sessions. The duration of the training sessions will vary.

Determine instructional methodology for end users - Will be based on results of he audience analysis. For complex, detailed, or high-risk functions involving a great deal of worker judgment, consider instructor led training. Determine the appropriate duration necessary for each class.

Determine instructional methodology for Core-CT staff - Core-CT maintenance and support staff, as well as functional resources, should receive a mix of technical and functional training. System administrators and development staff should attend formal Oracle/Peoplesoft training classes.

Determine methods for student assessment - Evaluate user proficiency on Core-CT functionality, and user sensitivity around testing.

Determine training schedule - The results of the audience analysis will determine the level of work effort required to effectively bridge the knowledge gap.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 103: Core-CT Assessment Final Report

103© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Develop Instructional Training Strategy (cont) Determine training schedule - The results of the audience analysis will determine

the level of work effort required to effectively bridge the knowledge gap. This factor also drives the training schedule, which needs to account for the urgency of bridging the gap.

Develop preliminary cost and resource estimates - This task involves presenting the expected costs and necessary resources to develop and deliver the end-user training and performance support program.

The Core-CT team should be prepared to make a sizable investment in this area. The opportunity to leverage past training efforts and existing documentation will be minimal because a formal, robust, and complete training strategy was not developed prior to the Core-CT go-live, nor has it been since.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 104: Core-CT Assessment Final Report

104© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Develop Training Plan Determine Role Mapping -The Core-CT solution is a role-based system. Users will be most

effective if they are familiar with their revised job functions, the expected challenges they will face in their new roles, and how to use the application to support their new roles. Map end users to their appropriate system roles.

Design Curriculum - Design training to center around ‘end-to-end’ processes. Highlight overall process visibility regardless of whether or not the users will be directly performing the entire process. Design the curriculum to provide each end user group with the series of specific courses it needs to develop the Core-CT skills relevant to their roles.

- Include actual agency functionality, and real business processes, in the training design. The training must be relevant to Core-CT users, and must reflect their actual, day-to-day, job responsibilities. This was a serious gap in the original training effort.

Design Training Delivery Method - Delivery methods can vary in terms of technological complexity. They can range from self study to the more complex training delivery methods such as formal learning management systems.

- The Core-CT team should educate itself on the benefits that all types of training deployment tools, and should consider their strengths, potential impact on current training gaps, as well as their complexity, and cost.

- A range of training deployment tools is listed on the next slide

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 105: Core-CT Assessment Final Report

105© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Develop a Training Toolset Deployment Plan Determine future state training delivery goals Assess current training processes

and technology Determine training delivery

capability gaps Develop a roadmap

that will enable the Core-CT team to provide future state training goals

Build a business case around training investments that are necessaryto evolve the training organization

High Technological Complexity

Low Technological Complexity

Self Study Procedures

Job Aides

On the Job Training

Instructor Lead Classroom

Electronic Templates

Computer Based Training (CBT)

Virtual Classroom

Web-Based Training

Learning Management System

Learning Portal

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 106: Core-CT Assessment Final Report

106© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

High Technological Complexity

Low Technological Complexity

Self Study Procedures

Job Aides

On the Job Training

Instructor Lead Classroom

Electronic Templates

Computer Based Training (CBT)

Virtual Classroom

Web-Based Training

Learning Management System

Learning Portal

Short Term

Long Term

Mid Term

Develop a Training Toolset Deployment Plan (cont) Create a realistic deployment timeline,

given the training materials, funding levels, and training personnel that Core-CT has in place today

Fund the effort appropriately Collaborate with central

and line agencies Staff the deployment

project with qualified training and technology personnel

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 107: Core-CT Assessment Final Report

107© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Develop Training MaterialsDevelop Instructional Materials Upon completing the design phase, training materials are developed Training modules are developed in detail according to the training designs, which break

out modules by business process functions. Coordination is required with the Core-CT application team to insert screenshots of the application in the instructional materials.

To the extent that business processes change, end users learn in training what the new processes are, and how their jobs fit into those new processes. The training team should pilot the training courses to a small group of end users during the pilot phase.

The team should capture training feedback and incorporate it into the training prior to delivering the full implementation training.

Develop Job Aids Create Quick Reference Guides for each major job function. Design and develop Quick Reference Guides when developing training materials and

manuals to support end users who have completed the system training.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 108: Core-CT Assessment Final Report

108© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Ensure Training Instance/Infrastructure Readiness Technical Environment Readiness

- A critical success factor for training is to create a dedicated training instance that is as realistic as possible, and is continually maintained.

- To ensure that end-user training goals are met, it is important that the training system contain realistic data.

- The training environment and training database should be built prior to the commencement of train-the-trainer classes.

Facility Infrastructure Readiness- The training should be delivered in a classroom setting that would need to support

fifteen users and two instructors. - Each end user would need a PC to be “hands-on” with the application. - Ensure that solutions function properly and reflect ‘real-life’ situations for all web

based and advanced training solutions. Confirm that data is appropriate.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 109: Core-CT Assessment Final Report

109© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Deliver Training

Training tools should be fully leveraged to support the full spectrum of training delivery. Content should be delivered at the optimal times, for the appropriate duration, using the most relevant tools.

Instructor Led Training- The training should be delivered in a classroom setting where each end user will have his

or her own PC so they are “hands-on” with the application. - The training should be designed to encourage interaction. - The size of the group should be no larger than 10-15 students and two

instructors/facilitators. One facilitator should lead the discussion in the front of the room, and the other observes from the back of the room to determine which participants are lagging and provide appropriate one-on-one coaching.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 110: Core-CT Assessment Final Report

110© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Set Expectations and Evaluation Metrics - A successful process includes setting realistic goals and expectations, as well as marketing the opportunities and communicating the results to agency management, Core-CT staff, and end users. Feedback through interviews and surveys can help enterprises determine the success of various aspects of the training/skill development program.

Develop and Deliver Certification Programs - The increased demand for expertise in new technologies, especially those related to the Internet (e.g., Java, HTML programming), has emphasized the need for certification (programs from vendors (product specific), industry or third party, and government). Certification acts as a strategic tool in ensuring proper completion of training.

Evolve Training Methodology and Toolset - Once the initial training strategy enters the execution phase, planning for the evolution of the training delivery methodology should begin in earnest. Determine a future state training environment and create a roadmap to achieve it, and approve necessary funding

Evaluate Performance - Each training module should include self-paced activities that participants are required to complete on their own in order to successfully complete the Core-CT training course. These activities will tie directly to the learning objectives delivered in the training modules.

Monitor Training Effectiveness - Utilize user competence testing, helpdesk ticket volumes, and trainee feedback to continually evaluate training effectiveness.

Core-CT Assessment – Detailed RecommendationDetailed Recommendation

Page 111: Core-CT Assessment Final Report

111© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationTraining – Recommendation Action Plan

Position training as a strategic component of the ongoing Core-CT support/enhancement program. Create a new training strategy, and make an appropriate commitment to training, in terms of training and qualified resources. Assign a training owner within the ERP Competency Center who will monitor, and be accountable for, the success of the initiative.

Benefits

Q2 20007 – Q2 2008 Develop, Deploy,

Monitor, Improve - TBD

Sponsors: Steering Committee Execution: Director Group, CC Director,

Training Lead

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Create ERP CC training organization (lead and trainers) that is leveraged across all functional and technical teams. Define vision and develop specific charter (Who – Directors/CC Director; When - M3-M7)

- Define Learning Vision and Obtain Leadership Buy-In - Link Core-CT Training to State Objectives

Perform Audience Analysis (Who - Training Lead; When - M9-11) Develop Instructional Training Strategy (Who - Training Lead; When -

M12-M14) Develop Training Plan (Who - Training Lead; When - M15-M16)

Primary Activities

Core-CT user feedback Level 1 helpdesk tickets User competence testing & certification

Dependency on Other Initiatives Dependent on implementing ERP CC structure Success is highly dependent on the ability of the Core-CT leadership team

to elevate the training initiative to a strategic level, and to fund it appropriately.

The timing of the remaining activities is dependent on the Training Plan Develop a Training Toolset Deployment Plan Deliver Training Set Expectations and Evaluation Metrics Develop and Deliver Certification Programs Evolve Training Methodology and Toolset Monitor Training Effectiveness Develop Training Materials Ensure Training Instance/Infrastructure Readiness

Fewer functional inquiry helpdesk tickets Improved accuracy of Core-CT data entry Increased agency effectiveness and efficiency Higher Core-CT user morale

Page 112: Core-CT Assessment Final Report

Final Report – February 2, 2007

Core-CT AssessmentRecommendation DetailsManagement Reporting

Is there an effective plan in place with adequate resources for the future use, administration and maintenance of the system?

What additional steps should the State take to protect its future investments in the system?

Page 113: Core-CT Assessment Final Report

113© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Many organizations invest a significant amount of money successfully implementing a single, integrated, enterprise solution; but cannot access the valuable data that they own.

If the Core-CT team repositions its information as a strategic asset, and follows the Gartner recommendations, the State will be able to gain value from its state-wide data.

Core-CT Assessment – Detailed RecommendationKey Messages

Page 114: Core-CT Assessment Final Report

114© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT users do not have the required knowledge to use the Core-CT Enterprise Performance Management (EPM) module for management reporting.

The Core-CT team has not developed or distributed canned reports that meet agency needs. There is no consistent and easy process to re-use valuable reports by one agency across all other agencies.

EPM analytical functionality has not been implemented, and is therefore not presently available to end users. Analysis needs to be done outside of the Core-CT solution.

Core-CT Assessment – Detailed RecommendationSummary Findings

Page 115: Core-CT Assessment Final Report

115© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Most of the return on investment for management reporting resides in broad deployments, as opposed to identifying a small team of specialized users, serving many managers and other constituents of management information.

The average number of management reporting users is typically relatively low. Approximately half of organizations have reported having fewer than 50 data warehouse users, and approximately 7 percent have reported having more than 1,000 users.

Gartner’s client interactions have not show a correlation between the time that management reporting functionality has been in production and the number of users.

- This demonstrates either a lack of strategic focus on management reporting or a deliberate unwillingness to share information broadly.

- In either case, it amounts to a missed opportunity for the vast majority of organizations.

Core-CT Assessment – Detailed RecommendationGeneral Observations

Page 116: Core-CT Assessment Final Report

116© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Despite the tactical Core-CT business intelligence initiative that is currently under way, it is appropriate for the Core-CT leadership to step back and to assess its effectiveness.

In order to establish a meaningful business intelligence strategy, a dialogue between Core-CT leadership, the Core-CT team, Core-CT EPM super users, and representatives from the user community should take place. The objectives of the discussion should be to:

- Verify business objectives. Are they appropriate, and well-articulated? - Understand how Core-CT EPM can contribute to the success of those objectives - Define the scope, size, and cost, of the business intelligence initiatives- Solidify executive sponsorship and adequate funding.- Confirm whether or not additional EPM functionality is necessary to meet defined objectives.- Determine the impact of improved EPM analysis functionality and increased use of the EPM

query tool.- Understand whether all appropriate users have the necessary training to utilize Core-CT.

Has the appropriate access to relevant data and analysis capability been granted? - Confirm key performance indicators.- Determine the appropriate schedule by which the key performance indicators will be

measured and analyzed.

Core-CT Assessment – Detailed RecommendationDetailed Recommendations

Page 117: Core-CT Assessment Final Report

117© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The State agency leadership, and the Core-CT team, should view Core-CT business intelligence/management reporting as a strategic priority. EPM should be made a strategic asset, rather than a tactical tool, by heightening its visibility.

Re-position the EPM Lead position as a strategic, cross-agency role. Make effective training an immediate focus in order to allow agencies to receive full benefit

from the valuable Core-CT data that exists today.- The State should develop and leverage its training program to provide users with the

necessary technical skills to fully utilize Enterprise Performance Management (EPM).- EPM users require advanced technical training, compared to regular Core-CT users; to

run queries in EPM, an understanding of the database table structure is necessary. Expand and enhance the EPM team by staffing it with qualified technical resources,

effective training staff, and business relationship managers whose goal is to understand and communicate agency requirements.

Implement EPM Analytical functionality. Build and deploy management reports/queries and a process to re-use them across

agencies. - Communicate new functionality effectively and constantly seek improvement feedback. - Management reports should be broadly leveraged across the line and central agencies,

not only within a small group of users.

Core-CT Assessment – Detailed RecommendationDetailed Recommendations

Page 118: Core-CT Assessment Final Report

118© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Management reporting should remain an ongoing strategic focus of the Core-CT competency center, after it has been successfully deployed.

The leadership and staff of the Core-CT competency center should understand the strategic value of business intelligence to the State agencies. The ongoing benefits of Business Intelligence can be ensured by:

- Demonstrating to agency executives how Business Intelligence plays a critical role in better managing the business

- Communicating to the agencies the important benefits that can be gained through Core-CT EPM

- Developing an effective business intelligence strategy that will enable the line and central agencies to make better and more proactive decisions with less effort

- Continually striving to enhance the value of the reports and query tools.- Developing input for EPM reporting and analytics training and building an effective

training vision.- Ensuring the alignment of executives, Core-CT users, the Core-CT Competency

Center, and DOIT leadership

Core-CT Assessment – Detailed RecommendationDetailed Recommendations

Page 119: Core-CT Assessment Final Report

119© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationInitiative Summary – Implement EPM Analytics and Expand EPM Team

Elevate Core-CT business intelligence/management reporting to a strategic priority. Make EPM a strategic asset, rather than a tactical tool. Re-position the EPM lead position as a strategic, cross-agency role. Expand and enhance the EPM team by staffing it with qualified technical resources, effective training staff, and business relationship managers whose goal is to understand and communicate agency requirements.

Benefits

Q1 2007 – Q2 2009 Sponsors: Comptroller, Steering Committee

Execution: Director Group, CC Director, EPM Lead

Metrics and Critical Success FactorsTime FrameSponsors / Execution Responsibility

Initiative Description

Consider expanding to include all reporting capabilities, not just EPM. Define vision and develop specific charter (Who – Directors/CC Director; When - M3-M6)

Re-position EPM as a more strategic service within the ERP CC. Integrate service descriptions and SLAs with ERP CC service catalog (Who – PMO; When - M7-M9)

Rationalize additional staffing gaps with budget request. Structure EPM with qualified technical resources, effective training staff, and business relationship managers whose goal is to understand/communicate agency requirements (Who – Directors/EPM Lead; When - M3-M6)

Short-Term Actions (Who – EPM Leader/Directors; When - M2-M7)- Make effective training an immediate focus to allow agencies to receive full

benefit from valuable Core-CT data.- Develop and leverage its training program to provide users with the necessary

technical skills to fully utilize Enterprise Performance Management (EPM) and create more EPM super users.

Primary Activities

Core-CT user feedback on info access Level 1 helpdesk tickets regarding reporting User ability to use canned reports and EPM

queries

Dependency on Other Initiatives Success of this initiative is highly dependent on the ability of the sponsors

to fund this initiative Dependent on implementing ERP CC structure and service catalog Dependent on training initiative implementation regarding reporting and

information access

- Ad-hoc reports and other reporting utilities (Crystal, Excel, etc.) should be more broadly leveraged across the line and central agencies, not only within a small group of users.

Implement action items in existing budget request (Who – EPM Leader; When - M6-M29)

- Staff EPM with 3 requested positions- Implement EPM Analytical and Portal functionality- Implement EPM Upgrade

Revisit (and possibly build and deploy) management reports/queries, and a process to re-use them across agencies. (Who – EPM Leader; When - do during upgrade)

Communicate new functionality and train effectively. Seek feedback and refine. (Who – EPM Leader; When - Follows implementation timeframe).

Increased use and value of existing data. Improved state level insight and decision-making capability

Higher perceived value of Core-CT investment Improved central agency audit capability

Page 120: Core-CT Assessment Final Report

Final Report – February 2, 2007

Appendix ACore-CT Functionality Gaps

Page 121: Core-CT Assessment Final Report

121© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Missing CoreCT Functionality HR Functions

- Leave accruals within CoreCT are not aligned with State leave accruals; employees are paid bi-weekly but their leave accrues monthly.

- Scheduling functionality gaps exist for the Dept of Correction and the Dept of Health and Safety Rotating averaging schedule functions cannot be performed for the Dept of Corrections. Regular hours are not paid correctly. The Dept of Corrections has to review each check every week to make sure that it’s correct.

- Within the Dept of Mental Retardation (DMR), important information about overtime hours worked by employees cannot be entered; the agency cannot determine whether or not employees are overlapping their regular shifts with their overtime hours.

- Retro pay processing is not always feasible; CoreCT can see only 4 prior pay periods if a person is fired/has a suspension making retro-pay and benefits restoration difficult in those cases. (DOC)

- Retro-active position changes cannot be performed; they must be done manually. This is an issue for agencies with many part time employees. (DOC)

- Holiday time conversion must be performed to convert hours to days within CoreCT. (DOC)- CoreCT has hiring limitations in that people can only be brought in at the beginning of a pay period; checks have to be run from the

petty cash account if new hires commence on any other date. (DOC)

- E-recruiting and employee self service functionality would benefit the central and line agencies

CoreCT Assessment FindingsCore-CT Functionality Gaps

Page 122: Core-CT Assessment Final Report

122© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Missing CoreCT Functionality (Cont) HR Functions

- Payroll Enhanced direct deposit functionality is needed – direct deposit should be expanded to at least two accounts, from only

one. The current i-savings bond should be included. ePay should provide employees with the ability to view pay stubs on line.

Finance Missing Functionality- Missing functionality exists in the following areas: grant processing; inventory, encumbrance; reporting; requisitioning

process. Employees are having difficulty effectively creating requisitions because of encumbrance gaps. Purchasing functionality is not a fit for line agency end user requisitioners

- The application is geared toward central purchasing and as a result the line requisitioners are less efficient.

- Additional purchasing info is available within CoreCT as compared to the legacy application, but the process is more relevant to central buyers, and not for line agency requisitioners.

CoreCT Assessment FindingsCore-CT Functionality Gaps

Page 123: Core-CT Assessment Final Report

123© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Missing CoreCT Functionality (Cont) Finance Missing Functionality

Indirect Materials Inventorying Needs/Catalog Management

- Only items that need to be managed via inventory control should be included in an internal catalog. Other items can be included in punchout catalogs Not all goods should be tracked within the inventory module, given the tight integration between CoreCT’s

inventory module and purchasing module and the need to include inventoried items within internal catalogs. Punchout cannot be leveraged, and as a result, the CoreCT team is devoting a great deal of time/effort

maintaining all internal catalogs.

- Difficulties exist when reconciling different unit of measures between the purchasing and inventory modules; unit of measure data should be synchronized.

- Commitment Control -

- P-Card information does not get into Core

- Federal billing – this functionality does not presently exist in CoreCT and this fact has been a major impediment for the Dept of Transportation. (The 8.9 version of Peoplesoft is going to perform the federal billing functionality that the DOT requires; the gap has been in the implementation timing.)

CoreCT Assessment FindingsCore-CT Functionality Gaps

Page 124: Core-CT Assessment Final Report

124© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Missing CoreCT Functionality (Cont) CoreCT Screen Edits and Validation

- Hard Edits – the ability to put in rules that will stop people from ‘going around the system’. The Peoplesoft application provides the users with a lot of flexibility, much more so than the legacy applications. The legacy applications had these ‘hard edits’. They tried to address this with training, but mistakes still occur. Eg. - The previous system would not let you move off of the screen until the appropriate fields have been entered. They’ve lost these real-time edits.

A few areas are: Salary edits are the most important – cases where people are being paid too much. People that don’t qualify for a job – these situations create a great deal of work. All union employees should only be associated with one union.

- Agency-specific front-end payroll edits have gone away with the introduction of CoreCT, leading to cases of inaccurate input; increased payroll data entry validation is necessary

EPM- The CoreCT application currently lacks useable EPM functionality and sufficient canned reports. The functional

upgrade path should include the creation of a basic data warehouse; analytical intelligence and usage; and, divisional and scorecard capabilities (dimensional reporting).

CoreCT Assessment FindingsCore-CT Functionality Gaps

Page 125: Core-CT Assessment Final Report

125© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Missing CoreCT Functionality (Cont) Security and Role Structure

- The structure of the current security roles, and the restrictions on the access to data that they provide, must be revisited because the current structure does not allow line agencies to perform certain functions in an efficient manner. For instance, a purchasing employee cannot view/process A/P, which is difficult for small agencies with limited resources.

Additional Modules- Program Management, Materials Management, and the Work Order modules would be beneficial for

certain line agencies.

CoreCT Assessment FindingsCore-CT Functionality Gaps

Page 126: Core-CT Assessment Final Report

Final Report – February 2, 2007

Appendix BCore-CT Detailed Staffing Gaps

Page 127: Core-CT Assessment Final Report

127© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Security Team Staffing Requirements

Summary Core-CT Security Staffing GapsStaffing gaps include:

1 Technical Specialist 1 Cross Team Support person for HR1 Cross Team Support person for FIN

Additional Gaps: There is a great need for additional PS Security technical expertise; Managing staff is difficult due to different agency assignments and varying department policies and

leadership. It is difficult to reward highly valued employees appropriately - IT compensation plans are inflexible Until December, 2005, only 1 analyst was assigned to the Security Product Support Team. Do not have the PS Security Engineering expertise in place to lead efforts on researching solutions and

implementing change to improve security configuration and procedures. Large projects relating to new module or agency implementation can monopolize the security team in

setting up new users which is causing a large backlog in daily user security requests, enhancement requests and production support.

Core-CT Security Standards need to be reviewed and updated, security documentation out of date. Specialized training is not always readily available to tech staff. Current IT job classifications are outdated. IT work schedules are limited at 35 hours a week.

Page 128: Core-CT Assessment Final Report

128© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT EPM Team Staffing Requirements

Summary Core-CT EPM Staffing GapsStaffing gaps include:

1 system developer1 HRMS EPM Query Specialist1 EPM Support Specialist

Additional Gaps: It is difficult to recruit qualified IT staff Managing staff is difficult due to multiple agency assignments and varying department

policies/leadership It is difficult to reward highly valued employees appropriately Career paths for Core-CT are non-existent Finding IT candidates with PeopleSoft or enterprise skills is difficult, and ultimately have to be trained Specialized training is not always readily available to tech staff Current IT job classifications are outdated IT Compensation plans are inflexible – compensation should be negotiable for highly skilled IT SMEs

that are not managers IT work schedules are limited at 35 hours a week Documenting procedures inconsistent across teams

Page 129: Core-CT Assessment Final Report

129© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT HR Team Staffing Requirements

Summary Core-CT HR Staffing GapsStaffing gaps include: Functional TeamFunctional Team Position - need one Benefits Team Lead (should report to Core, not Central Bens)Functional Team SME Position - need one more for Payroll and one more for Benefits.

Development TeamDeveloper positions - we have 7, are recruiting 3 and need one more newSupport developer - one new position neededTraining Support - we have lead, we need 2 trainers

Additional Gaps: HRMS lead - no additional resources required Support Level Position - handle tickets and do repetitive work - no additional resources requiredDevelopment Team Manager Position - no additional resources required Contractor position - we have one, which we'd like to keep on the books

Page 130: Core-CT Assessment Final Report

130© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Summary Core-CT Finance Staffing Gaps In addition to the positions already established/identified for the Core-CT Financial Team the Core-CT

team recommends increasing the staffing by a total of five new positions and re-classing one existing vacant technical position to management.

Additional Gaps: Training – two positions are needed to increase the training team staffing to meet the demands of the

user community. The training delivery must be a blend of instructor led and web-based training. The State of Connecticut must invest in new tools (i.e. UPK-User Productivity Kit) to leverage the use of technology for rolling training out to over 5,000 financial users.

Helpdesk – one position to support the implementation of the Projects & Contracts Modules. With the addition of DOT to full utilization of the production system, I anticipate the volume of calls to the helpdesk will significantly increase.

Implementation – the Core-CT team has a constant need to stay current with technology to position ourselves to take advantage of new opportunities. Inherent in this system is the need to constantly apply maintenance packs to the code-line in order to apply new fixes, tax upgrades, etc. This position will also support adding configuration updates to the production system.

Supply Chain - a position is needed to implement and support electronic purchasing commonly referred to as either punch-out or direct connect. This functionality needs to be implemented within the next year.

Page 131: Core-CT Assessment Final Report

131© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Summary Core-CT Finance Staffing Gaps In addition to the positions already established/identified for the Core-CT Financial Team the Core-CT

team recommends increasing the staffing by a total of five new positions and re-classing one existing vacant technical position to management.

Additional Gaps: Financial Development – (re-class an existing position to management) an assistant to the

development lead is needed to effectively manager the large number of developers and contactors assigned to that unit. The current structure has too many direct reports to the lead position, which detracts from his ability to focus on higher level assignments.

Contract Staff – The Financial Development Team has an ongoing need for developers that must continue to be included in the Core-CT funding. Two highly skilled PeopleSoft developers must continue to be part of this team to triage production related issues and develop complex system fixes. The current salary structure precludes us from attracting this unique skill set. It would be very risky to not have this level of expertise readily available and our ability to respond quickly to production issues would be greatly diminished.

Major Initiative – A need exists to develop a strategy to archive existing system data. My opinion is that funding should be budgeted to hire consultants to develop, test and implement an archiving program.

Page 132: Core-CT Assessment Final Report

132© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Draft revised descriptions (prepared by Finance Team leadership) for the 5 different Band classifications are provided on subsequent slides

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Page 133: Core-CT Assessment Final Report

133© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #1 – The Team Leads - four positions - Directs the overall strategic plan to implement effective, efficient and time saving service to the state through use of advanced technologies; directs programs, operations and staff activities and manages all related functions; develops comprehensive long and short range plans and strategies which support the mission and goals of Core-CT. Assists, participates and makes recommendations in review and formation of program priorities, funding, legislation and regulations. Plans, directs and coordinates operation of a major data processing installation which includes systems analysis, programming and computer operations; directs development of production controls and complex processing schedules, establishment and revision of internal operating procedures, preparation of maintenance schedules and records and development and maintenance of systems controls; directs training and assignment of employees; acts as consultant on data processing problems and new applications; assembles data for and prepares special projects and reports; perform related duties as required

Page 134: Core-CT Assessment Final Report

134© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band # 2 – Assist Team Leads, oversees major modules or functions – five positions

Performs a full range of financial analysis for the largest and most complex modules or oversees major activities on the Core-CT Financial Team.

Works directly with OSC, DAS, DOIT and OPM Directors to implement policy changes and to ensure compliance with internal operating controls and complex processing schedules.

Provides input and analysis for ongoing refinement of the financial system and recommends enhancements for director review.

Instructs agency personnel in the proper methods to achieve financial objectives; provides extensive technical assistance to agencies in financial processes of governmental operations.

Assists with long range financial and programmatic strategic analysis and planning. Directs development of production controls and complex processing schedules, establishment and revision of internal operating procedures, preparation of maintenance schedules, records and development, and maintenance of systems controls; directs training and assignment of employees.

Design and develop reports to assist agencies in meeting state and federal reporting requirements.

Page 135: Core-CT Assessment Final Report

135© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band # 2 – Assist Team Leads, oversees major modules or functions – five positions

Knowledge, skills and ability for functional Staff - minimum qualifications required

Considerable knowledge of principles and practices of governmental budget management and governmental accounting; Demonstrated proficiency in Asset Management, Accounts Payable, Accounts Receivable, Billing, Budgeting or Procurement processes.

Considerable knowledge of relevant state and federal laws, statutes and regulations and their significance in a module of the ERP system; ability to utilize an ERP system for financial management; considerable ability to analyze, troubleshoot and resolve the most complex data problems, knowledge of practices and issues of systems security; considerable knowledge of methods and procedures used to conduct detailed analysis of complex system problems and the impact on software; considerable technical problem solving skills; considerable logic and analytical skills; excellent interpersonal skills; excellent oral and written communication skills; The ability to identify significant weaknesses and propose comprehensive changes.

Requirements at this level consist of seven (7) years of experience in computer or network operations, production control, systems development, information technology analysis and planning, with exposure to and working knowledge of Oracle/Peoplesoft.

A minimum of five (5) years experience supporting PeopleSoft applications, of which at least 3 years must include supervisory duties, requirements analysis, design & development of online and batch functionality.

Page 136: Core-CT Assessment Final Report

136© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations (Cont)

Band # 2 – Assist Team Leads, oversees major modules or functions – five positions

Knowledge, skills and ability for functional Staff - minimum qualifications required

Experience working on 1 or more PeopleSoft implementations is required. Development experience with PeopleTools, PeopleCode, SQR, AppMessaging, AppEngine and SQL is required.

Analytical problem solving and excellent written/oral communication skills are also required. Detailed knowledge of PeopleSoft financials and/or human resources modules and module integration is required.

Experience with PeopleSoft version 8 development toolsets is desirable. Experience with PeopleSoft EPM data warehouse and Informatica is desirable. Experience developing interfaces between PeopleSoft and customer sub-systems is desirable. PeopleSoft Certification is a desirable.

Page 137: Core-CT Assessment Final Report

137© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #3 - Assist Team Leads, oversees modules or functions – 12 positions

Performs a full range of financial analysis for operating modules or oversees support activities on the Core-CT Financial Team.

Works directly with the Team Lead and central agency staff to review policy changes and to ensure compliance with internal operating controls and processing schedules.

Provides input and analysis for ongoing refinement of the financial system and recommends enhancements for Team Lead review.

Instructs agency personnel in the proper methods to achieve financial objectives; provides extensive technical assistance to agencies in financial processes of governmental operations.

Assists the Team Lead with long range financial and programmatic strategic analysis and planning.

Assists with the development of production controls and complex processing schedules, establishment and revision of internal operating procedures, preparation of maintenance schedules, records and development, and maintenance of systems controls; directs training and assignment of employees.

Design and develop reports to assist agencies in meeting state and federal reporting requirements.

Page 138: Core-CT Assessment Final Report

138© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #3 - Assist Team Leads, oversees modules or functions – 12 positions

Knowledge, Skill and Ability for Functional Staff - minimum qualifications required

Considerable knowledge of principles and practices of governmental budget management and governmental accounting; Demonstrated proficiency in Asset Management, Accounts Payable, Accounts Receivable, Billing, Budgeting or Procurement processes.

Considerable knowledge of relevant state and federal laws, statutes and regulations and their significance in a module of the ERP system. Ability to utilize an ERP system for financial management; considerable ability to analyze, troubleshoot and resolve data problems, knowledge of practices and issues of systems security; considerable knowledge of methods and procedures used to conduct detailed analysis of system related issues and the impact on software

Considerable technical problem solving skills; considerable logic and analytical skills; good interpersonal skills; good oral and written communication skills; proficiency in multiple software packages.

Considerable organizational and problem solving skills, an ability to work in a self directed manner and considerable knowledge of programming languages; strong SQL skills including usage of Oracle SQL Plus; proficiency with the suite of Peoplesoft development tools including Peoplecode, Peopletools, App Designer, Application Engine, Component Interface and Peoplesoft query; proficiency with the SQR programming languages; knowledge and use of Crystal Reports, Micro Focus Cobol and Nvision a plus.

Strong verbal and written communication skills including competence with development of clear and detailed specifications, policies and procedures.

Page 139: Core-CT Assessment Final Report

139© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #3 - Assist Team Leads, oversees modules or functions – 12 positions

Knowledge, Skill and Ability for Functional Staff - minimum qualifications required

A minimum of three (3) years of PeopleSoft financials development experience is required, of which at least one year must include experience developing general and detail design specifications.

Development experience with PeopleTools, PeopleCode, SQR, PSQuery, AppEngine & SQL is required. Development experience in Cobol could be required depending on the assignment. Analytical problem solving and excellent written/oral communication skills are also required. Detailed functional knowledge of PeopleSoft financial modules (General Ledger, Purchasing, Accounts Receivable, Projects, Accounts Payable, E-Procurement, and Asset Management) is preferred.

Development experience with PeopleTools version 8 is preferred. Experience developing interfaces between PeopleSoft and customer sub-systems is preferred. Experience mapping customer legacy data elements to PeopleSoft data elements is desirable. PeopleSoft Certification is desirable

Page 140: Core-CT Assessment Final Report

140© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #4 – Supports module or other Lead Functions – 15 positionsProvides support to leads with the most complex modules or to higher level functional or technical positions. Provide supervision to lower level staff assigned to their respective functions. Ability to determine priorities; assigns, oversee and reviews work; provides staff training and assistance.Developers would be responsible for; calculating project time and cost estimates; preparing necessary procedural specifications to meet design requirements; writing program specifications and systems specifications; defining data flow; design forms, screens, and reports. Assists in planning and establishment of new technological directions; assists in development of information technology policies, procedures and standards; serves as an expert resource and consultant for information systems staff and users in more complex applications.

Page 141: Core-CT Assessment Final Report

141© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #4 – Supports module or other Lead Functions – 15 positionsKnowledge, Skill and Ability for Functional Staff - minimum qualifications required Considerable knowledge of principles and practices of governmental budget management and governmental accountingDemonstrated ability in Asset Management, Accounts Payable, Accounts Receivable, Billing, Budgeting or Procurement processes. Knowledge of relevant state and federal laws, statutes and regulations and their significance in a module of the ERP system; ability to utilize an ERP system for financial management; ability to analyze, troubleshoot and resolve data problems, knowledge of practices and issues of systems security; knowledge of methods and procedures used to conduct detailed analysis of system related issues and the impact on softwareTechnical problem solving skills; logic and analytical skills; good interpersonal skills; good oral and written communication skills.Considerable organizational and problem solving skills, an ability to work in a self directed manner and considerable knowledge of programming languages; strong SQL skills including usage of Oracle SQL PlusProficiency with the suite of Peoplesoft development tools including Peoplecode, Peopletools, App Designer, Application Engine, Component Interface and Peoplesoft query; proficiency with the SQR programming languages; knowledge and use of Crystal Reports, Micro Focus Cobol and Nvision a plus. Strong verbal and written communication skills including competence with development of clear and detailed specifications, policies and procedures.

Page 142: Core-CT Assessment Final Report

142© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #4 – Supports module or other Lead Functions – 15 positionsKnowledge, Skill and Ability for Functional Staff - minimum qualifications requiredA minimum of two (2) years PeopleSoft financial development experience is required.  Development experience with PeopleTools, PeopleCode, SQR, SQL, AppEngine, and PSQuery is required. Development experience in Cobol could be required depending on the assignment.        Analytical problem solving and excellent written/oral communication skills are also required.Experience with PeopleTools version 8 development toolsets is desirable. Experience mapping customer legacy data elements to PeopleSoft data elements is desirable. Experience developing interfaces between PeopleSoft and customer sub-systems is desirable. PeopleSoft Certification is desirable.

Page 143: Core-CT Assessment Final Report

143© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Core-CT Assessment – Detailed RecommendationDetailed Core-CT Finance Team Staffing Requirements

Core-CT Finance Team Band Descriptions – Revision Recommendations

Band #5 – Supports Module or other Lead Functions – 14 positionsThis is a professional working level class having responsibility for independently performing duties under the direction of modules leads or higher level functional positions. The trainers and helpdesk staff will provide direct support to the user community. The functional/module staff will work closely with the module leads and developers to design and test system functionality. These positions will be fast track positions to move onto promotional opportunities either within Core-CT or at the agency level.

Knowledge, Skill and Ability for Functional Staff - minimum qualifications required Knowledge of principles and practices of governmental budget management and governmental accounting; knowledge of purchasing principles and proceduresKnowledge of Asset Management, Accounts Payable, Accounts Receivable, Billing, or Purchasing. Ability to understand relevant state and federal laws, statutes and regulations and their significance in an ERP systemAbility to utilize an ERP system for financial management; ability to resolve data problems, knowledge of practices and issues of systems security; technical problem solving skills; logic and analytical skills; interpersonal skills; oral and written communication skills.

Page 144: Core-CT Assessment Final Report

Final Report – February 2, 2007

Appendix CDetailed Initiative Roadmap Timeline

Page 145: Core-CT Assessment Final Report

145© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

The electronic file containing the work plan has been provided to the State of CT in a separate file.

CoreCT Assessment FindingsDetailed Initiative Roadmap Timeline

Page 146: Core-CT Assessment Final Report

146© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

CoreCT Assessment FindingsDetailed Initiative Roadmap Timeline

Page 147: Core-CT Assessment Final Report

147© 2007 Gartner, Inc. All Rights Reserved.Final Report – February 2, 2007

Michael KlubalGartner ConsultingTelephone:+ 1 416.804.7255Facsimile: +E‑mail: [email protected]

Thomas KrivdaGartner ConsultingTelephone:+ 1 215 280 4558 Facsimile: +E‑mail: [email protected]