COPYRIGHT © AREMA 2008 of 42 1 TUNNELS
Mar 29, 2015
COPYRIGHT © AREMA 2008
of 42 1
TUNNELS
COPYRIGHT © AREMA 2008
of 42 2
General
• Tunnel Inspections present unique challenges• Track Time Sensitive• Good lighting source required• Various types of Tunnels and
– Construction Materials• Conditions found may warrant Expert Evaluation
of structure
COPYRIGHT © AREMA 2008
of 42 3
SAFETY
• Confined / Enclosed Space• Fumes from motorized Inspection Vehicle• Adequate Lighting• Walking Hazards- Wet / Ice• Wildlife
COPYRIGHT © AREMA 2008
of 42 4
External Environment
Note areas over & around Portals• Vegetation• Ground Water• Adjacent Slopes• Rock Slopes
COPYRIGHT © AREMA 2008
of 42 5
Internal Environment
• Natural Gas Pockets / Ground Water
• Conduits for Utilities / Fiber Optics
• Cut-Outs for Inspectors
• Drainage
• Pumps
COPYRIGHT © AREMA 2008
of 42 6
Vegetation Adjacent Slopes
COPYRIGHT © AREMA 2008
of 42 7
Rock Slopes
COPYRIGHT © AREMA 2008
of 42 8
Portals (Tunnel Inspection)
• Openings at each end of Tunnel
• Headwalls / Wingwalls
• Concrete/Stone/Timber/Natural Rock– Height of Headwall / Wingwalls– Stability / Structural Integrity
• Lateral movement / water seepage
– Note Condition / Deficiency• Timber Decay / Concrete Cracks,Deterioration
COPYRIGHT © AREMA 2008
of 42 9
Headwalls(date)/Wingwalls
COPYRIGHT © AREMA 2008
of 42 10
Natural Rock Portal
COPYRIGHT © AREMA 2008
of 42 11
Drains in Wall
COPYRIGHT © AREMA 2008
of 42 12
Tunnel Shaft
• Fundamental Tunnel Structure– Detailed Inspection Notes Thru Tunnel– Permanent Stationing Makers Thru Tunnel
• Various Types of Construction or Combination of Types of Construction
- Natural Rock
COPYRIGHT © AREMA 2008
of 42 13
Natural Rock
COPYRIGHT © AREMA 2008
of 42 14
Natural Rock-Anchor Bolts
COPYRIGHT © AREMA 2008
of 42 15
Timber & Steel Sets
• Timber Posts on Sides of Tunnel with Timber cut at angles to form Arch
• Timber Mud Sills on Stone or Concrete
• Spacing of Timber Sets determined by stability of the surrounding material
• Steel Sets are fabricated similar to the Timber Sets construction with Steel Beams
COPYRIGHT © AREMA 2008
of 42 16
Original Construction
COPYRIGHT © AREMA 2008
of 42 17
Timber Portal /Shed
COPYRIGHT © AREMA 2008
of 42 18
Steel Set / Lagging
COPYRIGHT © AREMA 2008
of 42 19
Steel Set / Lagging
COPYRIGHT © AREMA 2008
of 42 20
Lagging / Cribbing
• Lagging-Timber or Steel placed horizontally between Timber or Steel Sets
• Lagging can fully line the tunnel or support only unstable areas
• Cribbing/Packing: Material Placed behind Lagging or Liner to fill void between lagging and failed material.
COPYRIGHT © AREMA 2008
of 42 21
Cribbing Behind Liner
COPYRIGHT © AREMA 2008
of 42 22
Concrete / Masonry
• Reinforced Concrete Walls / Arch
• Masonry Walls / Arch ( Brick, Stone)
COPYRIGHT © AREMA 2008
of 42 23
Concrete Lined Tunnel
COPYRIGHT © AREMA 2008
of 42 24
Brick Lined Tunnel
COPYRIGHT © AREMA 2008
of 42 25
Steel Lining
• Corrugated Steel
• Ribbed Tunnel Liner Plates
COPYRIGHT © AREMA 2008
of 42 26
Tunnel Floor
• Natural Ground when Tunnel was cut
• Struts below ballast to each side of Tunnel
• Reinforced Concrete
COPYRIGHT © AREMA 2008
of 42 27
Problems / Conditions
• Natural / Exposed Material– Cracks, Openings, Movement– New pieces of Rock on floor– Loose Rock Bolts, Anchors
COPYRIGHT © AREMA 2008
of 42 28
Material on Tunnel Floor
COPYRIGHT © AREMA 2008
of 42 29
Loose Rock Bolts
COPYRIGHT © AREMA 2008
of 42 30
Problems / Conditions
• Timber Sets / Lining– Decay; Sound and/or Drill for voids– Bottom Sill; Bearing Area, Crushing, Bulging– Joints, Gaps, Alignment– Bolts, Drift Pins
COPYRIGHT © AREMA 2008
of 42 31
Problems / Conditions
• Steel Sets / Lining– Benchwall: Anchors, Corrosion– Columns / Struts: Corrosion, Section Loss,
Buckling / Alignment– Bulging in Walls / Arch
COPYRIGHT © AREMA 2008
of 42 32
Failed Steel Liner
COPYRIGHT © AREMA 2008
of 42 33
Problems / Conditions
• Lagging: Timber, Steel– Decay , Corrosion, Section loss– Openings at Seams / Joints, Bulging– Ground or Failures behind lagging
COPYRIGHT © AREMA 2008
of 42 34
Problems / Conditions
• Concrete / Masonry Lining– New Cracks, Spalling, Bulging– Movement at Construction Joints– Water Seeping, weep holes– Brick / Concrete on floor– Movement , Hinging at Spring Line– Bulging of Walls and Arch – Benchwall / Footer
COPYRIGHT © AREMA 2008
of 42 35
Failed Concrete Liner
COPYRIGHT © AREMA 2008
of 42 36
Problems / Conditions
• Tunnel Floor / Roadbed– Track Surface– Muddy / Pumping / Fouled Ballast– Drainage Ditches / Culverts
• Train Impacts / Clearance– Signs of Impacts– Verify Dimensions-
• Top/Rail & Centerline Track
COPYRIGHT © AREMA 2008
of 42 37
Impact Damage
COPYRIGHT © AREMA 2008
of 42 38
Tunnel Inspection Checklist
• PORTALS– Soil / Rock Stability– Condition of Headwall and Wingwalls– Drainage behind Headwall and Wingwalls– Surface Drainage
COPYRIGHT © AREMA 2008
of 42 39
Tunnel Inspection Checklist
• SHAFT– Clearances-Bulges in Ceilings / Walls– Fractured or Scaling Stone– Condition of Rock Bolts and Anchors– Condition of Timber/ Steel Sets /Lagging
COPYRIGHT © AREMA 2008
of 42 40
Tunnel Inspection Checklist
• SHAFT– Condition of Concrete / Masonry Lining
• Bulges• Cracks• Tuckpointing• Surface voids
COPYRIGHT © AREMA 2008
of 42 41
Tunnel Inspection Checklist
• SHAFT– Tunnel Floor
• Debris on floor indicating problems• Buckling or heave• Fouled Ballast• Drainage• Water / Ice accumulation
COPYRIGHT © AREMA 2008
of 42 42
EMERGENCYIf the bridge inspector encounters a tunnel condition that affects the safe operations of trains in, or near the tunnel, contact the railroad dispatcher and responsible authority to stop any trains and arrange for immediate repairs. Criteria for limits of acceptable/tolerable conditions must be provided by the Railroad Owner or their designated engineer based on the principles of acceptable rating contained in the appropriate chapter of the AREMA Manual for Railway Engineering