Page 1 of 3 Addendum No. 1 CONTRACT DOCUMENTS AND SPECIFICATIONS FOR Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road) KENNER, LOUISIANA SEALED BID NO. 15-6280 ************************************************************* ADDENDUM NO. 1 DATE ISSUED: June 19, 2015 BID DATE: June 25, 2015 BID LOCATION: City of Kenner Purchasing Department, 1801 Williams Blvd. Building C, 3 rd Floor, Kenner, LA. 70062 I. SCOPE: This addendum shall be part of the Contract Documents as provided in the Instructions to Bidders. The following items are issued to add to, modify, and clarify the Contract Documents. These items shall have full force and effect as the Contract Documents and the cost involved shall be included in the bid price. Acknowledge receipt of the addendum by inserting its number on the Bid Form (page 11 of the Contract Documents). Failure to do so may subject the bidder to disqualification.
15
Embed
CONTRACT DOCUMENTS AND SPECIFICATIONS · b. Tie‐in work and/or bypass pumping will need to be coordinated with the City of Kenner Public Works Department and Veolia.passIf by pumping
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1 of 3 Addendum No. 1
CONTRACT DOCUMENTS AND
SPECIFICATIONS
FOR
Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road)
BID LOCATION: City of Kenner Purchasing Department, 1801
Williams Blvd. Building C, 3rd Floor, Kenner, LA. 70062
I. SCOPE:
This addendum shall be part of the Contract Documents as provided in the Instructions to Bidders. The following items are issued to add to, modify, and clarify the Contract Documents. These items shall have full force and effect as the Contract Documents and the cost involved shall be included in the bid price. Acknowledge receipt of the addendum by inserting its number on the Bid Form (page 11 of the Contract Documents). Failure to do so may subject the bidder to disqualification.
Page 2 of 3 Addendum No. 1
This Addendum No. 1 consists of Pages 1 through 3 and Attachment. The Addendum No. 1 will be sent to all interested parties no later than June 19, 2015, via email, and overnight delivery of hard copy.
II. CONTRACT DOCUMENTS AND SPECIFICATIONS A. GENERAL
1. The Engineer’s Opinion of Probable Cost of Construction is $1,050,500, including 10% contingency.
2. The pre-bid conference was held on June 11th, 2015 @ 10:00. The sign-in sheet
(1 page) and pre-bid agenda are attached and hereby made part of this addendum.
3. Questions have also been submitted to the Engineer from the various plan
holders and contractors. The list of the questions and responses are provided in Attachment.
B. SPECIFICATIONS
1. Technical Specification Section 16940, Process Instrumentation and Control (Page 16940-3), delete 1st line “Acceptable Manufacture…Jackson, MS.” of Part 4.01 Motor Control Center.
2. Delete No. 18 under “Information for Bidders” (current page 8) in its entirety and replace with the following:
“18. Award of Contract: Owner shall award a contract to the Bidder who, in Owner's judgment, is the lowest responsive, responsible Bidder. Owner reserves the right to reject any or all Bids, and to reject nonconforming, nonresponsive, or conditional Bids. In evaluating Bids, Owner shall consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, alternatives and unit prices if requested in the Bid Form. Owner may consider the qualifications and experience of Subcontractors and may reject the Bid of any Bidder who does not pass any such evaluation to Owner's satisfaction. The rejection procedure will be in accordance with the Louisiana Public Bid Law, LSA-R.S. 38:2212 et seq. In the event that a bid is awarded, a formal written notice of intent to award will be given to the lowest responsible bidder who had bid according to the contract, plans, and specifications as advertised. The low bidder’s attestation pursuant to LA R.S. 38:2212.10 (“Affidavit Employment Status
Page 3 of 3 Addendum No. 1
Verification”), LA R.S. 38:2227 (“Past Criminal Convictions of Bidders”), and LA R. S. 38:2224 (“Non-Collusion Affidavit”) shall be furnished by low bidder within ten (10) days after the bid opening. All other documentation required to be submitted by low bidder, including, but not limited to, a performance bond, labor and materials payment bond, hold harmless agreement, and insurance certificate(s), shall be furnished to Owner prior to contract execution. Should Contractor receive a notice of disapproval and/or deficiency from Owner or Design Professional regarding any of these documents, Contractor will be given seventy-two (72) hours from the date of such notice to correct deficiency. In the event that Contractor fails or refuses to furnish the required certificates, bonds, etc., Owner reserves the right to disqualify said Contractor and award the bid to the next lowest responsive bidder who had bid according to the contract, plans, and specifications as advertised. The date on bond forms shall be left blank for filling in by Owner. The certification date on the power of attorney also shall be left blank for filling in by Owner. Owner shall insert the date on bond forms, and power of attorney, and return copies to Design Professional for review and distribution. If contract is awarded, Owner shall do so within forty-five (45) days of the bid opening, unless the successful Bidder has agreed in writing to hold its bid price for a longer period.”
C. PLANS
No comments received at time of distribution. Note: The following items are attached and hereby made part of this addendum:
a. Supplementary Questions/Responses b. Pre-Bid Conference Sign-In Sheet (1 page) c. Pre-Bid Agenda (pages 1 thru 3) d. Plan Holder List as of June 18, 2015 (1 page) e. Revised Information for Bidders (pages 6 thur 9 of Contract Documents
Guide). Due to revision contract documents has one addition page (1 thru 62)
f. Revised Technical Specification Section 16940, (page 16940-3 )
END
Addendum No. 1
Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road)
Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road)
KENNER, LOUISIANA
SEALED BID NO. 15-6280
Additional Questions to the Engineer
1. Supplementary Conditions SC-2.06 Builder’s Risk Insurance. Is Builder’s Risk
Insurance required? No structure is being built, only demolished. Response: No.
2. Are the sanitary sewer pumps for 4103 Firehouse Road required to be explosion proof?
Response: Yes.
Page 1 of 3
PRE‐BID CONFERENCE AGENDA
DATE & TIME: June 11th, 2015 @ 10:00 a.m. – 11:00 a.m.
PROJECT: City of Kenner Sewer Repair Program Kenner Hanson City Sewer Lift Station Improvements For LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road) Sealed Bid No. 15‐6280 A/E Project No. 11‐011‐77
LOCATION: City of Kenner Public Works Auditorium 1610 Rev. Richard Wilson Dr. Kenner, LA 70062
BID DATE: All bids are to be submitted on Thursday, June 25, 2015 by 9:45 a.m. to the City of Kenner Purchasing Department, 1801 Williams Blvd. Building C, 3rd Floor, Kenner, LA. 70062. Bids will be opened and publicly read at 10:00 a.m. in the City of Kenner Purchasing Department.
I. Introduction
a. Introduction of attendees including the Owner, Project Engineer and their
representatives
II. Project Scope
a. Scope of Work, type of construction, and special features
The proposed Work consists of modifications to the existing Airline and Minden
(4102) and Firehouse Road (4103) sewer lift stations.
b. The project consists of the following:
Airline and Minden (4102): The modifications to the existing lift station will include
the replacement of the current self‐priming motors and pumps with two (2)
submersible pumps, the construction of a pile supported slab for valves and
discharge piping, the rehabilitation of the existing wet well, and the installation of a
new control panel including a pile supported slab, fence, and hatch covers along
with a new top slab.
Firehouse Road (4103): The modifications to the existing lift station will include the
removal and replacement of the three (3) Vertical Non Clog pumps and motors
including valves and discharge piping, the rehabilitation of the existing wet well, the
installation of a new control panel, removal of the existing building along with all
needed slab modifications.
Page 2 of 3
c. The Contractor is responsible for the layout of the work. Data for control points for the
Contractor’s use are included in the drawings.
d. The Contractor is responsible for pre‐construction videos and photos, as these are
critical due to the proximity of the lift station to other structures.
e. The Contractor shall not drive piles without a testing lab representative on site with
vibration monitoring equipment.
f. The Contractor is responsible for coordination with residents in the area regarding
access to their homes during construction.
g. The Contractor will be responsible for obtaining any site required for staging of
equipment and materials if it is required.
h. The Contractor will be required to provide as‐built information prior to final closeout.
III. Review Contract Time of Performance and Liquidated Damages
a. Contract time is 240 calendar days.
b. Liquidated damages are 0.1% of the contract amount including change orders per
calendar day of default, or $500 per day, whichever is greater.
IV. Procedures for Bidding and Awarding Contract
a. The bids must be submitted utilizing the bid package provided in the specifications. The
bidder must take care to comply with state bid laws
i. Proposals received after the time for opening will be returned to Bidder
unopened.
ii. Bids must be written in ink or typed and signed by a member of the firm
authorized to sign. No pencil written or photocopied bids will be accepted.
iii. Bids shall be submitted on bid form provided in these Specifications. Bid shall
be submitted in a sealed envelope with the name of the Bidder, his address,
Name of project and the State License number of the Bidder.
iv. Evidence of the agency, corporate, limited liability or partnership authority is
required for submission of bid. Such fact shall be contained in the bid
documents and proof shall be provided with the bid in accordance with the
provisions of LSA‐R.S 38:2212 (A)(1)(c) or LSA‐R.S. 38:2212 O. FAILURE TO DO
SO SHALL RESULT IN BID BEING REJECTED.
v. Proof of insurance and certificates of insurance naming the city and other
parties as required in the Supplementary Condition shall be supplied within
twelve (12) calendar days after receipt of notice of award of the Contract by the
Owner.
vi. The amount of the bid guarantee shall be not less than five (5%) percent of the
amount bid and at the option of the bidder may be a cashier’s check, certified
check, money order or a satisfactory bid bond attached to the bid form, unless,
a project, funded in whole or in part by State and/or Federal Funds, is governed
by State and/or Federal Regulations or Laws which require a bid guarantee in a
Page 3 of 3
different amount , in which event the State and/or Federal Regulations or Laws
shall take precedence.
V. Coordination with City of Kenner
a. The Contractor will be required to submit a traffic plan at least two weeks prior to
beginning construction for review and approval.
b. Tie‐in work and/or bypass pumping will need to be coordinated with the City of Kenner
Public Works Department and Veolia. If bypass pumping is required, a diesel engine
with sound attenuators with a sound less than 60 decibels may be used, if elected by the
Contractor.
c. Contractor is responsible for any permits that may be required including any applicable
fees. A building and electrical permit is required. For more information on permit fees,
please contact Ms. Billie Gautreaux with Kenner Code Enforcement at (504) 468‐4070.
d. The City of Kenner cannot provide water for the project. The Contractor must contact
Jefferson Parish to obtain water for the project.
VI. Project Funding
a. The work under this project has been funded by the Community Development Block
Grant (CDBG) Disaster Recovery program. Please review the contract documents for
CDBG Compliance Provisions including Section 3 requirements to ensure that
employment and economic opportunities be directed to low and very low‐income
persons and/or subcontractors in the project area. Details will be discussed at the pre‐
construction meeting.
b. Davis Bacon Wage Rates have been included in contract documents will be confirmed 10
days prior to the bid opening and if changed will be issued under an addendum. The
Contractor will have to abide by the Davis Bacon Act provisions.
c. Weekly certified payrolls shall be submitted with the monthly estimates for Contractors
and Sub‐Contractors, along with signed wage decision and equal opportunity statement.
CDBG may check posted regulations requirements, and interview workers at any time.
VII. Review Procedures for Submittals
a. Hartman Engineering, Inc. will review all submittals in a timely manner, and will
maintain adequate staff to provide quick turnaround to all requests.
VIII. Budget
a. Engineer’s Opinion of Probable Construction Cost is $ 1,050,500.00.
IX. Contractor Questions
a. Questions concerning plans and specifications will be investigated and changes if
warranted will be made by addendum.
Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road) Hartman Engineering Inc. Project No. 11-011-77-40
1. Receipt and Opening of Bids: The City of Kenner (herein called the "Owner"), invites bids on the form attached hereto. All blanks must be appropriately filled in. Bids will be received by the Owner at the office of Purchasing Department until 9:45 a.m. the 25th day of June, 2015, and then at said office publicly opened and read aloud. The envelopes containing the bids must be sealed, addressed to City of Kenner Purchasing Department at 1801 Williams Blvd., 3rd Floor Building C, Kenner, LA 70062 and designated as bid for Kenner Hanson City Sewer Lift Station Improvements for LS 4102 (Airline Drive/Minden) and LS 4103 (Firehouse Road). The Owner may reject any and all bids for just cause; such actions will be in accordance with Title 38 of the Louisiana Revised Statutes. Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified shall not be considered. No bidder may withdraw a bid within 45 days after the actual date of the opening thereof except as provided by law.
2. Preparation of Bid: Each bid must be submitted on the prescribed form. All blank spaces for bid prices must be filled in, in ink or typewritten, in both words and figures.
Each bid must be submitted in a sealed envelope bearing on the outside the bidder’s name and address and the name of the project for which the bid is submitted. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as specified in the bid form.
3. Contractors may obtain and submit bids electronically by visiting www.centralauctionhouse.com. If submitting bid electronically, a bid bond is the only acceptable form of bid security. A cashier’s or certified check will be NOT accepted
4. Subcontractors: The bidder is specifically advised that any person for or other party to whom it is proposed to award a subcontract under this contract must be acceptable to the Owner.
5. Method of Bidding: The Owner invites the following bid(s):
(THIS SECTION MUST BE COMPLETED: UNIT PRICE BID OR LUMP SUM BID)
6. Determination of Unit and Extended Prices: In unit price bids, the total amount bid shall be in the sum of the correct extensions of the unit price bid on each item of work multiplied by the approximate quantity of work shown for the respective item. Each extension shall be carried to one hundredth of a dollar, and the last digit in the extension (or cents’ place) shall not be rounded off.
7. Erasures: The bid submitted must not contain erasures. Any and all interlineations or other corrections shall be suitably authenticated by affixing in the margin immediately opposite the correction the initials of the person or persons signing the bid.
8. Prices: In the event of a discrepancy between the prices quoted in words and those quoted in
figures in the bid, the words shall control. The prices are to include the furnishing of all materials, plant, equipment, tools, and all other facilities, and the performance of all labor and
07/31/14 Page 7 of 62 Version 3.4
services necessary or proper for the completion of the work except as may be otherwise expressly provided in the contract documents.
9. Qualifications of Bidder: The Owner may make such investigations deemed necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy the Owner that such bidder is responsible and is properly qualified to carry out the obligations of the contract and complete the work contemplated therein. Any conditions placed on a submitted bid shall result in rejection of such bid.
10. Bid Security: Each bid must be accompanied by cashier’s check or certified check of the bidder, or a bid bond, duly executed by the bidder as principal and having as surety thereon a surety company approved by the Owner, in the amount of 5 percent of the bid made payable to the Owner. Such cashier’s checks, certified checks, or bid bonds will be returned to all except the three lowest bidders within three days after the opening of bids, and the remaining cashier’s checks, certified checks, or bid bonds will be returned promptly after the Owner and the accepted bidder have executed the contract, or, if no award has been made within 45 days after the date of the opening of bids, upon demand of the bidder at any time thereafter, so long as he has not been notified of the acceptance of his bid.
Sureties used for obtaining bonds must appear as acceptable on the U.S. Department of the Treasury Circular 570.
11. Liquidated Damages for Failure to Enter into Contract: The successful bidder, upon his failure or refusal to execute and deliver the contract and bonds within 10 days after he receives notice of the acceptance of his bid, shall forfeit to the Owner, as liquidated damages for such failure or refusal, the security deposited with his bid.
12. Time of Completion and Liquidated Damages: Bidder must agree to fully complete the project within 240 consecutive calendar days thereafter. Bidder must agree to pay as liquidated damages the sum of $500.00 or 0.1% of the contract amount including change orders (whichever is greater) for each consecutive calendar day thereafter until acceptance as hereinafter provided.
13. Conditions of Work: Each bidder must inform himself fully of the conditions relating to the construction of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of his obligation to furnish all materials and labor necessary to carry out the provisions of his contract. Insofar as possible the contractor, in carrying out the work, must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor.
14. Addenda and Interpretations: No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally.
Every request for such interpretation should be in writing addressed to Hartman Engineering, Inc., c/o Bryan K. Joseph, at 527 West Esplanade Avenue, Suite 300, Kenner, LA 70065 and to be given consideration must be received at least five (5) days prior to the date fixed for the
07/31/14 Page 8 of 62 Version 3.4
opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be mailed by certified mail with return receipt requested to all prospective bidders (at the respective addresses furnished for such purposes), not later than three (3) days prior to the date fixed for the opening of bids.
Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the contract documents.
15. Security for Faithful Performance: Simultaneously with his delivery of the executed contract, the successful bidder shall furnish a surety bond or bonds as security for faithful performance of this contract and for the payment of all persons performing labor on the project under this contract and furnishing materials in connection with this contract. The surety on such bond or bonds shall be a duly authorized surety company satisfactory to the Owner. Only those surety companies currently on the U. S. Department of Treasury Financial Management Services list (Circular 570) of approved bonding companies will be accepted. The agent selling the bond must be currently licensed to do business in Louisiana. This will be verified by the Owner.
The successful bidder will be required to file a performance bond in the total contract amount (100-percent) of the contract price for the full period of the contract and a payment bond in the total amount (100-percent) of the contract price for the full period of the contract.
16. Power of Attorney: Attorneys-in-fact who sign bid bonds or contract bonds must file with each bond a certified and effectively dated copy of their power of attorney.
17. Laws and Regulations: The bidder's attention is directed to the fact that all applicable State laws, municipal ordinances and rules and regulations of authorities having jurisdiction over construction of the project shall apply to the contract throughout, and will be deemed to be included in the contract the same as written herein in full.
18. Award of Contract: Owner shall award a contract to the Bidder who, in Owner's judgment, is the lowest responsive, responsible Bidder. Owner reserves the right to reject any or all Bids, and to reject nonconforming, nonresponsive, or conditional Bids.
In evaluating Bids, Owner shall consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, alternatives and unit prices if requested in the Bid Form. Owner may consider the qualifications and experience of Subcontractors and may reject the Bid of any Bidder who does not pass any such evaluation to Owner's satisfaction. The rejection procedure will be in accordance with the Louisiana Public Bid Law, LSA-R.S. 38:2212 et seq.
In the event that a bid is awarded, a formal written notice of intent to award will be given to the lowest responsible bidder who had bid according to the contract, plans, and specifications as advertised. The low bidder’s attestation pursuant to LA R.S. 38:2212.10 (“Affidavit Employment Status Verification”), LA R.S. 38:2227 (“Past Criminal Convictions of Bidders”), and LA R. S. 38:2224 (“Non-Collusion Affidavit”) shall be furnished by low bidder within ten (10) days after the bid opening. All other documentation required to be submitted by low bidder, including, but
07/31/14 Page 9 of 62 Version 3.4
not limited to, a performance bond, labor and materials payment bond, hold harmless agreement, and insurance certificate(s), shall be furnished to Owner prior to contract execution. Should Contractor receive a notice of disapproval and/or deficiency from Owner or Design Professional regarding any of these documents, Contractor will be given seventy-two (72) hours from the date of such notice to correct deficiency. In the event that Contractor fails or refuses to furnish the required certificates, bonds, etc., Owner reserves the right to disqualify said Contractor and award the bid to the next lowest responsive bidder who had bid according to the contract, plans, and specifications as advertised.
The date on bond forms shall be left blank for filling in by Owner. The certification date on the power of attorney also shall be left blank for filling in by Owner.
Owner shall insert the date on bond forms, and power of attorney, and return copies to Design Professional for review and distribution.
If contract is awarded, Owner shall do so within forty-five (45) days of the bid opening, unless the successful Bidder has agreed in writing to hold its bid price for a longer period.
19. Obligation of Bidder: At the time of the opening of bids, each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the plans and contract documents (including all addenda). The failure or omission of any bidder to examine any form, instrument or document shall in no way relieve any bidder from any obligation with respect to his bid.
16940-3
A. The services of a qualified representative of the selected Single Source System Supplier
shall be provided to inspect the completed installation, suggest all adjustments necessary to place the system in proper operation, and instruct operating personnel in the care and operation of the equipment furnished. A minimum of two days and two trips start-up service and training operating personnel shall be included. The services shall be furnished by the Contractor as a part of the work included under this section of the specifications.
B. The System Supplier shall show satisfactory evidence that he maintains, a fully equipped
factory organization capable of furnishing adequate service for the equipment furnished, including replacement parts within a 200 mile radius of job site. Suppliers employing outside organizations for "ON CALL" service shall not be considered.
3.02 GENERAL INSTALLATION
A. Installation of instrumentation and controls shall be in strict compliance with the manufacturer's instruction. The locations of these items as shown on the Contract Drawings are approximate only. Exact locations shall be as approved by the Engineer during construction. It is the duty of the Contractor to obtain, in the field, all relevant information required for proper placement of instrumentation and controls. In the case of interference with other work, proceed as instructed by the Engineer and provide all materials and labor required to prevent construction delays.
B. Execution of the installation shall be in full accordance with codes and local rulings. The
Contractor shall be responsible for any expenses that are a result of work performed contrary to said codes and regulations.
C. The System Supplier shall coordinate with the Contractor the installation, the location of
process equipment, and connections of process equipment to related equipment panels, subject to the Engineer's approval. Other equipment being furnished by the General Contractor with electrical controls or instrumentation must be submitted to the System Supplier for approval and coordination with all other control and instrumentation on this project. This engineer will not approve any equipment submittal until this coordination has been accomplished.
PART 4 - MOTOR CONTROL CENTER 4.01 Multi Unit Motor Control Center where and as shown on drawings and as herein specified.
A. Where materials, equipment, apparatus or other products are specified by manufacturer, brand name or type, or catalog number, such designation is to establish standards of desired quality and style and shall be the basis of the bid. Except where noted, it is implied that “or approved equal” follows all specified items. Approval for substitutions will be granted by the Architect/Engineer to the Electrical Contractor only, through the General Contractor. Where two or more designations are listed, choice shall be optional with the Contractor.