SUMMER TRAINING PROJECT REPORT CONTRACT AND PROCUREMENT MANAGEMENT SYSTEM AND RATIO ANALYSIS OF NTPC AT NTPC, NOIDA SUBMITTED TOWARD PARTIAL FULFILLMENT OF MASTER OF BUSINESS ADMINISTRATION 2009- 2011
Dec 14, 2014
SUMMER TRAINING PROJECT REPORT
CONTRACT AND PROCUREMENT MANAGEMENT
SYSTEM AND RATIO ANALYSIS OF NTPC
AT NTPC, NOIDA
SUBMITTED TOWARD PARTIAL FULFILLMENT OF
MASTER OF BUSINESS ADMINISTRATION 2009-2011
Under Guidance of:- Submitted by: Mr. P.K GOEL SAKSHI BHATNAGAR DGM (Finance) ROLL NO:0906370091
GLA INSTITUTE OF TECHNOLOGY AND MANAGEMENT MATHURA
PREFACE
This project report deals with the procedures, practices and guidelines adopted by the NTPC
Limited with respect to the procurement of various goods and services which are essential for
carrying of the smooth functioning of the activities performed at the office. These practices
are followed during all procurement by NTPC. The purchase procedure starts at Indenting by
the department that requires the material and goes to the cost department and finance
department for required approval and vetting. A brief introduction about the procedure along
with the procurement policy is given along with the recommendation and the limitations of
the procurement system. Furthermore this project aims to analyze the financial strength of the
company and aims to interpret them thereof with the help of ratio analysis.
i
ACKNOWLEDEMENT
The six weeks Summer Training at NTPC have been a great learning experience. It has been
one of the most enriching experiences for me to work along with the employees of one of the
best managed organizations, a company rightly considered as the Navratna among the public
sector undertakings of the India.
I am very thankful to Sh.P.K GOEL DGM (Finance) who has given an opportunity to learn
about the procurement procedures followed here by allowing me to undergo training at their
Finance (Concurrence) Department. He gave me full support to learn the crucial things of this
whole exercise. I am thankful to sir for the his kind support in completion of this project
report by guiding me throughout my training, for his support, guidance and providing the
valuable information from his vast experiences which has enabled me in successfully
completing the Summer training which is an essential part of my MBA course curriculum.
SAKSHI BHATNAGAR
ii
TABLE OF CONTENTS
S.N TOPIC PAGE
NUMBER
1 INTRODUCTION OF TOPIC 1
2 NEED AND RELEVANCES OF STUDY 3
3 OBJECTIVE OF STUDY 4
4 INTRODUCTION OF NTPC 5
6 POWER STATION IN INDIA OF NTPC 9
7 RESEARCH METHODOLOGY 12
8 PROCUREMENT STEPS 13
9 TENDERING PROCEDURE 14
10 RATIO ANALYSIS OF NTPC 40
11 FINDINGS 63
12 RECOMMENDATION 64
13 LIMITATION OF STUDY 65
14 CONCLUSION 66
15 APPENDIX 69
INTRODUCTION OF TOPIC
The report entitled “CONTRACT AND PROCUREMENT MANAGEMENT SYSTEM
AND RATIO ANALYSIS AT NTPC” is about the purchase practices followed at NTPC for
every equipment.
Procurement Management at NTPC starts with Indenting by the department that requires the
material and goes to the cost department and finance department for required approval. In
between various activities like Liquidated Damages calculation, Spare Parts procurement
terms, Guarantee in Liability Defect period etc are undertaken. Once all the terms and
conditions are formulated and approved, the tender document preparation starts. The tender
documents are issued to the prospective bidder for a cost that starts from Rs 200 to Rs 3000.
The content of the tender document is prepared in such a manner that the prospective bidder
comes to know about all the important details about the contract. The issuance of tender
document is followed by the receipt of Bids from various vendors in the specified format.
Once all the bids are received, they are opened in presence of some nominated officials from
Finance, Contracts and Materials department. The representatives from the bidders may also
be present. Then a comparative statement of the quoted bids is prepared and the contract is
1
awarded to the lowest quoting bidder.
During the document preparation phase, payments terms are also decided and documented in
the General Condition of Contract, which is issued to the bidder with the tender documents.
Apart from payments, there are various other issues like Arbitration, which are dealt in the
tender documents. Liquidated Damages is one of the very important clauses. Liquidated
damage is a payment to be made by the contractor in case he fails to complete the project in
the stipulated time. The purchase is followed by the evaluation, which is done for two things,
the vendor’s performance and the purchase performance. The Vendor evaluation comes in
handy for placing future orders where as the Purchase Performance evaluation provides
detailed insight into the procedures being followed to procure the required material.
Financial statement analysis is yet another one of the important part of the project where in
various crucial ratios which help to analyze the financial position of the company are being
calculated which provide inside into the growth prospects of the company. The tool used for
financial statement analysis is Ratio Analysis. Ratio Analysis is the process of determining
and presenting the relationship of items or group of items in the financial statement. It has
emerged as a principle technique for the analysis of the financial statements of the
companies.
These ratios are being calculated with the help of the 2 most important financial statements
of the company i.e. profit and loss account and balance sheet. These are important not only
for the working of the company but they are even important for the outsiders of the company
like creditors, investors etc. and further its comparison with other power sector players
Reliance Energy and Tata power will help to analyze the better position of the company in
comparison to others or in case of any loop holes the company can perform better in future.
The project also includes over all study of the power sector which will help in knowing the
company in much better sense and its position in power sector.
2
NEED AND RELEVANCES THE STUDY
This project is an effort to understand the procurement practices followed at NTPC and to
understand what they keep in mind before awarding a particular bid contract to the specific
bidder. Thus, the scope covers the following areas:
The rules, regulations and the appropriate policy that is taken as base, which serves as a
guideline to guide all through the procurement process.
Various steps involved in the procurement process.
The conditions of contracts, requirements to be submitted by the bidder during the
contract.
It will also highlight the condition taken into consideration in the award of contracts at the
NTPC.
Additionally the Ratio Analysis tool of Financial Statement Analysis has been used to
analyze the profitability, solvency, liquidity and performance of the company from year
2008-2010
All the above points covered helps an individual in understanding the What, Why, How
of the procurement procedures at the NTPC
3
OBJECTIVE OF THE STUDY
This project tries to achieve the following objectives:
To study the procurement procedure in NTPC.
To study how important is the role of finance concurrence department at various stages
of the procurement process.
To understand the criteria and procedure on which the bidders are selected for placing
an order
Using Ratio Analysis the aspects of the profitability, solvency, liquidity and performance
are adjudged.
4
INTRODUCTION TO THE NTPC LIMITED
NATIONAL THERMAL POWER CORPORATION
NTPC is the largest power generating company of INDIA and contributes one-fourth of the
thermal energy generated in the country. A public sector company, it was incorporated in the year 1975 to accelerate power development in the country as wholly owned company of the Government of INDIA. It has 463 rank in the World Top Class 2000 Companies which is
improve from the last year rank i.e. 486. At present, Government of INDIA holds 84.5% of the company and the balance is held by FIIS, Domestic Banks, Public and others. Within a
span of 35 years, NTPC has emerged as a truly national power company, with Power Company, with power generating in all major regions of the country
5
Vision And Mission
Vision"A world class integrated power major, powering India’s growth, with increasing global presence."
Mission“Develop and provide reliable power, related products and services at competitive prices, integrating multiple energy sources with innovative and eco-friendly technologies and contribute to society.”
Core Values – BCOMIT Business Ethics
Customer Focus
Organisational & Professional Pride
Mutual Respect & Trust
Innovation & Speed
Total Quality for Excellence
6
Recognitions & Awards
NTPC has a glorious record of excellence in every field of
its activities ever since its inception in 1975. Leading the
country’s power sector with a vision to become a 75,000
MW company by 2017, we take pride in our people and
their performance which has been acknowledged time and
again at various national and international level
Achievements: Sixth largest thermal power generator in the World and the Second most efficient
utility in terms of capacity utilization.
Contribution of NTPC in power generation: NTPC has contribution of 28% of total power generation capacity of India.
NTPC’S CULTURE Core values are both intensely and widely shared
Climate of high behavioral control
Low employee turnover
High agreement among the employees, for what NTPC stands for.
All these point to the fact that strong cohesiveness, loyalty and organization commitment exist in NTPC lowering he attrition Rate
7
Organization Structure of NTPC
Organization structure includes three levels of management i.e. corporate level including top management, then region level comprising management of SBU regional level management & last as planning level management as GMs of various plants.
Chairman & Managing Director
Director (HR)
Director (Finance)
Director (Projects)
Director (Operations)
Director (Commercial)
Director (Technical)
Executive Director (NR)
Executive Director (NCR)
Executive Director (NR)
Executive Director (WR)
Executive Director (SR)
General Manager General Manager General Manager
8
POWER STATION OF NTPC IN INDIA
Power Generation
Presently, NTPC generates power from Coal and Gas. With an installed capacity of 28840 MW, NTPC is the largest power generating major in the country. It has also diversified into hydro power, coal mining, power equipment manufacturing, oil & gas exploration, power trading & distribution. With an increasing presence in the power value chain, NTPC is well on its way to becoming an “Integrated Power Major.”
9 [ Singrauli | Korba | Ramagundam | Farakka | Vindhyachal | Rihand ]
[ Kahalgaon | NCTPP | Talcher Kaniha | Unchahar | Talcher Thermal | Simhadri |
Tanda]
[ Anta | Auraiya | Kawas | Dadri Gas | Jhanor-Gandhar | Kayamkulam | Faridabad]
PERFORMANCE OF NTPC’s COAL/GAS BASED POWER STATION
10
REGION WISE AND STATION WISE PERFORMANCE 2002-2003
STATION CAPACITY
GENERATION
1. North region 4280 31810
2. Singroli 2000 15474
3. Rihand 1000 7674
4. Unchahar 840 6561
5. Tanda 440 2101
6. National Capital Region 3152 23008
7. Dadri coal 840 6673
8. Anta 413 3060
9. Auraiya 652 4684
10. Dadri gas 817 5730
11. Faridabad 430 2861
12. Western Region 5653 39562
13. Korba 2100 16605
14. Vindhyachal 2260 15590
15. Kawas 645 3745
16. Jhanor-gandhar 648 3615
17. Eastern Region 3900 21634
18. Farakka 1600 8418
19. Kahalgaon 840 4514
20. Talcher kaniba 1000 6236
21. Talcher thermal 460 2466
22. Southern Region 2950 17178
23. Ramagundam 2100 15846
24. Kayamkulam 350 1316
25. Simhadri 500 1500
11
RESEARCH METHODOLOGY
The methodology adopted for the present study was discussion with company guide, experts
and doing daily practical work of the organization. The main focus was to gain knowledge
and experience during the training period that will help understand the whole process of
tendering in procurement management.
Research Design:
To achieve the objectives stated above, I have done “Descriptive Research” and for that data
is collected from secondary sources.
Research Method:
Secondary data collection technique to achieve the objectives stated above, “Descriptive
Research” is taken into account.
Collection of Data
The data and information for the project is collected by studying various handbooks, assist-
books, bidding documents and internal circulars.
The research methodology comprised of secondary data collected from various NTPC
records and through NTPC website.
Secondary Data:
1. NTPC website
2. Manuals of NTPC
3. NTPC Records
4. Other websites
12
PROCUREMENT STEPS
Procurement life cycle in modern businesses usually consists of seven steps:
Information Gathering : If the potential customer does not already have an established
relationship with sales/ marketing functions of suppliers of needed products and services
(P/S), it is necessary to search for suppliers who can satisfy the requirements.
Supplier Contact : When one or more suitable suppliers have been identified, Requests
for Quotation (RFQ), Requests for Proposals (RFP), Requests for Information (RFI) or
Requests for Tender (RFT) may be advertised, or direct contact may be made with the
suppliers.
Background Review : References for product/service quality are consulted, and any
requirements for follow-up services including installation, maintenance, and warranty are
investigated. Samples of the P/S being considered may be examined, or trials undertaken.
Negotiation : Negotiations are undertaken, and price, availability, and customization
possibilities are established. Delivery schedules are negotiated, and a contract to acquire
the P/S is completed.
Fulfillment : Supplier preparation, shipment, delivery, and payment for the P/S are
completed, based on contract terms. Installation and training may also be included.
Consumption, Maintenance and Disposal : During this phase the company evaluates the
performance of the P/S and any accompanying service support, as they are consumed.
Renewal : When the P/S has been consumed and/or disposed of, the contract expires, or
the product or service is to be re-ordered, company experience with the P/S is reviewed.
If the P/S is to be re-ordered, the company determines whether to consider other suppliers
or to continue with the same supplier
13
TENDERING PROCEDURE FOLLOWED AT NATIONAL
THERMAL POWER CORPORATION LTD(NTPC)
Procedure:
DOP (DELEGATION OF POWER) All the activities undertaken at NTPC are regulated by a guideline called “DELEGATION
OF POWERS” or “DOP” in short. The guideline lays down the responsibility and authority
of various level executives in the PSE (Public Sector Enterprises). Based on this guideline the
following major procedures have been identified.
However, procurement of any material for any plant or the office of NTPC is done by two
processes. These processes are:-
Procurement through tenders.
Emergent Procurement
Though in case of urgency the respective department is allowed to make procurement
through cash up to the limit of Rs. 10,000 only. But in case of the normal procurement that is
done by tendering, a standard procedure is followed where the intender sends the
procurement list to the finance department for the goods valued over Rs. 10,000 for vetting.
Once the finance department clears the cost aspect of the tender it is send for the
required approval from the competent authority as described in the DOP. After getting the
required authorization the indent is forwarded to materials, contracts or HR services as is
suitable. From there a tender notice is issued and the procurement process starts.
The following are the steps involved:
Promotion of competition, efficiency and economy in electricity industry can be conveniently
achieved through the process of competitive bidding. The Central Government issued
14
detailed guidelines for competitive bidding of power projects in January 1995 whereby the
competitive procurement of power sector projects was made mandatory. These guidelines
laid emphasis on project identification, justification and development before taking up
competitive bidding.
1. Indent by the engineering department who coordinates the equipment requirement.
2. Preparation of cost estimate in association with cost engineering department and
seeking approval thereof.
3. Preparation of the bid documents for issue of NIT. The documents include INB,
General Condition of Contract, and special conditions of contract. Once all the terms
and conditions are formulated and approved, the tender document preparation. The
content of the tender document is prepared in such a manner that the prospective
bidder comes to know about all the important details about the contract
4. Issue of NIT-usually the publication in the newspaper or trade journal. The tender
documents are issued to the prospective bidder for a cost that starts from Rs 200 to Rs
3000.
5. Receipt of bids and bid opening. The issuance of tender document is followed by the
receipt of Bids from various vendors in the specified format. Once all the bids are
received, they are opened in presence of some nominated officials from Finance,
Contracts and Materials department. The representatives from the bidders may also be
present.
6. Bid evaluation- a comparative statement of the quoted bids is prepared and the
contract is awarded to the lowest quoting bidder. The process involves Vendor
evaluation and assessment that includes the physical verification of assets and
manufacturing facilities as well as the financial capacity of the bidder.
7. Contract of award is given to the lowest bidder.
15
INTRODUCTION TO PROCUREMENT
Procurement activities to be taken by NATIONAL THERMAL POWER CORPORATION
(NTPC) are to satisfy varying project requirement of equipment, materials and services. Any
procurement-requiring adherence to the IDA procurement procedure, long equipment
delivery periods, intense engineering co-ordination or specialized engineering knowledge
during procurement etc. would be classified as category “A” contracts. All other procurement
contracts pertaining to a project will be classified as category “B” contracts.
Procurement at NTPC is initiated on the basis of approved indents/requisitions and
indicating budget and project estimate provisions. The contract services/materials
management services receive the requisition/indent for the procurement of
materials/equipment/services duly approved by the competent authority and then plan and
organize the procurement action.
Objective
The basic objective of procurement management at NTPC is to make available, the needed
equipment, material, works and services in the right quality and quantity, at the right time and
at the right price after giving fair and equal chance to renderers’, so as to obtain the optimum
value for each unit of expenditure
What is a contract?
A contract in its simplest form defined as a promise, or group of promises, that the law will
enforce. The promise is to do, or refrain from doing, a particular activity.
But in commercial context, a contract is a document in which the terms of the promise are
recorded. It can also be explained, as “a contract is an agreement enforceable at law between
two or more parties to undertake or perform a particular thing. In undertaking or performing
that activity both the parties accept certain responsibilities and in return receive certain
benefit for performing the same.
16
Procedure of procurement
Intent of the contracting parties :
An agreement between the two parties does not itself constitute a contract. There must be a
definite promisor, each of whom is legally capable of performing the intended part of the
agreement. It is necessary for the two parties to have their agreement legally binding, that is,
that the agreement be written and enforceable by law.
At NTPC the department, which requires the materials is known as intending department and
the department that procures the material is known as the material department. Hence
intending department is the customer for material department.
All these steps are discussed here in detail:
1. Intending for Procurement: Procedure for intending is as follow:
17
INDENT
COST ESTIMATION
FINANCE
CONTRACT MATERIAL HR
For the purpose of indenting, material planning is required. It is nothing but classifying
the materials into various categories to facilitate a speedy and efficient procurement. In this
process all the materials which may be required at any of the NTPC projects or offices are
classified in to five major categories and their procurement is to be done on the basis
predefined for them.
1. Stock item (Automatic Recoupement items/AR)
2. Insurance Items (I)
3. Unit Replacement item (UR)
4. Capital Item (P)
5. Other non-stock items (Not falling under any of the above category)
Identification of Responsibilities.NTPC being a utility organization with projects located away from the corporate office, has
divided the responsibilities of contracts management, both pre award and post award between
the corporate office and project site. A contract management functions as an independent
specialized techno commercial function unit to meet the overall corporate objective in the
area of project procurement. It has been in place since inception of NTPC as corporate
contract department or concurrence department.
The corporate contracts procures plants/ equipment and services for its projects, which are
characterized by the adherence to the procurement of external funding agencies, factoring of
the long process owner for award of all such contracts including high value civil works, its
monitoring and post award follow up till the delivery of equipment from the suppliers works
till the closure of the contracts.
The corporate contracts division/department is responsible for installation of the plant &
equipment and its execution is the responsibility of the project site.
There are number of the other small value contracts with lesser of engineering coordination,
whose pre award and post award contracts are handled by the project sites. The principles and
guidelines followed for these site contracts are similar to those applicable to corporate
contracts.
18
In view of the complexity involved in the construction of thermal generation projects. The
contracts management systems calls for the further sharing of responsibilities for specialized
functions such as engineering, finance, cost engineering, quality assurance and inception at
corporate center & erection, site finance, field quality assurance etc. as the project site. The
co-ordination and division of responsibility between the departments at two responsibility
centers are also clearly defined.
Stages of international competitive bidding (ICB)
Step 1
(a) Contract packaging
Contract packaging is the first step of procurement for a project. The total project work is
broken into smaller well-defined packages. This is done with the view to optimize the
number of contracts to be handled for the better planning, co-ordination and
implementation of the whole project and at the same time to execute the project at an
optimum cost to the owner.
(b) Development of packages
First of all feasibility report for any project is prepared which contains the details of the
various equipment systems and services required for a particular project.
Subsequently, as the conceptual design progresses, a detailed project description
emerges as design intent memorandum (DIM) incorporating station schematics like
thermal schematics, electrical signal line diagrams, and station water flow systems, coal
and ash handling systems etc. these schematics provide the inter linkage between the
various equipments and services. The engineering function is responsible for
development of such schematics. Taking into consideration the requirement of the
project master network (PMNW) schedule, grouping of equipment and services is done
to arrive at contract packages. Each package as developed above normally forms an
independent contract.
19
The development of contract package list for a project is done jointly by engineering,
contracts, and corporate planning and finance functions. The contract package being
extremely vital to a successful project implementation is approved for implementation
by the highest corporate level authority.
2. Cost Estimation: Cost estimation process is the most important financial activity in the process of budgeting
and procurement. Whenever NTPC procures some material, it is either financed from the
budget allocated to the particular department requesting for the material or it will be financed
from the central fund. The procurement of the second kind requires financial clearance from
the Finance Concurrence department. For the purpose, cost estimate is made before
forwarding the indent document to the Finance department. There are various methods of cost
estimation, which are used at NTPC. Some of the methods use very technical details and
procedures whereas others are simple to implement and uses market rate to prepare a cost
estimate.
Historical Cost Method:In this method of cost estimation. The cost engineering department at NTPC uses the latest
cost incurred for a similar kind of project. For example, if a cost estimate has to be prepared
for· a new Thermal Power Plant, the latest executed Thermal Power Plant rates will be used
not any other. Hence the rates thus obtained are very near to the actual that might be
prevalent in the market at present. But to
20
HISTORICAL COST METHOD
MARKET RATE METHOD
smoothen the effect of inflation and various other financial components in the price at the
time of the execution of that project, an escalation factor is used. All the prices of previous
projects are multiplied by this factor and a very close estimation of market rate is thus
obtained. The escalation factor calculation is discussed separately in the report.
Market Rate Method:
Market rate method is used for the procurements that are not in very large numbers and value.
In this method once an indent is prepared, some of the vendors registered at NTPC or listed in
trade journals are sent a request for quoting the prices of a particular good. This enquiry is not
a tender and the rates provided by the vendors are not part of the bid. After the information is
received, the rates quoted by various vendors are compared and the lowest quoted price is
taken as base rate for calculation. However if the difference in the price quoted by two
vendors are reasonably high an average of the two may be taken as the base. However for
civil works component of the contract, the wages rates are taken from the government
gazettes and similarly for some homogeneous products like cement, steel etc a standard
market prevailing rate is used
3. Tendering and Bidding Documents: Normally an open tendering system for procurement is adopted during construction stage of
a project. However depending on the circumstances and the requirements, limited tendering
or single tendering system is also adopted in specific cases. Following are three types of
tenders:
21
TYPE OF TENDERS :
1. Open Tender:
Procurements or value Rs 1 lakh and above must be done through open tendering. All the plant
packages are procured through Open Tender. Open tender is accessible to all known, reliable
and proven sources of particular equipment/material. For the purpose, a notice inviting
tenders must appear in two or more newspapers of all India repute in addition to one or more
local newspaper where the material/equipment is to be delivered. However to avoid frivolous
tenders, a pre-qualification procedure may be adopted. This process will take place once in
every three years by advertising in two or more newspapers of all India repute in addition to
one or more local newspaper where the material/equipment is to be delivered. The criteria for
pre-qualification will inter-alia consist of past performance, financial soundness, technical
competence, organizational capability etc. But for the items valued less than Rs 1 lakh the
pre-qualification can be done on the basis of data available in Trade Journals, Manufacturer's
Directory, or approved vendors list of State Government/Central Government/DGS&D
vendors to whom enquiries were floated in past.
22
Single tender
Limited tender
Open tender
2. Limited Tender :
Limited tender is a type of tender where instead of sending bid enquiry to all the possible
vendors through newspapers, a limited number of vendors arc intimated through post or fax.
But a Limited Tender may be invited only for the procurements worth less than Rs. 50000/-.
In limited tender, a minimum of four bidders are invited to quote the prices for the required
equipment/material /services and these four bidders must be from the approved list of
vendors mentioned in the open tender. However a Limited Tender is a special case and
cannot be issued without proper explanation and requirement. In case of urgency, items worth
more than Rs. 50000/- may also be procured with authorization of competent authority and
the reason must be recorded in the indent documents. However the next higher authority of
the procurement department will decide the number and names of supplier.
3. Single Tender: This type of tendering is the easiest and fastest to acquire a good but requires lot of paper
work and authorization before the acquisition can be initiated. These acquisitions take place
on the ground of proprietary items or standardization. To initiate a single tender, a Proprietary
Article Certificate must be issued by a competent authority and the purchase will not be made
without authorization of a Genial Manager or to whom the power is delegated. This type of
tendering is monopolistic in nature and is avoided to the extent possible. However Single
Tendering is done in many other cases which are not mentioned anywhere in the DOP.
The Invitation for Bids (IFB)/ Notice Inviting Tender (NIT) are published in leading national
newspaper as per guidelines and procedures. Copies of IFB/NIT are also sent to the bidders
who have evinced interest in supplying similar equipment/services in the past. An the case of
procurements funded by external funding agencies following International Competitive
Bidding procedures, the IFB us also published in the Indian Trade Journal and a copy of IFB
sent to each of the embassies/ High commissions of member countries of the funding agency.
In case of procurements under the World Bank funding, the IFB is also published in the
‘Development Business’ of United Nations when required.
23
CONTENTS OF BIDDING DOCUMENTS:
Every time when an open tender is invited, the bidders are provided with a set of
documents, which provides various required information and terms and condition of the
contract The documents also contains the various contract forms which the bidder is
expected to sign and return to NTPC to acknowledge the acceptance of the terms and
condition of the contract. The document also contains the guidelines for bidders for
bank guarantee. Earnest money and the like, this document is issued for a cost
that is decided on the basis of the total estimated value of the indent.
Every time a new tender is notified, a set of tender documents is issued against a payment of
stipulated fee according to the price list given above. This set of tender document consists of
many different documents meant for different purposes. The documents may vary from
project to project. Here we will see what the documents that are generally issued to bidders
are.
(A) Instruction to Bidder (1TB): This document is meant to provide the
bidders the vital information required to understand and evaluate the tender offer. The
document contains the general instructions like the Terms of Payment, Bid Security,
Contract Performance Security, Liquidated Damages, Currencies conversion, Defects
Liability and Work Schedule. The document also specifics the Qualifying/Eligibility
requirements of the bidder and the goods/services supplied. The ITB also contains
information for the foreign bidders. Additionally the ITB contains various references
to clauses of GCC (General Condition of Contract) and SCC (Special Condition of
Contract). Finally the document specify about the language and interpretation and
implied terms and condition of all the documents provided with the bid. ITB also
contains information about how to modify and withdraw the bids already submitted to
NTPC. Hence in short we can identify this document as the guidelines and
information brochure to bidders before they submit their quotation for the notified
work.
24
(B) Bid Proposal Sheet or Bid Data Sheet : Bid proposal sheet is a set of
documents which contains the formats for bidding, Summary price proposal, Break up
of Bid price, Equipment wise price break-up, civil works price break-up, commercial
deviation, Technical deviations, Guarantee declaration, Price Adjustment data, Price
break up of recommended spares, Construction Equipments, Special Maintenance
Tools, QR Data and capacity data, Work completion Schedule, Declaration of Import
content, Check list, Information regarding value addition and Type test charges. This
document is nothing but a standard format providing the bidder to -Furnish the details
required by the NTPC in a standard format used at NTPC.
(C) General condition of Contract: The document titled General
Condition of Contract of GCC is a document that takes care of the legal aspect of the
contract between the bidder and NTPC. This document also is an integral part
of all the bid documents with some minor changes or no changes at all. The
document starts with the definition for The terms used in various tender documents.
This is worth noting that all the terms used in the bid document are predefined and have
one and only meaning which is defined in the GCC. The document also contains different
formulae that are to be used on some future dates to calculate the LD or the Price
Escalation. Finally the document also refers to the unforeseen events like Out Break of a
War, Bankruptcy of the contractor or any other Force Majeure. The GCC also has a clause
called RESOLUTION OF DISPUTES that specifies the procedures to be followed if any
dispute occurs, arising out of or in connection with the Contract.
(D) Special Conditions of Contract: Special Condition of Contract or SCC is
not a standard document that is issued with all the tender documents. The document
takes care of the special issues that have come up or may come up in the course of the
execution of that particular contract and has not been covered in the General
Condition of Contract. The very first clause of the document is TIME-THE
ESSENCE OF CONTRACT. The document also talks about the detailed
25
(E) Manufacturing plan and Master Schedule of the execution of the contract. It is the
SCC where we mention the issues related to Liquidated Damage Clause. This is
mentioned in the document itself that "The following Special Condition (if Contract
shall supplement the General Condition of Contract. Wherever there is a conflict. The
provisions herein shall prevail over those in the General Conditions of contract.
Hence the document may also be considered as the amendments to the GCC.
(F) Erection Condition of Contract: This document again is specific
document which may not be issued with all the tenders. As the name itself suggests.
The document deals with the erection component of the contract (if any). In the
document some particular issues pertaining to the erection component of the contract
is dealt with. Typically, an Erection Condition of Contract deals with the civil
construction works undertaken at the site where the equipment is to be installed and
commissioned. This also takes into consideration the statutory and local authority who
may be in charge of monitoring the work in progress and whose permission may be
required. Hence this document is a must for all the work where there is an erection
component.
(G) Technical Specification: The document is the thickest document or any
bid document. This document contains all the specification required for that particular
project. The document is prepared by the Project Engineering department and
contains the technical specifications of the equipments and spares to be procured. It
may also contain the drawings of the equipment or layout of the project. Similarly the
document will also enlist all other possible alternatives to the already mentioned
specifications (if any). Since there are no financial aspects associated with this
document, a detailed study of this document is out of the scope of this report.
26
TENDER COMMITTEE:
As we have mentioned earlier, Delegation of Power has a very important role to play in
purchasing process At NTPC. For every purchase value of exceeding Rs 50000/-.
The committee consists of three members, one representative each from the
Indenting department, Materials Department and Finance (Concurrence). The representatives
are nominated by competent authority varying from Senior Manager to DGM depending
upon the value of the contract. This committee will take into consideration every possible
aspect of the terms and conditions, prices, inspection procedures, phasing delivery if required
etc. This committee also formulates the QR (Qualifying Requirements) for the bidders of that
particular tender.
TENDER OPENING:
Tender opening is the penultimate step in the purchasing process. Tenders are opened on the
due date and time mentioned in the tender notification without fail. If the data mentioned is
declared holiday, the next working day will be considered as the opening date but the time
will remain the same. The sealed envelopes containing the bid will be opened by the purchase
and finance executives nominated by their Head of the Department. The representatives of
the bidders may also present themselves if they wish so however their absence will not hinder
the process. The name and rates quoted by all the present bidders will be read out and any
omission or irregularity will be pointed out on the spot.
Alterations or erasures (if any) will be initiated by the officers present at the
time or the opening of the tenders. All the quoted figures should also be encircled and will be
written in words if the bidder have not done so already and will be attested. Total number of
erasures and correction will also be written and attested. These all activities are done to
ensure proper and transparent procurement process.
SECURITY DEPOSITS:
A refundable security deposit may be asked at the time of submission of the bid. This deposit
is taken to ensure that the vendor who is awarded the contract will not refuse to undertake the
contract. If the bidder after successful bid refuses to undertake the contract, the earnest
27
money deposited by him will be forfeited. However there arc various instances where this
deposit may be waived off. For example for all the purchases valued less than Rs. 50000/- the
EMD may be waived off. Similarly for the PSUs, NSICs and SSI parties, the EMD can be
waived also. On successful completion of bidding the earnest money may either be returned
to the bidder or may be adjusted towards the security deposit to be provided by the
bidder. Another major deposit is in form of performance guarantee or Liquidity
damage (LD) the equipments provided by the vendor fail to perform as per
the specification, the cost for this shortfall may be recovered from the vendor. This
guarantee is generally 10% of the awarded value and is generally in form of bank guarantee.
However in cases of procurement from OEM/OES or proprietary· vendor the same may be
waived depending upon the merit of case.
However in case of procurement of equipment/material/services there is a contract for
providing spares for the next three years. In case the prices of these spare parts goes up in the
future and the vendor refuses to supply the spares at the same rate this guarantee deposit will
be forfeited. As a matter of fact, this guarantee is taken just to make sure that the contractor
does not refuse to honor the contract in future after he realizes that the prices have gone up or
for some similar reasons.
4. Cost of Bidding Documents:
S.N. ESTIMATED VALUE OF INDENT COST OF TENDER DOCUMENT
1 Up to Rs. 10 lakhs 200
2 Above Rs 10 lakhs and up to 25 lakhs 300
3 Above Rs 25 lakhs and up to Rs 50 lakhs 500
4 Above Rs 50 lakhs and up to Rs 100 lakhs 750
5 Above Rs 100 lakhs and up to Rs 500 lakhs 1500
6 Above Rs 500 lakhs 3000
28
5: Receipt and Opening Submission, of Bids:
The time allowed for preparation and submission of bids by the bidders is decided taking
Into consideration the particular circumstances and complexity of work involved.
Generally, a period of not less than 6 weeks from the date of Invitation of Bids is
considered for preparation and submission of bids. For large and complex packages this
Period is extended to 10 –12 weeks.
Document comprising the bid
The bid submitted by the bidder shall comprise of the following documents:
1. Bid form duly completed and signed by the bidder.
2. All price schedule duly completed in all respect by the bidder.
3. The bid shall contain necessary detail of the equipment and mandatory spares to be
imported from associated /collaborator by manufacture or bidder.
Each bidder shall submit with its bid the following attachments:-
1. Attachment 1: Bid Security
2. Attachment 2: Power of Attorney
3. Attachment3: Bidder Qualification
4. Attachment4: Eligibility and Conformity of the Facilities
5. Attachment5: Subcontractors Proposed by Bidder
6. Attachment6: Deviations
7. Attachment7: Alternative Bids
8. Attachment8: Local Representation
9. Attachment9: Deemed Export Benefits
10. Attachment10: Functional Guarantees
11. Attachment11: Erection Tools and Tackles
12. Attachment12: Technical Data Sheet
13. Attachment13: Bought Out Items
29
14. Attachment14: Quality Assurance Program
15. Attachment15: Additional Information
16. Attachment16: Milestone Schedule
17. Attachment17: Price Adjustment Data
18. Attachment18: Equipment and Mandatory Spares to be imported from
Associated Collaborator.
Bid Form and Price Schedules
The bidder shall complete the form and appropriate price schedules furnished in the bidding
documents as indicated therein.
Bid Prices
Bidders shall quote for the entire facilities on a single responsibility basis such that the total
bid price covers all the contractors obligations mentioned in or to be responsibly inferred
from the bidding documents in respect of the design manufacture, including procurement and
sub contracting, delivery, constructions installation commissioning, completion of the
facilities and conduct of guarantee test for the facilities including supply of mandatory spares.
This includes all requirement under the contractors responsibilities for testing, pre-
commissioning and commissioning of the facilities conducting guarantee test and where so
required by the bidding documents the acquisition of all permits approvals and licenses etc.
the operation maintenance and training services and such other items and services as may be
specified in the bidding documents all in agree accordance with the requirement of the
general conditions of contract and technical specifications. Bidders shall give a breakdown
prices in the manner and detail called for in the price schedule. The bidder shall their prices in
the following manner:-
Schedule No.1 Plant and Equipment including Type test charges and Mandatory Spares to be
supplied from Abroad.
Schedule No.2 Plant and Equipment including Type test charges and Mandatory Spares to be
manufacture within the employers country.
30
Schedule No.3 Local transportation including port handling, port clearance, port charges
inland transit insurance and other local costs incidental to delivery of plant & equipment and
Mandatory Spares.
Schedule No. 4 installation services including erection works civil structural steel and allied
works insurance covers other then inland transit insurance and other services as specified in
the bidding documents.
Schedule No 5 Grand Summary (Schedule No 1 to 4)
Schedule No 6 Recommended Spares Parts
Schedule No 7 Taxes and duties not included in bid price
Schedule No 8a Break up of type test charges quoted in schedule-1
Schedule No 8b Break up of type test charges quoted in schedule-2
Schedule No 9 Unit rate Schedule
Benefits/Exemption to supply for Mega Power Projects
Inviting Bids for the package name in the bid data sheet on International Competitive Bidding
(ICB) basis has been approved by Ministry of Power, Govt. of India. Govt. of India is advised
to Indian State Govt. to exempt supplies made to Mega Power Project from sales tax and
local levies. In case the state govt. do not provide the exemption than the employer shall bear
and pay applicable sales tax and local levies as per provision of GCC.
Price Basis
Price quoted by bidders shall be subject to adjustment during performance of the contract to
reflect charges in the cost of labor, material etc. a bid submitted with a fixed price quotation
will not be rejected but the price adjustment will be treated as zero. The price adjustment
provision will not be taken into consideration in bid evaluation. Bidder must include the
name, source, and origin of labor and material indices along with there base values and
corresponding coefficients.
31
Bid security
The bidder shall furnish, as part of its bid security in a separate sealed envelope in the amount
and currency as stipulated in the Bid Data Sheet.
The bid security shall, at the bidders option be in a form of a banker’s cheque irrevocable
letter of credit or a bank guarantee. But the banks should be specified in the company’s list
that is given the instruction to fill up the contract.
In the case of foreign bidders, the foreign bidder shall be fill up the contract and security for
the contract he must look the bank name that is specified in the company’s procedure. That is
helped to the contractor and trust to the company. That is also helped in increase the goodwill
in the market. The bid security shall remain valid for 45 days. The format of guarantee letter
shall be accordance with the form of bid security include in the bidding document.
The bid security may be forfeited
a) If the bidder withdraws its bid during the period of validity specified by the bidder in the
bid form
b) The bidder does not accept the correction of its bid price.
c) If the bidder does not withdraw any deviation listed the cost of withdrawal idicated by him.
d) If the bidder refuses to withdraw, without any cost to the employer, any deviation not
listed but found else where in the bid.
e) In the case of a successful bidder, if the bidder fails with in the specified time limit there as
follows:-
(I) To sign the contract agreement, in accordance with ITB.
(II) To furnish the required performance securities.
32
Period of Validity of Bid
Bids shall be remain valid for a period of 180 days from the closing date prescribed by the
Employer for the receipt of the bid. A bid is valid for a shorter period shall be rejected by the
Employer as being non-responsive.
The bidder is required to keep the prices of recommended spares covered the validity of the
bid security shall be 6th month after notification of award for main equipment and mandatory
spares.
In exceptional circumstances the employer may solicit the bidder’s consent to an extension of
the bid validity period. The request and responses there to shall be made in writing by post or
by telefax followed by confirmation. If a bidder accept to extend the period of validity, the
validity of bid security shall also be suitable extended. A bidder may refuse the request will
not be required nor permitted to modify its bid.
Format and Signing of Bid
The bidder shall prepare an original and five(5) copies/sets of the bid clearly making each
one as “Original Bid” ,”Copy No.1”,”Copy No.2”…… etc, as appropriate. In the event of
any discrepancy between them, the original shall govern.
The original and all copies of the bid, each consisting of the documents shall be all typed or
written in indelible ink and shall be signed by the bidder or a person or person dully
authorized to bind the bidder to the contract.
Submission of Bids , Sealing and Making of Bids
The bidder shall seal the original and each copy of the bid in separate envelopes, duly
marking the envelops as “ORIGINAL BID “and “COPY NUMBER”. The bid security
33
furnished be sealed in a separate envelope, duly marking the envelope as “ATTACHMENT-
1”,”BID SECURITY”. The certificate regarding acceptance of importance conditions. The
bidder also is sealed in a separate enveloped entitled “CERTIFICATE REGARDING
ACCEPTANCE OF IMPORTANT CONDITIONS”. The envelops shall then be sealed in an
outer envelope.
The inner and outer envelopes shall:-
A] Be addressed to the employer at the address given in the bid data sheet.
B] Bear the package name indicated in the Bid Data Sheet, the invitation for bid number
indicated in the bid data sheet and statement “DO NOT OPEN BEFORE [DATE]”. TO BE
COMPELETE IN THE TIME AND SPECIFIED IN THE BID DATA SHEET
The inner envelops shall also indicated the name and address of the bidder so that the bid can
be return unopened in case it is declared “Late” or is received without any requisite.
The outer envelop is not sealed and marked that is employers responsibility for the bid
misplacement.
Deadline for submission of Bids
Bid must be received by the purchaser at the address specified under ITB later than the time
and date specified in the Bids date sheet. The all rights and obligation of the Purchaser and
Bidders previously subject to the deadline will thereafter be subject to the deadline as
extended.
Late Bids
If any bid received by the purchaser after the deadline of submission of bids prescribed by the
purchaser pursuant to ITB, will be rejected and returned unopened to the bidder.
34
Modification and Withdrawal of Bids
The may modify or withdraw its bid after the bid’s submission, provided that written notice
of the modification, including substitution or withdrawal of the bids, is received by the
Purchaser prior to the deadline prescribed for submission of bids. The bidder’s modification
or withdrawal notice shall be prepared, selected, marked and dispatched in accordance with
the provision of ITB .No bid may modified after the deadline for submiss
Receipt of Bids
Bids are received in a sealed condition at the place, date and time identified in the Invitation
for Bids/ Bidding Documents. A receipt is issued to the bidders for the bids delivered by hand
indicating the date and time of delivery.
Opening of Bids
The bids received are opened by a team comprising representatives from Engineering,
Contracts and Finance functions in the presence of bidders’ representatives who chose to
attend the bid opening. The details such as name of the bidder, bid price, availability of bid
security, guaranteed parameter, discounts if any, are read aloud during the opening. All the
participants in the bid opening are required to sign a register as a proof of attendance
maintained for the purpose.
6. Evaluation of Bids:
The bids are received, opened and evaluated by a duly constituted Tender Committee
comprising members from Contracts, Engineering and Finance functions in accordance with
the ‘Delegation of Powers’. The committee determines the lowest evaluated bid for award of
contract in terms of criteria for evaluation of bids stipulated in the bidding documents and
35
puts up its recommendation for the approval of competent authority in accordance with the
‘Delegation of Powers’.
The process of evaluation of bids begins with an examination of the bids to determine:
i. Bidders eligibility.
ii. Acceptability of bid security furnished by the bidder.
iii. Completeness of bid and correctness of signatures.
iv. Acceptability of Joint Deed of Undertakings (if envisaged in the bidding
documents).
v. Computational errors in the bid price.
vi. Stated deviations from the bidding conditions, which might reflect on the
“substantial responsiveness” of the bid and justify its rejection.
Though generally and to the extent possible avoided, clarifications may be
sought from the bidders, if considered necessary by the tender committee, with the approval
of competent authority. Due care is taken of the fact that such clarifications would not call for
any material alterations in the bidder’s bid.
The detailed evaluation is carried out only for bids, which are substantially responsive. Bid
evaluation considers price and other factors in a transparent manner and in accordance with
the stipulated evaluation criteria stated in the Bidding Documents such as cost compensations
for the deviations from the bidding conditions taken by the bidders, differential price factors
for guaranteed parameters etc.
In case of procurements under International Competitive Bidding procedures, the bid prices
are converted into a single currency i.e. in the Indian rupees based on the exchange rate
prevailing as on the date of bid and comparison of bids. Other factors such as a domestic
price preference (applicable in case of WB/ADB funded procurements) and purchase
preference to Public Sector Undertakings applicable as per the extant guidelines are also
considered for the purpose of evaluation of bids.
36
Once the lowest evaluated bidder is selected as above, the next step is to determine whether
the Qualification Requirements (QR) as stipulated in the bidding documents is met and
whether the bidder in question is capable to successfully executing the contract. An
affirmative determination of the above is a prerequisite for award of contract to the bidder. In
case the lowest evaluated bidder does not meet the above requirement, the similar
determination is done for the next lowest bidder. If the bidderalso fails, the process is
continued until the lowest evaluated and qualified bidder is chosen.
QUALIFYING REQUIREMENT FOR BIDDERS:
The following are the specific requirements.
1 The bidder should have engineered, fabricated/supplied, erected and tested at least
one (1) piping system, of minimum … MT, consisting of steel pipes of size … NB or above,
complete with valves and fittings, etc.
1.2 The average annual turnover of the Bidder, in the preceding three (3) financial years as on
the date of bid opening, shall not be less than Rs… million or in equivalent foreign currency.
1.3 The Net Worth of the Bidder as on the last day of the preceding financial year shall
not be less than 25% of the paid-up share capital.
1.4 The unutilized Bank Guarantee limits of the Bidder as on seven (7) days prior to the date
of bid opening, duly certified by the Bankers shall not be less than Rs… Million or in
equivalent foreign currency.
1.5 The Bidder shall have unutilized cash credit limits together with cash and bank
balances including fixed deposits, as on seven (7) days prior to the date of bid opening of not
less than Rs… million or in equivalent foreign currency.
37
Notes:
a) Net Worth means the sum total of the paid up share capital and free reserves. Free
reserves means all reserves credited out of the profits and share premium account but does
not include reserves credited out of the re-valuation of assets, write back of depreciation
provisions and amalgamation. Further any debit balance of Profit & Loss account and
miscellaneous expenses to the extent not adjusted or written off, if any, shall be reduced from
Reserves & Surplus.
b) Other income shall not be considered for arriving at annual turnover.
c) For unutilized BG limits, Cash Credit Limits and Turnover in foreign currency, the
exchange rate as on 7 days prior to the date of Bid opening shall be used.”
NEGOTIATION:
When adequate competition exists, the negotiation should and must be avoided. This
competition may be in form of many manufacturers making the same good or a single
manufacturer providing the goods through many retailers/suppliers and all the
retailers/suppliers are free to quote individually. However if it's found that the price quoted
by all individual bidders are unreasonably high in comparison to the last purchase
price/estimate or in case of some ambiguous technical/commercial terms and conditions,
negotiations can be done with the approval of competent authority as per DOP. In normal
circumstances, the negotiation should take place with the technically and commercially
evaluated lowest (Lt) vendor only. However, depending upon the situation the negotiation
may be carried out with more than one party at a time. Normally the negotiation is carried out
by the TC (Tender Committee). But in case a tender committee is absent i.e. no committee
was formed to monitor the procurement, representatives from finance and purchase may
complete the task of negotiation. However, negotiation process is not always for negotiating
the prices of equipment/material/services supplied but it may also involve terms and
conditions of supply, future commitments for supply of spare parts and consumables and
38
many other aspect of the contract. For example a lowest price bidder may not get the contract
if it’s found that another bidder who is quoting higher than him but is offering lower priced
spares. Hence in this case a negotiation may be conducted with the L 1 to make him offer the
spares at the same rate as being offered by his competitor. Once the negotiation process is
finished and the two parties involved in the negotiation reach a consensus, the committee's
purchase proposal/recommendation will be put up to the competent authority for approval
and subsequently the letter of intent may be faxed to the party.
7. Award of Contract:
All the activities related to evaluation of bids and approval of evaluation report/ award
recommendations by the competent authority, concurrence of the funding agency (wherever
applicable) and post-bid discussions with the successful bidder to resolve ambiguities/
nonconformity to the bidding provisions observed during the bid evaluation, are required
within the bid validity period.The contract is thus awarded to the bidder whose bid has been
found as the lowest evaluated techno-commercially-responsive bid and meets the specified
Qualifying Requirements.
Financial statement analysis
At National Thermal Power Corporation
Financial Analysis
Introduction
Financial analysis is the process of identifying the financial strength and weaknesses of the
firm by properly establishing relationship between the items of the balance sheet and the
profit and loss account. It is the critical examination of the financial information contained in
AWARD OF CONTRACT
LOWEST
BIDDER
the financial statements to understand and make decisions regarding the operations of the
firm.
40
Definitions
In the words of Myer,” Financial statement analysis is largely a study of relationships among
the various financial factors in a business, as disclosed by a single set of statements, and a
study of trends of these factors, as shown in a series of statements.
In the words of Kennedy and Muller,” The analysis and interpretation of Financial
statements are an attempt to determine the significance and meaning of financial statement
data so that the forecast may be made of the prospects for future earnings, ability to pay
interest and debt maturities (both current and long-term) and profitability and sound dividend
policy.
Purpose And Significance of Financial Analysis
1. Judging the earning capacity or profitability. On the basis of financial statements the
earnings capacity of the business concern maybe computed. In addition to this, the
future earning capacity of the concern may be forecasted. All external users of accounts,
specially the investors and potential investors, are interested in this.
2. Judging the managerial efficiency. The financial statements analysis helps to pinpoint
the areas wherein the managers have shown better efficiency and the areas of
inefficiencies. For example, using financial ratios, it is possible to analyse relative
proportion of production, administrative and marketing expenses. Any favorable and
unfavorable variations can be identified and reasons thereof can be ascertained to pin
3. Judging the short and long-term solvency of the concern. On the basis of financial
statements, the solvency of the concern may be judged. Debenture holders and lenders
judge the ability of the company to pay the principal and interest as most of the
companies raise a portion of their capital requirements by issuing debentures and raising
long-term loans. Trade creditors are mainly interested in assessing the short-term .
solvency of the business as they want to know that the business is in a position to pay
41
4. Inter-firm comparison. Financial statements of different enterprises may be analyzed
and comparison be made thereof. The inter-firm comparison helps in assessing own
performances as well as that of others, if mergers and acquisitions are considered. Inter-
firm comparison is better carried out if it is based on Ratios.
5. Making forecast and preparing budgets. Past financial statements analysis helps a
great deal in asseseing developments in the future, specially the next year. For example,
given a certain investment, it may be possible to forecast the next year’s profit on the
basis of earning capacity shown in the past. Analysis thus helps in preparing budgets.
Ratio Analysis Introduction
Ratio analysis is a powerful tool of financial analysis. A ‘ratio’ is defined as
“the relationship between two or more things.”
In financial analysis, a ratio is used as a benchmark for evaluating the financial position and
performance of a firm.Ratio analysis is a technique of analyzing the financial statements by
computation of ratios. In other words, Ratio analysis is a process of determining and
interpreting relationship between the items of financial statements to provide a meaningful
understanding of the performance and financial position of an enterprise.
According to Myers, “Ratio analysis is a study of relationship among various financial
factors in a business.”
Advantages and Uses of Ratio Analysis
Ratio analysis is an important technique of financial analysis. The advantages derived by an
enterprise by the use of accounting ratios are:
1. Useful In Analysis of Financial Statements. Ratios are useful for understanding the
financial position of the concern. They are an extremely useful device for analyzing
the financial statement. Bankers, investors, creditors etc, all analyse balance sheet
and profit and loss accounts by means of ratios.
42
2. Useful In Simplifying Accounting Figures. Ratios simplify, summarize and
systematize a long array of accounting figures to make them understandable. Its main
contribution lies in communicating precisely the interrelationship, which exists
between various financial statement elements. The importance of accounting ratios,
that is, relationships worked out among various accounting data which are mutually
dependent and which influence each other in a significant manner. Arises from the
fact that often absolute figures standing alone do not convey any meaning.
3. Useful In Judging The Operational Efficiency Of Business. Ratios are essential
for understanding the affairs of a firm. Specially its operating efficiency. They are
useful for diagnosis of the financial health of a business concern. This id done by
evaluating liquidity, solvency, profitability, etc. Such an evaluation enables
management to assess financial requirements and capabilities of various business
units.
4. Useful For Forecasting Purpose. Ratios are of much help in business planning and
forecasting. The trend ratios are analyzed and used as guide to future planning. What
should be the course of action in the immediate future is decided, many a time, on the
basis of trend ratios, i.e., ratios calculated for a number of years.
5. Useful In Locating The Weak Areas Of The Business. Ratios are of great
assistance in locating the weak areas of the business even though the overall
performance may be quite good. Management can then pay attention to the weakness
and take remedial action.
43
NTPC RATIO
YEAR 2010 2009 2008
1. Liquidity Ratio1.1 Current RatioCurrent Assets 2530269 2407840 2151340Current liabilities 1075816 1068860 792990
current ratio 2.35 2.25 2.711.2 Quick RatioQuick Assets 2195498 2083500 1883770Current Liabilities 1075816 1068860 792990Quick Ratio 2.04 1.95 2.37
1.3 Cash RatioCash & Bank Balance 1445948 1627160 1493320Current Liabilities 1075816 1068860 792990Cash Ratio 1.34 1.52 1.88
2010
2009
2008
0 0.5 1 1.5 2 2.5 3
cash ratioquick ratiocurrent ratio
44
1. LIQUIDITY RATIO
Liquidity ratio measures the ability of a firm to meet its short term obligation and reflect the short
term financial strength or solvency of a firm. Liquidity ratio includes current ratio, quick ratio and
inventory turnover ratio.
Current ratio
Current ratio is the ratio of total current assets by total current liabilities. Current ratio of the firm
measures its short-term solvency i.e. its ability to meets short term obligation. The higher the
current ratio the larger the amount of rupees available per rupee of current liability
CR= Current asset
Current liability
Ideally a company should have 2:1 current ratio its shows that company has enough funds to meet
its short term obligations. Higher the current ratio better it is for company as it enhances the
liquidity position of the company and builds creditors and investor’s trust.
FOR NTPC:
Current Ratio has been very good over the years.The current ratio of company shows fluctuating
trend but has always been good as current assets have always been more than current liabilities
which shows that firm has always enough funds to meet its day to day obligations.
Quick Ratio :
It measures the instant debt paying capability or company’s ability to pay unexpected demand for
working capital. This ratio establishes the relationship between quick or liquid current assets and
current liabilities
45
QR = Current assets – (Inventories + prepaid expenses)
Current Liabilities
Ideally it should be 1:1 but if the liquid ratio or quick ratio is more than 1:1 than company seems
to be sound and good. On the other hand if it is less than 1:1 the company is said to be unsound.
For NTPC
Quick Ratio came to 2.04 in the year 2010, this was better than the previous year ratio ,indicating
that the company is having quick assets to pay its current liabilities. This shows that company
keeps enough liquid funds to meet its unexpected cash requirements or obligations. For NTPC it
shows that it can meet unexpected need for funds easily.
Cash Ratio:
It measures the absolute liquidity of the company. It is a relationship between absolute quick assets
and quick liabilities.
Quick Assets include cash, bank and marketable securities and Quick Liabilities includes all
current liabilities except bank over draft.
C cash ratio = Absolute Liquid Assets
Q quick Liabilities
Ideally it should be 0.5:1
F For NTPC
Cash Ratio is 1.34 in year 2010 to showing the firm’s ability to quickly pay its
debt
2.ACTIVITY OR EFFICIECY
RATIO 46
2.1Receivables Turnover Ratio
Net Sales 4632259 4192380 3705010Receivables at the end 665146 358420 298270Receivables Turnover
Ratio 6.96 11.69 12.42
2.2 Total Assets Turnover Ratio
net sales 4632259 4192380 3705010Total assets 11287374 10522480 8938800
Total assets turnover ratio 0.41 0.39 0.41
2.3 Fixed Asset TuURNOVER Ratio
Net Sales 4632259 4192380 3705010Fixed Assets 6686560 3293770 2609370
Fixed Assets Turnover 0.69 1.27 1.41
Ratio
2.4 C/ATurnover RatioNet Sales 4632259 4192380 3705010
Current Assets 2530269 2407840 2151340Current Assets Turnover
Ratio 1.83 1.74 1.72
2.5 Working Capital Turnover RatioNet Sales 4632259 4192380 3705010
Net Current Assets 1454453 2023670 1761890W C Turnover Ratio 3.18 2.07 2.10
47
2010
2009
2008
0 2 4 6 8 10 12 14
wc turnover ratiocurrent asset turnover ratiofixed asset turnover ratiototal asset turnover ratioreceivable turnover ratioinventory turnover ratio
FIG ..2…ACTIVTIY RATIO
2. ACTIVITY RATIO
An activity ratio is the relationship between sales or cost of goods sold and investment in
various assets of the company. It is always expressed as turnover. They are intended to
describe how efficiently or intensively a firm uses its assets to generate sales.
Some of the important activity or efficiency ratios are as follow:
Receivable Turnover Ratio:
How far the company is efficient or successful enough in realizing its credit debtor’s turnover
ratio is being calculated. It establishes relationship between net credit sales and average
receivables of the year.
48
RT = Net Credit Sales
Average Receivables
Credit sales means all credit sales minus the sales returns. Or else a total sale is considered as
credit sales.
Average Receivables are computed as:
AR = Opening Debtors and B/R + closing Debtors and B/R
2
For NTPC
Receivables Turnover is 6.96 in 2010. NTPC collected its outstanding
credit account & its collection of the fund has reduced as compare to last
year .
Total Asset Turnover Ratio :
This ratio expresses relationship between costs of goods sold or net sales and total assets or
investments of a firm.
TAT = Net Sales or Cost of Goods Sold
Total Assets
Total Assets means all fixed and current assets but the provision for depreciation is adjusted
in it.
This ratio indicates the number of times the assets are turned over in a year in relation to
sales. A higher total assets turnover ratio is the indicator of effective utilization of investment
in assets where as lower assets turnover ratio indicates that assets are not properly utilized in
comparison to sales. Thus, there is an over investment in assets. Extremely high ratio means
over trading in the business.
49
For NTPC
Total Assets Turnover Ratio indicates that NTPC in the year 2010, for
every 1 rupees in total assets generate 41 paisa in sales.
This shows that company still need to concentrate more on this ratio for
its effective utilization of the funds as it can even go much higher .
Fixed Assets Turnover Ratio:
This ratio expresses the relationship between fixed assets (less depreciation) and net sales or
cost of goods sold. This ratio measures the efficiency and profit earning capacity of the firm.
FAT = Sales or Cost of Goods sold
Fixed Assets less depreciation
The higher the ratio the greater is the intensive utilization of fixed assets. Lower ratio means
under utilization of fixed assets and excessive investment in these assets.
For NTPC
Fixed Assets Turnover indicates that NTPC in the year 2007, for every 1
rupees in fixed assets generate 0.69 in sales. It shows intensive utilization
of fixed assets. Indicates the profit earning capacity of the company is
high.
Current Assets Turnover Ratio :
This ratio expresses the relationship between current assets and net sales or cost of goods
sold. This ratio reflects the efficiency and capacity of working capital. On the basis of this
ratio efficiency of current assets and over and under investment in the company can be
examined.
50
CAT = Sales or Cost of Goods Sold
Current Assets
For NTPC
Current Assets Turnover Ratio: indicates that NTPC in year 2010 is
1.83. This shows that company’s current assets are effectively utilized.
Working Capital Turnover Ratio :
This ratio establishes relationship between net working capital and net sales or cost of good
sold. This ratio is used to assess the efficiency with which the working capital is being used
in the business.
WCT = Sales or Cost of Goods Sold
Net Working Capital
A high working capital ratio indicates efficient management of working capital or over
trading i.e. low investment in working capital and more profits. Low working capital turnover
ratio implies under trading i.e. funds are not being utilized efficiently.
For NTPC
Working Capital Turnover Ratio: indicates the proper management of
the working capital in the firm which is required for the day to day
operations of the firm. It shows that in year 2010 it is 3.18 which has
comparatively increased over the years.
51
3. Profitability Ratio
(based on sales)
3.1 Gross Profit Margin
Gross Profit (PBIT)Net Sales 4632259 4192380 3705010
Gross Profit Margin
3.2 Net Profit RatioNet Profit 872820 820130 741480Net Sales 4632259 4192380 3705010
net profit Ratio 18.84% 19.56% 20.01%
FIG …..3….PROFITABILITY RATIO
52
3. PROFITABILITY RATIO
The management of the firm is naturally eager to measure its operating efficiency. Similarly
the owners invest their funds in the expectation of reasonable return. The operating efficiency
of a firm and its ability to ensure adequate returns to its shareholders depends ultimately on
the profit earned by it. Therefore profitability is measure of efficiency .it also indicate public
acceptance of the product and show that firm ca produce competitively.
When profitability ratio is computed by relating profit of a firm to its investments that ratio
are termed as return on investments
(i) Profitability based on sales
Gross profit Ratio:
This ratio expresses the relationship of gross profit on sales to net
sales in terms of percentage.
2010
2009
2008
0 5 10 15 20 25 30
NET PROFIT RATIOGROSS PROFIT RATIO
Gross Profit X 100
Net Sales
Gross profit can be computed as Net Sales – Cost of Goods Sold.
The ratio measures the trading effectiveness and basic profit earning
potentiality of a company. The higher the ratio the greater will be the
margin.
FOR NTPC:
Gross Profit Margin: has reduced from 49.12% in the year 2004 to
33.03% in the year 2007. This tells that NTPC generate 33 paisa from
every 1 rupee sales. Although it was good in year 2004 which could due to
the large sales in that particular year or may be due to market favoring
the environment of the sales. Still it is good for year 2007 i.e. for every
one rupee sale company can generate 33 paisa as profit after meetings it
expenses of generation.
53
Net Profit Margin:
This ratio measures the relationship between net profit and sales of a firm. Net Profit is the
excess of revenue over expenses during a particular accounting period. The net profit ratio is
determined by dividing the net profit by sales and expressed as percentage.
NP = Net Profit (after tax) X100
Net Sales
This ratio is the indication of over all profitability and efficiency of the business. A high net
profit ratio would only mean adequate returns to the owners. It also enables a firm to
withstand in cut throat competition when the selling price is declining or cost of production is
rising. A low net profit ratio on the other hand, would only indicate inadequate return to the
owners
For NTPC
Net Profit Margin: has reduced to 18.84% in year 2010 from 20.01% in
year 2008 . This shows that company is running efficiently and it can pay
more to its investors as it generates 18 paisa in the profit for every single
rupee of sale. Though it is less than year 2008 but yet it is not bad it still
displays the profit earning efficiency of the company as good.
54
2010
2009
2008
0.00% 500.00% 1000.00% 1500.00%
return on total assetreturn on equityreturn on capital employed
FIG …4…..PROFITABILITY RATIO
4.Profitability Ratio (based on capital)
4.1 Return of Capital Employed
Net Profit (PBIT) 1269439 935950 1025490
Capital Employed1002344
4 9193781 10615838Return of Capital Employed 12.66% 10.18% 9.66%
4.2 Return On Equity (ROE)Net Profit (PAIT) 872820 820130 741480
Shareholder's Fund 6243742 5737010 5263860return on equity 13.97% 14.29% 14.08%
4.3 return on total assetsnet profit after tax 872820 820130 741480
total assets1128737
4 10522480 8938800return on total assets 7.73% 7.79% 8.29%
55
4.PROFITABILITY RATIO CAPITAL BASED
Return on Capital Employed:
This ratio expresses the relationship between profit and capital employed and is calculated in
percentage by dividing the net profit by capital employed.
ROCE = Net Profit (PBIT) X100
Capital Employed
The return on capital employed provides a test of profitability related to long term funds. The
higher the ratio, the more effective and efficient would be utilization of capital or vice- versa.
For NTPC
Return on Capital employed: it has increased from 10.66% in year 2009 to 12.66% in year
2010 .This shows that company was making most effective utilization of its capital and it is
operating efficiently.
Return on proprietor’s funds or equity:
This ratio expresses the percentage relationship between the net profit (after interest and tax)
and proprietor’s funds or shareholder’s investment.
Net Profit (after interest and tax) X100
Shareholder’s funds
Shareholder’s funds include preference share capital as well as equity shareholders funds
which in turn comprises of equity share capital, share premium and reserves & surplus.
For NTPC
56
Return on Equity (ROE): It is also consistent over the years reflecting not much variation
till 2006. It is 13.97% for the year 2010 indicating that NTPC generate 13 paisa in profit per
1Rs invested in Equity.
Return on Total Assets:
Profitability of the company can also be measured by establishing relationship between net
profit and total assets. Total assets mean all net fixed assets, current assets and non trading
investments.
ROTA = Net Profit after Tax X 100
Total assets
This ratio measures the profitability of investments which reflects managerial efficiency. The
higher the ratio the better is the profit earning capacity of the firm or vice versa.
For NTPC
Return on Assets (ROA): It has been consistent over the years; it is 7.73% for the year
2010 indicating that NTPC generates 7.73 paisa of profit per one rupee invested in assets.
57
2010
2009
2008
0 1 2 3 4 5 6 7 8
interest coverage ratioDividend coverage ratiodebt to total asset ratiodebt equity ratio
FIG......5….LEVERAGE RATIO
5. leverage or Capital Structure Ratio
5.1 Debt - Equity RatioTotal Debt 3779702 3456780 2719060Net Worth 6243742 5737010 5263860
Debt - Equity Ratio 0.61 0.60 0.525.2 Debt to Total Assets ratio
Total Liabilities 4855518 4525640 3512050Total Assets 11287374 10522480 8938800
Debt to Total Assets Ratio 0.43 0.43 0.40
5.3 interest Coverage Rationet profit before interest and tax 1269439 935950 1025490
fixed interest chargesInterest coverage ratio
5.4 Dividend Coverage Rationet profit after interest and tax 872820 820130 741480
Dividend 313328 296830 288590Dividend Coverage Ratio 2.78 2.76 2.56
58
6.LEVERAGE RATIO
Debt – Equity Ratio:
This ratio indicates the relative proportion of debt and equity in financing the assets of a firm.
It reveals the relationship between internal and external sources of funds of a company.
D-E = Total Debts
Net Worth
Total debts refer to the total outside liabilities i.e. short term and long term loans. Net worth
mean total paid up amount of equity and preference share capital plus the total or
accumulated amount of reserves and surplus.
This ratio plays important role in analyzing the long term solvency of a company. It indicates
the firm’s capacity to pay long term debts and procure additional loans and informs whether
the firm is following the policy of trading on equity.
For NTPC
Debt Equity Ratio: are also consistent and there has been not much variation in this ratio
over it is 0.61 in year 2010 and 0.52 times in year 2008. This ratio shows that the long term
solvency of the firm is sound enough it has good capacity to pay its long term debts which
make it easy for it to procure funds from the market easily due to its long term solvency ratio.
Debt to Total Assets Ratio:
This ratio measures the long term solvency of the business. It reveals relationship between
total assets and total external liabilities. External liabilities mean all long term and short term
liabilities.
DTA = Total Liabilities
Total Assets
59
This ratio measures the proportion of total assets provided by creditors (long term as well as
short term) of the company i.e. what part of assets is being financed from loans. If total assets
are more than external liabilities the firm is treated as solvent. So, higher the ratio the greater
is the amount of creditors that is being used to generate profits for the owners of the firm.
FOR NTPC:
Total debt ratio is consistent over the year; it was 0.40 times in 2008, 0.43 times in 2009 and
0.43 times in 2010.
And 0.43 times in 2010 indicating that NTPC use 39% Debt and 61% Equity Capital
structure in the year 2007. This shows that company is solvent enough as its total assets are
more than its total debt. It uses less funds from outside to finance its working or for
generating profits.
Dividend Coverage Ratio:
It has increased from 2.56 times in year 2008 to 2.78 times in year 2010, this is good
indicator which shows that company is able to meet its dividend obligations of the
shareholder .
60
Dividend per share 3.8 3.6 3.5
2010
2009
2008
0 2 4 6 8 10 12
DPS EPS
FIG…6………INVESTMENT ANALYSIS RATIO
6.Investment
Analysis Ratio6.1 earning per share
profit after tax 878280 820130 741480
no of equity share 8245464400 8245464400 8245464400
earning per share 10.65 9.94 8.99
61
6.INVESTMENT ANALYSIS RATIO
Earning Per Share – EPSThe rate of dividend on shares depends upon the amount of profits earned by the firm. Whatever profits remains, after meetin EPS = Profit after tax – Preference Dividend
No. of equity sharesall expenses and paying preference share dividend, belongs to equity shareholders.
This is a popular ratio as it measures the profitability of a firm from owners’ standpoint. The higher the ratio the greater would be the market price of a company’s shares or vice versa.
EPS has been consistent over year it was 8.99 in the year 2008 and now it is 10.65 in 2010
FOR NTPC
62
FINDINGS
The tendering process requires too much of paperwork.
Certain steps like preparation of similar documents again & again, cross checking of
reports by different departments starting from scratch, eats too much of time.
Lack in use of Intranet facility over the departments.
NTPC have good short term financial strength
Company EPS is constantly increasing from the past year’s
Return on capital employed is constantly increasing.
The award of contract take place on a fair and transparent bases and everybody is
given equal opportunity to take part in bidding.
63
RECOMMMENDATIONS
Enough care should be taken while preparing the bid documents to avoid confusions,
delays, favors etc.
The tender committee officials should encircle and initial on each page of the tender
documents received from the parties on the tender opening date. They should mention
number of any corrections (if so made) on each page. Otherwise they should mention ‘no
cutting/no overwriting’. This will eliminate scope for tampering at the alter date.
While recommending award of a contact to a particular bidder, a justification analysis
should also be prepared.
All payment terms, including advance payments should be mentioned in the bid
documents itself so as to obviate release of any payment out of the purview of contract
later on
Equity & transparency in the bidding and evaluation process are being strictly followed
in NTPC; however certain leakage of data is possible because of involvement of multiple
groups. This aspect needs more attention\
64
Limitations of the study The study suffers from certain limitations like any other research. However, these limitations
cannot have a drastic impact on the analysis and the recommendations of the study as these
limitations are within manageable limits. These limitations are as follows:
The coverage of more information about the requirements of a Procurement Contract was
not highly successful because of the time limit involved in carrying out the project.
High degree of accuracy is doubtful as the fact-finding investigations in this project are
based on given factual information. Hence, an allowance should be made for deviations
and errors because no attempt has been made to check the accuracy and reliability of the
information provided.
It has been assumed that the information provided by the concerned authorities is correct.
Being a purely academic–based project, it has been limited to certain particular areas of
the Finance Concurrence Department which actively participates in the procurement
function
65
CONCLUSION
Contract/Purchase management activities at NTPC are one of the most vital activities
undertaken by the 25000MW Power Giant of India. The process followed by NTPC is found
to be very objective in nature and very professional methods are in vogue.
We have learned the following while studying the system in NTPC:
(a) Advantage of the competition: NTPC tries to take advantage of the
Competition in the field of heavy engineering where foreign manufacturers like MHI, GE etc.
are competing with Indian manufacturers like BHEL and L&T.
(b) Transparency: NTPC being a public sector company & to be free from nepotism and
favoritism has adopted a system where transparency and automation is at their highest levels.
Transparency is achieved by the formation of a multi member bid-opening team and the
bidders submitting their bids in sealed packets where no one knows in advance the quotation
offered by a particular bidder. Automation here signifies that almost all the contracts are
awarded following the same procedures, by awarding the contract to the lowest bidder that is
L1 provided that the lowest bidder qualifies himself technically too. Moreover the bid
documents are available on the website.
(c)Cost reduction: Cost must be reduced by means of optimum utilization of resources and
the resources thus saved can be channelized to more profitable segments. Cost estimation for
the purpose of cost and budgetary control is a very important aspect of learning during our
training in NTPC.
(d)Selection of proper contractor: While an order is placed for execution of any work, it
must be awarded to a proper contractor. If incapable contractor is chosen, he may not be able
to execute the work on time or he may abandon the work in between which will result in loss
of time, increase of cost and it disrupts the schedule for this package as well as the project
schedule. Hence assessment of capacity and capability of the bidder which includes detailed
financial analysis of his capacity is considered as a very important aspect in the whole
process.
66
Financial statement analysis of the national power thermal corporation shows that firm is
efficient enough to run its day to day business. The liquid ratios of the company i.e. current
ratio, quick ratio, and acid test ratio indicate that NTPC is able to pay its short term bills
without undue stress. This shows that company is liquid enough to meet its day to day
obligations.
The long term ratios i.e. debt equity ratio and interest coverage ratio indicates that NTPC is
easily able to meet its financial leverages. Turnover ratios i.e. inventory turnover, receivables
turnover, asset turnover indicates NTPC id efficiently using its assets to generate sales. Also
the profitability ratios i.e. profit margin, return on equity etc. indicates there is slight fall in
net income of the company. But the earning per share has remained same all the year this
shows the investors side is safe enough.
Over all it can be summarised that NTPC is financially sound i.e. financial position and
profitability of the company is quite acceptable.
67
BIBLOGRAPHY
Books
o “Khan & Jain”- Financial Management
o “I.M PANDEY” - Financial Management
Manuals
o Delegation of Powers Manual of NTPC
o Bidding Documents Sec.-I,II,III,IV,V
o Annual Report of NTPC
o Purchase Management Manual of NTPC
Websites Referred
o www.ntpc.co.in
o www.powermin.nic.in
o www.ntpctender.com
o www.pfc.com
o www.teriin.org
o www.ntpceoc.com
68
APPENDIX:
Financial Results
Audited Financial Results for the Year ended 31st March 2010
(Rs./Lakh)
Sl. Particulars
Stand Alone Consolidated
Quarter ended 31.03.2010 (Unaudited)
Quarter ended 31.03.2009 (Unaudited)
Year ended 31.3.2010 (Audited)
Year ended 31.3.2009 (Audited)
Year ended 31.3.2010 (Audited)
Year ended 31.3.2009 (Audited)
1 2 3 4 5 6 7 8
1 (a) Net Sales (Net of Electricity Duty)
1235339 1144578 4632259 4192373 4825641 4266132
(b) Other Operating Income
37815 74196 189873 217567 193211 226294
2 Expenditure
(a) Fuel Cost 834598 801583 2946274 2711069 3018766 2734645
(b) Employees Cost
74561 62025 241236 246313 252300 253251
(c) Depreciation 73216 72639 265006 236448 289438 249489
(d) Other Expenditure
59606 58984 202710 195209 247117 223864
Total (a+b+c+d)
1041981 995231 3655226 3389039 3807621 3461249
3 Profit from Operations before Other Income, Interest & Exceptional Items (1-2)
231173 223543 1166906 1020901 1211231 1031177
4 Other Income 24950 26709 102533 114668 101483 113893
5 Profit before 256123 250252 1269439 1135569 1312714 11450
Interest & Exceptional Items (3+4)
70
6 Interest & Finance charges
48179 54039 180893 199622 207803 214346
7 Profit after Interest but before Exceptional Items (5-6)
207944 196213 1088546 935947 1104911 930724
8 Exceptional items
- - - - - -
9 Profit(+)/Loss(-) from Ordinary Activities before Tax (7+8)
207944 196213 1088546 935947 1104911 930724
10 Tax Expenses:
(a) Current Tax (9762) (15623) 194544 113834 197908 119430
(b) Deferred Tax
15941 1043 20913 (44880) 22963 (45203)
(c) Fringe Benefit Tax (FBT)
0 585 269 2098 270 2186
Total (a+b+c) 6179 (13955) 215726 71052 221141 76413
Less: Deferred Tax Recoverable / Payable
- 1043 - (44880) - (45215)
FBT transferred to Expenditure during Construction / Development of coal mines
- 84 - 115 (5) 150
Tax Expenses (Net)
6179 (15122) 215726 115817 221146 121478
11 Net Profit(+)/ Loss(-) from ordinary activity after tax (9-10)
201765 211335 872820 820130 883765 809246
12 Extraordinary Items (Net of tax expenses)
- - - - - -
13 Net Profit(+)/ Loss(-) for the year before Minority Interest (11-12)
201765 211335 872820 820130 883765 809246
14 Minority Interest in Consolidated Profit
- - - - - (10)
15 Net Profit (+)/ Loss (-) for the year after Minority Interest (13-14)
201765 211335 872820 820130 883765 809256
16 Paid-up Equity Share Capital(Face value of share Rs. 10/- each)
824546 824546 824546 824546 824546 824546
17 Paid up Debt Capital
3779702 3456775
18 Reserves excluding revaluation reserve as per Balance Sheet
- - 5419196 4912460 5438227 4916208
19 Debenture Redemption Reserve
198672 168894
20 Earning per share - (EPS in Rs.)
(a) Basic and diluted EPS before Extra-ordinary items (not annualised)
2.45 2.57 10.59 9.95 10.72 9.81
(b) Basic and diluted EPS after Extra-ordinary
2.45 2.57 10.59 9.95 10.72 9.81
items (not annualised)
21 Debt Equity Ratio
0.61 0.60
22 Debt Service Coverage Ratio (DSCR)
3.92 3.67
23 Interest Service Coverage Ratio (ISCR)
13.64 10.19
24 Public Shareholding
(a) Number of shares
1278103220 865830000 1278103220 865830000 1278103220 865830000
(b) %age of share holding
15.50 10.50 15.50 10.50 15.50 10.50
25 Promoters and Promoter Group Shareholding
(a) Pledged/ Encumbered
- Number of Shares
- - - - - -
- Percentage of share (as % of the total shareholding of promoter and promoter group)
- - - - - -
- Percentage of share (as % of the total share capital of the company)
- - - - - -
(b) Non-encumbered
- Number of Shares
6967361180 7379634400 6967361180 7379634400 6967361180 7379634400
- Percentage of share (as % of the total shareholding of promoter and promoter group)
100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
- Percentage of share (as % of the total share capital of the company)
84.50% 89.50% 84.50% 89.50% 84.50% 89.50%
SUMMARY OF ASSETS AND LIABILITIES AS AT 31st MARCH 2010
(Rs./Lakh)
Particulars
Stand Alone Consolidated
Year ended 31.03.2010 (Audited)
Year ended 31.03.2009 (Audited)
Year ended 31.03.2010 (Audited)
Year ended 31.03.2009 (Audited)
SOURCES OF FUNDS
Shareholders’ Funds:
(a) Capital 824546 824546 824546 824546
(b) Reserves and Surplus 5419196 4912460 5438227 4916208
Deferred Revenue from Advance Against Depreciation
161084 193601 161084 193601
Deferred Income from Foreign Currency Fluctuation
- 60771 - 60765
Loan Funds
(a) Secured Loans 907992 896956 1537654 1321170
(b) Unsecured Loans 2871710 2559819 2877210 2561094
Deferred Foreign Exchange Fluctuation Liability
6105 5452 6105 5445
Deferred Tax Liability (net) after Recoverable
20925 13 22971 13
Minority Interest - 27893 16619
TOTAL 10211558 9453618 10895690 9899461
APPLICATION OF
FUNDS
Goodwill on Consolidation
- - 62 62
Fixed Assets incl. CWIP and Construction Stores & Advances
6686560 5934263 7648609 6589484
Investments 1480709 1398349 1177761 1169596
Deferred Foreign Currency Fluctuation Assets
36517 97344 36525 97349
Current Assets, Loans And Advances
(a) Inventories 334771 324342 353299 336157
(b) Sundry Debtors 665146 358418 708080 381892
(c) Cash and Bank balances
1445948 1627163 1605304 1725045
(d) Other current assets 84404 97946 86804 99336
(e) Loans and Advances 551311 684653 568062 703888
Less: Current Liabilities and Provisions
(a) Liabilities 768758 743907 975798 871909
(b) Provisions 307058 324953 315027 331439
Net Current Assets 2005764 2023662 2030724 2042970
Deferred Expenses from Foreign Currency Fluctuation
2008 - 2009
TOTAL 10211558 9453618 10895690 9899461AUDITED SEGMENT-WISE REVENUE, RESULTS AND
CAPITAL EMPLOYED FOR THE YEAR ENDED 31stMarch 2010(Rs./Lakh)
Sl. Particulars
Stand Alone Consolidated
Quarter ended 31.03.2010 (Unaudited)
Quarter ended 31.03.2009 (Unaudited)
Year ended 31.03.2010 (Audited)
Year ended 31.03.2009 (Audited)
Year ended 31.03.2010 (Audited)
Year ended 31.03.2009 (Audited)
1 2 3 4 5 6 7 8
1 Segment Revenue (Net Sales)
- Generation 1230529 1140489 4616867 4179119 4774989 4227388
- Others 4810 4089 15392 13254 50652 38744
- Total 1235339 1144578 4632259 4192373 4825641 4266132
2 Segment Results (Profit
before Tax and Interest)
- Generation 197550 159674 1015253 905305 1049376 902317
- Others 1664 1522 5816 4184 16085 12811
- Total 199214 161196 1021069 909489 1065461 915128
Less
(i) Unallocated Interest and Finance Charges
28584 31979 111682 208630 138312 220701
(ii) Other Unallocable expenditure net of unallocable income
(37314) (66996) (179159) (235088) (177762) (236297)
Total Profit before Tax
207944 196213 1088546 935947 1104911 930724
3 Capital Employed (Segment Assets - Segment Liabilities)
- Generation 3945020 3383665 3945020 3383665 4373991 3596247
- Others 5445 3226 5445 3226 33623 18185
- Un-allocated
2293277 2350115 2293277 2350115 1883052 2142941
- Total 6243742 5737006 6243742 5737006 6290666 5757373