Consultation on the grandfathering policy of support for Dedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation March 2010
Consultation on the grandfathering policy of support forDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
March 2010
Contents
1. ExecutiveSummary 3
2. ReasonsforConsultation 6
3. Optionsconsidered 9i. Grandfatheringatbandreceivedonaccreditation 9ii. Grandfatheringatcurrentlevels,withpotentialtoupband 11iii. Grandfatheraminimumlevel,withtherestfreefloating 12iv. Nochangetocurrentpolicy 13v. TreatmentofBioliquids 15
4. Preferredoption 16
5. CombinedHeatandPowerandEnergyCrops 18i. CombinedHeatandPower(CHP) 18ii. EnergyCrops 19
AnnexA–HowtheROworks 20
i
1
Theclosingdateforresponsesis28May2010.
E-mailresponsesarepreferred.Pleasesubmitrepliesto:[email protected],hardcopyrepliesshouldbesentto:
RFITeam,RenewablesDirectorate,DepartmentofEnergyandClimateChange,4thFloor,AreaA/B,3–8WhitehallPlace,London,SW1A2HH.
Additional copies Youmaymakecopiesofthisdocumentwithoutseekingpermission.Furtherprintedcopiesoftheconsultationdocumentcanbeobtainedfrom:
RFITeam,RenewablesDirectorate,DepartmentofEnergyandClimateChange,4thFloor,AreaA/B,3–8WhitehallPlace,London,SW1A2HH.
Telephone:03000686833
Anelectronicversioncanbefoundat:http://decc.gov.uk/en/content/cms/consultations/grandfathering/grandfathering.aspx.Otherversionsofthedocumentareavailableonrequest.
Confidentiality and Data Protection Whenthisconsultationends,membersofthepublicmayaskforacopyofresponsesunderfreedomofinformationlegislation.
Ifyoudonotwantyourresponse–includingyourname,contactdetailsandanyotherpersonalinformation–tobepubliclyavailable,pleasesaysoclearlyinwritingwhenyousendyourresponsetotheconsultation.Pleasenote,ifyourcomputerautomaticallyincludesaconfidentialitydisclaimer,thatwon’tcountasaconfidentialityrequest.
Pleaseexplainwhyyouneedtokeepdetailsconfidential.Wewilltakeyourreasonsintoaccountifsomeoneasksforthisinformationunderfreedomofinformationlegislation.But,becauseofthelaw,wecannotpromisethatwewillalwaysbeabletokeepthosedetailsconfidential.
Wewillsummariseallresponsesandplacethissummaryonourwebsiteatwww.decc.gsi.gov.uk.Thissummarywillincludealistofnamesoforganisationsthatrespondedbutnotpeople’spersonalnames,addressesorothercontactdetails.
Help with queries Pleasedirectanyqueriesaboutthisconsultationtoourdedicatede-mailaddress:[email protected],orinwritingto:
RFITeam,RenewablesDirectorate,DepartmentofEnergyandClimateChange,4thFloor,AreaA/B,3–8WhitehallPlace,London,SW1A2HH
Telephone:03000686833
2 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
Ifyouhaveanycommentsorcomplaintsabouttheconsultationprocess,pleaseaddressthemto:
FerryLienertDECCConsultationCoordinatorArea6A3WhitehallPlaceLondon,SW1A2AW
Email:[email protected]
AcopyoftheCodeofpracticeonConsultationscanbefoundat:www.decc.gov.uk/Media/viewfile.ashx?FilePath=Consultations\1_20090408170031_e_@@_codepracticeconsultation.pdf&filetype=4
Thisconsultationandcallforevidenceonthepolicyongrandfatheringsupportfordedicatedbiomass,anaerobicdigestion(AD)andenergyfromwaste(EfW)intheRenewablesObligation(RO)hasparticularrelevancetoelectricitygeneratorsandsuppliersoperatinginthesemarkets.Itisalsoofinteresttoindustriesindirectcompetitionforthefuelusedbythesegenerators.
WithinthecontextofthelevelandbalanceofsupportofferedtotechnologiesacrosstheROitisrelevanttoenergyconsumersandtheirrepresentatives,electricitysuppliers,energygenerators,networkoperators,Ofgem,environmentalandenergyefficiencyorganisations,energyservicecompanies,installers,theconstructionsector,financeinstitutionsandotherstakeholderswithaninterestintherenewableenergybusiness.
ExecutiveSummary 3
1.ExecutiveSummary
InaGovernmentstatementon3February2010,wesetoutourcommitmenttousingsustainablysourcedbiomasstomeetourrenewableenergyneeds.WealsorecognisedconcernsfromanumberofdevelopersandinvestorsinthebiomassindustryoverthecurrentlackofgrandfatheringofsupportundertheRenewablesObligation(RO)forbiomass,anaerobicdigestionandenergyfromwaste.
Grandfatheringisthepolicyintentionthat,onceaccredited,ageneratorreceivesasetlevelofsupportoveritsperiodofeligibilityfortheRO.Grandfatheringpolicyisthereforenottoapplyanychangestolevelsofsupportatsubsequentbandingreviewstoexistinggenerators.
Towardstheendof2009,representativesofthebiomassindustryraisedconcernsthatthelackofgrandfatheringhascausedanumberofprojectstostall,asinvestorsplaceahighdiscountrateonfutureRenewablesObligationCertificates(ROC)levels.Theyarguethatitisthereforedifficultfortheseprojectstosecureanadequatelevelofdebtfinancingtomakethemviable.
InvestorcertaintyintheRenewablesObligationiskeytooursuccessinencouragingthedeploymentofrenewables.Since2002wehaveseenathreefoldincreaseinrenewableelectricitybroughtonbytheRO.Buttomeetourlegallybindingtargetsonrenewableenergy,wemustcontinuetodevelopourrenewablesgenerationcapacity.
Biomasselectricitygenerationisoneofthefewrenewableelectricitysourcesthatisdispatchable;generationcanbeplannedandchangedtomeetconsumerdemand.Itisthereforeoneofthelowcarbonsolutionsthatcanhelptobalancemoreintermittentsourcesofenergysuchaswind.Itisthereforeanimportantpartofourlowcarbonenergymix.
Thebiomassindustryhaveidentifiedupto5GWofdedicatedbiomass,energyfromwaste,gasificationandanaerobicdigestionprojectsthatareinplanningorpre-buildphase;anestimated£13billionworthofpotentialinvestment.Butforsomeoftheseprojectstocomeforward,investorshavesaidthattheyrequirecertaintythattheRenewablesObligationwillprovidethenecessarysupport.However,wemustensurethatanyproposalsrepresentvalueformoneyasitwillbeenergyconsumerswhowillultimatelypaythroughincreasedenergybills.
TheROtakesintoaccounttheupfrontcapitalcostofnewrenewablesgenerators,ongoingoperationandmaintenancecosts,aswellastheongoingfuelcosts,netofelectricityrevenues
Unlikeotherrenewablesgenerators,biomassgeneratorshaveanongoingfuelcost.Industryhaveinformedusthattheyareunabletofixthisfuelcostforthefull20yearsoftheROsupport.Therefore,grandfatheringtheirtotalsupport(whichtakesinto
4 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
accountboththecapitalandfuelcosts)for20yearsatcurrentlevelscouldresultinfuturemarketdistortionifbandswerechangedfornewentrants.ItwaspreciselyforthisreasonthatwedidnotgrandfathersupportforbiomassontheintroductionofbandinginApril2009.
Likeothertechnologies,dedicatedbiomassdevelopersshould,however,beabletofixthenonfuelcostsfortheupfrontbuildoftheproject.Wearethereforeproposingapolicytograndfathertheproportionassociatedwithnonfuelcostfordedicatedbiomass,butnottograndfathertheelementofsupportwhichhelpspayfortheongoingfuelcosts.ThisbringsthebiomassgrandfatheringpolicymorecloselyinlinewithourpolicyforotherrenewablesundertheRO,andaimstoprotectexistinggeneratorsfromhavingsupportreducedduetoabreakthroughintechnologywhichreducestheupfrontcapitalcostfornewgenerators.
ItalsoretainsflexibilityfortheROtorespondtochangesinbiomassfuelcostsifrequired.Shouldbiomasspricesrise,thereisflexibilitytoraisethelevelofsupportforbothnewandexistingdedicatedbiomassgenerators,thusmaintainingalevelplayingfieldforsuchstationswhencompetingforfuel.Likewise,shouldbiomasspricesfall,supportlevelsforbothnewandexistinggeneratorscouldbereduced,subjecttoapolicyintentionnottogobelowtheminimumlevelforexistinggenerators.
TheGovernmentisaskingforevidencetoinformadecisiononwhattheappropriateproportionoftheROClevelshouldbefornonfuelcostsforgeneratorsaccreditedbeforethenextbandingreview,thatcanhelpinsettinganappropriateminimumlevel.
Werecognisethatanaerobicdigestion(AD)andenergyfromwaste(EfW)withcombinedheatandpower(CHP)haveadifferentfuelsupplyrisk.ADplantstendtobesmallscale,usinglocallysourcedfeedstock,oftenatloworevennegativecost.Thesesmall,oftenonfarm,ADgeneratorsshouldbelesssensitivetochangestosupportlevelsforfutureentrantstothemarketandlesslikelytobecompetingforthesamefuel.Underthefeed-in-tariff(FIT)scheme,duetolaunchon1April,supportistobemaintainedforthelengthofthetariffforalltechnologies(includingAD).WethereforeproposetobringtheROinlinewithFiTsupportwithapolicytograndfatherADplantsaccreditedby31March2013atthecurrentROClevel,i.e.2ROCsperMWh.Weproposethatanygeneratorsaccreditingfrom1April2013shouldbegrandfatheredattherateapplicablefollowingtheoutcomeofthe2010–2013BandingReview.
StandardenergyfromwastewithCHPplantsaremorelikelytosecurelongterm,upto20year,fuelcontractsaspartofPFIdealswithlocalauthorities.Thesecontractsarestructuredtomakeitcostlytoterminateearly,thusprovidingadegreeofcertaintyofcosts/incomeforboththeLocalAuthorityandtheEfWgenerator.WethereforealsoproposeapolicytograndfathersupportforEfWgeneratorsatthecurrentROClevel,1ROCperMWh,providedtheyareaccreditedby31March2013.AswithAD,weproposethatanygeneratorsaccreditingfrom1April2013shouldbegrandfatheredattherateapplicablefollowingtheoutcomeofthe2010–2013BandingReview.
ExecutiveSummary 5
The½ROCupliftprovidedforfordedicatedbiomasswithCHPisaimedatsupportingtheadditionalcapitalcostofthistypeofbuild.However,theRenewablesHeatIncentive(RHI)isduetobelaunchedin2011,andwewanttoensurethatthetwoincentivescomplementeachother.WewillthereforeconsiderfurtherwhethertograndfathertheCHPupliftandconsultinthesummer.
AsannouncedinBudget2010,wewillconsultonproposedsustainabilitycriteriaforbiomasslaterthisyear.Withsustainabilitycriteria,inordertoqualifyforsupport,bio-energygenerationwillneedtodemonstraterealgreenhousegassavingsandbecarriedoutinamannerwhichdoesnotgiverisetodamaginglandusechange,undermineglobalfoodsuppliesorinflatefoodprices.Anygrandfatheringwouldonlyapplywhereageneratorisusingsustainablebiomass.Onceinforce,ifgeneratorsareusingbiomassthatdoesnotmeetthesustainabilitycriteria,theywillbeineligibletoclaimROCsforgenerationfromthatfuel.
Wearenotcurrentlyproposingtograndfathersupportforgeneratorsusingbioliquids,asthereisaquestionastowhetherputtingbioliquidsintoelectricityisthebestwayofhelpingustoachieveourrenewableenergytargets(giventheirpotentialuseforheatandtransport).Ourpolicyremainsforflexibilitytoamendsupportlevelsforbioliquidsatfuturebandingreviewsforbothnewandexistinggenerators.
Therewasinsufficientevidenceonwhichtoconsiderchangingourpolicytowardsthegrandfatheringofadvancedthermaltechnologies,suchasadvancedgasificationandadvancedpyrolysis,attheircurrentlevelof2ROCperMWhsupport.Thispositionwillbereviewedusingtheevidencefromthisconsultation.
6 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
2.ReasonsforConsultation
WhentheROwasintroducedin2002,supportwastechnologyneutralandsetat1ROCperMWhforalltechnologies,sobringingononlythecheapesttechnologies.Itdidnothelpsupportthemoreexpensive,emergingtechnologies.
InApril2009bandingwasintroducedintotheRenewablesObligation,allowingustosetsupportlevelsgroupedbytechnologytypeintofourbands.Thisrecognisedthatsometechnologieswerecheapertodeploythanothers,andthatsomerequiredadditionalsupporttoreachmassdeploymentlevels.ThelegislationallowstheSecretaryofStatetoreviewthebandsatscheduledreviewpoints,withthefirstscheduledreviewduetobeginthisOctober,withanychangescomingintoeffectinApril2013.
Bandingreviewsallowustheflexibilitytoadjustsupportascircumstancesinthemarketetcchange,thusretainingvalueformoneyandensuringtechnologiesreceivetherightlevelsupport.
Thebulkofcostsformostrenewabletechnologiesarelargelyupfrontcapitalcosts,withlowongoingmaintenancecosts.Existinggeneratorsdonot,therefore,tendtobenefitfromanyfutureinnovationinthesectorthatreducesbuildcosts,orincreasestechnologyefficiency.
Inordertoensureinvestmentinthesetechnologies,weintroducedtheconceptofgrandfathering.ThisisapolicyintentiontomaintainingalevelofsupportforthefulllifetimeofeligibilityfortheRO,fromthepointofaccreditation.Forgrandfatheredgenerators,ourpolicyintentisnottochangetheoriginallevelofsupportreceivedatfuturebandingreviews.
Thepurposeofthispolicyistoallowgeneratorstofinancethefixedcostsoftheirdevelopmentoverthelifetimeoftheproject’seligibilityforsupportundertheRO.
Followingtheconsultationonbandingandgrandfatheringin2008,wemadeadecisionnottograndfathersupportforbiomassas,incontrasttootherrenewablestechnologies,alargeproportionofabiomassgenerator’scostsarefuelcosts,whichcanvaryovertime.Grandfatheringcouldthereforehavetwoeffects:
1. Ifsupportissettoohigh,stationscouldbeovercompensated.Settoolow,andplantswouldnotbeabletocompeteforfuel;
2. Generatorsenteringthemarketindifferentyearscouldreceivedifferentlevelsofsupport,yetwouldcompeteforthesamefuelstock,therebypotentiallydistortingthemarket(asonewillbeabletopaymorethantheother).
FutureRObandingreviewscouldthereforeresultinanamendmenttothelevelofsupportforexistingbiomassgenerators,aswellasnewones.InApril2009,actual
ReasonsforConsultation 7
supportwasincreasedforexistingbiomassgeneratorsfrom1ROCtobetween1.5ROCsperMWhto2ROCsperMWh,dependingontechnologytype.Ifexistingbiomassgeneratorshadbeengrandfathered,inlinewithothertechnologies,thisincreasewouldnothavebeenpossible.
Sincetheintroductionofbanding,andtheincreasedsupportforbiomass,wehaveseenanincreaseinplanningapplicationsforbiomassgeneratingstations.Thebiomassindustryhaveidentifiedupto5GWofdedicatedbiomass,energyfromwaste,gasificationandanaerobicdigestionprojectsthathavebeenproposedorareinplanningorpre-buildphase.
However,thebiomassindustry,banksandequityprovidershaverecentlyraisedconcernsovertheuncertaintyoffuturesupportlevels.Developersarguethatbanksandequityprovidersarenowholdingoffinvestmentinbiomassprojects.Withoutcertaintyoversupportlevels,developersarguetheywillbeunabletoobtainfinance,andprojectswillthereforenotgoahead.
Followingrepresentationsfromindustry,anddiscussionswithbanksandequityinvestors,weannouncedwewouldrevisitourcurrentgrandfatheringpolicyfordedicatedbiomass,anaerobicdigestionandenergyfromwaste.Wedonotintendtorevisitgrandfatheringpolicyforanyothertechnologyinthisconsultation.
Aspartofthisexercise,wehavealsoconsideredwhethertograndfatherthe½ROCupliftfordedicatedbiomasswithCHP,and/ortograndfatherthe½ROCupliftforgeneratorsusingenergycrops.
Inrevisitingourbiomassgrandfatheringpolicy,weengagedwithawiderangeofdevelopers,investorsandtradeassociations,andtheRenewablesAdvisoryBoard.
Inadditiontoaseriesofmeetingswithindividualbiomassdevelopersandinvestors,wesetuptwoworkinggroups:
1. Anindustryworkinggroupwithbiomassdevelopersfromarangeofcompanysizes,andfromacrossdedicatedbiomass,ADandEfWsectors
2. Aninvestorworkinggroup,withrepresentativesfromanumberofbanksandequityinvestors
Thepurposeofthisconsultationisto:
• seekviewsonwhetherourpreferredoptionisthebestwayforward
• gatherevidenceonthecostsfordedicatedbiomass,ADandEfW,andtheproportionofcostsattributabletononfuelcosts
• testourassumptionsoverinvestorreactiontograndfatheringandthereforethelikelyamountandtimingofinvestmentthatwouldcomeforwardunderdifferentoptions
8 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
• seekviewsastowhetherthereareanyotherunintendedconsequencesofourpreferredoption
ThetotalnumberofRenewablesObligationCertificates(ROCs)awardedforbiomasstechnologiesisnotbeingreviewed.WewillbereviewingbandinglevelsforalltechnologiesinthescheduledBandingReview,duetostartinOctoberthisyear.AnychangestobandsasaresultofthescheduledBandingReviewareduetocomeintoeffectfrom1April2013.
Optionsconsidered 9
3.Optionsconsidered
Wehaveconsideredfourpossiblepolicyoptions:
i. Grandfathering at band received on accreditation ii. Grandfathering at current levels, with potential to upband iii. Grandfather a minimum level (the rest free floating) iv. Do nothing scenario – business as usual
Wehavealsoconsideredhowtotreattheuseofbioliquids.
i. Grandfathering at band received on accreditation Underthisoption,biomassgeneratorsaccreditedby31March2013wouldbegrandfatheredatcurrentROClevels.Entrantsfrom1April2013wouldreceivenewsupportlevels,ifchangedfollowingthe2010–13BandingReview.
Thisisinlinewiththegrandfatheringprincipleforothertechnologies,andshouldgiveinvestorsthecertaintytheyneedoverfutureincome.Thisoptionwouldgrandfathernotonlythesupportforcapitalcost,butalsotheongoingfuelcost.
Fuelpricesarevariableovertime,andanumberofdevelopershavemadeclearthatlongterm,20yearfixedpriceandvolumefuelcontractsarenotcurrentlyavailable.DevelopersarethereforecurrentlysubjecttovariablefuelcoststhroughoutthelifetimeoftheireligibilityfortheRO,andwillhavetocompeteagainstbothexistingandfuturegeneratorsforfuel.Thereisconsiderableuncertaintyabouthowthemarketwilldevelopinthefuture.Itmaybethecasethat,asanE4Techstudysuggests,manypowerplantsarelookingforlongtermcontracts,somewithinvestmentinthebiomasssupplychain,withonlysmallamountsofspotbuying.Howeverinvestorsaresayingthatthecurrentfuelpricevolatilityandlackofcertaintyofsupportisstallingcurrentplans.
Thishasthepotentialtocreateafuturemarketdistortion;ifROClevelsarenotallowedtorespondtobiomassprices,generatorsaccreditingindifferentbandingreviewperiodswillreceivedifferentlevelsofoverallsupport,placingsomeinvestorsatacompetitivedisadvantagewhensourcingfuel,whileotherswillreceiveexcessrents.
Providinginvestorswithgrandfatheredsupportatcurrentlevelsmayincreaseavailabilityofdebtfinanceforbiomassdevelopers.However,itwouldbedifficulttoamendbands,eitherupordown,forfuturegenerators,withoutcausingthismarketdistortion.Thisriskmayprovetobetoogreatfortheequityinvestorstotake.As
10 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
projectsneedamixofdebtandequityinvestment,thisoptionmaylimitdeploymentpotential.
Whilstfuelpricevariabilityisamajorconcernfordedicatedbiomass,itislessofanissueforanaerobicdigestionandenergyfromwasteplants.
ADplantstendtobesmallscale,usinglocallysourcedfeedstock.LargerADplant,suchasthoseusingmunicipalfoodwaste,aremorelikelytosecurelongtermfuelcontracts.Theywouldthereforebelesssensitivetochangestosupportlevelsforfutureentrantstothemarket.
EnergyfromWasteplants(EfW)aremorelikelytosecurelongterm,upto20year,fuelcontracts,aspartofPFIdealswithlocalauthorities.
InvestorshavestatedthatgrandfatheringsupportforADandstandardEfWatcurrentrateswouldprovidethecertaintytheyneedandensurethecontinueddeploymentofthistechnology.AnumberofinvestorsanddevelopershavesuggestedthisasapotentialsolutionforjustADandEfWgeneratorswhooperateindifferentmarketconditions.
Impact on value for money.TheimpactonthecostoftheROwilldependonfuturefuelpricescenarios.Ifforexamplefuelpricesfallatthenextbandingreview,grandfatheringcouldleadtopotentialoversubsidyundertheRO.Thismakesgrandfatheringpotentiallypoorvalueformoney,particularlyfordedicatedbiomass.
Impact on deployment.Takinginvestorsassumptionthatthelackofgrandfatheringiscausingahiatusininvestment,whichcouldleadtolowerinvestmentinrenewablesintheUK,thengrandfatheringcouldreducetheriskofsuchahiatusrelativetooption4.Wearelookingforevidenceontheimpactofgrandfatheringoninvestmentdecisions.
Q1:Whatinformationcanyouprovideoncurrentbiomassfuelcontracts,feedstocksourcesandpricesfordedicatedbiomass?Howdoyouexpectthemarkettodeveloplongerterm?
Q2:Doyouagreethatgrandfatheringatcurrentlevelsfordedicatedbiomasscouldresultinunfaircompetitionifbandswerechangedfornewentrantsinafuturebandingreview?Pleaseprovideyourargument.
Q3CouldgrandfatheringADandEFWcausesimilarmarketdistortion?Doyouagreethattheriskislessforthesetechnologies?Pleaseprovideyourargument.
Q4:WhatarecurrentADandEfWfeedstockpricesorsubsidiesfordisposalandwhatdoyouestimatethesepricestobeinthefuture?Arethesearrangementsdrivenbylandfillgatefees?Doyouagreethatthesefeedstocksarelesssubjecttopriceuncertaintythandedicatedbiomassplant?
Optionsconsidered 11
Q5:WhatevidenceistherethatwithoutgrandfatheringtherewouldbeahiatusininvestmentforAD,EfWanddedicatedbiomass?
ii. Grandfathering at current levels, with potential to upbandUnderthisoption,ifatthenextbandingreviewweincreasetheROCbandfornewentrants,thenexistinggeneratorswouldbebandedup.However,ifthelevelofROsupportwasdecreasedfornewentrants,existinggeneratorswouldnotbebandeddown,butgrandfatheredattheleveltheyreceivedonaccreditation.
Thisoptionwouldinsulateinvestorsagainstanydownsiderisk,whilstprovidingaccesstoanyincreasesinsupport.
However,thisoptionislikelytoofferextremelypoorvalueformoneytoconsumers.Itlocksincurrentlevelsofsupport,whichmayleadtofutureovercompensationiffuelpricesfall.Consumerswouldbebearingallthecostofthis.
Grandfatheringatcurrentrateswouldessentiallyfixthefuelcostcomponentaswellasnonfuelcosts.Ifbiomasspricesfall,wewouldneedtoreducesupportfornewentrantstoensurevalueformoneytoconsumersandcomplywithEUStateAidrules.But,bykeepingexistinggeneratorsatahigherlevel,notonlydoesthisrepresentpoorvalueformoneyforelectricityconsumers,italsomeansthatnewentrantstothemarketmaybeunabletocompeteforfuel.Grandfatheringwithanupliftonlyexacerbatesthisissue,andplacestheriskofbiomasspriceincreasesontheconsumer.
Impact on value for money.TheimpactonthecostoftheROwilldependonfuturefuelpricescenarios.Ifforexamplefuelpricesfallatnextbandingreview,grandfatheringcouldleadtoincreasedoversubsidyundertheRO,asunderoption1.Moreovercostswillbehigherthanunderoption(1)underarisingfuelpricescenario.Underoption1,levelsofsupportremainfixedunderrisingfuelprices,whereasunderthisoptionadditionalcostswillbeincurredunderhigherfuelprices.
Impact on deployment.Takinginvestorsassumptionthatthelackofgrandfatheringiscausingahiatusininvestment,grandfatheringcouldreducethisriskrelativetooption4,andthereforethecostofmeetingtherenewabletargetrelativetothestatusquo.Wearelookingforevidenceontheimpactofgrandfatheringoninvestmentdecisions.
Q6:Towhatextentdoesgrandfatheringriskmarketdistortion?Isthereevidencetosupporttheextenttowhichthisdistortioncouldaffectfutureinvestment?
Q7:Doyouagreethatthisoptionofferslessvalueformoneytotheconsumer,duetothelackofresponsetofuturefuelprices?
12 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
iii. Grandfather a minimum level, with the rest free floatingUnderthisoption,aproportionoftheROCsupportlevelwouldbegrandfatheredtotakeintoaccountthefactthatsome,butnotall,ofthecostofabiomassgeneratorisfornon-fuelcosts,forexampletheupfrontcapitalcostofbuildingageneratingstation.FullROCsupportforothertechnologiesisgrandfatheredastheirupfrontcapitalcostsmakeupthemajorityoftheircostsanddonotchangeoncethegeneratorhasbeenaccredited;eveniftechnologyadvancesmeanthatcostscomedowninfuture.
Ifweweretoapplythesameprincipletobiomassgenerators,theproportionoftheROClevelthatisdeemedtobeduetonon-fuelcostscouldbegrandfathered,leavingtheelementthatsupportsthevariablefuelcost‘freefloating’i.e.subjecttochangeatfuturebandingreviews.Thiswouldprovidesomecomfortoverthelevelofsupportfornewplantandgiveafirmerbasisforinvestmentinthebiomasspowergenerationmarket.
Ifbiomassfuelpriceshavechangedatthetimeofthenextbandingreviewthensupportlevelsforallnewandexistinggeneratorswilltakeaccountofthenewbiomassfuelpricelevels.Existinggeneratorswouldreceivethenewlevelattributedtofuelcosts,howeverthegrandfatheredelement,attributedtonon-fuelcostswouldnotchange.Newgeneratorswouldhavetheirnon-fuelcostsgrandfatheredattheleveldeterminedbythereview.
Thisoptionshouldprovideinvestorswiththesecuritythatexistinggeneratorsreceiveaminimumlevelofsupport,allowingbankstolendonthatbasis,andanyallowancetheymightmakeforfutureuncertainbiomassprices.Italsoprovidesmoreprotectionforconsumersthanoptions1and2as,shouldbiomasspricesfall,supportcanbedecreasedwithoutriskingahiatusindeployment.
WewouldwelcomeviewswithsupportingevidenceastowhatproportionofthecurrentROClevelshouldbeattributabletothenon-fuelcosts.
Wehaveidentifiedtwopotentialwaystodeterminethesupportneededforcapexandopexelements
1. Takelevelisedcapitalandoperationalandmaintenance,netofelectricityrevenuestoestimatethelevelofROCtosupportbiomassnonfuelcosts.
2. Determinethecontributionofnon-fuelcoststototalcosts,andapplyproportionallytotheROCband.
Weareseekingevidencetosupportwhichmethodologywouldbemostappropriatetouse.
ThisoptionisnotconsideredappropriateforADandEfW.Small-scale,on-farmADgeneratorsarelesslikelytorelyonfeedstockswithfluctuatingprices,oftenusingon-farmwaste.Incaseswheretheysourcefuel,forexampleusingfoodwaste,theymaybepaidtotakethefueli.e.thefuelisnotacost,itisanincomestream.Thesame
Optionsconsidered 13
appliestoEfWplants,wherethereisoftenagatefeepaidtothegeneratorfortakingthewaste.
Furthermore,EfWplantsaremorelikelytobeabletosecurelongtermfuelcontractsunderLocalAuthorityPFIdeals.IftheyaresubjecttoanyelementofuncertaintyovertheleveloffutureROsupport,banksmayrestricttheleveloffunding,orrequirehigherratesofreturn,meaningthatfewerprojectsarelikelytobedeployedand/orathighercost.
Impact on value for money.Lessriskofexcessrentsduetolowerlevelgrandfathered.Thusbettervalueformoneyfortheconsumer.
Impact on deployment.Wearelookingforevidenceontheimpactofgrandfatheringoninvestmentdecisions.
Q8:Pleaseprovideevidenceofactualcostsandrevenuesfordedicatedbiomass,ADandEfWplants,includingevidencetodemonstratetheproportionofthesecoststhatisnonfuel?
Q9:Whichmethodologyfordeterminingasupportlevelfornonfuelcostsisthemostappropriate,andwhy?Arethereanyothermethodsweshouldconsider?
Q10:IsthisanapproachtothelevelofgrandfatheringthatcouldworkforADandEfWplants?
Q11:Whatevidencecanyouprovidetosupportwhetherthislevelofgrandfatheringcouldbringforwardinvestmentindedicatedbiomass/AD/EfW?Whatlevelsofdeploymentwouldyouexpecttosee,andwhenwouldyouexpectgeneratorstobeaccredited?
iv. No change to current policyThisoptionmaintainsourcurrentpolicy,atleastuntilanybandingchangesin2013.Thisleavesuswiththegreatestflexibilitytorespondtofuturepricechanges,andthusensuresthatconsumervalueismaintained.
Accordingtoindustry,thisoptionmayresultinahiatusindeploymentofbiomassgenerators.AnumberofdebtprovidershavestatedthattheywilldiscountROCrevenuewhenmakinglendingdecisions,meaningthattheyareunlikelytooffermuch,ifany,debtfinancing.
Itispossiblethat,intheabsenceofgrandfathering,someadditionalresourcewillstillcomethrough,assomeinvestmentscouldbeonbalancesheet,andcouldthereforeraisefinancewithoutthebenefitofgrandfatheringpolicy.SmallscaleADplantsalsohavetheoptionofoptingfortheFeedinTariff(FiTs),whichwillbegrandfathered.
14 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
Overall,giventhefeedbackwehavereceivedtodate,wewouldexpectdeploymentofbiomasselectricitylevelstobelowerthanundertheotheroptions.
ModellingbyRedpoint(2010)wouldsuggestthatifthereisahiatusinbiomass,therewouldbepotentialtomeettherenewableenergytargetof15%ofenergyfromrenewablesby2020,throughothermeanssuchasco-firing.Thiscouldreducetheoverallcostofreachingtherenewableenergytarget.
Nonetheless,werecognisebiomasselectricitygenerationhasanimportantroletoplayinensuringadiverseenergymix.biomassisoneofthelowcarbonsolutionsthatisdispatchable–i.e.thelevelofgenerationcanbeadjustedwithaconsumerdemand–andcanhelpcountertheintermittentnatureofotherrenewabletechnologies.
Useofanaerobicdigestioncanalsoreducetheamountofmethane,apowerfulgreenhousegas,losttotheatmospherethroughdiversionofwastefromlandfillandcaptureofmethanefrommanures,slurriesandsewagesludge.
WhilstmostADprojectscouldswitchtotheFeedinTariffs,duetocomeinon1Aprilthisyear,therecouldbeahiatusinADplantdeploymentifinvestorsrequireprojectstoundergoduediligenceunderthenewscheme.Dependingonprojectfinance,thereisariskthatsomeprojectscouldpotentiallybecancelled.
Additionally,energyfromwasteisintegraltoourwastemanagementpolicy.TheEULandfillDirectiverequirestheUKtocutthevolumeofbiodegradablemunicipalwastesenttolandfillto35%ofthatproducedin1995by2020andsetsinterimtargetsfor2010and2013.
ThecurrentpolicynottograndfatherROsupportforADandEfWmaythereforeriskbothdeliveryoftheADImplementationPlanandLandfillDirectivetargets.ItcouldalsoincreasethecostofwastedisposalforLocalAuthoritiesasalternateroutesmayneedtobefound.
Q12:Doyouagreethatalackofgrandfatheringwillimpactdeploymentlevelsfordedicatedbiomass,ADandEfW,andifso,towhatextent?
Q13:IstherepotentialforothertechnologiestobedeployedundertheRO?Ifso,atwhatlevels?
Q14:Ifthereisnochangetocurrentpolicy,howeasywoulditbeforproposedADprojectstoswitchtheirfundingtoFITs?
Optionsconsidered 15
v. Treatment of BioliquidsThemajorityofbiomassstationsuseasolidfuelsuchaswoodchips,strawandpoultrylitter.Currentsupportlevelshavebeensetforsolidbiomassplantswiththesetypesoffuelsinmind.However,thereisamuchsmalleramountofbioliquidsusedsuchastalloil.Bioliquidsdevelopedforthetransportsectorsuchasbio-dieselandbio-ethanolcanalsobeusedtogenerateelectricity.
Thereisaquestionastowhetherbuildingbioliquidelectricityplantandputtingbioliquidsintoelectricityisthebestwayofhelpingustoachieveourrenewableenergytarget,wheretheymaywellhavegreatervalueinhelpingachieveourtransporttargetandindecarbonisingheat.Assuch,wearenotproposingtoprovideanygrandfatheringforgeneratorsusingbioliquidsunderanyoftheoptionsabove.
Thiswillprovidetheflexibilitytoamendsupportlevelsforbioliquidsatfuturebandingreviewsforbothnewandexistinggenerators.
Q15:Doyouagreethatbioliquidsshouldnotbegrandfathered,andwhy?
16 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
4.Preferredoption
Basedontheevidencepresented,itseemsclearthataonesizefitsallsolutionisnotappropriateforbiomasselectricity.Thusweareproposingasplitsolution.
Fordedicatedbiomass,wearemindedtograndfathertheproportionofnon-fuelcosts.Dedicatedbiomassdevelopersneedaflexiblesupportregimethatcanadapttochangesinbiomassprices,whilstensuringalevelplayingfieldismaintainedbetweencompetinggenerators,accreditingatdifferenttimes.Thiswillensuremarketdistortiondoesnotoccurthroughfixingsupportforfuelsataparticularrate.Thisisalsonecessarytoprovidevalueformoneyforconsumers.
ADandEfWplantsontheotherhadappeartohavelessofanissuewithfuelpricevariabilityastheyareabletonegotiatelongertermfuelcontracts.
Wearethereforemindedto:
• grandfathersupportatcurrentlevelsforADandEfWgenerators;and
• grandfatheraminimumlevelofsupportfordedicatedbiomass,setastheproportionofcostsattributabletononfuelcosts.
Thiswouldapplytouseofbiomass,butnotbioliquids.InlinewiththegrandfatheringprinciplesforothertechnologiessupportedundertheRO,supportwouldbegrandfatheredfromthepointofaccreditation.
OurproposedgrandfatheringpolicyforADandstandardEfWprojectsmeansthataccreditedgeneratorswouldreceivethesamelevelofsupportreceivedonaccreditationfortheremainderoftheirlifetimeintheRO.
DedicatedbiomasswouldhaveaminimumlevelofsupportgrandfatheredonaccreditationandwouldreceivethislevelfortheremainderoftheirtimeintheRO.Ifsupportforfuelcostsfordedicatedbiomassareincreasedatafuturebandingreview,allexistingprojectswouldbebandedupsothatallgeneratorsreceivethesamelevelofsupportforfuelcosts.
However,ourproposedpolicytograndfatheraminimumlevelmeansthat,shouldbandsfordedicatedbiomassbeloweredtolessthantheminimumgrandfatheredlevelatanyfuturebandingreview,anygeneratorsaccreditedbeforethebandingreviewcomesintoeffectwouldreceivetheminimumlevel,withnewentrantsreceivingthenew,lower,rate.
Weproposetosettheminimumlevelfordedicatedbiomassastheproportionofcostsattributabletononfuelcosts.Thefreefloatingelementwillbebasedontheproportionofcoststhatareattributabletoongoingfuelcosts.Wewouldwelcomeviewsastowhatthisproportionorlevelshouldbe.
Preferredoption 17
Webelievethisproposalgivesthebestbalancebetweenensuringdevelopersandinvestorshavethecertaintytheyneedtoinvest,whilstretainingenoughflexibilitytocopewithpotentialvariationsinfuturebiomassandelectricityprices,somaintainingvalueformoneytotheconsumer.
TheGovernmentiscommittedtomeetingthe15%renewableenergytargetby2020,andthisoptionshouldhelpachievethat.Anydecisionongrandfatheringofsupportforbiomasswillneedtobemadeinthecontextofafullvalueformoneyanalysis,toensurethatconsumervalueismaintained.
Q16:Doyouagreethatthisproposaloffersthebestbalancebetweenvalueformoney,investorconfidenceandflexibility?Ifnot,pleasegiveyourreasonsandstatewhatalternativeoptionyouthinkwouldbemoreappropriate.
Q17:DoyouagreethatseparatesolutionsareneededforADandEfWanddedicatedbiomass?Pleaseprovideyourargument
Q18:Doyouagreethatthisoptionwouldallowcurrentinvestorstogoaheadwiththeirplans?Whatdeploymentlevelswouldyouexpectandwhy?
Q19:WhatbuildtimeswouldyouexpectforAD,EfWanddedicatedbiomassgenerators?
Q20:Howshouldsupportforadvancedthermaltechnologies,suchasadvancedgasificationandadvancedpyrolysis,betreated?Shouldwegrandfatherthenonfuelcosts,orgrandfatheratcurrentlevels?Pleaseprovideyourargument.
18 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
5. CombinedHeatandPowerand EnergyCrops
Underthecurrentbandingstructure,generatorswithCombinedHeatandPower(CHP)receiveanadditional½ROCuplift,uptothemaximum2ROC/MWhsupportlimit.Thismeansthatadedicatedbiomassgeneratorcanreceive2ROCsperMWhiftheyareaCHPgeneratorontheirgoodqualityelectricityoutput.Likewise,ifageneratorusesenergycrops,theyreceivea½ROCupliftcomparedtoregularbiomass.
i. Combined Heat and Power (CHP)TheCHPuplifttakesintoaccountthehigherupfrontcapitalcostsofCHPtechnologies.However,theRenewableHeatIncentive(RHI),duetobeimplementedinApril2011,willprovidefinancialsupportfortheheatgenerationofCHPstationsinthefuture.Detailsoftheschemearecurrentlybeingconsultedon,includingwhethertograndfathersupport.TheconsultationcanbeviewedonDECC’swebsite:http://www.decc.gov.uk/en/content/cms/consultations/rhi/rhi.aspx
TheproposedtransitionarrangementsfromtheROtoRHIforCHPgeneratorsare:
• CHPstationsaccreditedunderRObeforethepublicationoftheRenewableEnergyStrategy(i.e.before15July2009)willcontinuetoreceivetheROplusuplift,butwillnotbeeligiblefortheRHIontheirheatoutput.
• ROeligibleCHPstationsinstalledonorafter15July2009willbeofferedaoneoffchoicetoclaimtheROplusuplift,ortheRO(minusuplift)plustheRHI.OperatorsofCHPstationswillbeabletomakethischoiceatanypointupuntil1April2013
• CHPstationsaccreditedfrom1April2013willnolongerbeeligibleforthe½ROCCHPupliftontheirgoodqualityelectricityoutput.However,theywillstillbeabletoclaimROCs(minusuplift)ontheirelectricityoutputandtheRHIontheirheatoutput.
However,theproposedtransitionarrangementsareouttoconsultationandthereforesubjecttochange.Assuch,wewouldnotwanttosetagrandfatheringpolicyontheCHPupliftwithintheRO,untilboththetransitionalarrangementsaredecidedon,andadecisionhasbeenmadeonwhetherornottograndfathersupportundertheRHI.
WewillconsultfurtheronthisaspartofthestatutoryconsultationfortheRenewablesObligationOrder2011,laterthisyear.
CombinedHeatandPowerandEnergyCrops 19
ii. Energy CropsWhenbandingwasintroduced,theGovernmentwaskeentoencouragethedevelopmentoftheenergycropsupplychain.Thisremainsaveryimmaturemarket,andtheadditional½ROCperMWhforgeneratorsusingenergycropswasaimedatprovidingsupporttothesesupplychainsandtosupportthehigherfuelcost.Sinceweareproposingtograndfathernonfuelcosts,wedonotproposetograndfathertheenergycropuplift.
Assupplychainsmatureinthefutureitshouldbepossibletoreduceorremovethisuplift.Assuch,ifwedonotfeelthatitwouldbeappropriatetograndfatherthissupport,giventhatfuelpricesaresubjecttovariationovertime.
Q21:Doyouagreethattheenergycropupliftshouldnotbegrandfathered?
20 ConsultationonthegrandfatheringpolicyofsupportforDedicated Biomass, Anaerobic Digestion and Energy from Waste under the Renewables Obligation
AnnexA–HowtheROworks
• TheROworksbyplacinganobligationonlicensedelectricitysupplierstosourceaspecifiedandannuallyincreasingproportionoftheirsalesfromrenewablesources,orpayapenalty.
• Theleveloftheobligationis9.7%forthe2009/10obligationperiod,andwillriseto11.1%for2010/11.
• GeneratorsareissuedwithRenewablesObligationCertificates(ROCs)foreverymegawatthour(MWh)ofeligiblerenewableelectricitytheygenerate.Asof1April2009,whenweintroduced‘banding’,differenttechnologiesreceivedifferentnumbersofROCsperMWh.Thisreflectsdifferencesbetweentechnologiesincludingthecostofgenerationandpotentialforlarge-scaledeployment,andprovidesincreasedsupporttotechnologiesthatarelesswell-developedorfurtherfromthemarket.
• GeneratorsselltheirROCstosuppliersortraderswhichallowsthemtoreceiveapremiuminadditiontothewholesalepriceoftheirelectricity.ROCscanbesoldwithorwithouttheelectricitytheyrepresent.
• SupplierssatisfytheirobligationbypresentingROCstoOfgem,whoadministerthescheme.WheretheydonotpresentsufficientROCstheyhavetopayapenaltyknownasthebuy-outprice.Thisissetat£37.19/MWhfor2009/10(andlinkedtoRPI).
• ThismoneyisheldbyOfgeminthebuy-outfunduntiltheendoftheobligationperiod,whenitisrecycledtosupplierswhopresentedROCsonapro-ratabasis.