CONSTRUCTION UPDATE COMMUNITY & RECREATIONAL CENTER August 2, 2019 West Allis - West Milwaukee SITE PROGRESS: GOALS NEXT 2 WEEKS: MILESTONE DATES: CONSTRAINTS: • None Building • Begin constructing masonry elevator shaft • Start structural precast • Start underground electrical and plumbing in the addition Site Work • Finished footings and frost walls • Installation of rigid insulation on foundation walls • Completed backfill around foundations • Precast Erection – Start 8/5/19 • Structural Steel placement – Start 9/3 Angles for precast installed Column pads poured and base plates set Installation of insulation and backfill Elevator pit poured
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
CONSTRUCTION UPDATE
COMMUNITY & RECREATIONAL CENTER
August 2, 2019
West Allis - West Milwaukee
SITE PROGRESS: GOALS NEXT 2 WEEKS:
MILESTONE DATES: CONSTRAINTS:
• None
Building
• Begin constructing masonry elevator shaft
• Start structural precast
• Start underground electrical and plumbing in the addition
Site Work
• Finished footings and frost walls
• Installation of rigid insulation on foundation walls
• Completed backfill around foundations
• Precast Erection – Start 8/5/19
• Structural Steel placement – Start 9/3
Angles for precast installed
Column pads poured and base plates
setInstallation of insulation and backfill
Elevator pit poured
CONSTRUCTION UPDATE
COMMUNITY & RECREATIONAL CENTER
August 9, 2019
West Allis - West Milwaukee
SITE PROGRESS: GOALS NEXT 2 WEEKS:
MILESTONE DATES: CONSTRAINTS:
• None
Building
• Begin constructing masonry elevator shaft
• Start underground electrical and plumbing in the addition
• Field measurements for storefront framing
Site Work
• Started erection of Precast panels
• Completed rigid insulation on foundation walls
• Completed backfill around foundations
• Precast Erection – Finish 8/5/19
• Structural Steel placement – Start 9/3
North face of gym
West face of gym
Northeast corner of gym
CONSTRUCTION UPDATE
COMMUNITY & RECREATIONAL CENTER
August 16, 2019
West Allis - West Milwaukee
SITE PROGRESS: GOALS NEXT 2 WEEKS:
MILESTONE DATES: CONSTRAINTS:
• None
Building
• Complete masonry for stair and elevator shaft
• Complete precast detailing
• Complete underslab plumbing and electrical
Building
• Precast detailing
• Started underslab plumbing and electrical
• Started masonry for stairwell and elevator shaft
• Structural Steel placement – Start 9/3
Elevator and stairwellUnderslab plumbing
Underslab plumbing Precast detailing
CONSTRUCTION UPDATE
COMMUNITY & RECREATIONAL CENTER
August 23, 2019
West Allis - West Milwaukee
SITE PROGRESS: GOALS NEXT 2 WEEKS:
MILESTONE DATES: CONSTRAINTS:
• None
Building
• Complete masonry for stair shaft
• Complete precast detailing
• Complete final grading inside building
Building
• Masonry elevator shaft is complete
• Masonry stair shaft is near completion
• Preparing door and window openings in gym
• Structural Steel placement – Start 9/3
Elevator and stairwell
Door and window openings being prepared
Masonry stair shaft
Underslab plumbing - completed
CONSTRUCTION UPDATE
RECREATION & COMMUNITY SERVICES CENTER
August 30, 2019
West Allis - West Milwaukee
SITE PROGRESS: GOALS NEXT 2 WEEKS:
MILESTONE DATES: CONSTRAINTS:
• None
Building
• Complete final grading inside building
• Start erecting steel between existing building and gym
Building
• Underslab electrical is complete
• Masonry stairwell is complete
• Final grading of building pad is near completion
• Structural Steel placement – Start 9/6
Stairwell 1 – North elevationFinal grading of building pad
Stairwell 1 complete Final grading of building pad