CONSTRUCTION UPDATE COMMUNITY & RECREATIONAL CENTER August 2, 2019 West Allis - West Milwaukee SITE PROGRESS: GOALS NEXT 2 WEEKS: MILESTONE DATES: CONSTRAINTS: None Building Begin constructing masonry elevator shaft Start structural precast Start underground electrical and plumbing in the addition Site Work Finished footings and frost walls Installation of rigid insulation on foundation walls Completed backfill around foundations Precast Erection Start 8/5/19 Structural Steel placement Start 9/3 Angles for precast installed Column pads poured and base plates set Installation of insulation and backfill Elevator pit poured
5

CONSTRUCTION UPDATE - SharpSchool

Nov 18, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 2, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Begin constructing masonry elevator shaft

• Start structural precast

• Start underground electrical and plumbing in the addition

Site Work

• Finished footings and frost walls

• Installation of rigid insulation on foundation walls

• Completed backfill around foundations

• Precast Erection – Start 8/5/19

• Structural Steel placement – Start 9/3

Angles for precast installed

Column pads poured and base plates

setInstallation of insulation and backfill

Elevator pit poured

Page 2: CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 9, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Begin constructing masonry elevator shaft

• Start underground electrical and plumbing in the addition

• Field measurements for storefront framing

Site Work

• Started erection of Precast panels

• Completed rigid insulation on foundation walls

• Completed backfill around foundations

• Precast Erection – Finish 8/5/19

• Structural Steel placement – Start 9/3

North face of gym

West face of gym

Northeast corner of gym

Page 3: CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 16, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete masonry for stair and elevator shaft

• Complete precast detailing

• Complete underslab plumbing and electrical

Building

• Precast detailing

• Started underslab plumbing and electrical

• Started masonry for stairwell and elevator shaft

• Structural Steel placement – Start 9/3

Elevator and stairwellUnderslab plumbing

Underslab plumbing Precast detailing

Page 4: CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

COMMUNITY & RECREATIONAL CENTER

August 23, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete masonry for stair shaft

• Complete precast detailing

• Complete final grading inside building

Building

• Masonry elevator shaft is complete

• Masonry stair shaft is near completion

• Preparing door and window openings in gym

• Structural Steel placement – Start 9/3

Elevator and stairwell

Door and window openings being prepared

Masonry stair shaft

Underslab plumbing - completed

Page 5: CONSTRUCTION UPDATE - SharpSchool

CONSTRUCTION UPDATE

RECREATION & COMMUNITY SERVICES CENTER

August 30, 2019

West Allis - West Milwaukee

SITE PROGRESS: GOALS NEXT 2 WEEKS:

MILESTONE DATES: CONSTRAINTS:

• None

Building

• Complete final grading inside building

• Start erecting steel between existing building and gym

Building

• Underslab electrical is complete

• Masonry stairwell is complete

• Final grading of building pad is near completion

• Structural Steel placement – Start 9/6

Stairwell 1 – North elevationFinal grading of building pad

Stairwell 1 complete Final grading of building pad