CONSTRUCTION UPDATE JULY 27, 2017 Legend 1) Confed Phase #2 2) Emergency Access Road 3) Hwy 63 & Mackenzie Intersection 4) Hwy 63 & Saprae Creek Trail 5) Lift Station upgrades South Mackenzie 6) Mackenzie Blvd Lift Stations Diversion 7) Mills Avenue Stormwater Management 8) PLB Phase 2 9) PLB Phase 4 Hardin St to Morrison 10) Saline Watermain from Hardin to King Booster Station 11) SW Water Supply Line Phase 1 12) UIR 2014-2016 Contract 14 Road Rehab 13) C15 Road Construction 14) C15 Road Construction 15) C15 Road Construction Map 16) UIRP 2014-2016 C3 17) UIRP 2014-2016 C6 18) UIRP 2014-2016 C8 19) Road Rehab C13 20) C2 Rehab of Mckenzie, King & Grayling 21) UIRP 2017 C1 22) UIRP 2017 C3 23) C4 Rehab of Hill Drive & Mcleod Street 24) C5 Rehab of Poplar Cr., Crescent Heights, Biggs Ave. & Rae Cr. 25) RIRP Anzac C2 Pipes and Road Rehab 26) Rural Servicing Conklin C3 27) GLE Contract 1 Water & Sewer install 28) Thickwood Blvd- Abasand Drive Erosion
30
Embed
CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
CONSTRUCTION UPDATE JULY 27, 2017
Legend
1) Confed Phase #2
2) Emergency Access Road
3) Hwy 63 & Mackenzie Intersection
4) Hwy 63 & Saprae Creek Trail
5) Lift Station upgrades South Mackenzie
6) Mackenzie Blvd Lift Stations Diversion
7) Mills Avenue Stormwater Management
8) PLB Phase 2
9) PLB Phase 4 Hardin St to Morrison
10) Saline Watermain from Hardin to King Booster Station
11) SW Water Supply Line Phase 1
12) UIR 2014-2016 Contract 14 Road Rehab
13) C15 Road Construction
14) C15 Road Construction
15) C15 Road Construction Map
16) UIRP 2014-2016 C3
17) UIRP 2014-2016 C6
18) UIRP 2014-2016 C8
19) Road Rehab C13
20) C2 Rehab of Mckenzie, King & Grayling
21) UIRP 2017 C1
22) UIRP 2017 C3
23) C4 Rehab of Hill Drive & Mcleod Street
24) C5 Rehab of Poplar Cr., Crescent Heights, Biggs Ave. & Rae Cr.
25) RIRP Anzac C2 Pipes and Road Rehab
26) Rural Servicing Conklin C3
27) GLE Contract 1 Water & Sewer install
28) Thickwood Blvd- Abasand Drive Erosion
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name:
Confed Sanitary Sewer –Const, C1- MA30 to eagle ridge Overpass
• Laying of new sanitary line (larger diameter) along Confederation Way. Milestone Complete:
• Piping work complete 75% complete.
Current Progress to date:
• To complete 25% of remaining piping work. This includes Micro tunneling work.
• Landscape work.
Plan for Next 2 weeks:
• To complete 8% of remaining 25% piping work. This includes Micro tunneling work
Detour/Road Closure Details:
• There will be a partial closure of lane road during construction. (Full lane will be closed from July 10, 2017 to August 15, 2017 giving room for vehicles to have right turn at Eagle ridge overpass up.)
1 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/17/2017 Project/Contract Name:
• Contract #1: The Construction of a new Forcemain from the MacKenzie Blvd & Hwy 63 intersection to the newly build Gregoire East Sanitary Outfall. The existing Forcemain is scheduled to be relocated and upsized to coincide with the new MacKenzie Lift Station.
Contract #2: The MacKenzie Sewer Upgrades ‐ Phase 2 Project is proposed to divert flows from the Prairie Creek neighbourhood and the southern region of the MacKenzie Industrial area through the green space east of the Gregoire Neighborhoods. The upstream portion of this sewer between MacKenzie Boulevard and MacMillan Road will replace the existing sewer along the same alignment which travels through a 9 m wide RMWB right‐of‐way (ROW).
Milestone Complete:
• 95%
Current Progress to date: The majority of the Sewer, Storm and Water piping are complete. The restoration activities are currently taking place (Landscape and re‐paving of Mackenzie Blvd and Mackay Cres.
Plan for Next 2 weeks:
• Working on the deficiency items
• Landscape Scope
Detour/Road Closure Details:
• N/A
6 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/10/2017 Project/Contract Name:
• Construction of Prairie Loop Boulevard Phase 2(Macleod to Hardin) Milestone Complete:
• Substantially complete by November 2017 Current Progress to date:
• Installed 400 mm Water main from phase 1 towards north and connected 400mm water main to existing at the intersection of PLB and Father Merc
• Installed storm main, Catch Basin, CBMHs and backfilled the trench
• Continued to build embankment slopes between station 1+ 580 and 1+ 760
• Removed ATCO overhead power lines Plan for Next 2 weeks:
• Subgrade Construction 1+760 to 1+580
• 750 STM from 105 to 2+020
• 750mm STM from MH103 to MH102
• Subgrade Construction 1+620 to 1+460
• Cement Stabilization 1+770 to 1+500
• 750mm ST from 101 to 100; STMH 100
• STMH100 CBs, leads and inlet
• Subgrade Construction 1+460 to 1+280
• Cement stabilizing 1+46 to 1+280 Detour/Road Closure Details:
• There will be full closure on Hardin street (Between Public School Board to Morimoto and Hardin intersection). Detour will be available from Riedel to Snye Building (Note: Until PLB is open from Riedel to Snye Building, Hardin Street will not be closed.)
8 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: PLB Phase#4 Project Manager: Muhammad Asghar
• This project is to bring new water supply mains across the Athabasca River from the Water Treatment Plant, for servicing the Horse Plateau and Hangingstone Plateau, and tying into Lower Townsite and Abasand Reservoir, effectively providing complete redundancy in the system between the South and Southwest supply lines. Eventually (i.e. after 2016), this water supply main might extend down to the Southlands Industrial Area to meet the ultimate build-out of this area. (Ref: Water Master Plan - Associated Engineering, 2011).
Milestone Complete:
• 75% Current Progress to date: The Contractor mobilized back to the Abasand Site for the LTS Reservoir tie-in works and commenced setup of rigid fence panels, trail closure signage as well as take down of trail light poles from the north and east side of the reservoir fence. The Contractor locates and began hydrovac to expose the end of the steel casing pipe adjacent the skate park/reservoir as well as other key locations for the new watermain installation. The Contractor plans to commence open cut pipe installation at the LTS Reservoir site in early June
Plan for Next 2 weeks:
• Continue working on the water main entering the LTS Detour/Road Closure Details:
• N/A
11 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIR 2014-16 – C14 Project Manager: Yogesh Acharya
Start Date: 5/2/2017 Completion Date: 7/30/2017
Project Phase: Construction Contractor Name: H Wilson
• Leigh Crescent – Underground installation ongoing towards Dickins Drive. Concrete sidewalks and curb and gutter 50% installed. First phase of work is ready to be paved.
• Torrie Crescent (NW leg) - Underground installation complete. Ready for concrete sidewalk to be poured. Plan for Next 2 weeks:
• Fullerton Drive – Complete landscaping. Top lift asphalt to be completed.
• Farrell Crescent - Landscaping and top lift to be completed.
• Leigh Crescent – Complete the underground installation as far as Dickins Drive. Backfill and prepare sidewalks and road for paving.
• Rehab of Manning Avenue (Richard Street to Morrison Street & MacIver Street to McLeod Street) Milestone Complete:
• Work is substantially complete.
Current Progress to date:
• Manning Avenue (Richard Street to Morrison Street) – Underground, bottom lift asphalt and concrete complete. Atco Electric completing TAC design of streetlights. Streetlights to be relocated to allow existing separate sidewalk to be widened to meet RMWB standards. Top lift asphalt to be completed. Manning Avenue (MacIver Street to McLeod Street) – Top lift asphalt has been completed.
Plan for Next 2 weeks:
• Manning Avenue (Richard Street to Morrison Street) – Top lift asphalt to be planned. To be confirmed by E-Construction.
• Manning Avenue (MacIver Street to McLeod Street) - No activity Planned. Complete. Detour/Road Closure Details:
• Manning Avenue (Richard Street to Morrison Street) – Top lift asphalt to be planned. To be confirmed by E-Construction..
• Manning Avenue (MacIver Street to McLeod Street) - No activity Planned.
18 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIR 2014-16 – C13 Project Manager: Yogesh Acharya
Start Date: 4/26/2016 Completion Date: 11/30/2017
Project Phase: Construction Contractor Name: H Wilson
• Road, Sanitary and water Rehab at Caldwell crescent and Cowley Bay. Milestone Complete:
• It is about 45% completed.
Current Progress to date:
• Laneway parallel to Cornwall Drive – Work completed in 2016
• Cowley Bay – 50% of work completed in 2016. The remainder will be completed as Phase 2 of 2017 construction.
• Caldwell Crescent – Contractor H.Wilson closed down 150m of Caldwell Crescent from Cornwall Drive (Deep Road). Water and storm lines have been installed as far as the Caldwell Crescent landscaped island. Backfilling is following on behind underground installation.
Plan for Next 2 weeks:
• Caldwell Crescent – Phase 1 installation including underground completion to Caldwell Crescent landscaped island. Phase 2 start which will complete construction on.
• Cowley Bay - Phase 2 start which will complete construction on Cowley Bay.
Detour/Road Closure Details:
• 150m of Caldwell Crescent from Cornwall Drive (Deep Road) will remain closed
• Preparations will be made for 2017 Phase 2 construction in Cowley Bay and construction may start depending on Phase 1 progress and weather.
19 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIR 2014-16 – C2 Project Manager: Malik Lasker
Start Date: 8/5/2015 Completion Date: 8/31/2017
Project Phase: Construction Contractor Name: H Wilson
• Grayling Crescent – Top Lift Asphalt and concrete swales to be started. Landscaping deficiencies to be addressed.
Detour/Road Closure Details:
There will be partial closures required on Grayling Crescent for top lift asphalt. Contractor to apply for Utility Installation Permit and confirm schedule.
20 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIRP 2017 – C1 Project Manager: Muhammad Asghar
Start Date: 5/30/2017 Completion Date: 11/13/2017
Project Phase: Construction Contractor Name: Bird Construction
• 100% of piping work is complete on Parmenter Crescent.
• Construction started on Becker Crescent July 12 Current Progress to date:
• Oaks Crescent - Sidewalks have been poured and asphalt is being laid July 17.
• Parmenter Crescent - Final underground is being completed. The first 200m of street has road structure completed and is ready for concrete sidewalks.
• Becker Crescent – Phase 1 of the road was closed on July 12. First section of asphalt has been stripped. Plan for Next 2 weeks:
• Oaks Crescent - Landscaping and driveways to be completed.
• Parmenter Crescent – Concrete Sidewalks July 28, Asphalt Bottom Lift August 4.
• Becker Crescent Phase 1 – Underground installation scheduled for completion August 17.
• Construction on Brintnell will start from August 2, 2017.
• Construction on Leigh will start from September 20, 2017. Detour/Road Closure Details:
• Oaks Crescent should be open to public this week.
• There will be a full closure on roads during construction.
21 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIRP 2017 – C3 Project Manager: Muhammad Asghar
Start Date: 6/5/2017 Completion Date: 10/10/2017
Project Phase: Construction Contractor Name: H. Wilson
• Poplar Crescent – subbase and base course preparation will start on July 26, concrete work is scheduled for August 1, asphalt paving is scheduled on August 8.
• Crescent Heights/Biggs Avenue – underground work is scheduled on July 28,2017
Detour/Road Closure Details:
• Poplar Crescent should be opened by August 15
• Crescent Heights/Biggs Avenue should be opened on September 22, 2017
• Rae Crescent should be opened on October 12, 2017
24 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:
RIRP 2015-2017 Anzac C:2 Pipes & Road rehabilitation on the North & South half of Anzac
Project Manager: Adel Youssef
Start Date: 9/15/2017 Completion Date: 9/30/2019
Project Phase: Construction Contractor Name: Tender Phase
• Construct the roads in the rural areas within the hamlets of Anzac, water piping and the sewer collection system. Pipes & road rehabilitation will be on the North & South half of Anzac.
Milestone Complete:
• 0.00%
Current Progress to date: • Tender Phase
Plan for Next 2 weeks:
• Close the tender
Detour/Road Closure Details:
• N/A
25 July 27, 2017
Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name:
• Erosion remediation work behind the curb on Thickwood Blvd and Abasand Drive between the HWY interface and top of the hill. Includes grading, landscaping & concreting behind the curbs.
Milestone Complete:
• Tender closed on July 13, 2017
Current Progress to date:
• Bid evaluation in progress.
Plan for Next 2 weeks:
• Complete bid evaluation & award the construction contract.