CONSTRUCTION UPDATE Hales Corners Elementary SAFETY: SINCE LAST UPDATE: New Addition The interior courtyard playground has the rubber poured and is completed!! The exterior playground equipment has been set in place and is only waiting for wood chips in order to be completed. Ceiling grid is finished and MEP trades are dropping in their finishes to the ceiling grid before the above ceiling inspection when the ceiling tile will then be installed. Case is being installed. The classroom cabinets are installed, just working on the cubby spaces. Courtyard poured rubber surface Starting—June 3rd - Goal Achieved!! Flooring Starting—June 24th Please be mindful of the construction area as activi- ties continue. No students, parents, or school staff should pass the fence line without a CG Schmidt escort. May 27th—June 14th 2019 MILESTONE DATES: GOAL FOR NEXT UPDATE: New Addition Casework cubbies will be fully installed and complet- ed. Flooring will be start to be installed. Ceiling tile will be dropped and ceilings closed up. We will be installing marker boards/tack boards, doors/ hardware, and bathroom accessories Interior Courtyard Playground Rubber Poured Exterior Playground Equipment Installed Classroom Casework Installed Ceramic Tile Installed
1

CONSTRUCTION UPDATE · Flooring will be start to be installed. Ceiling tile will be dropped and ceilings closed up. We will be installing marker boards/tack boards, doors/ hardware,

Apr 12, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CONSTRUCTION UPDATE · Flooring will be start to be installed. Ceiling tile will be dropped and ceilings closed up. We will be installing marker boards/tack boards, doors/ hardware,

CONSTRUCTION UPDATE Hales Corners Elementary

SAFETY:

SINCE LAST UPDATE:

New Addition The interior courtyard playground has the rubber

poured and is completed!!

The exterior playground equipment has been set in place and is only waiting for wood chips in order to be completed.

Ceiling grid is finished and MEP trades are dropping in their finishes to the ceiling grid before the above ceiling inspection when the ceiling tile will then be installed.

Case is being installed. The classroom cabinets are installed, just working on the cubby spaces.

Courtyard poured rubber surface Starting—June 3rd - Goal Achieved!!

Flooring Starting—June 24th

Please be mindful of the construction area as activi-ties continue. No students, parents, or school staff should pass the fence line without a CG Schmidt escort.

May 27th—June 14th 2019

MILESTONE DATES:

GOAL FOR NEXT UPDATE:

New Addition Casework cubbies will be fully installed and complet-

ed.

Flooring will be start to be installed.

Ceiling tile will be dropped and ceilings closed up.

We will be installing marker boards/tack boards, doors/hardware, and bathroom accessories

Interior Courtyard Playground Rubber Poured

Exterior Playground Equipment Installed

Classroom Casework Installed

Ceramic Tile Installed