Top Banner
CONSTRUCTION SAFETY CONSTRUCTION SAFETY PART –III PRSENTATION BY AVINASH KUMAR GUPTA EE(TRANING) TRAINING INSTITUTE, SOOCHNA BHAWAN NEW DELHI
25

Construction safety PART III

Apr 11, 2017

Download

Engineering

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Construction safety PART III

CONSTRUCTION SAFETYCONSTRUCTION SAFETY

PART –III

PRSENTATION BY AVINASH KUMAR GUPTA

EE(TRANING)

TRAINING INSTITUTE, SOOCHNA BHAWAN

NEW DELHI

Page 2: Construction safety PART III

HAZARDOUS PROCESSRoof Work –

- Falls from the edge of roofs.

- Falls through opening in roofs.

- Through fragile roof materials.

Flat Roofs –

- Pitch < 100

- Guardrails & toe board if fall > 2m

- Cover the opening (adequate to take weight)

Page 3: Construction safety PART III

Edge protection for flat roof – diagram of what is required

Page 4: Construction safety PART III

Edge protection for flat roof – a real-life example

Page 5: Construction safety PART III

Sloping roofs: Two methods of providing edge protection

Page 6: Construction safety PART III

Hazardous ProcessSLOPING ROOF Pitch > 100

1. Edge protection is necessary.

2. High Guard rails.

3. Use, purpose- made crawling ladders.

FRAGILE ROOFS.

1) Asbestos cement sheeting, wired glass corrugated plastic sheets, rusted corrugated iron sheeting.

2) Use crawling ladders/ladders

3) Display warning signs.

Page 7: Construction safety PART III

Roof ladder for work on a sloping roof or over fragile materials

Page 8: Construction safety PART III

Roof ladder with ridge iron to place overroof ridge

Page 9: Construction safety PART III

Roofs

• Points to remember:• • Never work on a roof which is without adequate edge protection.• • Before you work on a roof make sure• you know which parts are made of• fragile material.• Never step on to a fragile roof

Page 10: Construction safety PART III

Hazardous Process, STEEL ERECTION • Properly DESIGN joint position, accessibility of

connections, fixing of working platforms and means of access and weights is relation to crane capacity.

• Proper SUPERVISION/ SUPERVISIONS from the MAIN CONTRACTOR.

• Storage area for steel work & materials need to be planned, not to interfere with vehicles & cranes.

• Not to work during windy/ wet weather.

• Provision of sufficient guys, props, bracing & temporary connection.

Page 11: Construction safety PART III

Hazardous ProcessSTEEL WORK

– avoid climbing bare steel, beam walking & straddling (feet on lower flanges)

– Use working platforms, staging, ladders.

– safety nets, safety belts & harnesses save lifes.

– REMEMBER – IF YOU CLIMB OR WALK ON BARE STEEL SOONER OR LATER YOU WILL FALL.

Page 12: Construction safety PART III

Mobile hydraulic platforms provide safemeans of access for steel erectors

Page 13: Construction safety PART III

Use of safety belts and harnesses – different ways of providing safe

anchorage points for safety lines

Page 14: Construction safety PART III

Use of safety belts and harnesses – different ways of providing safe

anchorage points for safety lines

Page 15: Construction safety PART III

Safety nets to prevent falls of steel erectors

Page 16: Construction safety PART III

Work over water1. WORKING PLATFORM IS SECURE. No tripping

hazards like tools, wire, timber or bricks.

2. Guard rail, toe board & access ladders.

3. Wear a safety helmet.

4. Wear a life jacket.

5. Use safety nets.

6. Life buoys flitted with lifelines are ready.

7. Marked safety board.

8. Know the routine for raising alarms & rescue drill.

Page 17: Construction safety PART III

Work over water

• Points to remember:• • Do not work alone when you are• working over water.• • Check the number of work regularly to• ensure that no one is missing

Page 18: Construction safety PART III

Hazardous Process DEMOLITIONDemolition

– Choose safe method of demolition.

– prevent unintentional collapse of building.

– written method, sequence, include drawings/ sketches.

– Use helmet, gloves, safety footwear.

– All services to be disconnected.

– Keep public away.

.

Page 19: Construction safety PART III

A scaffold platform from which demolition may be carried out safely

Page 20: Construction safety PART III

Hazardous Process

• Points to remember:• Never work on a tank or enclosed vessel

without a written permit to work.• Always check whether asbestos is present in

the building to be demolished.

Page 21: Construction safety PART III

Hazardous Process, Health Hazards

• Exposure to dust & fumes (plants)

– flame cutting of plant with zinc & cadmium paint, lead painted steel work

– use breathing apparatus, approved respirators & rescue equipment.

• asbestos bearing material (fire protection/ thermal insulation– use positive pressure breathing apparatus and protective

clothing.

– materials containing asbestos removed in isolation.

– safe disposal of asbestos contaminated debris.

Page 22: Construction safety PART III

Hazardous Process• Working In Confined Spaces

– open manholes, sewers, trenches bored pipes, pipes ducts, enclosed basements.

– danger of poisonous gases, toxic & flammable gases.

– unconsciousness, dizziness, sickness.

Page 23: Construction safety PART III

Hazardous Process, Confined Spaces• Precautionsa. – never enter without written permission.

b. – equipment for measuring atmosphere.

c. – forced ventilation.

d. – continuous monitoring.

e. – proper training & instruction.

f. – use rescue harness.

g. – always two persons (one always outside to offer rescue operation.

h. – proper procedure to be laid down.

i. Appropriate traffic signs while working in manholes.

Page 24: Construction safety PART III

When entering a confined space, use a lifeline with a second person

present and self-contained breathing apparatus apparatus