Construction Report July 28, 2009
69

Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Mar 28, 2015

Download

Documents

Delaney Aymond
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Construction Report

July 28, 2009

Page 2: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.
Page 3: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Projects

• KMS Phase II Close out– KMS Cafeteria Close out– KMS Renovations & Additions Close out– Royalwood Elementary Close out – Monahan Elementary Close out– KHS Cafeteria Close out– KHS Annex Close out

Page 4: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Projects

• Diamond Sports Project Close Out

•Walking Track Completed–Carroll Elementary

Page 5: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Projects

•Covered PE areasCompleted–Monahan Elementary–Royalwood Elementary

Page 6: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects

•Asbestos

•Paving / drainage / repairs

Page 7: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (KHS Choir Rm.)

Page 8: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Warehouse)

Page 9: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Cravens ECA)

Page 10: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (KMS)

Page 11: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (KHS)

Page 12: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Projects

•Site Improvements

•Track replacement and turf

Page 13: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Annex)

Page 14: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Annex)

Page 15: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Annex)

Page 16: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (Annex)

Page 17: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects: (KHS)

Page 18: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer Projects• Covered PE area: Sheldon Elementary

(Planning)• Walking tracks: In design $$$

– SECA, ME, RE

• Water wells As required

• Bleachers Pending

Page 19: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Bleachers

Page 20: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Royalwood Elementary: (Track)

Page 21: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Monahan Elementary: (Track)

Page 22: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects: (Track)

Page 23: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy: (Track)

Page 24: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects

•Air BalanceSheldon ElementaryECACarroll Elementary– KHS Annex– KHS two story– Monahan Elementary– Royalwood Elementary– C. E. King Middle School

Page 25: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects• Fence / gates• Science Classrooms / lab• Auditorium lighting• Sports Fields• Generators• Marquees• Scoreboard• Playgrounds

Page 26: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects: (KHS Auditorium)

Page 27: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Project: (KHS Science Labs)

Page 28: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Project: (KHS Science Labs)

Page 29: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Project: (KHS Science Labs)

Page 30: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects: (KHS)

Page 31: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

District Projects: (ELC)

Page 32: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Projects

• Sheldon ECA On schedule

• Early Learning Center On schedule• M. R. Null Middle School On schedule

Page 33: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 34: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 35: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 36: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 37: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 38: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 39: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 40: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 41: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 42: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 43: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Michael R. Null Middle School

Page 44: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy

Page 45: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy

Page 46: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy

Page 47: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy

Page 48: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Childhood Academy

Page 49: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Learning Center

Page 50: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Learning Center

Page 51: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Learning Center

Page 52: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Learning Center

Page 53: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Sheldon Early Learning Center

Page 54: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Maintenance Operations / Transportation Complex

(MOT)Property purchasedProgramming resumed/completedSurveys• Design development• Utility Service• Proposals in September 2009

Page 55: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Network Operations Center

ArchitectLand•Programming

Page 56: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 57: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 58: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 59: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 60: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 61: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 62: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 63: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Crenshaw Stadium Football Field

Page 64: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Technology

•Technology plan

•Renovations

•New construction

Page 65: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

S.I.S.D. Technology: Update

VirtualizationRecently approved project. As of to date 16 existing servers have been added to the virtual server listThis translates into ninety thousand dollars being pulled out of budget rotation over a four year periodTwo servers for new installations have been created as virtual servers-instant savings of ten thousand dollarsWe now have the capability of adding a server within hours of a requestAir conditioning costs are less and we are using less electricity

Page 66: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Summer 2009 Projects Projectors in every classroom Audio enhancement in every classroom In house wiring projects for video cameras and

network cabling – quality & savings Phone system at Null Middle School 15 additional mobile laptop carts containing 426

laptop computers ready for deployment to the campuses

Computer replacement at Sheldon Elementary (replacement cycle)

New computers for SECA and Null Middle School (Dell)

S.I.S.D. Technology: Update (cont.)

Page 67: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Technology

•Emergency communication system–Blackberry system–Pending Board approval

Page 68: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

Technology (Future)

•Network Operations Center•Technology Plan

–Planning for next year

•Language Lab Kits–Near term project

Page 69: Construction Report July 28, 2009. Projects KMS Phase IIClose out –KMS CafeteriaClose out –KMS Renovations & AdditionsClose out –Royalwood Elementary.

C.E. King High SchoolLanguage Labs

• King High School currently has nine foreign language teachers• The addition of two modern language labs will allow the teachers to push and pull lessons electronically to and from students• The High School Administration , selected foreign language teachers and technology have put forth a concerted effort to identify a lab that will fit the needs of the students and staff• Three companies have demonstrated their language labs and an onsite visit was made to the University of Houston to view a live classroom demonstration of the Sanako Lab• The High School has funds available to purchase the labs • The labs will be a turn key installation with about a 30-45 day completion time from the date of order• The two labs will have 30 stations each and a teaching station • The cost of the two labs will be over $100,000.00