Offshore Construction in South Korea
May 15, 2015
Offshore Construction in South Korea
LOCATION OF CONSTRUCTION TO LOCATION OF OPERATIONS
The Goal for 2011 onward; 6th generation Drill ships ready for operations in Brazil
The Goal only a few hundred years ago a 6th Generation Sail Ship to reach Brazil
Differences then and now:
• Same Goals
• Different technology
• Different dreams
• Different needs
Then it started out with Manual Labor
And more manual labor to build ships
Early 20th century the Mass Production
Only since the last 30 years: Little Manual Labor / Fully Automated cutting Machines.
Erection Block / Section
Pre Outfitting for Block Sections
Blasting & Painting & Coating
• Blasting will take in block stage in controlled environments (blast shops) with grid.
• Painting & Coating will take place in block stage will take place mainly in controlled environment.
• The Hull and Superstructure• The underwater part of the Hull• The Individual Tanks• The Equipment and it’s systems
The good old days
Block Construction / Use Sections
YARD Overall Project Plan Construction Facilities
• YARD will use 5 mayor location for construction of Block Sections & Modules
• Main yard: Majority of blocks and the Hull• Shin Han Yard: Living Quarters & Heli deck• Sung Jin: Certain curved blocks (bow & stern)• Posh: Mud module Roof sections• Hochang: Derrick and Flap & small sections
YARD planningBlock erection diagram
YARD reality – to Planning
YARD reality to Planning
YARD overall construction facilities for pre outfitting and piping spools
• YARD will use over 70 different vendors and subcontractors to assist with the production and fabrication of spools and outfitting materials:
• The biggest contributors (and mostly mentioned in the office)
• HARVARD, DEOK SU, TAECHANG, GANA, SAM NOK.
• KANG RIM, SUNG IL, SAM KUN, SHIN WOO, SUNG WANG
Process Piping well fabricated and inspected and installed
Welding Accepted, installation rejected
Failed After re-inspection
INSPECTIONS as there are thousands of inspections these are being catagorized
• YARD Witness Inspections; Owner and Class are invited for the inspection.
• YARD Monitor Inspection; YARD will perform the inspection Owner and Class could witness
• OWNER Patrol Inspection: Owner will inform YARD that a visit will take to a fabrication shop and a random inspection will take place
DOCUMENTATION for INSPECTIONS
• YARD Witness Inspection Sheet: To receive at each witness inspection for owner, YARD and Class
• OFR sheet: Owner performs a patrol inspection and finds a discrepancy. Owner will issue to YARD
• YARD NCR: A failure occurred, YARD will issue a NCR
• OWNER NCR: In case an OFR will not be resolved within a certain time Owner will change to a NCR
• Class discrepancy: Class will issue to YARD
• In any case of failure or rejection these items will become “punch items”
WEB SITES for inspections planning & tracking of results and punchitems
• YARD has 2 websites available to track the inspections and the punch items
• PCS: This website is for all inspections on and off site, excluding paint inspections; Also for the Punch items.
• E-QISS: This website is for all inspections on and offsite, including paint inspections AND the NDE reports.
See website: http://www.dsme.co.kr/eng/company/ceo/ceo01.jsp
Daily Activities and Inspection reviews in the site office, with Korean Inspectors
Present status in site office
• Every morning: we review the websites to review the inspection planning and locations
• Every Morning: we have a pre inspection meeting with all inspectors to review the daily schedule
• Every end of the day: we have a short summary on inspections; failures and owner findings
• Every Friday afternoon: we have an evaluation QA/QC meeting with YARD, Owner and Class on the results and the next week look ahead
Present Status for Site Inspection Team
• For construction Owner has hired and will further hire local inspectors specialized in construction for drill ships in various disciplines.
• Additionally part of the Engineering team will slowly grow into the construction and mechanical completion of the construction phase.
• Following Mayor Disciplines:
• HSE (safety first!)• Hull, Structure & Welding • Piping & Mechanical & Installation• Painting & Coating• Later: Outfitting, Electrical, Marine, Drilling, Subsea.
• All the inspectors will be lead by the construction and QA/QC department and for each discipline the leader will get involved in the failures, corrections, improvements and changes.
Construction Phase, Block Stage
• Total amount of small, block is 238
• Total amount of erection block is 14
• Separate are the Accommodation Block, the mud module, The Funnel Casing, The Derrick, The BOP, and the Deck Cranes
Block Stage on yard
Funnel Casing; Weight approx 500mT Accommodation: Weight approx 1800mT
Hull Block stage Program
Block Stage; Big Blocks on the Slipway
Load Out (Horizontal Launching) of Complete Hull
Lifting on large blocks
Lifting of Mud module: Weight 1400mT And Lifting of the Drill tower (Derrick) Weight 1200mT.
THE NEXT PHASES
• The Construction Phase is normally completed with the launching of the vessel.
• Then the Mechanical Completion Phase will start
• Followed by the pre commissioning phase• The commissioning and the integration
commissioning phase• And finally the Sea Trials• Closing with the delivery.
A completed drill ship
Let’s try to avoid Shipwrecking
And let’s make sure we will avoid a Blow Out.
Make sure we will be ready for our Company and Client in Brazil in 2011 ONWARD