Top Banner
Construction of Underpass Section in High Speed Railway Project ICCBEI 2015, Tokyo Convention Hall, Japan April 23, 2015 Department of Civil and Environmental Engineering, Yonsei University, Seoul, Korea Professor Sang-Ho Lee E-mail: [email protected] JACIC Session
14

Construction of Underpass Section in High Speed Railway ...

Jan 18, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Construction of Underpass Section in High Speed Railway ...

Construction of Underpass Section

in High Speed Railway Project

ICCBEI 2015, Tokyo Convention Hall, Japan

April 23, 2015

Department of Civil and Environmental Engineering,

Yonsei University, Seoul, Korea

ProfessorSang-Ho Lee

E-mail: [email protected]

JACIC Session

Page 2: Construction of Underpass Section in High Speed Railway ...

-1- ICCBEI 2015, April 23, 2015

1. Introduction

Field Introduction

• Construction of underpass tunnel for new high speed railway

• Cut & Cover method for elimination of existing piles

• Replacement of existing plies with load bearing girders and diaphragm walls

Load

bearing

girders

Diaphragm

walls

Page 3: Construction of Underpass Section in High Speed Railway ...

-2- ICCBEI 2015, April 23, 2015

1. Introduction

Construction Issues

Uncertain locations of

existing structures

& construction errors

Complicated false works

in limited space

Page 4: Construction of Underpass Section in High Speed Railway ...

-3- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

3D & 4D Modeling

Virtual construction

Laser scanning & update models

Reporting & feed backs

Procedures

Page 5: Construction of Underpass Section in High Speed Railway ...

-4- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

Periodic BIM conference

Eng.(Analysis)

BIM manager

BIM Modeler

Struct.Designer

H-QSE

Eng.BuilderConst.

Manager

Equipment Manager

Page 6: Construction of Underpass Section in High Speed Railway ...

-5- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

Laser scanning and model update for accurate analysis

Page 7: Construction of Underpass Section in High Speed Railway ...

-6- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

Check constructability for girder launching

Updating of 3D model with laser scan data

Laser scan data

Model based reviews

Page 8: Construction of Underpass Section in High Speed Railway ...

-7- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

28 issues (clashes 7, construction sequence 8, insufficiency of construction plan 13)

Example of clashes

Model based reviews

Page 9: Construction of Underpass Section in High Speed Railway ...

-8- ICCBEI 2015, April 23, 2015

2. Implementation of BIM

Model based reviews

28 issues (clashes 7, construction sequence 8, insufficiency of construction plan 13)

Example of false construction sequence

Temporary

Facility

Construction

Stage 3

Excavation (D/W Breaking)

Temporary Facility Construction

Stage 4

Excavation

(D/W Breaking Wire Saw)

Temporary Facility Construction

Installation of Supported-girder

Installation of Hydraulic Jack

Pre-loading

Pile Cutting

First Concrete Pour

Stage 5

Excavation

Temporary Facility Construction

Stage 6

Excavation

Temporary Facility Construction

Stage 7

Excavation

Temporary Facility Construction

Tim

e-

Ste

p

Page 10: Construction of Underpass Section in High Speed Railway ...

-9- ICCBEI 2015, April 23, 2015

3. Virtual Construction

Development of Web-based Virtual Construction System

• Development of virtual site with the 3D model

• Definition of crane location based on capacity analysis

• Measurement of distance between load bearing girder segments and other structures

Risk indicator is displayed when beam contact stiffener

Outrigger center line.

Water channel

Page 11: Construction of Underpass Section in High Speed Railway ...

-10- ICCBEI 2015, April 23, 2015

3. Virtual Construction

4D construction sequencing

Page 12: Construction of Underpass Section in High Speed Railway ...

-11- ICCBEI 2015, April 23, 2015

3. Virtual Construction

Simulation for installation of load bearing girders

Page 13: Construction of Underpass Section in High Speed Railway ...

-12- ICCBEI 2015, April 23, 2015

3. Virtual Construction

Virtual simulation vs Actual activity

Page 14: Construction of Underpass Section in High Speed Railway ...

-13- ICCBEI 2015, April 23, 2015

4. Concluding Remarks

Return on Investment (ROI) in this field

• Return: 35,000 USD

(prevention of construction holding due to clashes and re-design)

• Investment: 27,000 USD

• ROI: 130%

BIM is a tool for construction risk hedge

• BIM does not provide directly cost saving item

• Return on BIM can be estimated with risk hedge