PAC NP April 2004 PAC NP April 2004 Construction of the IREN source Construction of the IREN source Status&perspectives Status&perspectives Status of the project in current year During months after the 19 th PAC NP session main efforts were done on preparation for IBR-30 dismantling, installation of new linac and organization of transportation of IREN fuel elements from “MAYAK” plant and its storing at JINR. IBR-30 dismantling • It was delivered a shadow shielding for new storage bld. 117/6 • The set of documents necessary for licensing of the storage in Russian Agency for Radiation Safety is practically completed • But up to now it has not paid the dosimetric equipment necessary for commissioning of bld. 117/6. It can cause a derangement of full IBR-30dismantling by the end of current Linac installation • Very recently, on 11-12 March it was achieved practically planned parameters of the pulsed linac electron gun • By the end of April it was completed an assembling of linac grid with geodesic accuracy IREN fuel transportation • Transportation of the IREN fuel load is possible now only in autumn