Top Banner
Construction Issues at WWTPs Construction Issues at WWTPs What the Owner/Operator Needs to Know
33

Construction Issues at WWTPs - WWOA

Mar 13, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Construction Issues at WWTPs - WWOA

Construction Issues at WWTPsConstruction Issues at WWTPsWhat the Owner/Operator Needs to Know

Page 2: Construction Issues at WWTPs - WWOA

WWOA Annual Conference WWOA Annual Conference October 2010October 2010

Presented by:

John D. SzwedoBaxter & Woodman, Inc.

Consulting Engineers

www.baxterwoodman.com

Page 3: Construction Issues at WWTPs - WWOA

General OverviewGeneral OverviewBasic Introduction to Construction Issues

• Common terminology (Or lingo)

• Owner and Engineer Relationship

• Happy Ending to Project (hopefully)

Page 4: Construction Issues at WWTPs - WWOA

Topics CoveredTopics Covered#1 - Common Terminology:

• Plans

• Specs

• Shop Drawings

• Change Orders

• Substantial/Final Completion

• As Built Plans

• Bonds

Page 5: Construction Issues at WWTPs - WWOA

Topics Covered Topics Covered #2 - What the Owner should expect from the Engineer prior to and during the project:

• Involvement during the design phase

• Involvement during equipment selection

• Involvement during SCADA design

Page 6: Construction Issues at WWTPs - WWOA

Topics CoveredTopics Covered#3 - What happens if the Contractor doesn’t finish the job?

Page 7: Construction Issues at WWTPs - WWOA

Topic #1- Common TerminologyTopic #1- Common TerminologyPlans -• Plans are the engineer’s vision, or blueprint, of

what is to be.

• Plans provide a wealth of information.

• Piping plans, elevations, hydraulic profiles, flow diagram, etc.

Page 8: Construction Issues at WWTPs - WWOA

Plans Plans (continued)(continued)

• Flow Diagram – Details where process flows go

• Piping Plan – Shows piping runs

• Legend – Tells what symbols and abbreviations stand for

• Hydraulic Profile – Shows elevations starting at beginning of facility

• Details – Gives specifics to items such as manholes, outfall structures, wall sleeves, etc.

Page 9: Construction Issues at WWTPs - WWOA

SpecsSpecs

• Spec Sections in Project Manual provide detail of equipment specified

• May not specify manufacturer, but provides enough detail to eliminate non-worthy equipment

• Also details things such as door/hardware, masonry, pipe materials, contractor guidelines, etc.

Page 10: Construction Issues at WWTPs - WWOA

Shop DrawingsShop DrawingsProvide detailed information about particular piece of equipment.

• Submitted to engineer by equipment supplier for approval prior to purchase of equipment

• Model #, features, drawings, ancillary equipment, controls and spare parts

• Example- Blower + associated valves, filters and motor

Page 11: Construction Issues at WWTPs - WWOA

Change OrderChange Order• A change in work due to unforeseen circumstances.

It might include:- A time extension- Piping modifications- Equipment changes

• Request for information (RFI) usually precedes the Change Order

• Change Orders must be approved by Engineer/Owner. Note: NOT BY OPERATOR!

Page 12: Construction Issues at WWTPs - WWOA

Substantial/Final Completion Substantial/Final Completion • Substantial Completion

Allows for start up of facility, with major work being completed. Facility must run effectively and meet all permit limits.

• Final CompletionAll items have been completed, including punch list (laundry list) items.

Page 13: Construction Issues at WWTPs - WWOA

As Built PlansAs Built PlansAlso known as “As Builts”

• Revised plans/drawings due to changes in the field

• Example: Change in piping due to unforeseen circumstances

• Are the latest and most accurate drawings

Page 14: Construction Issues at WWTPs - WWOA

As Built PlansAs Built Plans((continuecontinuedd) )

What happens next?

• Marked up in field, dated and signed• Original plan/drawing marked up

OR• Marked up in field• Redrawn, with original plan/drawing left in, but noted

Page 15: Construction Issues at WWTPs - WWOA

BondsBonds

• Bid Bond

• Performance Bond

• Payment Bond

Page 16: Construction Issues at WWTPs - WWOA

Bid BondBid Bond

• Required of a contractor submitting lowest bid

• Ensures contractor is serious about his bid

• If contractor negates, developer is paid the difference between that bid and the next lowest bid.

Page 17: Construction Issues at WWTPs - WWOA

Performance BondPerformance Bond

• Replaces Bid Bond

• Ensures work is completed as specified

• Guarantees client will be compensated for any monetary loss up to the amount of the bond

Page 18: Construction Issues at WWTPs - WWOA

Payment BondPayment Bond

• Guarantees payment to laborers, suppliers and subcontractors in the event of the contractor defaulting

• Usually issued with the Performance Bond

Page 19: Construction Issues at WWTPs - WWOA

Topic #2 – Expectations During ProjectTopic #2 – Expectations During ProjectInvolvement during design phase

• Owner involvement when developing vision

• Owner takes part in design meetings

• Engineer keeps owner involved along the way

Page 20: Construction Issues at WWTPs - WWOA

Owner InvolvementOwner Involvement• Owner/Operator need to contribute• Should present/discuss

Past operational issuesProblems meeting permit limitsEquipment performance issuesDevelop a “Wish List” for considerationDiscuss issues with staff

Page 21: Construction Issues at WWTPs - WWOA

Equipment SelectionEquipment SelectionOwner should have input, based on:

• Past experiences

• Current needs/problems

• Preference

Page 22: Construction Issues at WWTPs - WWOA

Flow SheetsFlow SheetsPlan sheets outlining each step of process

• Work with Engineer on Flow Sheets• Discuss each process, and what you expect it

to do

Page 23: Construction Issues at WWTPs - WWOA

SCADA DesignSCADA Design• What are you trying to accomplish?

Monitoring vs. complete control

• Be creative when controlling equipment

• Reporting

• Alarms- Who?

- What?- When?

Page 24: Construction Issues at WWTPs - WWOA

SCADA DesignSCADA DesignExamples of screens:

• General OverviewProvides a “quick glance” status report

• MaintenanceNotification when maintenance is due

• TrendingProvides history of events

Page 25: Construction Issues at WWTPs - WWOA

General OverviewGeneral Overview

Page 26: Construction Issues at WWTPs - WWOA

General OverviewGeneral Overview

Page 27: Construction Issues at WWTPs - WWOA

General OverviewGeneral Overview

Page 28: Construction Issues at WWTPs - WWOA

MaintenanceMaintenance

Page 29: Construction Issues at WWTPs - WWOA

TrendingTrending

Page 30: Construction Issues at WWTPs - WWOA

ReportingReporting

Page 31: Construction Issues at WWTPs - WWOA

Topic #3 - What Happens if the Topic #3 - What Happens if the Contractor Doesn’t Finish?Contractor Doesn’t Finish?

• Performance Bond

• Engineer/Owner informs contractor that Bond Company will be notified

• 30-day period to respond

• If no action, Bond Company responds

• Contractor’s rating is affected

Page 32: Construction Issues at WWTPs - WWOA

SummarySummary

• Owner involvement critical

• Engineer and Owner need to work together

• Engineer and Owner need to have same long range goals

Page 33: Construction Issues at WWTPs - WWOA

Questions?Questions?

John D. [email protected] • 847.223.5088 • www.baxterwoodman.com