1. The procurement (bidding) requi rements are
a. a part of the construction documents, butnot the contract documents.
b. a part of the project manual.c. a part of the construction documents but
not the project manual.d. in the same part as the contract
modifications.
8/12/2019 Construction Documents Review Ver010712
3/38
1. The bidding requi rements are
a. a part of the construction documents, butnot the contract documents.
b. a part of the project manual.c. a part of the construction documents but
not the project manual.d. in the same part as the contract
modifications.
8/12/2019 Construction Documents Review Ver010712
4/38
2. Procurement (Bidding) documents are
a. Legally enforceable requirements which become part of the signed contract.
b. Include all of the construction documents exceptthe bidding requirements.c. Defined as all the construction documents issued
to bidders before the signing of an owner-
contract agreement.d. Only the documents bound in a three ringnotebook.
8/12/2019 Construction Documents Review Ver010712
5/38
2. Bidding documents are
a. Legally enforceable requirements which become part of the signed contract.
b. Include all of the construction documents exceptthe bidding requirements.c. Defined as all the construction documents issued
to bidders before the signing of an owner-
contract agreement.d. Only the documents bound in a three ringnotebook.
8/12/2019 Construction Documents Review Ver010712
6/38
3. EJCDC 1910-16 is a document whi ch
a. Is also called A521 by the AIA. b. Is used to coordinate between construction
documents.c. Suggests the primary location for specific
information in the constructiondocuments.
d. All of the above
8/12/2019 Construction Documents Review Ver010712
7/38
8/12/2019 Construction Documents Review Ver010712
8/38
4. The Procurement (Bidding) Requi rementsinclude
a. The invitation to bid, bid forms, and theagreement.
b. The instruction to bidders, the invitation to bid and the bid form.c. The information to bidders, the payment
bond and the bid security forms.d. The bid security forms, the information to
sub-contractors and the agreement.
8/12/2019 Construction Documents Review Ver010712
9/38
4. The Bidding Requi rements include
a. The invitation to bid, bid forms, and theagreement.
b. The instruction to bidders, the invitation to bid and the bid form.c. The information to bidders, the payment
bond and the bid security forms.d. The bid security forms, the information to
sub-contractors and the agreement.
8/12/2019 Construction Documents Review Ver010712
10/38
5. The Contr act Documents include
a. The contract forms, the bid forms, thespecifications and addenda.
b. The drawings, the specifications and theinformation to bidders.
c. The conditions of the contract, the drawingsand specifications.
d. Everything except the contract modifications.
8/12/2019 Construction Documents Review Ver010712
11/38
5. The Contr act Documents include
a. The contract forms, the bid forms, thespecifications and addenda.
b. The drawings, the specifications and theinformation to bidders.
c. The conditions of the contract, the drawingsand specifications
d. Everything except the contract modifications.
8/12/2019 Construction Documents Review Ver010712
12/38
8/12/2019 Construction Documents Review Ver010712
13/38
6. The Contract F orms include
a. The agreement. b. The performance and payment bonds.c. The certificates.d. All of the above.
8/12/2019 Construction Documents Review Ver010712
14/38
7. The Conditions of the Contract include
a. The General Conditions. b. The Supplementary Conditions.c. The Conditions to the Bidders.d. All of the above.
e. A and B only.
8/12/2019 Construction Documents Review Ver010712
15/38
8/12/2019 Construction Documents Review Ver010712
16/38
8. Addenda are
a. Changes to the contract documents beforethe agreement is signed.
b. Changes to the contract documents at anytime.
c. Changes to the contract documents afterthe agreement is signed.
d. None of the above.
8/12/2019 Construction Documents Review Ver010712
17/38
8. Addenda are
a. Changes to the contract documents beforethe agreement is signed.
b. Changes to the contract documents at anytime.
c. Changes to the contract documents afterthe agreement is signed.
d. None of the above.
8/12/2019 Construction Documents Review Ver010712
18/38
9. The Project M anual Concept
a. Was originated by CSI to replace thetitle specifications.
b. Provides an organizational format andstandard location for all documentsinvolved.
c. Includes only the specifications in the bound manual.d. Uses the UniFormat system.
8/12/2019 Construction Documents Review Ver010712
19/38
9. The Project M anual Concept
a. Was originated by CSI to replace thetitle specifications.
b. Provides an organizational format andstandard location for all documentsinvolved.
c. Includes only the specifications in the bound manual.
d. Uses the UniFormat system.
8/12/2019 Construction Documents Review Ver010712
20/38
10. What are the three components of projectdesign team coordination?
a. Duplication, omissions and discrepancies. b. Division One, Division Two, and Division
Three.c. General, Products and Execution.d. Organization, Execution and Quality
Assurance.
8/12/2019 Construction Documents Review Ver010712
21/38
10. What are the three components of projectdesign team coordination?
a. Duplication, omissions and discrepancies. b. Division One, Division Two, and Division
Three.c. General, Products and Execution.d. Organization, Execution and Quality
Assurance.
8/12/2019 Construction Documents Review Ver010712
22/38
11. The general clauses that establ ish how theproject is to be administered are known as:
a. Conditions of the Contract. b. General Conditions.c. Supplementary Conditions.d. Addenda.
8/12/2019 Construction Documents Review Ver010712
23/38
11. The general clauses that establ ish how theproject is to be administered are known as:
a. Conditions of the Contract. b. General Conditions.c. Supplementary Conditions.d. Addenda.
8/12/2019 Construction Documents Review Ver010712
24/38
12. On most projects, all of the following
are pr incipal enti ties EXCEPT:a. Contractor.
b. Ownerc. Electrical Consultantd. Architect/Engineer
8/12/2019 Construction Documents Review Ver010712
25/38
12. On most projects, all of the followingare pr incipal enti ties EXCEPT:
a. Contractor. b. ownerc. Electrical Consultantd. Architect/Engineer
8/12/2019 Construction Documents Review Ver010712
26/38
13. F or engineer ing projects, an Archi tect servesas a consultant to the Engineer :
a. Never. b. Sometimes.c. Always.d. Partially.
8/12/2019 Construction Documents Review Ver010712
27/38
8/12/2019 Construction Documents Review Ver010712
28/38
8/12/2019 Construction Documents Review Ver010712
29/38
14. In 1964, the term Project Manual wasintroduced by the:
a. American Bar Association b. American Institute of Architectsc. Construction Specifications Instituted. Department of Defense
8/12/2019 Construction Documents Review Ver010712
30/38
15. As part of the __________, the Agreement isconsidered a Contract Document:
a. Contract Conditions b. Contract Formsc. Bidding Requirementsd. Specifications
8/12/2019 Construction Documents Review Ver010712
31/38
15. As part of the __________, the Agreement isconsidered a Contract Document:
a. Contract Conditions b. Contract Formsc. Bidding Requirementsd. Specifications
8/12/2019 Construction Documents Review Ver010712
32/38
16. The Procurement (Bidding) Documentsinclude al l of the fol lowing EXCEPT:
a. Procurement (Bidding) Requirements b. Contract Modificationsc. Project Manuald. Drawingse. Addenda
8/12/2019 Construction Documents Review Ver010712
33/38
8/12/2019 Construction Documents Review Ver010712
34/38
8/12/2019 Construction Documents Review Ver010712
35/38
17. Project specifications shoul d be directed towhich of the following:
a. The Owner. b. The Contractor.c. Contractors, Subcontractors and material
suppliers.d. The Owners legal counsel
8/12/2019 Construction Documents Review Ver010712
36/38
18. The term Contract Documents typicallyincludes:
a. Contract Forms. b. Drawings.c. Specifications.d. All of the above.
8/12/2019 Construction Documents Review Ver010712
37/38
18. The term Contract Documents typicallyincludes:
a. Contract Forms. b. Drawings.c. Specifications.d. All of the above.
8/12/2019 Construction Documents Review Ver010712
38/38
Answers
1. a 2. c 3. c
4. b 5. c 6. d 7. e 8. a 9. b
10. d 11. b 12. c
13. b 14. b 15. b 16. b 17. b 18. d