Top Banner
Construction Dewatering General Permit (GP) & Groundwater Remediation GP Navigating the Permitting Process IECA Conference November 18, 2014 Margo Griffin Permits Section Water Quality Control Division
28

Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Mar 17, 2018

Download

Documents

doque
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Construction Dewatering General Permit (GP) & Groundwater Remediation GP Navigating the Permitting Process

IECA Conference November 18, 2014 Margo Griffin Permits Section Water Quality Control Division

Presenter
Presentation Notes
I work for the WQCD at CDPHE. We write permits for discharges to waters of the state. Today I will discuss two closely related permits.. Construction Dewatering and Remediation. They are so closely related that the Permits Unit has created one combined application to cover both permits.
Page 2: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Presentation Map

Construction Dewatering vs. Remediation Activities Covered Ensuring the right permit coverage

through the application process

Alternatives to these permits

Presenter
Presentation Notes
We will look at differences and similarities of these two permits, then discuss some alternatives to permitting.
Page 3: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Presentation Map

Construction Dewatering vs. Remediation Activities Covered Ensuring the right permit coverage

through the application process

Alternatives to these permits

Page 4: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Activities Covered Both permits cover discharges to GW and/or SW from

construction activities (e.g., excavating, grading)

Photographs by Tom Gore

Presenter
Presentation Notes
These activities are covered under both the construction dewatering and the remediation general permits. The discharge of groundwater to surface water(picture 1) Discharge of surface water, groundwater, and stormwater comingled with surface and groundwater (picture 2) Discharge is surface water. The project is diverting the surface water in order to work in the stream bed. (picture 3)
Page 5: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Activities Covered

Construction Dewatering GP Discharges of uncontaminated water that

has come into contact with construction activities

Remediation GPs

Discharges of potentially contaminated water from construction activities Permit

Delays!

Presenter
Presentation Notes
The biggest difference is that CDW covers uncontaminated discharge and Remed covers contaminated discharge. Contaminated water can lead to project delays…. Which is why the permit application process is so important.
Page 6: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Presentation Map

Construction Dewatering vs. Remediation Activities Covered Ensuring the right permit coverage

through the application process

Alternatives to Permitting

Presenter
Presentation Notes
So how do you know which permit is right for you? I’ll show you four steps to get you through the permit process… and to get you the right permit coverage.
Page 7: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Determining Permit Coverage

Step 1: Applicant identifies nearby sources of potential groundwater contamination (due diligence)

Voluntary Cleanup Programs (VCUPs) Corrective Action Sites

Historical Landfills Superfund Sites

National Priorities List (NPL ) Sites

Leaking Underground Storage Tanks

Presenter
Presentation Notes
Step 1 – determine if CDW site could be impacted by a contaminated site Whether contaminants are present at the CDW site and in what concentration will determine appropriate permit coverage
Page 8: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Submitting Data with the Permit Application

Step 2: As needed, collect a water sample and submit analytical data for the proposed discharge

Presenter
Presentation Notes
Step 2 – Submit data if you are located nearby contamination.
Page 9: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation
Presenter
Presentation Notes
Now you are probably wondering : What does the division consider “nearby,” what data do I submit?, and how do I find these sites anyway??!
Page 10: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Determining Permit Coverage

Required* Monitoring Parameters

Project Location Relative to a Source of Potential Groundwater Contamination

Analytical Data Likely to be Required with the Permit

Application

Within 0.5 mile of an open Leaking Underground Storage Tank (LUST) site (Note that closed LUSTs are assumed to pose a low risk for potential groundwater contamination and, therefore, the submission of analytical data based on proximity to a closed LUST is not required)

Benzene Toluene

Ethylbenzene Xylenes

(BTEX) only

Within 0.5 mile of a Voluntary Cleanup (VCUP) site

Metals/Volatiles/Semi-volatiles (as listed in the permit

application) *Note: Additional parameters may

be required

Within 0.5 mile of an Environmental Covenant

Within 0.5 mile of an open Resource Conservation Recovery Act (RCRA) Corrective Action Site

Within 1.0 mile or more of a Superfund site or National Priorities List (NPL) site with associated groundwater contamination

*Monitoring for the indicated parameters is required unless the permit applicant can demonstrate that the source of contamination does not impact the construction dewatering site

Presenter
Presentation Notes
This table from the combined applications helps answer these questions. – Note that we want to be flexible.
Page 11: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Identifying Potential Sources of Contamination

Leaking Underground Storage Tanks (LUSTs): CO Division of Oil and Public Safety - Storage Tank Information System (“COSTIS”): http://costis.cdle.state.co.us/home.asp

Voluntary Cleanup Sites (VCUPs): CDPHE Hazardous Materials and Waste Management Division (HMWMD) - List of VCUPs by County:

https://www.colorado.gov/pacific/cdphe/voluntary-cleanup

Presenter
Presentation Notes
Here are online resources…
Page 12: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Identifying Potential Sources of Contamination

Environmental Covenants: https://www.colorado.gov/pacific/cdphe/sites-environmental-covenants-and-use-restriction

Superfund Sites: https://www.colorado.gov/pacific/cdphe/superfund-sites

RCRA Corrective Action (RCRA) Sites:

www.epa.gov/myenvironment

Presenter
Presentation Notes
More online resources
Page 13: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Identifying Potential Sources of Contamination

Contact the Permits Section for assistance at

303-692-3500.

Presenter
Presentation Notes
More resources
Page 14: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Submitting Data with the Permit Application

Step 3: Submit a complete permit application.

No known GW contamination No analytical data required Construction Dewatering GP

Known potential GW contamination

Analytical data is required May be Construction Dewatering or

Remediation GP

Presenter
Presentation Notes
Recap…
Page 15: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Step 4: Upon application receipt, the Division will:

Review your application and due diligence effort

Evaluate any data submitted with the application

Request data as needed

Presenter
Presentation Notes
Step 4 When we get your application and any required data, we review the data for reasonable potential to exceed a water quality standard. Our need to ask for data at this point can slow the process.
Page 16: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Reasonable Potential (RP) Analysis

Is there “reasonable potential” for a constituent in your discharge to exceed a water quality standard?

Presenter
Presentation Notes
Step 4 When we get your application and any required data, we review the data for reasonable potential to exceed a water quality standard.
Page 17: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Reasonable Potential (RP) Analysis

Are Detected Concs > ½ Water Quality Standards? No Construction Dewatering GP Yes Remediation GP

Presenter
Presentation Notes
Step 4 When we get your application and any required data, we review the data for reasonable potential to exceed a water quality standard.
Page 18: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Construction Dewatering Permit Certification

Step 5: Division Issues Permit Certification

Remediation Permit Certification (example)

Presenter
Presentation Notes
And we issue a cert… Construction includes basic parameters Remediation includes those parameters plus others The Remedation limits are the standards. It is possible that treatment may not be required. There are other differences (such as bmps and preparing for possible treatment).
Page 19: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Permit Type What type of discharge? Limited Parameters Type of

Treatment

Construction Dewatering

Uncontaminated source water encountered during construction

-Flow -TSS or TDS -pH -Oil & Grease -E. Coli/Total Coliform -BTEX

Passive Treatment Only

Remediation Discharges

Potentially Contaminated source water

Same as above, plus: -Organics, Inorganics, Metals, Rads, etc.

Active Treatment May be Required

Construction Dewatering vs. Remediation

Page 20: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Overview of Permit Application Process

Presenter
Presentation Notes
This is from the combined permit application. Explains the process.
Page 21: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Presentation Map

Construction Dewatering vs. Remediation Activities Covered Ensuring the right permit coverage through

the application process

Alternatives to these permits

Presenter
Presentation Notes
Let’s look at alternatives..
Page 22: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Alternatives to these Permits

Discharge Under Your Construction Stormwater Permit

Low Risk Discharge Policy

Ship Water Offsite

Beneficial Use

Presenter
Presentation Notes
Alternatives
Page 23: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Discharge Under Your Construction Stormwater Permit

Source water is uncontaminated GW (due diligence)

Source is identified in SWMP

Land application only

No runoff Photograph by Tom Gore

Presenter
Presentation Notes
If you have a Construction Stormwater permit, you can land apply uncontaminated water under that permit.
Page 24: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Low Risk Discharges Water Quality Policy 27

Source water is uncontaminated GW (due diligence)

Land application only

Low risk criteria apply

Low Risk = No CDPS Permit Required

Presenter
Presentation Notes
Or you can land apply uncontaminated water under the Division’s low risk policy.
Page 25: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Ship Contaminated Water for Lawful Disposal Offsite

No Discharge = No permit required

Determine water rights first

Presenter
Presentation Notes
Or send the water offsite (clear water rights first). Make sure you know where it’s going! ;-)
Page 26: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Beneficial Use of Construction Generated Water

Find approved beneficial uses Application rates matter

Determine water rights first

Presenter
Presentation Notes
Or use the water for beneficial use (get approval from Solid Waste and clear water rights first)
Page 27: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

Beneficial Use Contacts

Beneficial Use Questions: CDPHE Solid Waste Program 303-692-3320 Toll-free 1-888-569-1831 Ext 3320

Water Rights:

State Engineer Office 303-866-3581

Presenter
Presentation Notes
Pass the baton to DNR
Page 28: Construction Dewatering General Permit (GP) & …mountainstatesieca.org/wp-content/uploads/2015/03/Margo-Griffin... · Construction Dewatering General Permit (GP) & Groundwater Remediation

WQCD Permit Section Contact Information

coloradowaterpermits.com

Permit Section Main Line: o 303-692-3500

Margo Griffin, Permit Writer

o 303-692-3607 o [email protected]