Top Banner
CONSTRAINTS TO IMPLEMENTING EARNED VALUE MANAGEMENT (EVM) AS A TOOL FOR PROJECT PLANNING AND CONTROL – A SOLUTIONS PERSPECTIVE - A CASE STUDY AMONG NIGERIAN CONSTRUCTION PROJECT MANAGERS MASTER THESIS International Master of Science in Construction and Real Estate Management Joint Study Programme of Metropolia UAS and HTW Berlin Submitted on 20.08.2019 by Gbolahan Opeyemi Ola Metropolia UAS student number:1707883 HTW-Berlin student number: S0562663 First supervisor: Prof. Dr.-Ing. Nicole Riediger Second Supervisor: Arch. Eric Pollock
89

CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

May 15, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

CONSTRAINTS TO IMPLEMENTING EARNED VALUE

MANAGEMENT (EVM) AS A TOOL FOR PROJECT PLANNING

AND CONTROL – A SOLUTIONS PERSPECTIVE - A CASE STUDY

AMONG NIGERIAN CONSTRUCTION PROJECT MANAGERS

MASTER THESIS

International Master of Science in Construction and Real Estate

Management

Joint Study Programme of Metropolia UAS and HTW Berlin

Submitted on 20.08.2019 by

Gbolahan Opeyemi Ola

Metropolia UAS student number:1707883

HTW-Berlin student number: S0562663

First supervisor: Prof. Dr.-Ing. Nicole Riediger

Second Supervisor: Arch. Eric Pollock

Page 2: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

i

ACKNOWLEDGEMENT

This thesis and the past two years of study, though challenging, were only

completed through the constant support and encouragement from my family and

friends.

I appreciate my mother and father for their prayers, care and concern. I want to

say thank you to my elder sister, Damilola, for being such a role model, and with

her husband, Adekunle, their endless support. I am also thankful to my younger

siblings and cousins (Boluwatife, Mojisola and Monisola) who have cheered me

on during this journey.

I am sincerely grateful for the immeasurable support from a cousin turned big

brother, Gbenga Komolafe and his beautiful family. Morenike, Seyi, Tosimi,

Segun, Tolulope and Shashank who have helped with logistics and advised me,

I say a big thank you.

I want to thank the faculty and administrative staff of HTW-Berlin and

Metropolia UAS that have taught and guided me throughout this program.

Once more into the fray, Into the last good fight I’ll ever know, live and die on this

day, live and die on this day. (Carnahan, 2012).

Page 3: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

ii

International Master of Science in Construction and Real Estate Management

Joint Study Programme of Metropolia Helsinki and HTW Berlin

Date: 06.06.2018

CONCEPTUAL FORMULATION

Master Thesis for Mr Gbolahan Ola

Student number S0562663, 1707883

Topic: CONSTRAINTS TO IMPLEMENTING EARNED VALUE MANAGEMENT (EVM) AS

A TOOL FOR PROJECT PLANNING AND CONTROL – A SOLUTIONS

PERSPECTIVE - A CASE STUDY AMONG NIGERIAN CONSTRUCTION PROJECT

MANAGERS

Signature of the Supervisor

Page 4: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

iii

CONSTRAINTS TO IMPLEMENTING EARNED VALUE

MANAGEMENT (EVM) AS A TOOL FOR PROJECT PLANNING

AND CONTROL – A SOLUTIONS PERSPECTIVE - A CASE STUDY

AMONG NIGERIAN CONSTRUCTION PROJECT MANAGERS

Master thesis proposal

International Master of Science in Construction and Real Estate

Management

Joint Study Programme of Metropolia UAS and HTW Berlin

By

GBOLAHAN OLA

HTW-Berlin registration number: S0562663

Metropolia UAS registration number: 1707883

First supervisor: Prof. Dr.-Ing. Nicole Riediger

Second Supervisor: Eric Pollock

Submitted on 16.04.2018

Page 5: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

iv

INTRODUCTION

There are several developed techniques used in project control. Earned value

analysis (EVA) seems to be a widely known and accepted method to use on

projects to understand, manage and forecast performance. It is a technique that

measures three important baselines in project management (scope, cost and

time) to give the overall health and progress of a project. These measurements

provide the project manager with the ability to review the project beyond the

independent reviews of these three baselines. As most projects almost certainly

never go entirely according to the project plan and corrective measures are

required, information from the EVM process is crucial for evidence-based

decisions and actions needed to keep the project on its planned baselines or as

close as possible to them.

Significant advantages of using EVM is that it increases project accountability,

and it can anticipate future project setbacks along the three cardinal baselines

early enough. Through using index-based forecasting, project managers are able

to determine amongst other parameters, cost and schedule variance, Schedule

Performance Index (SPI), Cost Performance Index (CPI), Budget at Completion

(BAC), Estimate of costs To Completion (ETC) and most importantly the To

Completion Performance Index (TCPI).

RESEARCH PROBLEM

Cost and schedule overruns are the usual criticisms of project execution in

Nigeria. As early as Idoro (2009) mentioned that project delay is the major

problem facing the Nigerian construction Industry. It is common that when a

schedule overrun occurs, project durations are extended or more resources are

applied to the project to crash its schedule; in both cases, this leads to additional

project costs. While most projects start with varying levels of detailed planning,

during execution, there is minimal effort committed to monitoring and control

and use of EVM as a tool for monitoring and steering a project to better

Page 6: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

v

performance. Its skills and adoption among Project managers in Nigeria appear

low, even in the face of tight project constraints and increasing global completion

in the local market. This thesis would seek to study the applicability of EVM in

controlling projects in Nigeria. It would consider the method of integrated project

control (if any), among construction managers, it would also seek to determine

the best approach to address the constraints how earned value could be

implemented in the construction project organisation.

RESEARCH QUESTIONS

1. What is the impact of EVM on overall construction project performance?

2. What are the constraints for implementing EVM in Construction projects?

3. What is the most effective way to enhance the application of EVM in

construction projects for better performance?

METHODOLOGY

To accomplish the objectives of the research, the author conducts exploratory

research through literature reviews, surveys and focus groups/interviews. The

literature review will focus on project management control and earned value

management and its usefulness in construction projects. Survey questionnaires

would be randomly distributed to project managers and focus group/interviews

would be conducted for senior project managers, architects and Engineers.

Results from the analysis of distributed questionnaires would be used to answer

research question 1& 2, while focus group or interviews would be used to answer

research questions 1 & validate solutions to question 3 that the researcher would

provide.

Page 7: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

vi

EXPECTED RESULTS

This thesis presents earned value method to solve the problem of poor project

control; with emphasis on Nigerian construction projects. Through researching

project contracts; project accountability culture; and performance recording and

analysis methods, Conclusions from this thesis should provide a framework for

project managers on how to use EVM at an organisational level.

THESIS OUTLINE

This thesis would be divided into five chapters. First chapter; the Introduction

and study background of earned value management. The second chapter will

cover literature reviews the author would connect the research topic to previous

academic works where more in-depth studies into the concept of earned value

management from multiple perspectives.

The fourth chapter, called ‘Results/Findings’, represents the author’s analyses

of research data. Lastly, the Discussions Conclusions and Recommendations

chapter closes out the research and the author shows his

interpretation/observation from the data analyses within the context of the

research topic.

REFERENCE

Idoro (2009), “Evaluating the level of use of bar chart and its influence on project

performance in the Nigerian construction industry”, Department of Building,

University of Lagos, Akoka, Lagos, Nigeria, COBRA 2009, Pp 37-44

Page 8: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

vii

ABSTRACT

This thesis examines the constraints to implementing Earned value management

in construction projects and provide solutions to these constraints. This thesis

begins by presenting the historical background of EVM, how it is derived and

effectively used, the benefits possible through its use, and finally, its limitations.

To answer the research questions, literature reviews and questionnaires are

used. Seventy-three construction project managers participated in the survey.

Notably, a key observation from literature review, reveals that current

information do not examine comprehensively, the relationship between EVM and

strategic project organization.

From fragmented works of literature and the analysis of survey responses, the

author identifies several factors that impede the effective implementation and

use of EVM. These factors are; flexibility to scope changes, error reporting and

data manipulation, standardization of processes, punishment of contractors and

lastly, IT and software support.

To conclude, the author presents recommendations to overcome each impeding

factor and offers two strategic EVM organisational models centered around these

recommendations. These models having varying emphasis on individual factors

are designed to cater to different implementation environments.

Page 9: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

viii

TABLE OF CONTENTS

ACKNOWLEDGEMENT .......................................................................................................................... i

CONCEPTUAL FORMULATION ............................................................................................................ ii

ABSTRACT ............................................................................................................................................... vii

TABLE OF FIGURES .............................................................................................................................. x

LIST OF TABLES ..................................................................................................................................... x

LIST OF ABBREVIATIONS .................................................................................................................. xi

1 INTRODUCTION ............................................................................................................................. 1

1.1 INTRODUCTION ...................................................................................................................... 1

1.2 RESEARCH PROBLEM .......................................................................................................... 2

1.3 SPECIFIC THESIS OBJECTIVE .......................................................................................... 3

1.4 BROADER RELEVANCE OF THE THESIS ...................................................................... 3

1.5 RESEARCH QUESTIONS ...................................................................................................... 4

1.6 METHODOLOGY ..................................................................................................................... 4

1.7 THESIS SCOPE ........................................................................................................................ 4

1.8 EXPECTED RESULTS ............................................................................................................ 5

2 LITERATURE REVIEW ................................................................................................................. 6

2.1 INTRODUCTION ...................................................................................................................... 6

2.2 HISTORICAL BACKGROUND .............................................................................................. 7

2.3 EVM AND PROJECT MANAGEMENT: CONCEPTUAL CONNECTIONS ............... 10

2.4 EVM INDEXES, PERFORMANCE ANALYSIS AND FORECAST .............................. 13

2.4.1 Primary EVM Indexes ................................................................................................... 13

2.4.2 Performance Metrics ...................................................................................................... 14

2.4.3 Forecast metrics ............................................................................................................. 18

2.5 EVM, PROJECT DELIVERY AND CONSTRUCTION PERFORMANCE ................. 22

2.6 PROCUREMENT AND EVM ............................................................................................... 25

2.7 EVM AND PROJECT MANAGEMENT INFORMATION SYSTEMS .......................... 28

2.8 CRITICISMS/LIMITATIONS OF EVM .............................................................................. 30

3 METHODOLOGY ........................................................................................................................... 34

3.1 INTRODUCTION .................................................................................................................... 34

3.2 RESEARCH PHILOSOPHY AND DESIGN ...................................................................... 34

3.3 SAMPLE POPULATION ........................................................................................................ 36

Page 10: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

ix

3.4 SAMPLING PROCEDURE ................................................................................................... 36

3.5 VALIDITY AND RELIABILITY OF THE RESEARCH INSTRUMENT ....................... 37

3.5.1 Validity .............................................................................................................................. 37

3.5.2 Reliability ......................................................................................................................... 37

3.6 DATA ANALYSIS TECHNIQUE .......................................................................................... 37

3.6.1 Analysis of quantitative data ..................................................................................... 37

3.6.2 Analysis of qualitative data ........................................................................................ 38

3.7 MEASUREMENT OF VARIABLES .................................................................................... 38

4 DATA ANALYSIS ........................................................................................................................... 39

4.1 INTRODUCTION .................................................................................................................... 39

4.2 QUESTIONNAIRE RETURN RATE ................................................................................... 39

4.3 QUESTIONNAIRE ANALYSIS ............................................................................................. 39

5 RECOMMENDATIONS AND CONCLUSION ........................................................................ 51

5.1 FLEXIBILITY TO SCOPE CHANGES ............................................................................... 51

5.2 ERROR REPORTING AND DATA MANIPULATION ..................................................... 53

5.3 STANDARDIZATION OF PROJECT MANAGEMENT PROCESSES ........................ 56

5.4 PUNISHMENT OF CONTRACTORS ................................................................................. 58

5.5 IT PROJECT SUPPORT ........................................................................................................ 60

5.6 CONCLUSION ......................................................................................................................... 63

DECLARATION OF AUTHORSHIP ................................................................................................... 67

APPENDIX A ............................................................................................................................................ 68

BIBLIOGRAPHY ..................................................................................................................................... 72

Page 11: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

x

TABLE OF FIGURES

FIGURE 1: PROJECT MANAGEMENT PROCESS ...................................................................... 6

FIGURE 2: EVM HISTORICAL TIMELINE .............................................................................. 8

FIGURE 3: GRAPHICAL REPRESENTATION OF THE BODY OF KNOWLEDGE SEARCH RESULTS ....... 9

FIGURE 4: GRAPHICAL REPRESENTATION OF THE BODY OF KNOWLEDGE SEARCH RESULTS ..... 10

FIGURE 5: PROJECT AHEAD OF SCHEDULE USING SCHEDULE VARIANCE ............................. 15

FIGURE 6: PROJECT OVER BUDGET USING COST VARIANCE ............................................... 16

FIGURE 7: EVMS SYSTEM. ............................................................................................ 30

FIGURE 8: ENGINE CHOICE CHECKLIST TO BUILD AN EVMS ............................................... 61

FIGURE 9: MODEL 1 TO OVERCOME IMPLEMENTATION CONSTRAINTS OF EVM ...................... 64

FIGURE 10: MODEL 2 TO OVERCOME IMPLEMENTATION CONSTRAINTS OF EVM .................... 65

LIST OF TABLES

TABLE 1: SUMMARY OF METRICS, MEASUREMENTS AND INTERPRETATION ............................. 20

TABLE 2: EVM MEASUREMENT SCENARIOS AND CORRECTIVE ACTIONS................................. 21

Page 12: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

xi

LIST OF ABBREVIATIONS

ABBREVIATION DESCRIPTION

AC Actual Costs

ACWP Actual Cost of Work Performed

AEC Architecture, Engineering and Construction

BAC Budget At Completion

BCWP Budgeted Cost of Work Performed

BCWS Budgeted Cost of Work Scheduled

CPI Cost Performance Index

CR Critical Ratio

CV Cost Variance

C/SCSC Cost/Schedule Control System Criteria

EAC Estimate At Completion

ES Earned Schedule

ETC Estimate to Completion

EV Earned Value

EVM Earned Value Management

EVMS Earned Value Management Systems

PMB Project Management Baseline

PMIS Project Management Information System

PV Planned Value

SPI Schedule performance index

SV Schedule Variance

TCPI To Completion Performance Index

WBS Work Breakdown Structure

WPM Work Package Method

Page 13: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

1

1 INTRODUCTION

The difficulty of measuring progress does not justify the conclusion that it should

not be done. You cannot have control unless you measure progress- (Heagney,

2012).

1.1 INTRODUCTION

Sound project management practices and techniques have increasingly become

integral to managing construction projects since project management began in

its modern form in the 1950s. As new projects continue to drive for cost

efficiencies, multi-stakeholder satisfaction, tight schedules and competition

along shrinking profit margins, the competencies of project managers have

become critical to the success of public and private construction offices.

Complex projects in the execution phase, are composed of large volumes of

activities that generate real-time data which are used by project managers to

measure and anticipate future behaviour of the project; and taking necessary

actions where needed. Performance measurement of program outputs and

outcomes provide vital information on current program status and how much

progress has been achieved towards important program goals (NAPA, 1994). The

project manager is proactive and finds problems early, looks for change and

prevents problems (Mulcahy, 2013).

Selectively paramount from data generated from completed and ongoing project

activities are indicatives of the rate of progress/milestone completion and actual

costs. Through analysis of these, useful information is derived in respect of the

triple constraints of project management. These constraints are scope, time and

cost. As mentioned in (Project Management Body of Knowledge book, 2013),

these constraints must be controlled by the project manager (pp 12) and are part

of the bases of measuring success on a project (pp 32). It is the duty of project

Page 14: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

2

managers, therefore, to keep up to date with current project data related to these

constraints and trend analysis methods (to derive actual performance), to be

informed enough to maintain control and manage the project to successful

completion. This is known as monitoring and control. The project manager

measures progressive performance against planned performance to determine

project performance in terms of substantial completion, schedule and budget.

“Based on project performance measurement, the project team can activate a

project control process to ameliorate any issues and return the project more in

line with its scheduled course,” thus combating project failure (Ritz, 1994).

Projects lacking monitoring and control could easily experience delayed

completion and poor budget performance. Likewise, as cited in (De Marco, Rafele,

& Briccarello, 2009), (Sterman, 2018), control decisions delayed until late in the

project are mostly expensive and ineffective.

While several decades of modern project management practices have seen the

development of multiple techniques for project monitoring and control, this

thesis will mainly focus on overcoming the current constraints of the use of

Earned Value Management, and improving its application among project

managers.

1.2 RESEARCH PROBLEM

Cost and schedule overruns are the usual criticisms of project execution in

Nigeria. As early as (Idoro, 2009) mentioned that project delay is the major

problem facing the Nigerian construction Industry. It is common that when

schedule overrun occurs, project duration is extended, or more resources are

applied to the project to crash its schedule; in both cases, this leads to additional

project costs. While most projects start with varying levels of detailed planning,

during execution, there is minimal effort committed to monitoring and control

and use of EVM as a tool for monitoring and steering a project to better

performance. Its skills and adoption among Project managers in Nigeria appear

low, even in the face of tight project constraints, erratic inflation and increasing

Page 15: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

3

global completion in the local market. Studying the application of Project

management techniques, (Blili & Raymond, 1993), asserted that innovative

analysis and forecasting techniques are scarcely applied in small and medium-

scale organisations. This thesis seeks to study the applicability of EVM in

controlling projects in Nigeria. It would consider the method of integrated project

control (if any) among construction managers; it would also seek to determine

the best approach to address the constraints how earned value could be

implemented in construction projects at an organisational level.

1.3 SPECIFIC THESIS OBJECTIVE

This Thesis aspires to provide a framework for project control optimisation

through the delivery of measures and processes that encourages Construction

managers in Nigeria to adopt EVM. The author seeks to study in-depth

theoretical knowledge of this control tool, to the end that he can implement EVM

on projects and Project Management Offices’ processes. The author believes that

systematic implementation accurate monitoring and forecasting tools in a

projectised environment are a value-adding skill modern project managers

should possess.

1.4 BROADER RELEVANCE OF THE THESIS

(De Neufville & Field, 2018) Described a thesis as an opportunity for students to

be creative, to bring together and integrate skills they have acquired to make a

real professional contribution. This infers that it is geared towards not only

nurturing curiosity and becoming experts themselves but also contributing to

the body of knowledge in their chosen fields.

Successful completion of this thesis would likewise provide an opportunity for

interaction and knowledge sharing among professionals from construction

Page 16: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

4

industries in developing countries, advanced countries and academic

institutions.

Through developing guidelines and mechanisms for project monitoring and

reporting within project management and EVM framework, the author is keen to

increase project transparency and accountability.

1.5 RESEARCH QUESTIONS

1. What is the impact of EVM on overall construction project performance?

2. What are the constraints to implementing EVM in Construction projects?

3. What is the most effective way to enhance the application of EVM in

construction projects for better performance?

1.6 METHODOLOGY

To realise the objectives of the research, the author conducts an exploratory

research through literature reviews, surveys and focus groups/interviews. The

literature review focused on project management control and earned value

management and its usefulness in construction projects. Survey questionnaires

would be randomly distributed to project managers and focus group/interviews

would be conducted for senior project managers, architects and Engineers.

Results from the analysis of distributed questionnaires would be used to answer

research questions one and two, while interviews would be used to answer

research questions 1 & validate solutions to question 3 that the researcher would

provide.

1.7 THESIS SCOPE

This thesis focuses on EVM from multiple perspectives. These perspectives

represent planning for the use of EVM in projects through the need for flexibility,

standardization, correct reporting, contactor buy-ins and the tools for accurate

performance recording, reporting and analysis.

Page 17: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

5

The thesis presents the analysis of questionnaires and interviews will be

conducted with EVM experts.

1.8 EXPECTED RESULTS

This thesis presents earned value method to solve the problem of poor project

control; with emphasis on construction projects. Through research within the

thesis scope, analyses and recommendations are provided on suitable

approaches on how project managers can successfully use EVM at an

organisational level.

Page 18: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

6

2 LITERATURE REVIEW

2.1 INTRODUCTION

EVM derives as a tool developed for use during the planning, monitoring and

control phases of projects. Projects, according to (Project management Institute,

2013), follow a 5 phase process from conceptualisation to completion.

Figure 1: project management process. (Eby, 2018)

Achieving the objectives within each of these phases is vital to achieving success

on any project. (Munns & Bjeirmi , 1996) described these processes as essential

to management to achieve project success. (Bower, 2007) mentioned that these

sequential processes need to be followed to achieve project success.

Project endeavours, managed from initiation to completion, can have

complicated interrelationships, processes and restrictions necessary to achieve

its requirements. To achieve success, (Levine, 2002) mentions that It involves

planning for and controlling scope; budget; schedule; quality; risks; human

resources; procurements; and stakeholder communication. These factors

described as knowledge areas in the PMBOK are developed to avoid budget

overruns, projects delays, stakeholder dissatisfaction, among other project

challenges and failure factors. These five phases and knowledge areas are

designed to have defined inter-related processes to guide project managers and

Page 19: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

7

teams to plan, deliver, anticipate and control project activities and their

challenges.

There are methods and tools specific to each project process; the choice of the

approach adopted in a process is dependent on the output requirement of that

process. One such method/tool is EVM. EVM is used for operations in the

planning, execution and monitoring & control phases that relate to scope, budget

and schedule knowledge areas. In line with the objectives of project management

to plan and organise activities, EVM can be described as a project manager’s

policing tool. (Turner, 2007) Identified that the purpose of project management

as to foresee challenges to plan for and control project activities to be

successfully delivered despite these challenges.

2.2 HISTORICAL BACKGROUND

EVM was developed in the 1960s by the US Department of Defence as a financial

tool to measure defence acquisition projects. Project deviations were corrected

using pre-established control baselines of interrelated cost and schedule

indicators. When introduced, it was known as schedule/cost system criteria

(SCSC) but later renamed as earned value analysis. Before its introduction,

schedule and costs measuring tools and reports were used discretely or

independent of each other. A significant limitation of this method is that they

failed to estimate planned costs against actual costs spent to complete real work.

(Chen, 2008) Mentioned, actual costs do not reflect actual accomplishment on

projects. Understanding how efficiently costs were being utilised with relation to

task progress and completion was the motivation behind why EVM was

developed.

Over the following decades, “EVM use spread to other US government agencies

such as the United States Department of Energy, NASA and US Defence

Acquisition Department etc.” (Khamidi, Khan, & Idrus, 2011). It also proved

popular among project stakeholders in the private sector. Liable to terms of an

agreed contract, “contractors are faced with challenges within or outside their

Page 20: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

8

control. It is, therefore, crucial for contractors to monitor potential cost overruns

and delays in project execution” (Khamidi, Khan, & Idrus, 2011). (Fleming &

Koppelman, 1998), put forward that EVM is now a necessary tool being used to

determine the value of work achieved when planning payments to contractors

whose jobs are paid for in phases.

(VanderVeen, 2018) also, put forward that EVM is also being used as an

instrument to motivate and boost the morale of the project team when a project

is shown to be ahead of schedule or under budget or both. Literature shows that

while EVM was birthed to address shortfalls in measuring efficient government

project spending, its use has broadened to private projects and is being utilized

to provide an expanding spectrum of human resource and procurement

solutions key to every stakeholder involved in a project. “EVM was developed to

monitor the performance of a project, created from the needs of its own project

EVM era 1

(1956-1967)

•Need for a tool better that PERT/cost

•Development of Work breakdown structure

•Development of cost/schedule control systems criteria

EVM era 2

(1967-1983)

•Over implementation led to resistance from project managers and government agencies

•C/CSCS became dismissed as a financial control tool only for financial analysts

•taught in project management programs for AEC industry

EVM era 3

(1983-1991)

•Began being used by project managers and executives

• Inclusion in the first PMBoK by PMI

•Was included in project procurement criteria

•Development and use of Micro frame progam manager (MPM) which included EVM

EVM era 4

(1992-2002)

• Adoption of more flexible regulations

Adoption in more industrialized nations like Australia , UK and other european countries

• Renamed earned value management system

• Increased reasearch and closer integration & expansion of EVM into Project management methodologies

• Became a compulsory tool across all US Government agencies

Private sector adotion

• EVM calculations integrated into management tools like MS Project and MS Excel

EVM era 5

(2002-2008)

•EVM receives increased attention in Publicly listed companies in the USA in response to Sarbanes-Oxley Act of 2002

EVM era 6

(2008-Present)

•EVM is used as a program management tool in facilities integrated program managemnt

Figure 2: EVM historical timeline. Elaborated from (College of performance management, n.d.)

Page 21: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

9

members and more specifically of the members of the project management and

its stakeholders” (Ammari, 2017).

With adoption in construction, manufacturing, oil & gas, IT, infrastructure and

similar industries, EVM is a multi-disciplinary project control tool. To this end,

it has earned recognition among project management professional bodies. Since

its first introduction in 1987, EVM is included in the PMI’s PMBoK guide; which

is a collection of processes; guidelines, best practices and required standards for

project managers in the USA. PRINCE 2, a UK developed project management

methodology built on product-based planning, uses EVM at different levels

ranging from overall project level detail down to activity level detail.

EVM has also picked the interested of researchers, scientists and professional

institutions. An international e-materials search on Metropolia UAS MetCat done

on July 23, 2018, using the search word ‘earned value’ yielded 390, 983 results

with a content type distribution illustrated with the graph below;

Figure 3: Graphical representation of the Body of Knowledge search results. (Author)

A similar search done by (Thomas, 2015) across eight cross-disciplinary

databases gave 145 full-texts, 65 were conceptual, 70 were empirical, and 10

could not be distinguished unambiguously. He presented the distribution of his

results in the chart below:

0 50,000 100,000 150,000 200,000 250,000

1

62329321667041,7122,9795,007 143,784 236,773

EVM document type

E-article Newspaper article

Text resource Review

Website Reference entry

Conference proceeding Other

Book Dissertations

Book chapters

Page 22: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

10

Figure 4: Graphical representation of the Body of Knowledge search results. Source: (Thomas, 2015)

From the chart above, it can be seen that as is the reason for the thesis, EVM is

historically most popular in the construction industry.

It is important to note that during its early years in the 1970s and early 1980s,

EVM is documented to have faced challenges of adoption by project managers.

As mentioned by (Fleming & Koppelman, 2010), the general criteria set for EVM

was resisted and sometimes ignored by project managers in both government

and the private industries. In its early days as cost/schedule control systems

criteria (C/SCSC), it was widely misunderstood as a mere a financial control tool

with perplexing definitions and should only concern accountants and analytical

specialists. Perceived to be overly prescriptive criteria and confusing, it was

unsuccessful on many commercial projects (Fleming & Koppelman, 2006)

2.3 EVM AND PROJECT MANAGEMENT: CONCEPTUAL CONNECTIONS

As already established, EVM is a well-known methodology in project

management and in construction. The primary motive of having a project

management team dedicated to a construction project is to have it deliver all

project requirements on schedule, within budget and achieve stakeholder

Page 23: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

11

satisfaction. The success of project managers is highly dependent on their choice

and level of expertise of methodologies they apply to their tasks. (Lehtonen &

Martinsuo, 2006); Methodologies provide more predictable project success than

projects that do not use one. Methodologies adopted in the executing and

monitoring and control phases of project management are processes that use

project success baselines, project data and skills of a project team to produce

output information necessary to enhance ongoing project performance. It is

therefore crucial for the purposes of achieving project success, to have these

three factors harmonized for best results.

In addition to requiring good skills from the project manager and pre-determined

project baselines, EVM analyzes quantitative data generated on ongoing projects

to support project review and forecasting among project stakeholders. The

essence of EVM is to accurately and early as possible, draw attention to trends

that could have negative impacts the project success. In other words, it is can

be described as a risk assessment tool. Through measuring the occurrence and

risks of cost overruns and schedule delays, output figures from EVM present

project teams with information in order to maintain or improve project efficiency.

Management is able to forecast cost and time trends based on the actual

performance of the project and obtain crucial information about future costs and

time shifts due to delays (Ammari, 2017).

Another key concept the use of EVM is accurate record keeping. EVM establishes

a single management control system providing reliable data (kshirsagar &

Konnur, 2017). EVM requires the analysis of historical data and current project

data collected at time intervals or milestone achievements to present reliable

information for project control measures. By doing so, it strongly encourages the

project team to actively collect and archive project information in a central

project or program database. By encouraging record keeping and organized

information database systems for every project and program, archived and

historical data from previous projects can be extracted by a project team as

inputs to plan with better accuracy, schedules, costs and procurements on

similar projects. Through collecting data, its use can go beyond monitoring and

Page 24: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

12

controlling current projects to be vital information repository for the planning

phase of future projects in an organization (Villafiorita, 2014).

An ancillary concept associated with EVM is the Kaizen theory. Kaizen means an

improvement in Japanese. Kaizen requires constant assessment and

readjustments to allow improvements and better efficiency. (Badgujar, Konnur,

& Landage, 2016) informed that utilization of earned value technique for project

control results in better assessment of schedule and budget requirements.

“Productivity can be improved by taking regular feedbacks of cost and schedule

performance”. The frequent feedback required with the aim of enhancing

efficiency in budget and schedule performance through the EVM process is

central for encouraging a Kaizen culture among the project team.

(Haupt, 2017), mentioned that for EVM to achieve suitable outcomes, project

managers and contractors should have a good working relationship and often

communicate each other’s project analysis. This can be inferred as a

collaborative two-way communication approach. It is therefore ideal for both

parties to agree on how information is reported in status, progress, trend, Earned

value and forecast reports. EVM, thus, pushes for effective information exchange

using a clearly understandable Project assessment and reporting system.

A connection can be made between EVM and project team motivation on projects.

EVM provides information about performance which can be used as the basis

for the organisational application of well-known motivation theories. Basic

performance measurements of work efficiency, cost efficiency and variances can

provide an empirical source to support two of the six major factors proposed by

Herzberg’s two-factor theory that motivate employees (Herzberg, 1968). The

project members are, therefore, able to motivate themselves with a sense of

achievement and expect positive recognition for this achievement if EVM

measurement results indicate a positive performance. Similarly, in a reward-

based project environment, adopting the philosophy of Taylorism theory for

financial rewards to motivate project team members, EVM performance results

will provide justification for reward decisions.

Page 25: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

13

It appears through a review that the application of EVM either adopts or supports

a number of broader project management concepts. Adopting Integrated project

management concept, risk management, constant assessment and

improvement, records keeping, KPIs, team motivation, and so on all fall within

the traditional practice of project management. Through monitoring and

enforcing the project schedule, cost and scope baselines, EVM is able to directly

influence the project team to perform a comprehensive spectrum of parallel

project management functions.

2.4 EVM INDEXES, PERFORMANCE ANALYSIS AND FORECAST

2.4.1 Primary EVM Indexes

Several EVM metrics and terminologies exist, that could be cumbersome and off-

putting (Christensen, 1999), Earned value management metric measurements,

however, are all done in monetary terms (Prasad, Rajkumar, & Rastogi, 2006).

There are, however, three basic metrics that all other EVM measurements are

derived from (Christensen, 1999). They are; the budgeted cost of work performed

(BWCP), budgeted cost of work scheduled (BCWS) and Actual cost of work

performed (ACWP). These terms exist under different names in modern project

management books and articles. BCWS and ACWP are now commonly referred

to as Planned Value (PV) and Actual Cost (AC), respectively. Budgeted cost of

work performed is now referred to as Earned Value (EV).

I. EV is the quantification of the worth of work done to date; in simpler terms,

the value of work done to date (Reichel, 2006). A theoretical description by

(Anbari, 2003), states “When the predefined, tangible criteria for the

milestone are met, the balance of the value associated with the milestone

is earned”. Mathematically, it is derived by multiplying the percentage of

work completed date by the budget allocated to the completion of the work.

It can be expressed at different levels of a WBS and can be represented as

a cumulative or static figures.

Page 26: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

14

II. PV is the budgeted cost of work scheduled to have been completed to date.

(Kim & Ballard, 2002) defined it as the sum of all the planned costs in the

project, or any given part of the project, up to the reporting date. It

requires a well-defined and decomposed scope of work (WBS) as well as

allocated schedules and budgets for work packages (Reichel, 2006).

III. AC refers to expenditures that have been incurred in the execution of

project work packages to date. “It is the sum of what has actually been

spent irrespective of what has been planned” (Fleming & Koppelman,

Using earned value management, 2002).

Other measurements in EVM are a derivative of arithmetic relationships among

these metrics mentioned above. These derivative metrics are classified as either

Performance or forecast metrics.

2.4.2 Performance Metrics

I. Schedule Variance (SV)

“SV measures a volume of work done versus the volume of work planned”

(Vanhoucke & Vandervoode, 2006). SV is the variance between Earned

value and the present value done to date. It is a measure of how much

deviation the budgeted cost of work performed is against the budgeted cost

of work scheduled, i.e. a measurement of actual work accomplished in

relation to planned accomplishments. Owing to the fact, its determining

metrics are expressed in monetary value; schedule variance is also

expressed in monetary values. Its Formula is expressed in both equations

below;

SV = EV-PV

SV = BCWP – BCWS

Page 27: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

15

Figure 5: Project Ahead of Schedule using Schedule Variance (Hinze, 2007)

A derived positive value indicates that the project is ahead of schedule, a

Zero result indicates that the project on schedule and should the value be

negative, it is an indicator that the project is behind schedule. (Biafore,

2007) suggests a risk scale for schedule variances after a project is

determined to be behind schedule:

• Less than 5% shows a low risk but may be an early warning of

potential problems.

• Between 5% and 10% shows a moderate risk and should demand

control actions from the project team.

• Greater than 10% shows high risk and demands that demands swift

and major control actions from the project team.

Percentage schedule variation is derived by

(SV/BCWS) ×100

II. Cost variance (CV)

CV measures the deviations in the budget or cost planned (Yismalet &

Patel, 2018). It is the variance between earned value and actual costs. It

measures the deviation of the budgeted cost of work performed and the

actual cost of work performed, i.e., a measurement of the actual project

Page 28: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

16

expenditure in relation to planned costs to date. It is expressed in

monetary values. Its formula is expressed in both equations below;

CV = EV – AC

CV = BCWP – ACWP

Figure 6: Project over Budget using Cost Variance (Hinze, 2007)

A derived positive value as similar to Schedule various indicates project

spending is healthy and under budget. A Zero result shows that spending

is precise as planned while a negative value indicates the project is over

budget. Risk limits differ on different projects. Projects having narrow

profit margins have lower thresholds for minor variances than those with

higher margins. Some projects having a cost variance of three per cent

would signal significant risks that demand immediate control actions

while other projects may manage this deviation as low risk. These different

perceptions may depend on factors such as geographical economy of a

project and access to finance.

III. Schedule performance index (SPI)

“Schedule performance index measures schedule efficiency and is

expressed as a ratio of earned value to planned value” (Project

management Institute, 2013). This ratio measures the efficiency of task

Page 29: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

17

completion rates in relation to the overall schedule of a project. Its formula

is expressed in both equations below;

SPI = EV/PV

SPI = BCWP/BCWS

An SPI value more than 1 indicates that more work has been completed

than planned, a zero value indicates work completion progressing as

planned and a negative SPI indicates that more work was planned to have

been completed than work actually completed. Control measures adopted

for undesirable SPI are similar to those earlier expresses for schedule

variance.

IV. Cost performance index (CPI)

“Cost performance index measures cost efficiency of budgeted resources,

and it is expressed as a ratio of earned value to actual costs” (Project

management Institute, 2013). This ratio measures the efficiency of costs

already consumed by a project in relation to the overall budget of the same

project. Its formula is expressed in both equations below

CPI = EV/AC

SPI = BCWP/ACWP

A CPI value greater than 1 indicates cost underruns to date. A zero value

indicates a project consumes cost exactly as planned while a negative CPI

indicates more cost overruns in a project. Its control measures are similar

to the control measures for cost variance.

V. Critical ratio (CR)

CR combines both the cost performance index (CPI) and schedule

performance index (SPI) to represent the project status. This indicator seeks

to draw parallels from both the CPI and the SPI in order to provide an overall

indication of a project’s health. The formula is given below;

CR = CPI * SPI

Its interpretation is the same as its indices. A value greater than 1 indicates

good project performance and values lower than 1 indicates poor project

performance

Page 30: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

18

2.4.3 Forecast metrics

These are the metrics a project team monitors and analyses in order to influence

the future behaviour of projects in order to reach its schedule and cost baselines

as efficiently as possible. They are;

I. Budget at completion (BAC)

This is the total budget for every work package scheduled within a project.

It is a monetary expression of the total planned value expected after the

completion of a project. It is derived by the summation all of periodic or

milestone planned values.

II. Estimate at completion(EAC)

This is the expected cost of completion of a project based on cost

performance to date. It is derived by multiple formulas which depend on

the reason the EAC is being generated. When an event occurs, or a future

event that will significantly affect the BAC is anticipated or planned, the

BAC must be reviewed to reflect the changes to the BAC. It is derived by

adding the Actual cost of work performed till date to the sum of the

planned values of work packages left to complete the project. It is derived

from the formula below;

EAC = ACWP + ETC

ETC (estimate to completion) is the additional sum required to complete

the project, i.e., the sum of planned values of work packages left to

complete the project.

An alternative approach to deriving the EAC of a project is to assume that

current spending efficiency to date will continue until the end of the

project. This approach fixes the current CPI to date as the expected

performance for the BAC. It is expressed in the formula below

EAC = BAC / CPI

Where the CPI is 1 or greater, the EAC would be equal to or less than the

BAC respectively. CPIs lower than 1 will equate a higher EAC than the

BAC.

Page 31: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

19

A third approach is to assume that the CPI will not reflect future cost-

efficiency. Future costs are expected to perform as planned. The actual

cost of work performed and the budgeted cost of work performed is used

as an independent variable. This approach is expressed in the formula

below

EAC = AC+ (BAC – BCWP)

A fourth approach is deriving the cost estimate required to complete a

project within its planned schedule with current costs efficiency. By

including the critical ratio, the overall health of the project to date is taken

into account in relation to ACWP and BCWP.

EAC = ACWP + (BAC – BCWP) / (CPI * SPI)

III. To complete performance index (TCPI)

This is the cost efficiency required to complete outstanding project work

packages with the remaining budget. This assumes no additional budget

is available to the project. It is derived through the equation below

TCPI= (BAC – BCWP) /(EAC-ACWP)

The value derived from this equation indicates the CPI that must be

achieved to remain within the BAC. It is useful in determining the

feasibility of achieving the BAC by factoring the amount of work left to

completed and remaining budget available.

IV. Variance at Completion (VAC).

This is a forecast to determine if a project would be over budget or under

budget at completion. It is the variance between BAC and EAC. It

measures the deviation of the expected project cost at completion from the

budgeted cost of all work scheduled in the project. It is derived from the

equation below;

VAC = BAC – EAC

Positive values indicate that the project will be completed under budget

while a negative value indicates the project would be finished over budget.

Page 32: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

20

Table 1: Summary of metrics, measurements and interpretation. Revised from (Prasad ,

Rajkumar, & Rastogi, 2006) 1

1 More EAC formulas added by the author

Basic measurement metrics

Performance metrics

Forecast metrics

Expenditures that have been incurred

in the execution of project work

packages till date

Budgeted cost of work

performed(BCWP)

Earned Vaue(EV)

Planned Value(PV)

Budgeted cost of work

scheduled(BCWS)

Actual costs (AC)

Terminology Formula Interpretation

The costs initially budgeted for all work

completed up to the reporting date

% project complete x

budget

Description

Quantification of the worth of work

done till date

It measures the deviation of the

budgeted cost of work performed

against the budgeted cost of work

scheduled

Schedule variance (SV)

Cost variance (CV)

SV = EV-PV

It measures the deviation of the

budgeted cost of work performed

against the actual cost of work

CV = EV – AC

CV = BCWP – ACWP

CPI = EV/AC

SPI = BCWP/ACWP

This ratio measures the efficiency of

costs already consumed by a project in

relation to the overall budget of the

same project

Greater than 1= Project is under

budget, equal to 1= project is on

budget, less than 1= Project is over

budget

This is the total budget for every work

package scheduled within a project

Estimate at completion

(BAC)

Σ PV

Σ BCWS

Greater than 1= Project is performing

better than planned, equal to 1= project

is performing as planned, less than 1=

Project is underperforming

CR=SPI x CPIMeasures the overall health of a project

according to its planCritical ratio (CR)

EAC = ACWP + ETC

EAC = BAC / CPI

EAC = AC+ (BAC – BCWP)

Actual cost of work

performed(ACWP)

EAC = ACWP + (BAC –

BCWP) / (CPI * SPI)

Cost performance index

(CPI)

SPI = EV/PV

SPI = BCWP/BCWS

Greater than 1= Project is ahead of

schedule, Equal to 1= project is on

schedule, less than 1= Project is behind

schedule

A ratio that measures the efficiency of

task completion rates in relation to the

overall schedule of a project

Schedule performance

index (SPI)

Positive= Project is ahead of schedule,

Neutral= project is on schedule,

Negative= Project is behind schedule

Positive= Project is under budget,

Neutral= project is on budget, Negative=

Project is over budget

SV = BCWP – BCWS

VAC must be greater than or equal to

zero for the project to be healthy

TCPI less than 1 = more funds and less

work; It is easier to complete the project

ETC=EAC-ACWP

expected difference between the a

project's budget and total actual costs at

completion

Variation at completion

(VAC)

VAC= BAC-EAC

Estimate to completion

(ETC)

Additional budget required to complete a

project

EAC must be equal to or less than the

BAC for the project to be healthy

TCPI equal to 1 = Just enough funds to

complete the project

TCPI greater than 1= funds are less

than work left. It is difficult to complete

the project

TCPI= (BAC – BCWP)

/(EAC-ACWP)

Cost efficiency required to complete a

project with no additions to the BAC or

EAC

To completion

performance index (TCPI)

This is the expected cost of completion of

a project based on cost performance till

dateEstimate at completion

(EAC)

Page 33: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

21

Table 2: EVM measurement scenarios and corrective actions. (Prasad , Rajkumar, & Rastogi, 2006)

Redeploy resources to other future

Ahead of Schedule /On Schedule

Corrective Actions

Ensure that Quality is further improvedProductivity higher than estimated

Possible Causes

More resources deployed than necessary

Original planned schedule was very

conservative

Review planned schedule and sustain

performance

Behind Schedule

Use Productivity tools, Retrain resources; get Excessive Rework

Lack of Scope Clarity

Unclear Roles and responsibilities

Skilled resources not available in time

Scope creep is absorbed

Discuss with end users

Clearly define and communicate Responsibility

Try for better skilled resources; invest in

Define scope change process; raise Change

Scope Creep absorbed

Redeploy resources from less to more critical

tasks

Productivity lower than estimated; Wrong

estimates

Closer interactions with team to resolve their

issues; change the team if necessary

Involve senior management team from client's

side to resolve issues

Define scope change process; raise Change

Resources lack requisite skills

Over Budget

Train them; or possibly replace them

Introduce automation/ reusable components;

invest in training

Low productivity of resources

Improve planning and review; Identify team

issues and resolve them

Low utilization (high idle time) of

resources

Under Budget / On Budget

Ensure Quality is not suffered

Ensure cost efficiency does not lead to delay

Delay is caused by client's processes or

indecision

Low utilisation of budgeted resources

Celebrate- for contributing to higher profit

margin to company

Re-estimate remaining Tasks; off-load

resources to other projects

Process automation/ Tools deployed

Original Estimates were on higher side

Lower cost resources deployed

More team productivity than estimated

Use Productivity tools, retrain; get clear

specifications; motivate team

Excessive re-work

Try monitoring the Off-shore- On-shore ratio;

or have right mix of resources

Costlier resources deployed

Improve planning process, re-deploy idle

resources if possible; train for future needs

Unplanned resources deployed

Involve senior management team from client's

side to resolve issues

Delay caused by client's processes

Re-estimate the remaining work and ask for

change request

Incorrect original project Effort estimates

Reduce avoidable Direct, Indirect, Fixed, and

Variable costs

Costly delivery process

Page 34: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

22

2.5 EVM, PROJECT DELIVERY AND CONSTRUCTION PERFORMANCE

(Humphreys & Associates, 2012) stated that EVM is a concept that improves

project visibility and accountability. The decision to use EVM forces upfront

planning and a disciplined approach to management standards. It is primarily

hinged on the premise of comparing work completed against efforts and

resources spent- it seeks visibility and accountability of value of money spent till

date in and assesses the most efficient approach to future spending. Many works

of literature confirm this benefit that EVM presents. With an increased focus on

planning, periodic project progress measurement, it is assumable that

construction performances are improved with the use of EVM. Construction

performance here refers to the delivery of construction projects on schedule, on

budget and the planned scope of work.

As already previously established, the premise of improved construction

performance stems from higher visibility of project activities progress in order to

make control decisions. In a few case studies of real-life projects, problems have

been found in the ability of EVM to accurately visualize project progress. In a

case study of a 26 floor, 20547.72 SQM business tower, (Candidi, Heineck, &

Neto, 2014) demonstrated that the use of EVM was unsuitable for their

construction site. One major reason presented in their report is that forecasting

variability was high. Predication variability was high for both project cost and

duration. They went on to posit that with too much doubtful information, undue

pressure may be put on project managers as they would try to reschedule work

in response to the discomforting forecasts. Also highlighted were disparages

between cost-based monitoring and man-hours based measurements of physical

work. The author believes that these disparages were as a result of EVM taking

into account direct and indirect project costs while man-hours measurement

considering only direct costs of activities. To conclude their report, they suggest

that EVM is best suited for financial progress evaluation as regards project

performance. To obtain better schedule visibility for accountability, they propose

exploring methods to combine the theories of EVM and lean construction.

Page 35: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

23

(Tzaveas, Katsavounis, & Kalfakakou, 2010) Case studied the infrastructure

project ‘Egnatia Odos’, an EU priority highway project of 682km stretching

across Greece. They demonstrated conclusions similar to the ones highlighted

in the previous paragraph. However different to the earlier mentioned case study,

earned schedule (ES) technique was tested alongside EVM. ES was determined

to give better schedule visibility and accurately forecast project schedule

performance. EVM was determined to be reliable for measuring schedule

performance only up until roughly 50% project completion. They also make the

conclusion that EVM’s assessment of schedule performance in their case study

was reliable in detecting underperformances early on in the project.

In an ERP project for a large university in Asia, (Prasad, Rajkumar, & Rastogi,

2006) used EVM to steer a project back to within its schedule baseline. EVM was

effectively used to control scope creep and changes that were negatively affecting

the project schedule. Through offering visibility of the schedule slippage arising

from poor scope management, stakeholders were more disciplined with scope

changes and the project was delivered on time. Despite delivering the project

slightly over budget, they conclude that the intervention of EVM had a generally

positive impact but recommended better stakeholder management and project

communication infrastructure for better use of EVM in the future.

(Valle & Soares, 2004) in a paper reviewing their use of EVM on the Monica

Theme Park project in Rio de Janeiro, referred to project management without

the use of EVM as blind management. Using EVM to deliver the project on time

and within budget, they made the following conclusions:

I. EVM very Sensitive for scope changes and need to be managed

carefully.

II. EVM reports allowed for easy and fast identification of planning and

reporting mistakes.

III. Reporting systems provided consistency in the analysis that provided

support for decision-makers.

IV. EVM assisted during scope change management. It helped keep an eye

on the final budget of the project when analysing providing alternatives

Page 36: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

24

to decide on what activities to reduce specifications to save money in to

accommodate cost overruns in other activities.

They gave a comprehensive list, enumerated below, as necessary to

successfully implement EVM in projects

I. Obtain top-level organization commitment with EVM

II. EVM education and training for all project team members

III. Well defined scope, detailed and identified, with proper WBS and

packages

IV. Scheduling and budgeting according to the WBS

V. Clear Project Responsibility Tables with corresponding descriptions of

such responsibilities

VI. Clear flowchart of activities showing their relationship with project

stakeholders

VII. A Cost and Schedule Control System having a database and data

collection procedures

VIII. Suitable reports related to EVM, well planned, analyzed and distributed

IX. Procedures to consistently analyse and validate information being used

X. Lessons Learned - continuous improvement process.

XI. Changing the name of SPI to progress performance index

With a majority perception from the above cases that EVM helps partially or

sufficiently improve project visibility and performances, there is a common

theme of the need to pay attention to its schedule measuring and forecast

function. Also, to be considered are combining its use with other project

management tools, having a supporting organization/project structure, proper

scope decomposition and management, sound reporting systems amongst

others. With the plethora supporting requirements needed, it is reasonable to

assume that that the contribution of EVM to project performance can only be

exploited if it is adequately implemented. This is aligned with a study by

(Thamhain , 1998), who after analyzing the perceived value of 29 project

Page 37: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

25

management tools and techniques; including EVM, concluded that project

performance is conditional and dependent on how project managers integrate

them into their work processes and need organizational acceptance. With

acknowledged positive contribution to project cost visibility but apathy due to

potential faults in schedule monitoring, it is comprehensible why EVM was

classified as a project management tool with a higher than average level of

potential to improve the performance of projects but with a lower average level

of use. This was in a survey by (Besner & Hobbs, 2006) comparing the perceived

value of different project management tools among project managers. Some

shortcomings of EVM will be discussed later in this chapter.

2.6 PROCUREMENT AND EVM

Cost and Schedule planning: Procurement “is a systematic process of acquiring

goods, services and other facilities to ensure high standards of management for

controlling the project” (Simm & Masters, 2003). It is now evident that EVM is

concerned with the accurate planning and control of cost and schedule

performances on a project. The controlling of the cost and schedules can be

achieved through project procurement, and it is supportive to EVM for

measuring the performance of the project (Lee, 2004). “The delivery dates for

equipment and materials and the work completion dates for contracted works

are placed on the project schedule” (Watt, n.d.). She goes to state that the

eligibility of suppliers is determined by the capacity to perform the work to meet

project requirements. One of such capacities is being able to meet schedule

requirements of the project schedule, and another is cost requirements. In order

to support large, complex projects, late delivery of materials and services

required for critical path activities must be avoided as much as possible using

the procurement contracts.

Procurement contracts can also be a tool for early detection of future schedule

or cost problems on a project. (Watt, n.d.) suggests that the project team, through

procurement documents, can determine the feasibility of particular services or

Page 38: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

26

materials being available when they are needed; and thereof taking control

decisions from the planning phase. In an illustration, a project team may decide

to choose to transport critical activity materials by sea cargo rather than air

freight should it be realised that cost saving could be realized without delaying

the arrival of these materials and impacting the schedule negatively. This

illustration could be vice-versa.

It is paramount that procurement contracts support the cost and schedule

guides of the EVM curve and the EVM curve is a reflection of the contracts

attributed to each activity in the project. The implication is that should

procurement not be efficient in the acquisition of goods and services, efficient

prosecution of project activities become challenging, leading to exposure to

project cost overruns and schedule delays and inevitably, EVM will report

inefficiencies during project execution.

Costs and Schedule monitoring & reporting: To ensure a project plan is developed

with the necessary data to facilitate reporting Earned Value analysis during the

execution phase, it is essential that in addition to the project plan, contracts

explicitly state the required baselines and system of reporting before being

approved. Schedules should have a work breakdown structure for activities.

Activities within the work breakdown structure should show allocated resources

and times when they will be started completed. Having a resource loaded

schedule prepared, facilitates the generation of the project’s S-curve. The S-curve

can thus serve as a reference baseline to measure contract performance in terms

of cost, rate of project consumption and time (EVM). Having a resource loaded

schedule included in contracts also serves the purpose of showing the

interdependence of activities and resources in a construction project (Sears,

2008). Showing interdependencies assists the Project management team to

determine the feasibility of the overall project schedule and cost baselines on the

S-curve. On projects, determining real progress for work packages can be

difficult, but is crucial for ensuring earned value analysis is accurate and

meaningful (Lukas, 2012).

Page 39: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

27

In reporting systems, contracts need to express the method of measuring

progress and performance. While multiple approaches to performance

measurements exist, a suitable reporting method should be decided on, taking

into consideration, the complexity of activities and dependencies within the

project, type of data to be collected and among other project-specific factors.

Accurate reporting systems, according to (Lukas, 2002, Cited in Lukas 2012)

include:

I. Units completed: Used for simple, measurable work where each

activity consume equal effort.

II. Incremental milestones: Progress is reported only through sequential

completion of set milestones.

III. Start to finish: Suitable for capturing the only the start and

endpoints of activities and nothing in between. Progress is measured

either with 0/100 rule, 50/50 rule or 20/80 rule for slightly longer

duration tasks.

Other contract reporting mechanisms exist in the event that no empirical

information is available.

IV. Expert opinion: Relies heavily on the subjective opinion of the

reporting person and hence a potential source of disagreement.

V. Level of effort: Assumes that EV=PV as completion of such activity

is solely dependent on the level of effort imputed.

In practice, however, project managers are likely required to use one or both of

the following methods

VI. Combination techniques: Adopted for complex work, interrelated

activities with different progress measuring systems occurring over

extended periods.

VII. Weighted Units: Adopted for works that occur over extended periods

with multiple subtasks having different measuring units. Monetary

values or level of effort of each subtask is weighted and then

Page 40: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

28

converted to a single measuring unit reflecting percentage

completion of its summary activity.

It is crucial that the most suitable reporting system be adopted for each project

activity. For instance, floor tiling can be measured and reported using units

completed as it easily measurable in terms of a wall or floor area completed.

Concrete placement can only be measured with a start to finish system. It is

logical to measure overall projects efficiency using weighted units. Inaccurate

progress reporting can prevent detection of early warning signs and thus must

be avoided (Sadhu, 2015).

2.7 EVM AND PROJECT MANAGEMENT INFORMATION SYSTEMS

Software and Project management information systems (PMIS) were

introduced to assist project managers to perform their tasks better. They are

aimed at increasing the efficiency of project managers. They are used across

all phases; in the case of EVM, from the planning phase up until closing.

(Gartner Research Group, 2008) mentioned that the use of PMIS does not

guarantee project success, but they are still instrumental in the construction

industry and become mandatory in most construction projects.

According to (Kraemer, 2018), Software and their database systems can assist

project managers to gather, organize, store, analyze and generate reports on

data obtained from projects. With these, project managers can keep track of

the schedules and cost of project activities and likewise follow up on control

decisions. Leveraging on this, EVM has become more effective with better

monitoring and oversight possibilities. When high-quality software and

information management systems are used correctly (Raymond & Bergeron,

2008) posit that the chances of project success can be increased as much as

75%.

Project management software was first introduced in 1977 when the software

companies of Oracle and Artemis were founded and two years later in 1979,

the introduction of Scitor. The software offered during this period were mostly

Page 41: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

29

used for major Government projects, and it was not until the 80s and 90s; a

period that experienced the introduction of personal computers and

networked facilities did project management software become easily accessible

and widely available (Azzopardi, n.d.). In 2010, software having cloud-based

functionalities were introduced, allowing projects to be implemented through

virtual teams working remotely (Yves, 2017). He goes on to mention that the

current era of ‘the internet of things’ is driving the demand and supply of

tailor-made software solutions for organizations and projects.

Numerous software are available on the market today that can support the

use of EVM on projects. These software are diverse and heavily fragmented.

Some focus on schedule; others focus on business intelligence, while others

focus on cost. According to Pinnacle management, to have comprehensive

software support for EVM, an Earned Value Management System (EVMS) has

to be set up. An EVMS integrates schedule, cost and business intelligence

software engines into a unified system using individual working parts that

collectively complement each other to support and enhance the use of EVM.

Some popular software engines integrated into EVMS listed by Pinnacle

management include Microsoft Project, Primavera P6, Deltek open plan,

Safran and Artemis for scheduling; Deltek Cobra, EVMSforProject and

Hexagon for costs; and finally Encore Empower, Deltek Winsightand Deltek

PM compass for business intelligence. The vast array of software options and

the need to integrate them together in order to support EVM effectively is an

indication of the dependence project managers and controllers have on

information technology infrastructures for their specialized duties. This is

mostly driven by the need to improve work productivity on complex projects,

filter for relevant information needed run projects easily, communicate with a

large number of stakeholders, managing remote teams, improve project skills

maturity amongst other reasons.

Page 42: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

30

Figure 7: EVMS system2. Revised from (Brunton, 2016)

2.8 CRITICISMS/LIMITATIONS OF EVM

Numerous literature review suggests that project managers struggle with

adopting the EVM method. As mentioned earlier in this chapter, (Fleming &

Koppelman, 2006) stated that in its earliest form, EVM confused project

managers with complicated terminologies and never understood the real benefit

it offered in the field of project management. Despite several re-iterations,

simplified definitions, inclusion in most Project management Institutional

training programs, (Thamhain , 1998) mentions the following problems project

teams face with adopting EVM. They are;

I. EVM is perceived as a threat owing to its demand for transparency,

II. Integration of EVM into business processes is low

III. implementation is expensive, time and effort-intensive.

In using the EVM tool, a report by (Lukas, 2012), he listed the following as

common mistakes that influence the ineffectiveness of EVM. They are;

2 Business intelligence added by the author.

Page 43: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

31

I. No documented requirements;

II. incomplete requirements;

III. WBS not used

IV. Incomplete WBS

V. Plan not integrated (WBS-Schedule-Budget)

VI. Incorrect Schedule and/or budget

VII. Change management not used or ineffective

VIII. Cost collection system inadequate

IX. Negative management influence and/or control.

In his report, he explains the dangers of not having a planned value derived from

a well-defined scope and WBS; which serves as the PMB, would lead to a healthy

project that does not deliver on project quality requirements. This is supported

by (Kopelman & Fleming, 1999) where it is suggested that the absence of a work

breakdown structure may lead to inaccurate data in relation to costs and

timeframe of the project as a whole. (Lukas, 2008) also indicates the danger of

relying solely on project invoices to calculate AC. Projects often have invoices

that lag behind their corresponding work, which can cause misleading

calculations. In another explanation, he expresses concern regarding

uncontrolled scope creep and effective change control processes. Scope creep

easily influences the schedule and cost baselines of a project without being

captured in the scope of work planned. To avoid reporting false overruns for

activities on which contingencies are spent, but covered with a risk budget, he

counsels change management to update the baselines of the project to reflect the

changes since contingencies are still within the project cost baseline.

(Howes, 2000) suggested concerns regarding absolute dependence on EAC

values. He explains that project works in the future may be entirely unrelated

for project work completed up until the time of forecast assessment. He

determines that future performance is not automatically an indication of past

cost performance. While the author agrees to the logic regarding this theory, he

does not concede the fact that EAC forecasts are misleading. Multiple formulas

exist for estimating this metric and only those that make use of the CPI as an

Page 44: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

32

input factor in calculating the EAC are prone to be misleading. (Howes, 2000)

also posits SV does not take into consideration, sufficient relevant information

in its calculation. He explains that SV does not incorporate time or logical

sequence of activities in the future when forecasting. He describes SV as a

scheduling metric based entirely on cost performance. This is especially

problematic when through the calculation of the SV and SPI, an accumulation

of ahead of schedule non-critical activities eclipse critical activities running

behind schedule. EVM does not distinguish or prioritize schedule performance

of critical or near-critical activities which bear higher risks of influencing project

failure. To conclude, he proposed an alternative tool he calls the Work Package

Method (WPM) where he separates a project into a series of discrete work

packages. He splits work packages that are unconnected through time or

sequence. (Valle & Soares, 2004) recognising deficiencies in schedule measuring,

proposed that the name should be changed to progress performance index and

not left as SPI. They suggest that changing the name serves to portray better the

scope of data the metric calculates.

(Ghorbani, 2017) draws attention to the unreliability of schedule performance

measurements beyond two-thirds of the project. She further explains that

schedule slippages are difficult to detect as project activities begin to wind down.

This is because SPI is based on the premise that at the end of projects, SPI is

equal to 1 irrespective of the time they are completed. For this, it is possible to

have a healthy SPI of 1, even beyond the planned completion date of a project as

long as all scheduled activities are registered as completed. Citing references

from the United States Department of Defence guidelines, she suggests that EVM

should not be used as the only measuring tool to assess project schedule status.

While numerous works of literature suggest that EVM implementation is

expensive and data gathering is time-consuming, (Custer, 2009), dismisses these

this criticisms citing that information gathering and reporting already

continuously carried out for legacy reasons and that the data need for EV

calculations already exists in cheaply available software. He posits that the

demand for automation of the entire EVM (EVMS) is the reason for high

Page 45: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

33

implementation costs. Citing that data in estimating scheduling and financial

software are adequately organised to suit their individual functions, he suggests

that key or relevant information can be extracted and compiled in EVM formats

and then stored in into an EVM repository that can be set up on inexpensive

database systems; making reference to Microsoft Excel spreadsheets as one of

such databases. The author expresses caution towards this approach. This is

because this process has attempted to reduce the cost of implementation, but

brings additional work of extracting and organising data from and between

software and database systems. Data extraction can only be done by a person

with adequate training and experience in order to be able to identify and correlate

multi-dimensional data from different software stored in different metadata

formats. This may ultimately result in project team training costs or slower

reporting. This could be in contradiction to (Gershon, 2013), that emphasizes

the importance of good and punctual information for EVM to work correctly.

Page 46: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

34

3 METHODOLOGY

3.1 INTRODUCTION

(Potter, 1996) defines methodology as methods and processes used to gather,

analyze, and present information to reach a set-out objective; it describes how

specific tools can be adopted to achieve the aforementioned. The literature review

from chapter two has presented the theoretical background that is used to

answer the research questions one and two, while this methodology presents the

approach to answer question one and validate the author’s proposals in this

thesis.

This chapter describes and discusses; the research design, sample size and

selection, the data collection methods used and their corresponding data

collection instruments, data management and analysis procedure as well as

steps that will be taken to ensure validity and reliability during the study and

measurement of variables.

3.2 RESEARCH PHILOSOPHY AND DESIGN

Research philosophy reflects the development of knowledge and the nature of

knowledge; it explains the thought process of the author and how it affects the

way research has been carried out (Saunders, Lewis, & Thornhill, 2009).

According to (Sekaran, 2003) a research design shows the details of the study in

relation to the purpose of such study, types of investigation, and the extent of

author interference, measurement and measures, unit of analysis, sampling

design, data collection method and data analysis, are integral to research design.

This research is approached mainly in two ways; inductive and deductive. The

inductive approach aligns with qualitative techniques while deductive approach

aligns with quantitative methods.

To analyse the best way to enhance the adoption of EVM, Interpretivism method

is adopted. This is owing to its philosophy that individuals are different, complex

and interpret the same objectivity in varying ways. It is established on

Page 47: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

35

observation, opinions and concepts. Interpretivism acknowledges that research

takes place in a complex and dynamic and unique environment (Saunders,

Lewis, & Thornhill, 2009). (Collyer & Warren, 2013) established projects occur

in dynamic environments, hence the suitability of Interpretivism.

Instruments

I. Interviews: For this, semi-structured interviews are to be conducted. This

is to allow respondents to give untethered opinions regarding the subject

matter, which may also be influenced by lived experiences, feelings and

attitudes. While responses may be perceived as generalised, (Saunders,

Lewis, & Thornhill, 2009) posit that the qualitative approach does provide

an interpretive understanding of a phenomenon within a particular

context - in this case, the interviewee. Supported by (Creswell, 2014),

understanding of an individual’s lived experience is vital understanding

the psychology of a research problem. In addition, Interviews offer the

author the opportunity to adapt questions, clarify the questions by using

the appropriate language, clear doubts and establish rapport and probe

for more information (Sekaran, 2003)

II. Surveys: Measuring the attitudes and constraints of implementing EVM,

quantitative analysis is adopted. For this, a questionnaire is the tool for

information gathering. Questionnaires are one of the most popular means

of collecting data, and questionnaires are often closely associated in

conjunction with research (Rowly, 2014). “They are a valuable method of

collecting a wide range of information from a large number of individuals,

often referred to as respondents” (Menta & Roopa, 2012). The advantage

of using a questionnaire is that it offers the author statistically relevant

data to make logical inferences from.

Page 48: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

36

3.3 SAMPLE POPULATION

A population of 100 respondents is expected for this survey. Respondents will

have formal education in project management or a similar field. Some

respondents would also hold project management certifications by either PMI,

Prince2, IPMA or have at least three years’ experience. This satisfies the condition

that respondents have either received formal project management training or

have sufficient professional experience or have both in order to be familiar

enough with the subject matter.

The questionnaire has three parts. The first part seeks to profile the respondents’

level of education, experience and role within their organisation. It is intended to

ensure that only responses from respondents who meet the above-mentioned

criteria are recorded. Part B measures respondents’ level of knowledge and

experience in respect of the subject matter “Earned Value Management”. Part C,

leveraging on opinions in addition to experience and knowledge, measures

responses to factors the author believes can assist the organisational/project

implementation EVM. Part C is measured with a Likert scale.

3.4 SAMPLING PROCEDURE

Random sampling is used leveraging on the local PMI chapter and LinkedIn

communities of practice for project managers. Communities of practice are

online forums with members having specific work roles in common. The

motivation of communities of practice is to master their discipline, learn about

the speciality, and solve problems together (Garfield, 2016). They achieve this

through creating dialogue, ideas exchange, information and advice sharing as

well as providing answers to questions posed by other members. Communities

of practice offer the author, the advantage of agglomerating project managers

from more geographical locations into a virtual pool of knowledge area-specific

respondents; thus providing access to a broader collection of project managers

as well as doing so quickly and inexpensively. Questionnaires would also be

distributed among project managers within the Author’s network.

Page 49: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

37

3.5 VALIDITY AND RELIABILITY OF THE RESEARCH INSTRUMENT

3.5.1 Validity

To certify validity, the questionnaire is developed and given to two judges to

review each question’s relevance to the study. This is to achieve a consensus

estimate, as suggested by (Stemler, 2004). A consensus estimate measures the

extent to which experts agree with the development of the questionnaire. To

measure this, a content validity index will be derived by dividing the number of

validated questions by the total number of questions. (Amin, 2005), posits that

a figure not less than 0.7 is sufficient for a validity test.

3.5.2 Reliability

To certify the reliability of the questionnaire, a pre-test was done on ten

respondents who did not participate in the final survey. Their responses were

analysed using Cronbach’s Alpha Reliability Coefficients function contained the

statistical package for social scientists (SPSS) computer program. A Cronbach’s

alpha reliability coefficient of above 0.7 will be acceptable (Sekaran, 2003).

N %

Cases Valid 10 100.0

Excludeda 0 .0

Total 10 100.0

Reliability Statistics

Cronbach's

Alpha

N of

Items

.729 5

3.6 DATA ANALYSIS TECHNIQUE

3.6.1 Analysis of quantitative data

Data analysis from the survey is carried out using SPSS. Frequency counts and

percentages are used to analyse the respondents’ demographic characteristics,

Page 50: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

38

and the mean and standard deviation will be used to analyse the spread of the

average opinion of respondents.

3.6.2 Analysis of qualitative data

Owing to the fact that the author was unable to find a suitable EVM expert who

was willing to be interviewed within the limited time-frame allowed for the

preparation of this thesis, although planned, no interviews were conducted.

Consequently, no qualitative analysis is done.

3.7 MEASUREMENT OF VARIABLES

Data on the respondent’s views and opinions about EVM will be obtained using

scaled variables from a self-developed questionnaire. A five-point Likert scale of

a= strongly agree b= agree, c= neutral d= disagree and e= strongly disagree is

used to collect respondents’ experience and opinions regarding the proposed

factors.

Page 51: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

39

4 DATA ANALYSIS

4.1 INTRODUCTION

In this chapter, the results of the research and analysis are presented in

tables. The main objective of the survey is to measure different soft factors

proposed as influential to a project or organisational implementation of EVM.

While very limited literature exists regarding soft factors that may influence

EVM, the author adapts the presentation of (Mullaly, 2018) where he lists

different possible orientation type roles that PMOs may choose to pursue in

order to adapt to different alternative futures. In addition, the author also

takes into consideration, literature reviews and discussions in different EVM

communities of practice on LinkedIn. These factors include;

I. Flexibility to scope changes

II. Manipulations and error reporting

III. control & standardization

IV. Punishment contractors

V. IT project support

4.2 QUESTIONNAIRE RETURN RATE

The survey had a target sample size of 100 formally trained or experienced or

both; project managers, team members, portfolio managers and project

consultants. Seventy-three replies were received and accepted, which is a 73%

response rate. While this falls slightly short of the 75% response rate

recommended by (Babbie & Mouton, 2001), the time restriction regarding

submission of this dissertation did not permit more waiting time to receive more

responses to reach this threshold.

4.3 QUESTIONNAIRE ANALYSIS

Part A of the questionnaire intended to find out the profile details of the

respondents. Features include their role in their organisation, size of their

Page 52: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

40

organisation, level of education and project management related experience.

Results are listed below:

I. Respondents’ job roles

Frequency Percentage

Project Manager 33 44.4

Team member 24 33.3

Portfolio Manager 0 0

Consultant 16 22.2

Total 73 100

From the responses, most of the respondents are either project managers or team

members. These groups account for close to 80% of respondents. This can

suggest that survey respondents are either directly involved in executing and

reporting projects or those who take responsibility for delivering them. A small

population of respondents are consultants.

II. Staff size of respondents’ organisations

Frequency Percentage

0 – 10 people 17 22.2

10 – 49 people 24 33.3

50 – 249 people 8 11.1

Over 250 people 24 33.3

Total 73 100

Two-thirds of respondents work in organisations having less than 250 members

of staff. The European Commission classifies these firms as Small and Medium-

sized enterprises. SMEs are more likely to carry out their projects with a close,

personal and professional relationship. For example, having a closer relationship

with clients for requirements gathering and also may have contractors they are

Page 53: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

41

comfortable working with. They may be better suited to capturing client’s

baselines and communicate better with their contractors.

III. Respondents’ level of education

Frequency Percentage

Bachelors 8 11.1

Masters or higher 48 66.7

PM certification 17 22.2

None 0 0

Total 73 100

All respondents reported having some level of project management education.

More than 80% of respondents reported having an education. This fulfils the

requirement for participating in the survey; hence, no one was excluded. More

than 80% reported specialised or advanced levels of education. It is therefore

assumable that most of the respondents have an appreciable knowledge of

project control, which may include some proficiency in EVM.

IV. Respondents’ Project management experience

Frequency Percentage

0 – 3 years 17 22.2

3 – 5 years 32 44.4

5 – 7 years 24 33.3

Over 7 years 0 0

Total 73 100

In addition to the level of education, the number of years of experience plays

adds to the level of knowledge of project managers. Close to 80% of respondents

Page 54: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

42

have at least three years of project management practice suggesting moderate

knowledge to make informed or semi-informed opinions regarding the subject

matter area.

Part B of the questionnaire is intended to profile the knowledge and experience

of the survey respondents, specifically in EVM.

V. Respondents’ level of knowledge of EVM

Frequency Percentage

Elementary 32 44.4

Working Knowledge 41 55.6

Expert 0 0

No knowledge 0 0

Total 73 100

With all respondents’ reported having project management education and

varying years of experience, some knowledge of EVM is to be reasonably

expected. However, reported knowledge among respondents appears almost split

between working knowledge and elementary knowledge. Only 5% separates the

two knowledge classifications. No expert knowledge was reported. This validates

numerous literature stating that the knowledge and adoption of EVM among

project managers remain limited. This will significantly hamper a quicker rise to

the performing level of project teams in the process posited by (Tuckman, 1965).

VI. Respondents’ method of tracking projects

Frequency Percentage

EVM alone 0 0

Network-based

techniques

16 22.2

Combination of both 41 55.6

Page 55: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

43

None 16 22.2

Total 73 100

A little above half of the respondents reported having used EVM, albeit only in

combination with other schedule tracking tools. This as well means that slightly

less than half of respondents have never used EVM in professional practice.

While its use with other schedule tracking tools is advised by (Ghorbani, 2017),

use among respondents on their projects is still low, even thirteen years after

(Besner & Hobbs, 2006) made this statement.

VII. Respondents’ experience with EVM

Frequency Percentage

Positive 41 55.6

Neutral 0 0

Counter productive 0 0

Never used 32 44.4

Total 73 100

All respondents that indicated past or current use of EVM unanimously confirm

that their experience with EVM is positive. It is also curious that despite this

acknowledged advantage that EVM presents both by respondents and numerous

literature, slightly less than half of the respondents reported never used it. The

author considers 44% non-use an unusually high percentage for a tool with

confirmed benefits in controlling projects.

Part C of the survey intends to indirectly measure the factors enumerated at

the beginning of this chapter

Using a five-point Likert scale was applied to survey responses; 1 representing

“strongly agree” to 5 representing strongly disagree. Using this ranking scale, a

mean value and standard deviation of each factor were derived as part of the

analysis. From the linguistic coding of the questionnaire, a mean closer to 1 and

Page 56: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

44

2 suggests that the measured principle in current practice, negatively influences

the sample population’s use, knowledge or opinion of EVM. A mean closer to 4

and 5 suggests vice-versa. The table below shows the response of survey

respondents.

VIII. Standardisation of respondents’ project organisation

Frequency Percentage

Fully standardised 8 11.1

Partially standardised 41 55.6

Not standardised 24 33.3

Total 73 100

The data suggests close to 90% of respondents reported partial or no

standardisation of processes in their organisation. With this, according to

(Monteiro, Santos, & Varajao, 2016), respondents may face difficulties

implementing project management tools and methodologies aimed at improving

efficiency and effectiveness.

IX. Poor Stakeholder

participation

Valid 73

Missing 0

Mean 2.14

Median 2.00

Mode 2

Std. Deviation .346

Range 1

Page 57: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

45

Frequency Percentage

Strongly agree 0 0

Agree 63 85.7

Neutral 10 14.3

Disagree 0 0

Strongly disagree 0 0

Total 73 100

As already posited by (Prasad, Rajkumar, & Rastogi, 2006), poor stakeholder

involvement causes poor scope management. Should there be constant moving

baselines regarding project scope; that always influences schedule and cost, the

use of EVM may become defeated and unnecessary. This is because EVM is more

worthwhile where there is a relatively constant long-term baseline to measure.

With a long-term baseline, control decisions can be taken with better confidence

and made for the long-term benefit and stability of a project. With 85% of

respondents suggesting poor stakeholder participation, it is reasonably certain

that not all requirements in the project baseline would be captured during the

initial and planning phases. While better stakeholder management has been put

forward by earlier literature, additionally, the author suggests that the

implementation of EVM should include measuring the flexibility of a project to

accommodate changes essential to deliver quality success. This, in combination

with changing stakeholder requirements; analysed later in this chapter, are

proposed as two factors to consider for considering scope flexibility.

Page 58: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

46

X. Error reporting

and data

manipulation

N Valid 73

Missing 0

Mean 2.27

Median 2.00

Mode 2

Std. Deviation .692

Range 2

Frequency Percentage

Strongly agree 0 0

Agree 63 85.7

Neutral 0 0

Disagree 10 14.3

Strongly disagree 0 0

Total 73 100

If linked to the almost 90% reported partial and or no form of standardisation, a

connection with error reporting and data manipulation can be assumed. While

the mean of this factor is closer to two, a standard deviation bordering between

one and two standard deviations of the mean suggests that opinions are more

spread out regarding this factor, especially when the only other response is a

disagreement. Still, 85% of respondents agree that data presented for EVM

analysis may be unreliable. It is imperative that this problem; which would

further be discussed in chapter 5, be addressed to protect the integrity of results

derived from earned value management analysis.

Page 59: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

47

XI. Changing client

expectations

N Valid 73

Missing 0

Mean 2.29

Median 2.00

Mode 2

Std. Deviation .456

Range 1

Frequency Percentage

Strongly agree 0 0

Agree 52 71.4

Neutral 21 28.6

Disagree 0 0

Strongly disagree 0 0

Total 73 100

Project management methodologies do not only encourage capturing

requirements before commencing execution of a project but also acknowledge

and encourage stakeholders to change the scope of a project if those changes are

necessary for end satisfaction and acceptance. As is common practice, it is

expected that as high as 70% of respondents would agree to this factor. Unlike

poor stakeholder management mentioned earlier, changes may not necessarily

be as a result of poor requirements gathering; changes may arise from

uncertainties in the planning process, thus are unable to be accurately

incorporated into project performance baseline. Traditional project management

allocates contingencies and management reserves for these risks and

uncertainties. (Lukas, 2008) Advice that projects’ EVM curve be plotted

excluding these reserves and only be updated when these set-aside funds are

Page 60: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

48

spent. The problem here again is that these funds need to be measured to

monitor their trends and efficiency. Knowing their trends and efficiency can be

instrumental in determining if a project is flexible enough to accommodate any

future change request. Information gotten from this may help in prioritising

change requests. Flexibility is discussed in chapter 5.

XII. IT Project Support

N Valid 73

Missing 0

Mean 2.00

Median 2.00

Mode 2

Std. Deviation .764

Range 2

Frequency Percentage

Strongly agree 21 28.6

Agree 31 42.9

Neutral 21 28.6

Disagree 0 0

Strongly disagree 0 0

Total 73 100

This is the only measured factor that had some respondents report strongly

agree, albeit only 29% reporting this. EVMS was introduced in chapter 2.

However, EVMS can be fragmented and expensive to set-up. Being an

unavoidable expense to be incurred, it is paramount that the choice of engines

running within the EVMS is optimised as much as possible to suit individual,

Page 61: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

49

organisational objectives. This is because the author believes organisations differ

in size, project management skill maturity, project team network, among other

factors.

XIII. Punishment tool

N Valid 73

Missing 0

Mean 2.56

Median 2.00

Mode 2

Std. Deviation .726

Range 2

Frequency Percentage

Strongly agree 0 0

Agree 42 57.1

Neutral 21 28.6

Disagree 10 14.3

Strongly disagree 0 0

Total 73 100

Dividing opinions and with an appreciable population neutral, is expanding the

use of EVM to include contractor appraisals. There still exists a dichotomy of

motivation to implement EVM between contractors and project managers. (Song

& Shalini, 2009) stated that contractors do not consider the contract type when

deciding to implement EVM while clients are more inclined to readily adopt EVM

in cost plus fee contracts. (Nkiwane, Meyer, & Steyn, 2016) Reported the cynic

attitude contractors to hold towards using EVM for controlling fixed-price

Page 62: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

50

contracts on milestones-based payment contracts because they are usually not

familiar with the tool. The author believes that for impartiality and transparency

in the project environment, EVM needs to be equally understood and bought-in

to by all concerned stakeholders. There are also numerous influencing issues to

consider when demanding strict accountability from project contractors that

would be discussed later.

Page 63: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

51

5 RECOMMENDATIONS AND CONCLUSION

5.1 FLEXIBILITY TO SCOPE CHANGES

Real-life projects and Modern project management methodologies accept and

encourage scope changes, especially if such changes are necessary for crucial

project success. Existing literature on EVM suggests the proper control

processes for scope changes and discourages scope creep. (Lukas, 2008) wrote:

“Change management must be addressed in the project plan, and includes the

procedure for handling scope and variance changes, the forms to record and

evaluate change requests, the review and approval process for changes, and the

process to ensure changes are incorporated into the current plan, so the earned

value calculations remain relevant.”

(Totin, 2012) Mentioned the following terminologies for project controllers to be

aware of when involved with Earned value. The author believes these terms are

necessary to be understood for EVM to remain relevant despite scope changes.

They are:

Original Contract Value

This the planned cost of construction. Depending on the type of delivery method,

it may be synonymous with the contractor’s bid price. The author believes this

is likewise synonymous with planned value and budget at completion value

Approved Changes to Date

This is the sum of all changes that result in money added to the contract. Since

these changes are crucial for project success, (Lukas, 2008) suggests the original

EVM baselines should be updated with the time and cost additions from these

changes. The sum of these costs (approved changes + original contract value),

becomes the “committed contract value”. Aligning with Lukas’s posit, the author

Page 64: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

52

believes the committed contract value should become the revised EVM cost

baseline.

Contract Time

This is the initial amount of time planned to complete the project.

Days Added

This is the amount of time added to the contract necessary to execute work as a

result of changes. This should, in addition to contract time, should become the

new schedule baseline.

Existing literature, however, is silent regarding monitoring the ability of a project

to be flexible to scope changes. This is amongst other factors, mostly dependent

on cost. Projects have a limited management reserve set aside for unknown risks

such as scope changes. These changes can only be possible if contingency funds

are left to accommodate these changes. For this reason, management reserves

need to be monitored just as carefully as the project cost baseline. For this, the

author proposes a different S-curve to be plotted for the management reserves.

This will show early on; how much reliance is put on these management reserves.

This can be a basis for revisiting the project scope, and costs plan to check for

errors.

Most importantly, this curve will give early warning signs of the project’s future

flexibility to adapt to cost changes, scope creep and scope additions further along

the project duration. The principle is similar to the project’s EVM curve; with

SPIs and CPIs of less than one indicates the project is less flexible to scope

changes or cost overruns. A TCPI greater than one should suggest to the project

team that there is not sufficient management reserve left to accommodate

potential future risks. This would be helpful, especially in the case of target price

or Guaranteed maximum price contracts. Owing to the fact that unlike project

direct and indirect costs that are associated with specific project activities

occurring at particular dates, management reserves do not have related tasks. It

Page 65: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

53

is therefore proposed that the schedule axis on the s-curve for management

reserves be planned using milestone intervals. This is because milestones are

not project activities themselves but checkpoints that embody completion of

groups of summary activities. Traditionally, they are periods when reviews are

done for completed activities, and risk analysis is done for future activities. It

may be measured with a reserves milestone performance index. With the

management milestone performance index, project teams can have quantifiable

data to demand disciplined and timely scope changes from other project

stakeholders.

5.2 ERROR REPORTING AND DATA MANIPULATION

“The goal is to turn data into information and information into insight.” – Carly

Fiorina, however, Errors using inadequate data are much less than those using

no data at all.” – Charles Babbage

EVM loses its reliability once data analysed is wrong or manipulated. The author

proposes that PMOs in which the following factors exist, bear more risks of

unreliable data.

• Absence of consistency and standardisation,

• Not enough time allowed for data collection,

• Confusion on what and how to measure,

• Punishment oriented monitoring,

• Promotion of individualism, private interests and subjective appraisals,

• Setting vague baselines.

While measuring techniques have been introduced earlier in Chapter 2 of this

research, these techniques are classified in numerous Project management

literature as discrete, apportioned and level of effort.

Of the three, apportioned techniques are subjective opinions and can be sources

of individualism, biased appraisals and difference in reporting styles

Page 66: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

54

(communication), especially considering expert judgement. Being only an

estimate, it is effectively a guess subjective to the objectives and knowledge level

of the appraiser or appraising team. The danger this poses is that without

quantifiable data, the status of critical or near-critical activities with very limited

float can be poorly-measured and intentionally or unintentionally

miscommunicated. Accurate work performance insights may be impaired until

it is too late to make control decisions. This effectively defeats the benefit of early

warning signs EVM presents. This can cause loss of control; slipping from

proactive decision making to reactive decision making.

All three categories of measurement reporting may be adversely influenced in

complex projects having a plethora of data that consumes considerable time and

effort for sorting at all times during project execution. Without clear guidelines

on what data is necessary, timeliness requirement of such data, irrelevant and

untimely data presents a risk to the integrity of EVM results.

To alleviate these problems, the author suggests;

Expert judgment measuring and reporting technique should be limited to short-

duration project activities. This is to ensure that warning signs for difficult to

measure activities; which may affect subsequent activities, are detected early.

Despite the reliance on the qualitative judgement of the reporting person or team,

errors can be spotted early if the scheduled finish date is not far from the

reporting date, yet enough work is not perceived as close to completion. This

allows for swift and frequent review of activity performances that are measured

anecdotally. Reducing the duration of activities where possible decreases the

risks from error reporting. The threshold of ‘short duration’ may be decided by

the project team taking into consideration, total project duration, average total

float of each activity and unit of time measurement for activities. The author

strongly advices against any iteration of qualitative measuring for critical and

near-critical activities. Additionally, the author proposes that a project scope

Page 67: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

55

should be decomposed to the level where most activities are short to medium-

term in duration.

A second proposal is having a predefined measurement basis for apportioned

reporting. This can be developed by project facilitation or focus groups before the

commencement of the project. This should allow for an all-stakeholder

understood and collaborative rationale for reporting, thus reducing the

possibility of data manoeuvring for personal objectives. A system that objectively

assesses subjective measurements. This may be achieved by taking into account

the completion of lower-level tasks. Lower-level tasks may be assigned weights

that will collectively sum of to the task completion rate of 100%. For a discrete,

level of effort, 0/100 and 50/50 techniques; units of measurement, the

technique to be used and reporting level should be prescribed before the project

commences.

Participating stakeholders may each have consistent internal measuring and

reporting processes, the existence of various techniques means that units,

approach and processes may differ among stakeholders. It is, therefore, once

again, essential to define project-specific measurement techniques or align

processes with that of other stakeholders. This requires repetitive work for each

project. An alternative to this repetitive proposal is to have a comprehensive

legislated, standardised measurement and reporting guideline book that can be

referred to, to form the basis of any project reporting. What the author suggests

here is similar to the German HOAI, which is referenced to for the calculation of

architects and engineers service fees.

For data integrity issues, it is pertinent to EVM that standardised rules for

activity measurement and reporting should be prepared, understood and aligned

among participating stakeholders. This may be gotten by developing an AEC-

EVM general guideline book of standards or best practices or be expressed in

project-specific documents such as contracts and project management manuals.

Page 68: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

56

Punishment oriented monitoring would be discussed later in this chapter

5.3 STANDARDIZATION OF PROJECT MANAGEMENT PROCESSES

The most apparent approach to achieving standardisation is the establishment

of a Project management office.

(Monteiro, Santos, & Varajao, 2016) Stated that the Project Management Office

(PMO) “is an organisational structure created in order to promote and improve

project management practice, by adopting appropriate methodologies to achieve

high levels of efficiency and effectiveness”. A PMO performs centralised oversight,

supporting and consulting duties for projects. Various models of how project

management offices should be set up exist; however, the design of each model

depends on the objective of the PMO. However, for alignment with EVM,

controller PMO models are most suited. The models below are listed according

to the services they offer;

I. Supporter model (Desouza & Evaristo, 2006)

Serves as a project administrator, identifying risks, providing project

status, raising possible issues and keeping project records.

II. Supporter model (Unger, Gemünden, & Aubry, 2012)

They provide team training and steer project team members towards

working with Project management standards and methodologies.

III. Information management model (Desouza & Evaristo, 2006)

They track and report the progress of the projects for reviews and

forecasts. They are always well informed of the current status of their

projects

IV. Knowledge management (Desouza & Evaristo, 2006)

They are the source of the best practices, project expertise, training and

mentoring project team.

V. Coaching model (Desouza & Evaristo, 2006)

They are focused on constant improvement through the enforcement of

project management methodologies in an organisation.

Page 69: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

57

VI. Federated PMO (Gartner Research Group, 2008)

Consists of a corporate PMO and lower-level division PMOs where the

corporate PMO is responsible for methods, training, and tools while the

lower division PMOs are responsible for project reporting, oversight, and

delivery.

VII. Project management Office (Gartner Research Group, 2008)

Seeks to establish a consistent baseline of processes and to use formalised

project tracking and reporting systems.

VIII. Project control office (Crawford, 2010)

This handles large and complex single projects. This PMO is dedicated to

one project at a time.

IX. Controller model (Unger, Gemünden, & Aubry, 2012)

They are responsible for gathering, preparing and providing information

that is required for decision making, as well as proposing corrective

measures.

X. Projectized PMO (Project management Institute, 2013)

They are set up temporarily for the specific purpose of delivering project-

related services in a particular project. The office is disengaged or

reassigned at the completion or termination of a project.

Other models exist; however, the author believes that all models mentioned

above are capable of delivering EVM standardisation. Specific suitability of these

models varies from project to project and organisation to organisation. Some

models are better suited for low project management maturity and others, for

higher-level maturity; some support, train and motivate, others enforce. Choice

of the model to adopt may be decided by determining the level of organisational

or project influence desired; some models deliver monitoring and archiving

services while others hold control and steering authority. A third factor to

consider may be the choice between a temporary, single project focused PMO or

a long-term, multiple project PMO setup.

Page 70: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

58

While the premier objective for advocating for a PMO is to have a focal point

providing standardisation, coordination and consistency in project monitoring

and control, organisations with little or no EVM and project control

standardisation should first attempt a hybrid model of ‘training’ and ‘project

specific’ models in order to raise internal proficiency levels. This would involve

the adoption of EVM control methodologies, as well as developing templates for

project control framework.

While the author acknowledges that introducing a PMO would demand effort,

increase overhead costs and cut into profit margins, organisations having many

projects or working on complex projects should have a central project control

office best aligned with their objectives and helps define, optimise, coordinate

and maintain best control practices.

5.4 PUNISHMENT OF CONTRACTORS

Punishment oriented monitoring is one of the challenges to successful project

deliveries.

A potential hindrance to proper use of EVM is the fear of negative consequences

that may arise from control decisions. This may be in the form of claims against

the contractor, and extreme cases, termination of services. While some literature

exists encouraging the use of EVM as a human resources tool, the author

believes that there can exist, a multitude of other reasons why EVM could

indicate poor contractor performance without being the fault of the contractor.

The first, as observed from questionnaire responses and analysed earlier, is the

problem of standardisation. Lack of standardised measuring and reporting, non-

alignment and understanding of reporting processes may lead to a poor

measurement of ACWP and discrepancies from contractor to contractor. A

second factor to consider is that higher competition for contracts leads

contractors to underbid projects in expectations of future income from claims or

submit high risk fast-tracked schedules with very limited float. These can cause

Page 71: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

59

an extremely difficult execution of the project. Being a tool that works best having

set reliable and realistic baselines, using EVM as a basis to punish contractors

for unrealistic targets can be unfair.

Another reason to discourage punishment is that external factors beyond the

control of contractors may influence project performance. These factors include

but are not limited to erratic weather, unplanned site conditions, changes in the

regulatory requirement. Without being able to distinguish between internal

inefficiencies and negative external factors influencing poor performance, EVM

is mostly by itself, unable to measure both project performance and contractor

performance.

Punishment causes contractors to hide and try to fix problems that may be a

flaw in the overall project itself and not born as a result of poor contractor

performance. The fright of punishment may also compel contractors to conceal

or manipulate reports such that they can avoid negative scrutiny on their

performance. As is often an area of debate in project management, in the event

of challenges, contractors assume ownership of floats and resource reallocation

to correct their challenges without informing the project owner or his project

manager. The danger this poses is that early warning signs of a faulty plan may

be missed when all focus is placed on only on completing activity and milestones

within their planned budgets. Secondly, as is with the project management iron

triangle, quality may suffer when constant pressure of performance is placed on

schedule and cost performance.

Projects can be delivered according to cost, schedule and quality baselines;

however, they rarely go according to plan for the entirety of their duration. They

always require control decisions that balance scope, cost, schedule and quality

to steer projects back on track. For this reason, the author believes that EVM

should be used only as a compass and not a weaponised project control tool.

Despite the necessity to pursue excellent project performance, the project

environment should be such that contractors are encouraged to report truthfully

and transparently poor project performance, whatever the reason behind it is.

Having this allows all stakeholders to deliver a collaborative control plan that

Page 72: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

60

requires collaboration and trust amongst all participating stakeholders. Steadier

long-term control decisions may be developed rather than focusing on firefighting

project management that is more preoccupied with short term results by the

contractor. Principles of alliance contract project delivery method can be adopted

to encourage collaboration and shared problem-solving. For EVM to work

transparently and effectively, it is vital that every project stakeholder sees it as

a tool that supports their work and shares a common desire to deliver a

successful project.

5.5 IT PROJECT SUPPORT

Computers and software are vital tools in modern-day workplaces. Project

management workplaces are no exception to this with software such as Oracle’s

Primavera P6, and MS Project in widespread use in the construction project

management community. These project software help overcome challenges of

traditional project management systems that may be characterised by multiple

unorganised interrelated schedules, graphs and reports. By replacing

inefficiencies of conventional manual methods, the additional general

advantages of project management and control EVMS include; reduction in

computational errors, straightforward and consistent reporting formats,

improved efficiency through reducing the man-hours required for gathering,

analysing and reporting data, leaving project managers more time to focus on

other responsibilities. There must, however, be the awareness that these

advantages come at some costs to the organisation. Purchase of licenses,

integrating different software, and staff training for are often expensive and a

barrier for small-sized organisations. Software available may also not fit the

business processes of the organisation and may require the business processes

to fit the framework of the software instead. This is more a problem for

standardised project management offices. A solution to this problem is to have

customised bespoke made EVMS, which will incur additional costs.

Page 73: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

61

Despite the benefits that EVMS brings to project control, modern projects are

growing in complexity and challenging schedules yet demanding higher cost

efficiencies in management infrastructure. It is therefore imperative that to build

an EVMS, the benefits of individual software should be chosen to balance as

much as possible, ease of use by its intended users, organisational standards,

inter-operability and multiple other factors while keeping set-up or use costs as

low as possible.

Figure 8: Engine choice checklist to build an EVMS. Owner's elaboration

Using the figure above, the author suggests a checklist of feasibility and cost-

benefit relationship that can be useful when building an EVMS. Alignment with

organisational standards and policies and user requirements are feasibility

conditions that should be considered, while the cost to the organisation, use,

general requirements and quality are cost-benefit conditions to be assessed.

Page 74: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

62

The quality of an EVMS can significantly influence the successful delivery of

projects they are used on. With relevant, consistent and comprehensive reports,

they can assist in making right control decisions, while its interoperability can

improve overall project & portfolio intelligence. User requirements demand that

the engines be adaptive and uncomplicated enough for intuitive use. With these,

project managers would be further encouraged to use and share information on

the EVMS. Projects and portfolios may also have multiple site teams that require

the support of multi-location EVMS as opposed to single-site project teams.

The author acknowledges that smaller sized organisations may be unable to

invest in specialised EVM software irrespective of accompanying benefits,

perhaps as a result of skills maturity or financial constraints. To alleviate these,

simple spreadsheets may be used; as they are mostly cheaply available but

require increased effort. There are large pools of materials and manuals available

on the internet on how to use spreadsheets like Microsoft Excel to calculate EVM

for simple project tasks. However, more complex projects requiring the need to

incorporate combinations of different progress measuring systems for different

activities supervised by a large number of people over extended periods would

require high EVM knowledge and Excel proficiency to write formulas as well as

high levels of synchronisation, collaboration and organization. It would likewise

need the project team to determine the right size that project activities should be

measured. Measuring tasks that are too small will cause a floodgate of

information to be analysed on a limited functionality software. Project activities

that are too big may not be measured early enough to catch early warning signs

that may have negatively impacted on the projects beyond if they had been

detected earlier. More basic software like Microsoft Excel is recommended only

in the event of the following conditions:

I. Project managers have good projects, EVM and spreadsheets maturity.

II. A small-sized project team is involved.

III. The project scope and activity relationships are relatively simple.

IV. The project is short term (1-3) years.

Page 75: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

63

5.6 CONCLUSION

Factors identified by the author, as factors that are important for the successful

project/organisational implementation of EVM have been discussed earlier.

Recalling, they are flexible to accommodate scope changes, standardisation of

processes, mitigating against manipulation of figures, the punishment of

contractors and use of software support. These factors need to be individually

satisfied and collectively balanced in order to provide an enabling environment

for EVM to be reliable. The ratios to which they are adjusted would be determined

by the type of control decisions expected from the project team. EVM itself is

described as a powerful measuring tool; however, strategic project organisation

influences how it is implemented for measurements.

Strategic project organisation that is more aligned with strictly policing and

controlling a project are more likely to use EVM for a firm and accurate

enforcement of original baselines and processes. They may choose to place a

higher emphasis on standards, consistency, strict accountability, discipline and

prefer specialised software and EVMS. Conversely, they may place a lower

emphasis on flexibility and collaboration. This model is more suitable for project

controllers working on large projects and organisations. It involves assigning

people to pre-determined processes. EVM measurements in this model are

reasonably reliable, limited expected deviations and variances from the EVM

curve, and usually difficult to manipulate. Negatively, it is less useful for

delivering projects with uncertainties.

Page 76: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

64

Figure 9: Model 1 to overcome Implementation Constraints of EVM. (Author)

On the other hand, strategic project organisation that is more aligned with

project advocacy and support are more likely to use EVM to inform adaptive

approaches to controlling the project to successful delivery. They may place a

higher emphasis on people’s experiences, and capacity, flexibility to changes,

stakeholder collaboration and may not require standardised software.

Conversely lesser emphasis is placed on consistency, standards, discipline and

processes. Accountability would still be demanded but at higher tolerance for

poor work performance if it guarantees transparency of reporting and highlights

contractor challenges. With fewer regimented processes, frequent deviations

from the EVM curve is reasonably expected; however, the higher likelihood of

collaboration and buy-ins from all participating stakeholders increases the

chance of achieving the baseline targets EVM measures.

EVM for project

Policing and control

Standards

Strict accounta

bility

Consistency

Collaboratio

n

Specialized

software

EVM and

control maturit

y

Flexibility

Page 77: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

65

Figure 10: Model 2 to overcome Implementation Constraints of EVM (Author)

Baselines may be adjusted to accommodate changing requirements necessary

for achieving success criteria outside the purview of EVM measurements. This

EVM use model may be better suited for projects with limited stakeholders, not

very complex scope and organisations with developed EVM and project control

maturity.

The models presented above are presented as different environments in which

EVM implementation can be iterated depending on its purpose. The features of

model one may be more embraced by project organisations representing project

clients while project organisation on the side of contractors may find themselves

better suited to model two.

EVM for project

advocacy and support

Collaboration

Flexibility

EVM and control

maturity

Standards

Specialized

software

Consistency

Strict accountability

Page 78: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

66

To end this thesis, the author also proposes that university syllabi in the field of

project controls need to be updated. Despite the relative ease of understanding

the classroom version of earned value management, this thesis has shown that

its practice on real projects is low. There should be more in-depth technical

training, software proficiency training and knowledge of organisational

environments influencing project control. Practising organisations need to be

aware of the interrelated factors that must all be individually satisfied and then

collectively balanced to provide an enabling structure for EVM to be reliable, thus

enhancing its application of construction projects.

Page 79: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

67

DECLARATION OF AUTHORSHIP

I hereby declare that this Master’s thesis was completed independently and

without the prohibited support of third parties, and that no sources or support

were used other than those listed. All passages whose content or wording

originates from another publication have been marked as such. Neither this

thesis nor any variant of it has previously been submitted to an examining

authority or published.

Signature: ……………………… Date: ………………………………

Page 80: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

68

APPENDIX A

EARNED VALUE MANAGEMENT (EVM) RESEARCH QUESTIONNAIRE

I am a Construction and Real Estate Master's degree student from Berlin,

Germany.

This survey is meant for project managers and controllers and is intended to give

the researcher an insight into important, yet often overlooked soft factors to

consider for the accurate use of the EVM tool. The research is purely for

academic purposes and responses would be treated with the highest

confidentiality.

Kindly fill this survey according to your knowledge, experience and opinion.

PART A

1. What is your current role within your organisation?

a. Project manager

b. Project team member

c. Portfolio manager

d. Consultant

2. What is the staff size of the organisation in which you are employed?

a. 0-10 people

b. 10-49 people

c. 50-249 people

d. 250 or more people

3. What is your project management level of education? Multiple answers

can be chosen

a. Bachelor’s degree

Page 81: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

69

b. Master’s degree

c. Project management certification, e.g. PMP or Prince 2

d. No project management education

4. How many years’ project management/control related experience do you

have?

a. 0-3 years

b. 3-5 years

c. 5-7 years

d. More than 7 years

PART B

5. How would you rate your knowledge of Earned value management?

a. Elementary

b. Working knowledge

c. Expert

d. No knowledge

6. How do you track and monitor progress on your projects?

a. Earned Value management method

b. Network-based techniques, e.g. CPM or PERT

c. Combination of A & B

d. None of the above

7. To what extent has EVM positively influenced the successful deliveries of

your past projects?

a. Positive

b. Neutral

c. Counterproductive

d. I have never used EVM on Projects

PART C

8. Project management & Control processes are standardised in your

organisation. (evaluating control process aspect)

Page 82: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

70

a. Fully standardised

b. Partially standardised

c. Not standardised

9. All stakeholders and departments involved in project control do not

participate in scope and cost planning. Please respond based on your

experience.

a. Strongly Agree

b. Agree

c. Neutral

d. Disagree

e. Strongly disagree

10. Project managers and contractors manipulate or do not report

progress measurements properly. Please respond based on your

experience.

a. Strongly agree

b. Agree

c. Neutral

d. Disagree

e. Strongly disagree

11. Work breakdown structures from the planning phase do not

completely represent client expectations at the end of the project. Please

respond based on your experience.

a. Strongly agree

b. Agree

c. Neutral

d. Disagree

e. Strongly disagree

12. Data gathering, collection, storage, and extraction requires

specialised project management software. Please respond based on your

experience.

a. Strongly Agree

Page 83: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

71

b. Agree

c. Neutral

d. Disagree

e. Strongly disagree

13. EVM is a strong basis to terminate underperforming project

contractors. Please respond based on your experience.

a. Strongly Agree

b. Agree

c. Neutral

d. Disagree

e. Strongly disagree

Page 84: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

72

BIBLIOGRAPHY

Amin, N. (2005). Social science research: Conception methodology and analysis.

Kampala: Makerere University Printery.

Ammari, S. (2017). Why the Earned Value Analysis method fails? Critical Analysis of its

implication to the Construction Industry. Master thesis at Berlin School of

Economics and Law, 13.

Anbari, F. (2003). Earned value project ,management method and extensions. Project

management Journal, 12.

Azzopardi, S. (n.d.). The Evolution of Project Management - Part 2. Retrieved July 23,

2019, from Project Smart: https://www.projectsmart.co.uk/evolution-of-project-

management-part-2.php

Babbie, E. (2012). The practise of social research. Belmont: Wadsworth Publishing.

Babbie, E., & Mouton, J. (2001). The practice of social research. Capetown: Oxford

University Press, South Africa.

Badgujar, K., Konnur, B., & Landage, A. (2016). A Review of EVM analysis with

Primavera. International journal of engineering research, Vol 5, No SP 1 pp 164-

167.

Besner, C., & Hobbs, B. (2006). The perceived value and potential contribution of project

management practices to project success. PMI Research Conference: New

Directions in Project Management. Montreal: Project Management Institute.

Biafore, B. (2007). Microsoft. Retrieved May 08, 2019, from Determine the right

threshold for project cost and schedule variances:

https://support.office.com/en-us/article/determine-the-right-threshold-for-

project-cost-and-schedule-variances-3ae31373-65b8-4ba4-9402-

83940caab6d4?ocmsassetID=HA010173335&CorrelationId=44519daa-9de9-

4d70-b1f8-779218b13f26&ui=en-US&rs=en-US&ad=US

Blili, S., & Raymond, L. (1993). Information Technology: Threats and Opportunities for

SMEs. International Journal of Information Management.

Bower, D. (2007, July). http://researchbank.rmit.edu.au/. Retrieved from RMIT

University: https://researchbank.rmit.edu.au/eserv/rmit:6332/Bower.pdf

Brunton, R. (2016). Using Earned Value Management Concepts to Improve Commercial

Project Performance. Retrieved August 3, 2019, from

https://www.projectmanagement.com/videos/319221/Using-Earned-Value-

Management-Concepts-to-Improve-Commercial-Project-Performance

Page 85: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

73

Candidi, L., Heineck, L., & Neto, J. (2014). CRITICAL ANALYSIS ON EARNED VALUE

MANAGEMENT (EVM) TECHNIQUE IN BUILDING CONSTRUCTION. (pp. 159-

170). Oslo: Internation Group for Lean construction.

Carnahan, J. (Director). (2012). The Grey [Motion Picture].

Chen, M. (2008). The ABCs of Earned Value Application. AACE International

Transactions, 1-8.

Christensen, D. (1999). Value!Cost!Management!Report!to!Evaluate!the!Contractor's!

Acquisition&Review&Quarterly, 14.

College of performance management. (n.d.). Collecting the History of EVM. Retrieved

June 13, 2018, from http://www.mycpm.org/the-history-of-evm/evm-history/

Collyer, S., & Warren, C. (2013). Project Management Approaches for Dynamic

Environments. International Journal of Project Management., 355-364.

Crawford, J. (2010). The strategic project office: A guide to improving organizational

performance. Florida: CRC press.

Creswell, J. (2014). Research design. Washington, DC: Sage Publications, Inc.

Custer, K. (2009, January 21). The Seven Deadly Myths of Earned Value Methods in

Project Management. Retrieved July 12, 2019, from Project Smart UK:

https://www.projectsmart.co.uk/the-seven-deadly-myths-of-earned-value-

methods-in-project-management.php

De Marco, A., Rafele, C., & Briccarello, R. (2009). Cost and schedule monitoring of

industrial building projects: a case study. Journal of Construction Engineering and

Management, 1.

De Neufville, R., & Field, F. (2018, July 05). MIT.edu. Retrieved from

http://tpp.mit.edu/tpp/tpp_thesis_manual_current.pdf

Desouza, K., & Evaristo, J. (2006). The Project management offices: A case study of

knowledge-based archetypes. International Journal of Information management,

26, 414-423.

Dissanayake, P. (2007). Application of earned value management system for Hong Kong

Science Park Phase 2 development. PMI global Congress 2007-Asia Pacific.

Newton Square: Project management Institute.

Eby, K. (2018). Demystifying the 5 Phases of Project Management. Retrieved August 17,

2019, from Smartsheet Inc: https://www.smartsheet.com/blog/demystifying-5-

phases-project-management

Fleming, Q., & Koppelman, J. (1998). Earned Value Project Management, a powerful

tool for software projects. The Journal of Defence Software Engineering, 19-23.

Page 86: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

74

Fleming, Q., & Koppelman, J. (2002). Using earned value management. Cost enginering,

32-38.

Fleming, Q., & Koppelman, J. (2006). Start With “Simple” Earned ValueOn All Your

Projects. Retrieved July 31, 2018, from Penn State University:

http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.644.7422&rep=rep1

&type=pdf

Fleming, Q., & Koppelman, J. (2010). Earned value project management. Newton Square:

Project management Institute.

Garfield, S. (2016, 10, 17). Communities of Practice. Retrieved 06 28, 2019, from

LinkedIn: https://www.linkedin.com/pulse/communities-practice-stan-garfield

Gartner Research Group. (2008). PMOs: one size does not fit all. Gartner Inc.

Gershon, M. (2013). Using Earned Value Analysis to Manage Projects. Journal of Applied

Business and Economics, 15(1), 11-14.

Ghorbani, S. (Director). (2017). Why the EVM Scheduling Indicators are Not Reliable

[Motion Picture]. Retrieved July 12, 2019, from

https://www.youtube.com/watch?v=qaZgsp3cYwU

Haupt, E. (2017, February 19). Eleanor Haupt & Susan Wood Success Stories. (M.

Doucette, Interviewer)

Heagney, J. (2012). Fundamentals of Project Management. New York: AMACOM.

Herzberg, F. (1968). One more time: How do you motivate employees. Harvard Business

Review, 53-62.

Hinze, J. (2007). Construction planning and scheduling. New Jersey: Prentice-Hall.

Howes, R. (2000). Improving the performance of Earned Value management Analysis as

a construction project management tool. Engineering construction and

Architectural management, 408-410.

Humphreys & Associates. (2012). Basic Concepts of Earned Value Management (EVM).

Retrieved June 02, 2019, from https://www.humphreys-assoc.com/evms/basic-

concepts-earned-value-management-evm-ta-a-74.html

Idoro, G. (2009). Evaluating the use of bar chart and its influence on project

performance in the Nigerian construction industry. COBRA, 37-44.

Khamidi, M., Khan, W., & Idrus, A. (2011). The Cost of measuring construction projects

through earned value analysis project. International Conference on Economics and

Finance Research, 124-128.

Kim, Y., & Ballard, G. (2002). Earned value method and customer earned value. Journal

of construction research , 55-56.

Page 87: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

75

Kopelman, J., & Fleming, Q. (1999). Earned Value Analysis. Newton Square,

Pennsylvania: Project Management Institute.

Kraemer, M. (2018). Management Information systems Module. Berlin, Germany.

kshirsagar, A., & Konnur, B. (2017). Earned value management tool for controlling

project duration and budgeted cost. International journal of engineering

technology science and research, 1275-1280.

Lehtonen, P., & Martinsuo, M. (2006). Three ways to fail in project management: The

role of project management methodology in achieving project management

success. Project perspectives, XXVIII(1), 6-11.

Levine, H. (2002). Practical Project Management. New York: John Wiley & Sons, Inc.

Lukas, J. (2012). How to make Earned Value work on your project. PMI Global Congress.

Vancouver: Project Management Institute.

Lukas, J. (2008). Why doesn't EVM work? Aace International Transactions.

Menta Satya, R., & Roopa, S. (2012, June). Questionnaire Designing for a Survey. The

Journal of Indian Orthodontic Society, 46(4), 37-41.

Monteiro, A., Santos, V., & Varajao, J. (2016). Project Management office models.

Procedia Computer science, 1085-1094.

Mulcahy, R. (2013). PMP exam Prep. RMC publications Inc.

Mullaly, M. (2018). The Future of PMOs. Project management Expo 2018. Virtual

conference: Projectmanagement.com.

Munns, A., & Bjeirmi, B. (1996). The role of project management in achieving project

success. International journal of project management, 84-85.

NAPA. (1994). Toward Useful Performance Measurement: Lessons Learned from Initial

Pilot Performance Plans Prepared under the Government Performance and Results

Act. Washington DC.

Nkiwane, N., Meyer, W., & Steyn, H. (2016). The Use Of Earned Value Management For

Initiating Directive Project Control Decisions: A Case Study. South African Journal

of Industrial Engineering, 27(1), 192-203.

Potter, W. (1996). An analysis of thinking and research about quantitative methods. New

Jersey: Lawrence Erlbaum Associates, Inc.

Prasad, V., Rajkumar, P., & Rastogi, S. (2006). Managing firmed fixed price projects

using EVM: a case study. Paper presented at PMI Global congress 2006- Asia

Pacific. Bangkok: Project Management Institute.

Project management Institute. (2013). PMBOKGuide. Project Management Institute Inc.

Page 88: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

76

Raymond, L., & Bergeron, F. (2008). Project Management information systems: An

Empirical study of their impact on project managers and project success.

International Journal of Project management, 26(2), 213-220.

Reichel, C. (2006). Earned value management systems (EVMS): "you too can do earned

value management". PMI Global Congress, 2006. Washington: Project

Management Institute.

Ritz, G. (1994). Total Construction Project Management. New York: McGraw-Hill Inc.

Rowly, J. (2014). Designing and using research questionnaires. Management Research

Review, 17(3), 308-330.

Sadhu, R. (2015, March 28). Measuring Project Progress: 6 Methods You Should Know.

Retrieved June 29, 2019, from Planacademy:

https://www.planacademy.com/measuring-project-progress-methods/

Saunders, M., Lewis, P., & Thornhill, A. (2009). Research methods for Business students.

Harlow: FT Prentice Hall.

Sears, S. (2008). Construction Project Management A Practical Guide to Field Construction

Management 5th Edition. Hoboken: John Wiley & Sons, Inc.

Sekaran, U. (2003). Research Methods for Business. New York: John Wiley & Sons, InC.

Song, L., & Shalini, H. (2009). A global cross-country perspective on EVM practice and

future trends. The University of Houston.

Stemler, S. (2004). A comparison of consensus, consistency, and measurement

approaches to estimating interrater reliability. Practical Assessment, Research,

and Evaluation, 9(4).

Sterman, J. (2018, July 05). System Dynamics Modeling for Project Management.

Retrieved from Mit.edu: http://web.mit.edu/jsterman/www/SDG/project.pdf

Thamhain , H. (1998). Integrating Project Management tools with Project team. 29th

Annual Project Management Institute Institute Seminars and Symposiums. Long

Beach: Project management institute.

Thomas, B. (2015). Earned green value: a conceptual framework to measure

sustainability in projects based on earned value methodology. Project

management Master Thesis Northumbria University & Chalmers University of

Technology.

Totin, C. (2012). Effective Construction Schedule Management: Construction Project

Monitoring With Project performance indicators & The project status Report. Texas:

University of Texas.

Tuckman, B. (1965). Developmental sequence in small groups. Psychological Bulletin,

384-399.

Page 89: CONSTRAINTS TO IMPLEMENTING EARNED VALUE …

77

Turner, R. (2007). Gower Handbook of Project Management. Gower Publishing Ltd.

Tzaveas, T., Katsavounis, S., & Kalfakakou, G. (2010). Analysis of Project Performance

of a Real Case Study and Assessment of Earned Value and Earned Schedule

Techniques for the Prediction of Project Completion Date. Advancing project

management for the 21st century: Concepts, tools and techniques for managing

successful projects (pp. 752-759). Crete: IPMA.

Unger, B., Gemünden, H., & Aubry, M. (2012). The three roles of a project portfolio

management office: their impact on portfolio management execution and success.

International Journal of Project management, 30, 608-620.

Valle, J., & Soares, C. (2004). The Use of Earned Value Analysis in the Cost Management

of Construction Projects. Brazillian Cost Engineering Institute, 1.

VanderVeen, J. (2018, July 22). 7 Benefits of Agile Earned Value Management (EVM).

Retrieved from TEMPO BLG: https://blog.tempo.io/2015/7-benefits-earned-

value-management-evm

Vanhoucke, M., & Vandervoode, S. (2006). A comparison of different project duration

forecast methods using earned value metrics. International Journal of Project

Management.

Villafiorita, A. (2014). introduction to software project management. Retrieved from

spmbook.com: http://spmbook.com/downloads/slides/pdf/C03.08-09-

ExecutionMonitoringControl.key.pdf

Watt, A. (n.d.). Procurement Management. Retrieved July 1, 2019, from opentextbc:

https://opentextbc.ca/projectmanagement/chapter/chapter-13-procurement-

management-project-management/

Yismalet, A., & Patel, D. (2018). A Critical Literature Review On Improving Project Cost

Management Practice and Profitability of Domestic contractors. International

Journal of Engineering Technologies and Management Research, 52.

Yves. (2017, December 26). Zentao Project Management. Retrieved July 26, 2019, from

The History of Project Management Software:

https://www.zentao.pm/blog/history-of-project-management-114.html