Page 1: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Connector Ahead

www.connectorjpa.net

Page 2: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Capital SouthEast Connector Project

Sheldon/Wilton Community

Workshop #3

www.connectorjpa.net

Page 3: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Agenda

• Introductions & Meeting Purpose• Connector Overview & Working Group Process• Connector Alternatives• Working Group Role & Assessment of

Alternatives• Next Steps• Questions and Comments• Wrap Up

www.connectorjpa.net

Page 4: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Sheldon/Wilton Community Working Group

• Richard Bisnett• June Coats• Tom Franzoia• Bill Kutzer• Bill Myers• Shirley Peters• Russ Shields• Tom Shine• Barbara Washburn

Page 5: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

WelcomePatrick Hume, Mayor, City of Elk Grove

www.connectorjpa.net

Page 6: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Connector Project Overview

www.connectorjpa.net

Page 7: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

General Need

• Mobility– Improve access to, and connections between,

residential and employment areas

• Land Use– Preserve open space and habitat that may be

threatened as the region develops

www.connectorjpa.net

Page 8: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Project Purpose

– Minimize impacts to the livability of residences and communities along the project corridor

– Provide efficient, multi-modal transportation options– Serve and support planned growth– Improve access to exiting and planned job centers– Facilitate goods movement– Preserve open space, wildlife habitat and agricultural

uses– Incorporate sustainable design principles

www.connectorjpa.net

Page 9: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

UPDATE GRAPHIC

Page 10: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Environmental Process

NOI/NOPScoping Meetings(30 days)

Technical Studies

(180-270 days)

Circulate Final

EIS/EIR(30 days)

Record of

Decision

SACOG Phase 1

Study

Prescoping(Current Activity)

Public Hearings(30 days)

Draft EIS/EIR

(270 days)

www.connectorjpa.net

Page 11: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Community Working Group Process

• Formation of Sheldon/Wilton Community Working Group (CWG)

• Mission Statement

• Process

Page 12: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Sheldon/Wilton Alternatives

Page 13: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Image to be updated to show bypass options

Page 14: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Grant Line Rd Alternative w/access roads

• 4 Lane Widening• Preserve right of

way for future six lanes

• Limited access • Left turns at

signalized intersections only

• Internal access roads

Page 15: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Grant Line Road AlternativeInitial Four Lane Roadway

Page 16: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Image to be updated to show bypass options

Page 17: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Bypass Alternative

www.connectorjpa.net

•Overall length 7-9 miles•Structure length 4.5-6 miles•Two lanes w/passing lane•No access to Wilton Road

Page 18: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Sheldon/Wilton Community Working Group Role & Assessment of

Alternatives

www.connectorjpa.net

Page 19: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Next Steps

• Develop recommendations for Board

• Meeting with CWG for review of Staff Report

• Present Staff Report at October 23rd Board

Meeting

www.connectorjpa.net

Page 20: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

QuestionsAnd

Comments

www.connectorjpa.net

Page 21: Connector Ahead . Capital SouthEast Connector Project Sheldon/Wilton Community Workshop #3 .

Wrap Up

www.connectorjpa.net