Page 1: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

1

Congress Parkway and

Wacker Drive

Page 2: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

2

Presentation Outline

• Congress Parkway Project Overview

• Congress Parkway

Traffic Management Plan

• Wacker Drive Project Overview

• Alternate Routes/ Synchro

Page 3: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

3

Congress Parkway

Built in 1956

IDOT owns 10 movable bridges

Chicago owns 37 movable bridges

Trunion Bridge: A trunion bridge is a style of

movable bridge that rotates about a fixed

point.

Repairs

1981 New grid deck

1997 Steel Repairs

2002 Bridge Paint

Page 4: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

4

Project Purpose & Need,

Scope & Schedule

Purpose & Need of Project

- Improve Bridge Condition & Load Rating

- Improve Public Safety (skid reduction, delineate lanes, off-

road crash mitigation (F-shape), lighting, surveillance, etc.

Scope of Work

- Rehab Bascule Bridge structural, electrical and mechanical

- Replace open grid deck with closed deck system w/skid

resistant surface

General Schedule – Two Construction Seasons

– EB (Inbound) Bascule Bridge - April 2010 to January 2011

– WB (Outbound) Bascule Bridge - April 2011 to October 2011

Page 5: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

5

OVERVIEW

Rehabilitation Issues

• Bridge Rehabilitation

• Two Bridges

• Narrow Bridge/Lane Widths

• Post Office Constraint

• Boat Traffic

Alternate Routes

• Inbound / Outbound

• Peak Hours

Operational Concerns

• Inbound High Speeds

• Traffic / Ramp Volumes

• EB Spill-Over onto I-290

• Event Traffic Dispersion

• Incident Management

Page 6: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

6

Congress Parkway Bridge

Traffic Control Considerations:

– Rehab work with bridge in open position

– Speed Limits - Inbound Freeway Speeds 35 MPH

– Traffic Volumes (139,000 ADT)

– Lane widths on Bascule Bridge

(4 lanes – 43 feet face to face)

– Lane widths under Old Post Office

(4 lanes - 38 feet wide/portal)

– Distance between Post Office and Bridge < 200 feet

Page 7: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

7

– City of Chicago

– Chicago Department of Transportation (CDOT)

– Office Of Emergency Management and Communications

(OEMC)

– Emergency Services

– Emergency Traffic Patrol (ETP)

– Federal Highway Administration (FHWA)

– State Police

– Coast Guard

– Corp of Engineers

– Public / Business

– Others within Corridor

Coordination

Page 8: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

8

Advance Work

– Overhead Sign Contract/ Misc. Striping

– Dolphin Replacement (in-stream work)

– Alternate Route Patching Contract

– Traffic Signal Modification Contract

• Wacker Drive at Monroe Street

• Wacker Drive at Adams Street

– Van Buren at Canal Street Modification

– Traffic Signal Timing Modifications

– Public Outreach

• Brochures

• News Releases

• Radio / TV

• Motorists Advance Signing / CMS

• IDOT Website

Page 9: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

9

Transportation Management Plan

• Traffic Control Plan (TCP):

Temp. Widening, Restricted Lane closures,

Incentive/Disincentive provisions, Detours/Alt Routes….

• Transportation Operations Plan (TOP):

Corridor/Network management i.e. signal timing, WZ Safety,

Incident Management, Enforcement/hirebacks…

• Public Information Plan (PIP): Media Outreach/DMS

Work Zone Mobility (3-08)

Page 10: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

10

5 scenarios were evaluated during the Phase I Process

• Scenario #1: Maintain All Inbound Lanes; All Outbound lanes would be detoured

• Scenario #2: Provide Two Inbound Lanes and One Outbound lane

• Scenario #3: Provide Two Inbound Lanes and Two Outbound Lanes

• Scenario #4: Provide Two Inbound Lanes and One outbound for Stage 1 (2011);

Then Provide Two Inbound and Two Outbound lanes for Stage 2 (2012)

• Scenario #5: Same as Scenario 1; however work would continue through Winter

to Shorten Construction Season.

Traffic Control

Alternates

Page 11: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

11

RSA- Defintion: A Formal, independent and comprehensive safety performance review of a road transportation project conducted by an experienced team of safety specialists to maximize safety of the roadway environment for all users.

Members Included:

• FHWA

• IDOT Central Office-Bureau of Traffic Safety and Engineering

• IDOT Central Office- Bureau of Construction

• Illinois State Police

• Chicago Police Department

Roadside Safety Assessment

Page 12: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

12

APPENDIX

Page 13: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

13

Traffic Contribution to Bridge,

AM Destination, PM Origin

Quick Zone for All Scenarios

Page 14: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

14

RSA- recommendations :

Improve Signage and Striping, Unexpected Queues, Poor Pavement Conditions, Improve Pedestrian Signals, Coordinate Emergency Response, Repair Barrier Gates…

Most recommendations were executed in advance contracts or into the main contract.

Roadside Safety Assessment

Recommendations

Page 15: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

15

Perferred Scenario:

Scenario 2: 2-Lanes In & 1-Lane Out• Similar To TCP utilized in 1980

• Provides Better Lane Shifts During construction

• Provides One Lane Outbound for Emergency

and Unfamiliar Users

• Higher Risk Lane Shifts Minimized

Other scenarios not preferred due to…• Scenario 3 & 4 (2-in 2-out): increases higher vehicular crash risk,

higher risk in substandard lane shifts, and substandard lane widths without lateral barrier offset.

• Scenario 1 & 5 (All in): does not provide outbound lanes for emergency/unfamiliar drive access and increase Ped./vehicle conflicts on alternate routes

Roadside Safety Assessment

Preferred Scenario

Page 16: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

16

I-90/94 INBOUND RAMPS

I-90/94 ramps inbound closed due to capacity and safety issues

• Safety - Closed to eliminate merge maneuver within lane

shift/median cross-over

• Reduction in traffic from ramp closures will significantly improve

operations and safety along Congress Parkway

• Additional traffic load on Congress Parkway may result in back-ups

onto I-290 and at I-90/94 ramps,

• FHWA expressed concerns relative to back-up potential and effect

on safety along I-290.

Ramp Issues

Congress Parkway Outbound to I-90/94 ramps

• Ramps to I-90/94 will remain open however alternate route will be

designated to minimize congestion and provide travel time savings

Page 17: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

17

I-90/94 ALTERNATE

ROUTES

1: 90/94 North:

Michigan Ave. – Ontario St. (Ohio St.)

2: 90/94 South:

Jackson Blvd. – Lakeshore Dr. – I-55

2

1

1

2

Page 18: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

18

2 LANES INBOUND

1 LANE OUTBOUND

POST OFFICE

STAGE I

Outbound Inbound Closure

Traffic Control Plan

APRIL 2010 - January 2011

Page 19: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

19

TCP/Emergency Pull-Outs

Page 20: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Google Image

20

Can

al S

treet

Clin

ton

Str

eet

Congress Parkway

Page 21: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Google Image

21

Congress Parkway

Page 22: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Demolition

Page 23: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Demolition

Page 24: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Steel Installation

Page 25: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

25

Congress Parkway Alternate

Routes

Congress Parkway Bascule Bridge Project

Alternate Routes:

• Outbound/WB Alternate Routes –

Roosevelt Road & Adams Street

• Inbound/EB Alternate Routes – Roosevelt

Road & Warren/ Washington Street.

Page 26: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

26

Alternate Routes

Stage I & II Outbound

Michigan Ave. – Adams St. – Ogden Ave. – Van Buren St. – I-290 WB

Michigan Ave. – Roosevelt Rd. – Sacramento Blvd. – I-290 WB1

2

1

2

WORK

ZONE

Page 27: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

27

Alternate Routes

Stage I & II Inbound

I-290 EB - Sacramento Blvd. – Warren/Washington Blvd – Michigan Ave.

I-290 EB - Sacramento Blvd. – Roosevelt Rd. – Michigan Ave.

I-290 EB – Canal St. ramp – Harrison St. – Michigan Ave. (CDOT Alt .Rte)

1

2

2

1

WORK

ZONE

23

3

Page 28: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

28

Scenarios Evaluated

– Scenario #1 – Stage I traffic control lane configurations with

existing signal settings.

– Scenario #2 - Stage I traffic control lane configurations with existing

cycle length and optimized timings and offsets

– Scenario #3 - Stage I traffic control lane configurations with

optimized cycle length, timings and offsets

Stage I Synchro Model

Scenarios

Page 29: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER

Synchro Evaluation Zones

SYNCHRO ZONES

Mic

hig

an

Ave.

Page 30: Congress Parkway and Wacker Drive - University Of …conferences.illinois.edu/traffic/2010PDF/File_8_Congress.pdfCongress Parkway and Wacker Drive . ... Chicago owns 37 movable bridges

CONGRESS PARKWAY

OVER SOUTH BRANCH

OF CHICAGO RIVER Adjacent Projects

– Jackson Street Bridge west of SBCR (2009/2010) – CDOT

– Congress Streetscape Project (2010/2011) – CDOT

– North/South Wacker Drive Project (2010-2012) – CDOT

– I-90/94 / Hubbard’s Cave Project (2009/2010) - IDOT

– I-290 Resurfacing (2010) - IDOT

– Ohio Feeder Resurfacing (completed) - IDOT

– I-290 Ramp Drainage Improvements (competed) - IDOT