Page 1: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 1 -Confidential: For internal use only

EAI PROGRAM STRUCTURING

Program Management Office Role & Reporting (Draft v. 1.2)

October 16, 2003

Page 2: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 2 -Confidential: For internal use only

PMO Principles

• The EAI PMO is responsible for helping EAI project managers to be successful

• The EAI PMO facilitates the successful and consistent use of project management practices on all EAI projects

• The EAI PMO is focused on delivering an environment where EAI projects can flourish

• The EAI PMO “does not” actually manage projects

Page 3: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 3 -Confidential: For internal use only

PMO VALUE STATEMENT

• Gartner Group has published research suggesting that organizations could cut project overruns by 50% by "establishing enterprise standards for project management including a project management office with suitable governance.

• Standish Group study concluded that 60% of IT projects experienced cost overruns in the range of 15-20%.

Page 4: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 4 -Confidential: For internal use only

Project ManagementProject ManagementProgram ManagementProgram Management

EAI PMO Role vs. EAI Project Management Role

Identify

Analy

ze

Plan

Track

Control

Communicate, Coordinate &

Document

Advising

Men

torin

g

Facilitating

Plan

nin

g

Reviewing

ManagingManaging Project Knowledge Project Knowledge

& Helping& Helping

Page 5: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 5 -Confidential: For internal use only

SCE EAI Project PlansSCE EAI Project Plans

SCE EAI Program PlanSCE EAI Program Plan

Program Management Reporting

• All EAI Project Plans will be rolled up into a single Master Plan

• Master Plan will be used to Derive & Report Program Status and Health Reports

EV / Status Report

Master EAI Program

Plan

EAI Framework Plan

EAI IBUS Migration

EAI Process Plan

Integrator PlanIntegrator Plan Integrator PlanIntegrator Plan Integrator PlanIntegrator Plan

Master Project

Status Report

Page 6: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 6 -Confidential: For internal use only

Project Status Reporting

• Schedule• Budget• Variance• % CMPLT

• Issues

Page 7: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 7 -Confidential: For internal use only

Program Health (Earned Value)

• BCWP• ACWP• BCWS• ETC /

EAC• % CMPLT

• Variances• Issues• Forecast

Page 8: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 8 -Confidential: For internal use only

Reporting Tool Plan

Work Packages

Near term: Work breakdown structure

(WBS) tailored for effective internal

management control.

Phase 1

Phase 2

Phase 4Phase 5

Phase 3

MS Project

Plan View

Strategic Planning

PackageFuture integration of the

company's planning,

scheduling, budgeting,

work authorization and cost

accumulation processes.

FY03 FY04 FY05 FY06 FY07

Page 9: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 9 -Confidential: For internal use only

Phase III+ Reporting

Work Package

SCE Standard Portfolio Performance

Management System.

Page 10: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 10 -Confidential: For internal use only

Benefits

• Standards• Methods• Guidelines• Repository (re-use)• Training

Cost Aversion

Cost Aversion Cost SavingsCost Savings

ProgramBudget

Governance

ProgramBudget

Governance

PMO = Cost Aversion

Page 11: Confidential: For internal use only - 1 - EAI PROGRAM STRUCTURING Program Management Office Role & Reporting (Draft v. 1.2) October 16, 2003.

- 11 -Confidential: For internal use only

Financial Report09/01/03 thru 09/30/03

Capital BudgetedActual &

CommittedBudget Forecast

Software 500,000 500,000 100% 350,000 350,000 100%

Hardware 1,075,883 1,075,883 100% 1,130,000 -1,130,000 -100%

Training 32,880 32,880 100% 30,000

Labor-SCE 129,328 24,000 105,328 81% 152,000

Labor-Non-SCE 638,119 23,000 615,119 96% 714,000

Total 2,376,210 47,000 2,329,210 98% 2,376,000 0 -780,000 -33%

Inception to Date Project Budget

Variance($ and %)

Variance($ and %)

Budget Actual Budget Forecast