Top Banner
Conducti veConcreteO verlayfo r Bridge Deck Deicing Sh er ifYehia,Ph.D.,PE March200 8
57

Conductive Concrete Overlay for Bridge Deck Deicing

Feb 03, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Conductive Concrete Overlay for Bridge Deck Deicing

Conductive Concrete Overlay for

Bridge Deck Deicing

Sherif Yehia, Ph.D., PE

March 2008

Page 2: Conductive Concrete Overlay for Bridge Deck Deicing

Acknowledgment

ÅResearch TeamïChristopher Tuan, Ph.D., PEUniversity of Nebraska - Lincoln

ïOsama Abudayyeh, Ph.D., PE

ïIkhlas Abdel-Qader, Ph.D., PEWestern Michigan University

ïAmmar Zalt, Bridge Engineer, PARSONS

ïVijay Meganathan, Terasoft International Inc., Arlington Heights, IL

Page 3: Conductive Concrete Overlay for Bridge Deck Deicing

Outline

ÅBackground

ÅWhat is Conductive Concrete

ÅConductive Concrete Mix Design

ïMixing Procedure

ï Implementation Projects

ÅConstruction

ÅOperation

ÅModified Mix at Western Michigan University

ÅConcluding Remarks

ÅQuestions

Page 4: Conductive Concrete Overlay for Bridge Deck Deicing

Background

Existing Deicing Methods

ÅDeicing Chemicals

ÅInsulation against Freezing

Page 5: Conductive Concrete Overlay for Bridge Deck Deicing

Background

Heating Systems

Electric Cables in the Bridge Approach

Roadway, Newark, New Jersey 1961

Approximate Cost

$5/ft2

Page 6: Conductive Concrete Overlay for Bridge Deck Deicing

Background

Heating Systems

Deck Heating System on Approaches of a

Pedestrian Overpass in Lincoln, NE, 1993

Approximate Cost

$16/ft2

Page 7: Conductive Concrete Overlay for Bridge Deck Deicing

Background

Heating Systems

Deck Heating System in the Buffalo

River Bridge, Amherst, Virginia, 1996

Approximate Cost

$35/ft2

Page 8: Conductive Concrete Overlay for Bridge Deck Deicing

ÅWhat is Conductive

Concrete?

ÅConductive Concrete

Applications

Conductive Concrete

Page 9: Conductive Concrete Overlay for Bridge Deck Deicing

Conductive Concrete Mix Design

The Conductive Concrete Mix Contains :

ïCarbon & Graphite Products

ïSteel Fiber

In addition to cement, fly ash, silica fume,

sand, coarse aggregate, water, and

superplasticizer

Page 10: Conductive Concrete Overlay for Bridge Deck Deicing

Deicing 1998

Deicing 1999

Page 11: Conductive Concrete Overlay for Bridge Deck Deicing

Deicing 2000

Page 12: Conductive Concrete Overlay for Bridge Deck Deicing

Mixing Procedure

(Mass production)

Page 13: Conductive Concrete Overlay for Bridge Deck Deicing

Mixing procedure

(Mass Production)

Page 14: Conductive Concrete Overlay for Bridge Deck Deicing

Mixing procedure

(Mass production)

Page 15: Conductive Concrete Overlay for Bridge Deck Deicing

Implementation Projects

ÅTest section on I-480 Missouri River

Bridge, 1999

ÅImplementation Project at Shelby City,

OH, 2001

ÅRoca Spur Bridge, Roca Nebraska, 2002

Page 16: Conductive Concrete Overlay for Bridge Deck Deicing

Test section on I-480 Missouri River

Bridge using conductive concrete

mix.

Implementation Project

Material evaluation - Durability test (I-480 Patch)

under traffic load and freeze-and-thaw action.

Poured on December 3, 1999

Page 17: Conductive Concrete Overlay for Bridge Deck Deicing
Page 18: Conductive Concrete Overlay for Bridge Deck Deicing
Page 19: Conductive Concrete Overlay for Bridge Deck Deicing
Page 20: Conductive Concrete Overlay for Bridge Deck Deicing
Page 21: Conductive Concrete Overlay for Bridge Deck Deicing
Page 22: Conductive Concrete Overlay for Bridge Deck Deicing

Implementation Project

at

Shelby City, OH

September 2001

Page 23: Conductive Concrete Overlay for Bridge Deck Deicing

Temperature Sensors

Page 24: Conductive Concrete Overlay for Bridge Deck Deicing

Site Before Casting Concrete

Page 25: Conductive Concrete Overlay for Bridge Deck Deicing

Casting

Page 26: Conductive Concrete Overlay for Bridge Deck Deicing

Finishing I

Page 27: Conductive Concrete Overlay for Bridge Deck Deicing

Finishing II

Page 28: Conductive Concrete Overlay for Bridge Deck Deicing

Finishing - Final Touch

Page 29: Conductive Concrete Overlay for Bridge Deck Deicing

Implementation Project - Roca

Spur Bridge

ÅRoca, located about 15 miles south of Lincoln, Nebraska

ÅThe Roca Spur Bridge is a three-span slab type bridge has a 45.70m (150 ft) long and 11m (36 ft) wide concrete deck

ÅThe Bridge has a 36 m (117 ft) long and 8.5 m (28 ft) wide conductive concrete inlay

ÅThe inlay consists of 52 individual 1.2m 4.1m (4 ft 14 ft) conductive concrete slabs

Page 30: Conductive Concrete Overlay for Bridge Deck Deicing
Page 31: Conductive Concrete Overlay for Bridge Deck Deicing
Page 32: Conductive Concrete Overlay for Bridge Deck Deicing
Page 33: Conductive Concrete Overlay for Bridge Deck Deicing
Page 34: Conductive Concrete Overlay for Bridge Deck Deicing
Page 35: Conductive Concrete Overlay for Bridge Deck Deicing

Working with Ready Mix Concrete ïLincoln, NE

Mixing Procedure

ÅThe conductive concrete mix with steel fibers

and carbon and graphite products was used

to cast the inlay

ÅSeveral, two cubic yards, trial batches were

prepared to examine the mixing procedure

and travel time from the mixing plant to the

job site

ÅThe contractor and the pouring and finishing

crews practiced at a test site

Page 36: Conductive Concrete Overlay for Bridge Deck Deicing
Page 37: Conductive Concrete Overlay for Bridge Deck Deicing
Page 38: Conductive Concrete Overlay for Bridge Deck Deicing
Page 39: Conductive Concrete Overlay for Bridge Deck Deicing
Page 40: Conductive Concrete Overlay for Bridge Deck Deicing
Page 41: Conductive Concrete Overlay for Bridge Deck Deicing
Page 42: Conductive Concrete Overlay for Bridge Deck Deicing
Page 43: Conductive Concrete Overlay for Bridge Deck Deicing
Page 44: Conductive Concrete Overlay for Bridge Deck Deicing
Page 45: Conductive Concrete Overlay for Bridge Deck Deicing
Page 46: Conductive Concrete Overlay for Bridge Deck Deicing
Page 47: Conductive Concrete Overlay for Bridge Deck Deicing

March 21, 2006

Page 48: Conductive Concrete Overlay for Bridge Deck Deicing

Feb 13, 2007

Page 49: Conductive Concrete Overlay for Bridge Deck Deicing

Temperature Time History - Dec. 17, 2003

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

50.0

0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00

Time (hrs)

Te

mp

. (F

)Slab 1 Slab 2

Slab 3 Slab 4

Slab 5 Slab 6

Slab 7 Slab 8

Slab 9 Slab 10

Slab 11 Slab 12

Slab 13 Slab 14

Slab 15 Slab 16

Slab 17 Slab 18

Slab 19 Slab 20

Slab 21 Slab 22

Slab 23 Slab 24

Slab 25 Slab 26

Slab 27 Slab 28

Slab 29 Slab 32

Slab 33 Slab 34

Slab 35 Slab 36

Slab 37 Slab 38

Slab 39 Slab 40

Slab 41 Slab 42

Slab 43 Slab 44

Slab 45 Slab 46

Slab 47 Slab 48

Slab 49 Slab 50

Slab 51 Slab 52

Ambient

Page 50: Conductive Concrete Overlay for Bridge Deck Deicing

1

2

3

4

5

6

7

-25 -15 -5 5 15 25

Temperature (oC)

Ele

ctr

ica

l c

urr

en

t (A

mp

s.)

1/25/2004

2/1/2004

2/5/2004

1/6/2005

2/8/2005

2/17/2006

3/18/2006

1/13/2007

1/19/2007

2/13/2007

Stability of Electrical Conductivity

Page 51: Conductive Concrete Overlay for Bridge Deck Deicing

Modified Conductive Concrete

Mix Developed at WMU

ÅThe main objective of this research project

is to make the conductive concrete an

economical viable deicing method. This

can be achieved by the following:

ïReduction of the operating voltage and

current requirements.

ïDevelopment of a simplified mix procedure

Page 52: Conductive Concrete Overlay for Bridge Deck Deicing

Conductive Concrete Mix

Developed at WMU

ÅOptimization and mix proportioning

ÅEvaluation of the mechanical properties

of the optimized mix

ÅInvestigation of an electric model for the

optimized mix

Page 53: Conductive Concrete Overlay for Bridge Deck Deicing

Temp Vs Time

0

10

20

30

40

50

60

70

80

0 5 10 15 20 25 30 35 40 45

Time in Min

Te

mp

in F

Slab 1

Slab 2

Slab 3

Slab 4

Slab 5

Slab 6

Salb 7

Comparison of all Slabs Temperature readings

Page 54: Conductive Concrete Overlay for Bridge Deck Deicing

Temp vs Time

0

10

20

30

40

50

60

0 5 10 15 20 25 30 35 40 45

Time in Minutes

Tem

p in

F

Slab #4(80 volts)

Slab #5(80 Volts)

Slab #6 (80 volts)

Slab #4(60 volts)

Slab # 5(60 volts)

Slab #5 (100 volts)

Slab #6(100 volts)

Slab #4( 100 volts)

Temperature vs. Time Using Different

Voltage Values

Page 55: Conductive Concrete Overlay for Bridge Deck Deicing

Concluding Remarks

ÅThe conductive concrete deicing technology can

be readily implemented at accident-prone areas

such as bridge overpasses, exit ramps, airport

runways, street intersections, sidewalks, and

driveways

ÅThe heated bridge deck of Roca Spur Bridge is

the first implementation in the world of using

conductive concrete for highway bridge deicing

Page 56: Conductive Concrete Overlay for Bridge Deck Deicing

Concluding Remarks

ÅThe initial results showed that the modified

conductive concrete mix which was

developed at Western Michigan University

has the potential to be used for bridge

deck deicing application as well as the

proposed new applications including

Electromagnetic Shielding and Cathodic

protection of reinforcement.

Page 57: Conductive Concrete Overlay for Bridge Deck Deicing

Questions