COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG. WATER SUPPLY PONDS. Water Quantity and Conservation #1. Use land according to its capability and treat it according to its needs Use management to gain the most agricultural benefit from precipitation and shallow groundwater - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG. WATER SUPPLY PONDS

Page 2: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Water Quantity and Conservation #1

Use land according to its capability and treat it according to its needs

Use management to gain the most agricultural benefit from precipitation and shallow groundwater

Improve water use efficiency

Keep runoff clean

Capture runoff and use it on the farm

Page 3: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Farmers, Consultants and Partners #1

NRCS wants the opportunity to assist you in development of a conservation plan that adds value to your land.

Why is NRCS ability to assist you with pond development limited to a preliminary site assessment?

Time- people w/ pond experience, broader mission

Money- program funds targeted, demand v. supply

Red tape- the federal compliance burden

Page 4: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Farmers, Consultants and Partners #2

This process is for ag. water supply ponds- irrigation, stock watering, wash water and cooling water.

Do you need to use this process? NRCS workload priorities might be

directed elsewhere when you request assistance.“ I won’t be able to assist you right now, but I’d like

to get some information about your needs and if time becomes available we’ll get in contact with you.”

Page 5: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

NRCS and District folks- #1

Are we getting back into the pond business?

Is this the only training I’m going to get? Please don’t over-think this assessment

Off-site evaluationNo lay-outNo design

Page 6: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

NRCS and District folks- #2

Use pond interest to engage in on-farm planning.“Can I get you to go on site to look at my place?”

Prelim. Site Assessment “pre-planning service” evaluate candidate site’s natural resources for

capability of land to support pond development

explain potential regulatory issues

enable early identification of problems with a proposed site that can be changed or solved because the idea is still being developed

help farmer’s develop ponds they need

will save farmer’s time in the overall process by ensuring practical alternatives, site limitations and regulatory issues are considered before large investments of time or money are made

Page 7: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Not all sites are good candidates: Soils and geology can cause limitations

Size of drainage area

Flood hazards

Unique cultural or environmental features

Ratio of drainage area to pond surface area affects water level At least 10:1. Not more than 30:1. Mid-range is ideal.

Good soil conservation in the drainage area is important

Rules of Thumb #1

Page 8: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Rules of Thumb #2

Irrigation storage: at least 1.3 to 1.5 acre-feet of storage per acre irrigated

Evaporation and seepage losses: 2.5 to 4 ft. per irrigation season

Beef cattle require at least 15-20 gallons per animal per day.

Pond may not be best alternative for livestock water supply.

NRCS has published technical references that can be used to support planning and design:

National Eng. Handbook, Ponds and Reservoirs

NC Irrigation Guide

Conservation Practice Standard: Pond (378)

Page 9: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 10: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Use ArcMapNavigate toArea of Potential Pond Site

Page 11: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 12: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Define Area of Interest

Page 13: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Bare Earth Data Converted to Tin

Page 14: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Tin Converted to 5ft Contours

Page 15: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Site Characteristics Question 1:Estimated

Drainage Area

Page 16: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

For THIS Example - 10:1 Ratio of Drainage Area to Surface Area of Pond Needed

IDEAL = 20:1 Ratio

ASSUMPTION:

Page 17: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

68 Acre Drainage Area=

6.8 Acre Pond

Page 18: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Site Characteristics Question 2:

Estimated Pool Area

Page 19: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Site Characteristics Question 3:Estimated Depth of Water

Elevation Difference - Lowest Point to Top of Pool Area

955’

931’

Page 20: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Site Characteristics Question 4:Estimated Embankment Height

Add 5ft to Embnakment Height for Freeboard and Spillway

960’

931’

Page 21: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Site Characteristics Question 5: Estimated Length of Dam

Page 22: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 23: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Look Downstream

What Hazards are Observed?

• Measure the Distance to Any Downstream Hazards • Create .pdfs to Attach to Assessment Showing Potential Hazards

Page 24: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Following General Guidelines Referenced in USDA: Ponds – Planning, Design, and Construction

Page 25: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Based on Embankment Height of 29ft =

Dam Width of 14ft

Ass

ume

3:1

– O

utsi

de T

oe

Assum

e 3:1 – Inside Toe

94 ft 94 ft

Estimated 188 ft of the Stream Filled by Embankment

Page 26: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 27: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Using Soil Data Viewer

ArcMap or Toolkit Environment

Page 28: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 29: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 30: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 31: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS
Page 32: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Use the NC Floodplain Mapping Program Stream

Data to Determine if a Blue Line Stream Exists

Page 33: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Calculate Feet of Stream Inundated by Pond

Length of NCFPMP Stream Inside Pond

MINUS

Length of Inside Toe

631 ft – 94 ft= 537 ft

Page 34: COMPLETEING A PRELIMAINRY ASSESSMENT FOR AG.  WATER SUPPLY PONDS

Does the potential pond area fall within the boundaries of the property owned by the person?