Top Banner
Page 1 of 3 CORPORATE INFORMATION Full Company Name : Oilfield Technical Inspection Sdn. Bhd. Business Address : Headquarters 142 Jalan Kapar 27/89, Seksyen 27 40400 Shah Alam Selangor Darul Ehsan MALAYSIA Tel : +60 – 3 – 5191 1615 Fax : +60 – 3 – 5191 1605 Date of Incorporation : 30 th August 2005 Registration No. : 708006-M Authorised Capital : RM5,000,000.00 Paid-Up Capital : RM1,500,000.00 Name & Address of Banker : HSBC Bank Malaysia Berhad Damansara Heights Branch Level 1 Annexe, Menara Milenium Jalan Damansara, Pusat Bandar Damansara Demansara Heights 50490 Kuala Lumpur, MALAYSIA Account No. : 359-055779-725 (Swift Code : HBMBMYKL) Principal Owner of Company : Vital Concept Management Sdn Bhd : 71.0% Zamrin Mohamed Daud : 29.0% Equity Structure : Malaysian Bumiputra : 100.0% Board of Directors : Zamrin Mohamed Daud : Director Ahmad Rizal Abdul Rahman : Director L.P.T.A. License : LPTA/A/1169 Petronas License : 708006-M ISO Certificate No. : 11066
50

Company Profile.pdf - MOGSC

Feb 06, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Company Profile.pdf - MOGSC

Page 1 of 3

CORPORATE INFORMATION

Full Company Name : Oilfield Technical Inspection Sdn. Bhd.

Business Address : Headquarters142 Jalan Kapar 27/89, Seksyen 2740400 Shah AlamSelangor Darul EhsanMALAYSIATel : +60 – 3 – 5191 1615Fax : +60 – 3 – 5191 1605

Date of Incorporation : 30th August 2005

Registration No. : 708006-M

Authorised Capital : RM5,000,000.00

Paid-Up Capital : RM1,500,000.00

Name & Address of Banker : HSBC Bank Malaysia BerhadDamansara Heights BranchLevel 1 Annexe, Menara MileniumJalan Damansara, Pusat Bandar DamansaraDemansara Heights50490 Kuala Lumpur, MALAYSIA

Account No. : 359-055779-725(Swift Code : HBMBMYKL)

Principal Owner of Company : Vital Concept Management Sdn Bhd : 71.0%Zamrin Mohamed Daud : 29.0%

Equity Structure : Malaysian Bumiputra : 100.0%

Board of Directors : Zamrin Mohamed Daud : DirectorAhmad Rizal Abdul Rahman : Director

L.P.T.A. License : LPTA/A/1169

Petronas License : 708006-M

ISO Certificate No. : 11066

Page 2: Company Profile.pdf - MOGSC

Page 2 of 3

HISTORY AND NATURE OF BUSINESS

Oilfield Technical Inspection Sdn Bhd (OTI) provides expertise and equipment in third partyengineering inspection, non-destructive testing (NDT) and quality assurance/quality control(QA/QC) with a niche in the inspection of the joints of newly laid pipelines.

In order to ensure its competitiveness in this NDT market segment, OTI has developed andmanufactured its own series of Pipeline Crawlers equipment for the radiographic inspection.

Pipeline Crawler 24” Crawler with 300kV tube

Prior to mid 2007, projects executed under OTI were put under the name of its sistercompany – Focus Inspection Sdn Bhd. This is mainly due to the strategies employed at thatpoint of time by the previous shareholders, where Focus and OTI has commonshareholders. The Project Management Team (PMT), equipment and personnel were allfrom OTI.

However in mid 2007, OTI was taken over completely by the current shareholders, and assuch, common shareholders between Focus and OTI no longer exists. The period until mid2008 was the transition period between Focus and OTI, where OTI started to bid for worksunder OTI itself and was building its own track records.

During the next five (5) years, OTI has expanded into providing other related services suchas the supply of QA / QC personnel, radiation safety consultancy, training and certification ofNDT personnel to the American Society of Non Destructive Testing (ASNT) Level I andLevel II by qualified Level III, and research, design and fabrication of NDT equipment andaccessories such as pipeline crawlers and film drying system.

OTI also offers the following NDT services – Ultrasonic Testing, Magnetic ParticleInspection, Dye Penetrant Testing, Thickness Gauging, Phased Array inspection and others.

Page 3: Company Profile.pdf - MOGSC

Page 3 of 3

In January 2011, OTI became the first Malaysian NDT company to acquire AutomatedUltrasonic Testing (AUT) Phased Array system from General Electric (GE). OTI is also thefirst NDT Company in Malaysia to be able to offer both conventional RT crawler systems andAUT Phased Array capabilities.

Two AUT Phased Array systems Scanner with two 64 elements PA probe

OTI is managed by a team of professionals who have been in the inspection business foronshore and offshore projects in the Oil & Gas and Marine Industries for the last fifty (50)years. In terms of accumulated experience, its management team has more than twenty(20) years of experience and worked on more than one hundred projects worldwide.

This progressive approach together with its multi-skilled staff has allowed OTI to rapidlypenetrate both the domestic and international markets by performing the NDT work on amajority of the pipelaying contracts in the Asian region.

OTI’s qualified and well trained staffs, supported by a strong and dedicated managementteam which aims to delight all our customers by exceeding client expectations on all projectsundertaken.

Page 4: Company Profile.pdf - MOGSC

KEY MANAGEMENT

Zamrin Mohamed Daud has been with OTI since2008 as the Managing Director. He started hiscareer with PETRONAS before joining one of theMalaysian’s Government Linked Company (GLC).He has 15 years experience in NDT with 8 yearsin managerial level. He has managed NDTactivities for various projects : 300km offshorepipeline, 350km onshore pipeline andconstruction of LNG plant.

Md Suhaimi Baharom leads the accounting,finance and corporate affairs. He has more than15 years experience in financial relatedmanagement and has been involved incommercial and financial aspects of broadspectrum of domestic and international trade.He has been in the oil and gas industry for thepast 10 years.

Page 5: Company Profile.pdf - MOGSC

KEY MANAGEMENTS. Vijayan’s scope of responsibilities coverstraining and certification as per the AmercianSociety of Non Destructive Testing (ASNT). Hehas 35 years experience in the oil and gas andpower industry. His professional qualificationincludes ASNT Level III in RT, UT, MT, PT, ET andVT; as well as API Inspectors and Senior WeldingInspector. He is currently heading the AUTinitiatives. He holds a Diploma in RadiationPhysics and MSc (Physics).

Clifton George O’Keeffe is the General Managerfor Marketing and Operations. He has more than20 years extensive professional experience in theOil & Gas and Energy sector. Apart from NDT, hewas also involved in Heat Treatment, In ServiceInspection and has also served as CountryManager for Indonesia.Currently, he is in charge of both internationaland domestic projects.

Page 6: Company Profile.pdf - MOGSC

KEY MANAGEMENT

Lim Bian Seng provides technical support andconduct R & D on the NDT equipment. Hegraduated in Science and Mechatronic fromTaiwan University. He has more than 40 yearsexperience in the field of NDT. He is highlyrespected by the local and foreign NDTcommunity owing to his strong technicalbackground, management and trouble shootingskills.

Page 7: Company Profile.pdf - MOGSC

Doc. No. : OTI-QM-02

Rev. No. : 4

Effective Date : 1-May-14

B.O.D

Managing Director

Zamrin Mohamed Daud

RPO/ SafetyMazlan Abu Bakar

Business Development Fin & Admin

RPS

Technical Store & Logistic Nik Salimi N. M Salleh NDT Level III General Manager General Manager General Manager

S Vijayan Clifton George O'Keeffe William Shon Laird Md Suhaimi Baharom

Manager Manager Manager Snr. ManagerLim Bian Seng M. Balasubramaniam Siti Daria Mohd Muzaini Darus

Admin Exec.Ezuni AUT Snr Exec. Marketing Asst. Acct. Asst. Mgr HR

Specialist J. Shahbiah Jamaluddin Muzammil Zakaria Azliza SaadSupervisor Executive SupervisorK. Gunalan Anandan a/l Raman Operator

Scanner TechOffice Asst.Aziz Bakar

Asst. NDTMohanasundari Balu Supervisor

Technicians

Ops. AssistantRohaya

OILFIELD TECHNICAL INSPECTION SDN BHD

Management Rep.

Operation Support

ORGANISATION CHART

S Vijayan

Operations & Marketing

Page 8: Company Profile.pdf - MOGSC
Page 9: Company Profile.pdf - MOGSC

Pada menjalankan kuasa-kuasa yang diberi oleh Seksyen 7, Akta Kemajuan Petroliam, 1974 dan mengikut Peraturan 5, Peraturan-Peraturan Petroliam,1974, yangdiwakilkan kepada saya oleh YAB Perdana Menteri Malaysia, saya dengan ini mengeluarkan lesen dibawah Peraturan 3, Peraturan-Peraturan Petroliam ini bagi tujuandi atas kepada:

Tarikh Dicetak: 17.12.2015OILFIELD TECHNICAL INSPECTION SDN BHD (708006-M)142, JALAN KAPAR 27/89, SEKYEN 27 40400 SHAH ALAMSELANGOR

Butir-butir Lesen adalah seperti berikut:-

Nombor Syarikat : 708006-M

Jenis Syarikat : LESEN

Tempoh Sah Lesen : 09.01.2016 - 08.01.2019

Yuran Lesen : RM 1,500

Bidang pembekalan/perkhidmatan : Seperti di Lampiran 'BIDANG-BIDANG LESEN / PENDAFTARAN'.

Syarat-syarat Khas yang dikenakan ke atas Lesen ini:-

Tertakluk kepada syarat khas seperti di lampiran berkaitan.

Syarat-syarat Am Lesen ini adalah seperti yang tercatit di halaman seterusnya.

LESEN MEMBEKAL PERALATAN/MEMBERI PERKHIDMATAN KEPADASYARIKAT-SYARIKAT CARIGALI DAN PENGELUAR MINYAK/GAS DI MALAYSIA

Peringatan: Pemegang Lesen Hendaklah Memohon Pembaharuan Lesen Tiga (3) Bulan Sebelum Tarikh Tamat Lesen.

Sijil ini dicetak oleh komputer dan tandatangan pihak Petronas tidak diperlukan. Muka Surat 1 / 5

Page 10: Company Profile.pdf - MOGSC

SYARAT-SYARAT AM LESEN PETRONAS

1. Syarikat ini dikehendaki berdaftar, mendapatkan lesen, permit atau kebernaran daripada pihakberkuasa yang berkenaan untuk mengendalikan perkhidmatan atau pembekalan peralatan ataubahan-bahan yang berkaitan dalam operasi atau aktiviti-aktiviti syarikat ini yang diperlukan;

2. Lesen ini tidak boleh dipindahmilik kepada mana-mana syarikat/pihak lain;

3. Lesen ini akan dibatalkan sekiranya syarikat ini didapati berada di dalam proses penyelesaianhutang-hutangnya (liquidation), penggulungan (winding-up) atau pembubaran (dissolution);

4. Syarikat ini hendaklah memaklumkan kepada PETRONAS sebarang perubahan ke atas kedudukansyarikat seperti pemilikan ekuiti, lembaga pengarah dan kakitangan pengurusan dalam masaempat belas (14) hari dari perubahan tersebut berlaku. Kegagalan untuk berbuat demikianboleh mengakibatkan lesen ini dibatalkan;

5. Syarikat ini hendaklah mengambil tindakan segera untuk memenuhi syarat-syarat khas yangdikenakan di dalam lampiran lesen dan memaklumkan kepada PETRONAS atas perkembangantindakan tersebut;

6. Syarikat ini tidak dibenarkan mengambil syarikat lain sebagai prinsipal, agen, sub-kontraktor atausebaliknya untuk memberi apa-apa perkhidmatan atau membekal apa-apa kemudahan, kelengkapanatau peralatan bagi pihaknya tanpa kebenaran bertulis daripada PETRONAS terlebih dahulu;

7. Syarikat hendaklah membenarkan wakil pihak PETRONAS membuat lawatan pemeriksaan/audit keatas premis/syarikat dan menyemak/menyalin dokumen-dokumen serta menemubual kakitangansyarikat dan pihak yang berkaitan;

8. Lesen ini hendaklah ditunjukkan kepada pegawai-pegawai PETRONAS apabila dikehendaki untukdiperiksa;

9. Lesen ini adalah sah untuk memberi perkhidmatan dan membekal peralatan bagi bidang-bidangyang tercatat di lampirannya sahaja;

10. Syarikat ini boleh dikenakan tindakan sekiranya pada pendapat PETRONAS, syarikat melakukansatu atau lebih daripada perkara-perkara seperti berikut;

a. Gagal melaksanakan kerja yang diberikan sehingga selesai.

b. Gagal untuk melaksanakan tanggungjawab kontrak atau mana-mana tanggungjawab lain dibawah undang-undang terhadap rakan kongsi, prinsipal, agen, sub-kontraktor dan sebagainya.

c. Menerima 'garnishee order'.

d. Menghadapi tindakan muflis.

e. Tidak dapat dikesan melalui alamat terakhir.

f. Mengsub-kontrak kerja kepada kontraktor lain tanpa kebenaran bertulis daripada PETRONAS.

g. Menolak mana-mana kontrak atau tender yang diberikan.

h. Memasuki atau menerima kontrak atau tender semasa di dalam penggantungan lesen.

i. Memberi maklumat palsu, tidak tepat atau mengelirukan.

j. Tidak mematuhi peraturan-peraturan dan etika-etika tender meliputi tetapi tidak terhad kepadamenghantar surat layang, memberi rasuah atau melobi;

k. Melakukan kegiatan yang tidak sewajar dengan Lesen ini.

11. Menurut peraturan 9, Peraturan-Peraturan Petroliam 1974, seseorang yang memulakan ataumeneruskan sesuatu urusan atau perkhidmatan yang tersebut dalam Peraturan 3 tanpa lesen atautidak mematuhi apa-apa syarat lesen tersebut adalah melakukan suatu kesalahan dan apabiladisabitkan boleh dikenakan denda tidak lebih daripada RM 50,000.00 (Ringgit Lima Puluh Ribu)atau penjara selama tempoh tidak lebih daripada dua (2) tahun atau kedua-duanya dan mengenaisesuatu kesalahan yang berterusan ia boleh dikenakan denda lanjutan RM 1,000.00 (Ringgit Seribu)tiap-tiap satu (1) hari atau sebahagian daripada satu (1) hari kesalahan itu berterusan selepas haripertama sabitan itu direkodkan;

12. Kelulusan ini bukan satu perjanjian/jaminan bahawa syarikat tuan akan dipanggil untuk menyertaitender atau sebutharga oleh PETRONAS atau anak-anak syarikatnya;

13. Syarikat ini sama ada secara dengan sendirinya, melalui pekerja-pekerjanya, pengarah-pengarahnya,agen-agennya atau kakitangan-kakitangannya:-

a. Tidak dibenarkan menggunakan logo titisan minyak (oil drop) PETRONAS atau perkataan"PETRONAS" atau menggunakan sebarang tanda, logo atau perkataan atau memakai gayacetakan (typeface), gaya huruf (font), rupa atau warna yang menyerupai cap-cap daganganyang dimiliki atau yang digunakan oleh PETRONAS ataupun anak-anak syarikatnya ("cap-capdagangan PETRONAS") dalam sebarang bentuk sekalipun sama ada pada bahan cetakan, lamanweb ataupun papan tangan; dan

b. Tidak dibenarkan melakukan apa-apa perbuatan atau dalam apa-apa cara sama ada secaralangsung atau tidak langsung mengaku bahawa ia adalah rakan kongsi atau mempunyaisebarang kaitan/hubungan dengan PETRONAS dan/atau anak-anak syarikatnya,MELAINKAN DAN KECUALI Syarikat ini dibenarkan menggunakan rujukan [Syarikat] inidilesenkan oleh PETRONAS [No. lesen], di bawah Peraturan 3 Peraturan-peraturan Petroliam1974.

14. Lesen ini boleh dibatalkan, digantung atau disenaraihitamkan pada bila-bila masa jika mana-manasyarat di atas, syarat-syarat am pelesenan dan pendaftaran PETRONAS dan syarat-syarat lain yangterkandung didalam Panduan Am Permohonan Lesen dan Pendaftaran PETRONAS tidak dipatuhi.

Muka Surat 2 / 5

Page 11: Company Profile.pdf - MOGSC

NAMA SYARIKAT : OILFIELD TECHNICAL INSPECTION SDN BHD (708006-M)

NO LESEN : 708006-M

TEMPOH SAH LESEN : 09.01.2016 - 08.01.2019

B I D A N G - B I D A N G L E S E N / P E N D A F T A R A NBIDANG-BIDANG LESEN YANG DILULUSKAN

(Approved License Categories)L/R Kod Perkhidmatan / Bekalan

(Service / Supplier Code)Bentuk Operasi(Mode of Operation)

Nama Produk / Rig / Kapal(Bila Mana Berkaitan)

Tarikh Lulus /Masa

Tarikh Tamat

L SC3010200CONSULTANCY SERV-PIPELINE

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:09

08.01.2019

L SC3020700CONSULTANCY SERVICES-ENGINEERING CONSULTANCY SERVICES-PIPELINEENGINEERING CONSULTANCY

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:09

08.01.2019

L SC3060900CONSULTANCY SERVICES-UPSTREAM CONSULTANCY SERVICES-SPECIALIZEDDRILLING AND COMPLETION CONSULTANCY (RECLASSIFIED FROMSC3060105,CONSULTANCY SERV-DRILLING CONSULTANCY)

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:09

08.01.2019

L SC3070000CONSULTANCY SERV-COMPUTERIZD INSPECTN&MAINT CONSULTANCY SERV

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:09

08.01.2019

L SI1040100ICT SERVICES-SOFTWARE SERVICES-SOFTWARE DEVELOPMENT SERVICES(RECLASSIFIED FROM SI1040300-ICT SERVICES-SOFTWARE SERVICES-SOFTWARESUPPORT SERVICES)

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:08

08.01.2019

L SM2021000MANPOWER SUPPLY-SKILLED MANPOWER-WELDING INSPECTOR

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:10

08.01.2019

L SM2021100MANPOWER SUPPLY-SKILLED MANPOWER-PAINTING INSPECTOR

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:10

08.01.2019

L SM2030300MANPOWER SUPPLY-MATERIAL, CORROSION & INSPECTION SPECIALIST

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:10

08.01.2019

L SP1040104PIPELINE & ASSOCIATED SERV-RISER REPAIR & MAINT-(SQ1030308 reclass toSP1040104)

SELF-OPERATED NOT APPLICABLE 19.11.201517:51:09

08.01.2019

L SP2370000PRODUCTION/DRILLING/WORKOVER ASSOCIATED SERVICES-RIG INSPECTIONSERVICES

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:08

08.01.2019

L SQ1010100QUALITY ASSURANCE-MATERIAL,CORROSION &INSPECTION-(NDT)SERVICES-BASIC NDT (SQ1010101, SQ1010102, SQ1010104,SQ1010105, SQ1010106, SQ1010107, SQ1010200, SQ1010300, SQ1010401, SQ1010402,SQ1010409 & SQ1011200 reclass to SQ1010100)

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:07

08.01.2019

Sijil ini dicetak oleh komputer dan tandatangan pihak Petronas tidak diperlukan. Muka Surat 3 / 5

Page 12: Company Profile.pdf - MOGSC

NAMA SYARIKAT : OILFIELD TECHNICAL INSPECTION SDN BHD (708006-M)

NO LESEN : 708006-M

TEMPOH SAH LESEN : 09.01.2016 - 08.01.2019

B I D A N G - B I D A N G L E S E N / P E N D A F T A R A NBIDANG-BIDANG LESEN YANG DILULUSKAN

(Approved License Categories)L/R Kod Perkhidmatan / Bekalan

(Service / Supplier Code)Bentuk Operasi(Mode of Operation)

Nama Produk / Rig / Kapal(Bila Mana Berkaitan)

Tarikh Lulus /Masa

Tarikh Tamat

L SQ1010201QUALITY ASSURANCE-MATERIAL,CORROSION &INSPECTION-(NDT)SERVICES-ADV NDT-ULTRASONIC TESTING (SQ1010403,SQ1010404, SQ1010405, SQ1010406, SQ1010407 & SQ1010408 reclass to SQ1010201)

SELF-OPERATED NOT APPLICABLE 21.11.201510:22:29

08.01.2019

L SQ1010203QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-NONDESTRUCTIVE TEST (NDT)SERVICES-ADVANCED NDT-RADIOTRACER (SQ1010103reclass to SQ1010203)

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:06

08.01.2019

L SQ1010204QUALITY ASSURANCE-MATERIAL,CORROSION &INSPECTION-(NDT)SERVICES-ADV NDT-HYDROGEN ATTENUATION (SQ1010410reclass to SQ1010204)

SELF-OPERATED NOT APPLICABLE 19.11.201517:51:09

08.01.2019

L SQ1010207QUALITY ASSURANCE-MATERIAL,CORROSION &INSPECTION-(NDT)SERVICES-ADV NDT-VISUAL AID INSPECTION (SQ1010700reclass to SQ1010207)

SELF-OPERATED NOT APPLICABLE 19.11.201517:51:09

08.01.2019

L SQ1010211QUALITY ASSURANCE-MATERIAL,CORROSION &INSPECTION-(NDT)SERVICES-ADV NDT-LEAK TESTING (SQ1010901, SQ1010902,SQ1010903 & SQ1010904 reclass to SQ1010211)

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:06

08.01.2019

L SQ1030100QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-INSPECTIONSERVICES-RISK BASED INSPECTION

SELF-OPERATED NOT APPLICABLE 19.11.201517:51:09

08.01.2019

L SQ1030303QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-INSPECTIONSERVICES-PIPING INSPECTION

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:07

08.01.2019

L SQ1030305QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-INSPECTIONSERVICES-STORAGE TANK INSPECTION

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:07

08.01.2019

L SQ1030306QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-INSPECTIONSERVICES-STRUCTURE INSPECTION

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:08

08.01.2019

L SQ1030307QUALITY ASSURANCE: MATERIAL, CORROSION & INSPECTION-INSPECTIONSERVICES-COOLING TOWER INSPECTION

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:08

08.01.2019

Sijil ini dicetak oleh komputer dan tandatangan pihak Petronas tidak diperlukan. Muka Surat 4 / 5

Page 13: Company Profile.pdf - MOGSC

NAMA SYARIKAT : OILFIELD TECHNICAL INSPECTION SDN BHD (708006-M)

NO LESEN : 708006-M

TEMPOH SAH LESEN : 09.01.2016 - 08.01.2019

B I D A N G - B I D A N G L E S E N / P E N D A F T A R A NBIDANG-BIDANG LESEN YANG DILULUSKAN

(Approved License Categories)L/R Kod Perkhidmatan / Bekalan

(Service / Supplier Code)Bentuk Operasi(Mode of Operation)

Nama Produk / Rig / Kapal(Bila Mana Berkaitan)

Tarikh Lulus /Masa

Tarikh Tamat

L SS1120000SPECIAL CATEGORIES MAINT-POST WELD HEAT TREATMENT

SELF-OPERATED NOT APPLICABLE 24.10.201512:12:10

08.01.2019

R E M A R K V D P / O T H E R SSQ1010100 Excluding Sabah & Labuan Operations (VDP) SQ1010201 Excluding Sabah & Labuan Operations (VDP) SQ1010203 Excluding Sabah & Labuan Operations (VDP) SQ1010204 Excluding Sabah & Labuan Operations (VDP) SQ1010207 Excluding Sabah & Labuan Operations (VDP) SQ1010211 Excluding Sabah & Labuan Operations (VDP)

*** TAMAT ***

Sijil ini dicetak oleh komputer dan tandatangan pihak Petronas tidak diperlukan. Muka Surat 5 / 5

Page 14: Company Profile.pdf - MOGSC
Page 15: Company Profile.pdf - MOGSC

GE Weldstar – Hybrid AUT Girth Weld Inspection

DesignThe ultrasonic electronics are located on the scanner head (known as UTR – Ultrasonic TestingRemote ). With the combination of shielding and natural cancellation, the Weldstar is able toovercome the problem of Electro Magnetic Interference ( EMI ) or Radio Frequency ( RF ) noisefrom other equipment such as from welding machines. In addition to this, since the pulser – receiveramplifiers are on the scanner, there is no need for a complex umbilical connecting the scanner andthe pulser – receiver.

Other equipment has the ultrasonic electronics away from the scanner head, and as such, complexumbilical need to be connected between the scanner head and the pulser – receiver unit. Since theultrasonic is running down the umbilical, it is more susceptible to noises from EMI.

At the other end of the umbilical is the computer, which processes all the information receivedthrough the umbilical from the UTR. The computer unit is known as UTM – Ultrasonic Testing Main.

There is also GPS capability built-in onto the scanner head – more appropriate for onshore pipeline.

FlexibilityThe scanner head contains ( UTR ) all its ultrasonic hardware in 4 modules which can be replaced onsite. It can be configured as follows :

1. Four 8-channel conventional modules giving 32 conventional ultrasonic channels2. Two 64-channel PA modules and two 8-channel conventional modules giving 128 PA

channels and 16 conventional channels

This flexibility allows the operator to configure optimum inspection solution for any given jobscope.

Inspection can be done to conform API 1104, DNV-OS-101 and others.

Page 16: Company Profile.pdf - MOGSC

Reliability

The Weldstar has been tested to operate in ambient temperatures from -50C to +60C. GE has alsointroduced fully modular electronics ( plug and play function ), drive mechanism, and a single stepdetachable umbilical. The average time taken to replace the item is 1 min for drive motor; 2 mins forumbilical replacement and 5 mins for PA modules.

Software

The SetUp Wizard software on the UTM would allow the Operator to perform the complete set upwithin 1 day as compared for a few days for other equipment. This set up would include generatingthe calibration block design and complete definition of inspection parameters.

The PlusWeld software organises and archives the scan data almost immediately. Beside thescanning date, other info included on each weld data set includes the date, time and GPScoordinates.

Inspection capabilityThe scanner is optimised for 12” dia and above; by using a special band, Weldstar can do inspectionfrom 8” dia.Wall thickness is from 7-8mm and above.Scanning speed is 100mm / sec.Minimum coating cutback is 150mm.

Weldstar Items

Weldstar UTR Scanner Weldstar UTM Main computer

Two ( 2) units of Weldstar

Page 17: Company Profile.pdf - MOGSC

Ultrasonic Remote ( UTR ) – 2 units UTR – close up

16 conventional channels 4 PA module channels

Ultrasonic Main ( UTM ) – complete with 25m umbilical cable – connecting UTR and UTMSet Up Wizard and PlusWeld software

Page 18: Company Profile.pdf - MOGSC

Drive Motor Assy Drive Motor Assy on Scanner Band

38deg Phased Array Probe Wedge 64 element Phased Array probe

38deg wedge with 64 elements Encoder Assy ( top _ and Frame Link ( bottom )Phased Array probe

Page 19: Company Profile.pdf - MOGSC

TOFD probes & wedges, PA probes and wedges TOFD probe holder

Accessories kits Shoes with couplants

Page 20: Company Profile.pdf - MOGSC

Technical SpecificationPipeline outside diameter range…………... 5.25 – 16.0 inches Exposure safety delay………………….. Adjustable (standard : 5 seconds)Power source (rechargeable battery pack)... Lead Acid Dry Cell Radiation source units…………………. 160/180/200kV 3/2/2.3mATraction motor rating (2/4 wheel drive)…... 1/8 hp at 24VDC X-ray source supply voltage…………… 48VDC

(1 / 2 units) Number of articulated unit inControl Unit (Electronic box)…………….. OTI E-Box crawler train……………………………. 1Running wheel diameter…………………..Travel speed……………………………….

3 inches1 ft per second

Overall length of operational crawler(assembly with recovery ring)…………. 66 inches (1676mm)

Angle of climb (clean pipe)……………….Braking system…………………………….

30 deg, maximumDynamic

Overall weight of operational vehicle….Operating temperature limits…………...

44 kg- 25 deg C to + 70 deg C

Mean position accuracy…………………... + / 5mm (0.2 inch) Battery charger (for Lead acid pack)…... Constant voltageExposure time (pre-set)…………………… 0 to 255 seconds Control (signaling) and Tracker isotope.. Cs 137 / Co-60 (20mCi / 15mCi)

Specification subject to change without notice owing to continual improvement of products.

6 – 16 INCHES PIPELINE X-RAY RADIOGRPHY CRAWLER

( 2 WHEEL / 4 WHEEL DRIVE )

Page 21: Company Profile.pdf - MOGSC

Technical SpecificationPipeline outside diameter range…………... 9.75 – 60.0 inches Mean position accuracy………………... + / - 5mm (0.2 inch)Power source (rechargeable battery pack)... 10 units Exposure time (pre-set)………………... 0 to 255 seconds

Lead Acid Dry Cell Exposure safety delay………………….. Adjustable (standard : 5 seconds)(12VDC 17AH) Radiation source units…………………. 160/180/200/300 kV X-ray

Traction motor rating (2/4 wheel drive)…... 1/4 hp at 130V X-ray source supply voltage…………… 48/120VDC(1 / 2 units) Number of articulated unit in

Control Unit (Electronic box)…………….. Microprocessor based crawler train……………………………. 1Running wheel diameter………………….. 7.25 inches Overall length of operational crawler

(assembly with recovery ring)…………. 106 inches (2240mm)Travel speed………………………………. 1 ft per second

(Approx)Overall weight of operational vehicle….Operating temperature limits…………...

128 kg- 25 deg C to + 70 deg C

Angle of climb (clean pipe)………………. 30 deg maximum Battery charger (for Lead acid pack)…... Constant voltageBraking system……………………………. Dynamic Control (signaling) and Tracker isotope.. Cs 137 / Co-60 (20mCi / 15mCi)

Specification subject to change without notice owing to continual improvement of products.

10 – 60 INCHES PIPELINE X-RAY RADIOGRPHY CRAWLER

( 2 WHEEL / 4 WHEEL DRIVE )

Page 22: Company Profile.pdf - MOGSC

Technical SpecificationPipeline diameter range.................... 24 to 60 inches Exposure time (pre-set)……………….... 0 to 255 secondsPower source……………………… 10 units rechargeable

lead acid dry cellExposure safety delay (pre-set)…………Operating temperature limits…………...

Adjustable (standard : 5 seconds)- 25 to + 70 degree C

(each 12VDC, 24/28Ah) Battery charger…………………………. Constant VoltageTraction motor (4-W Drive)............. 1/4 hp at 130VDC (2 units) X-Ray source units……………………... 300kV at 3mAElectronic Box……………………. Powerful Microprocessor X-Ray source power supply……………. 120VDC

controller based Number of articulated units in crawlerTravel speed………………………. 40 ft per minute (approx) train…………………………………...... One OnlyRunning wheel……………………. Rubber Wheel Overall length for crawler c/w recoveryAngle of climb (clean pipe)………. 35 deg maximum ring……………………………………... 1270mm (50 inches)Braking system……………………. Dynamic Overall weight of crawler inclusive ofMean positioning accuracy……….. + / - 5mm (0.2 inch) battery pack…………………………….. 232 kg

Specification subject to change without notice owing to continual improvement of products.

24 – 60 INCHES PIPELINE X-RAY RADIOGRPHY CRAWLER

( 4 WHEEL DRIVE )

Page 23: Company Profile.pdf - MOGSC

OTI Crawler

Page 1 of 5

OTI CRAWLER OUTLINE DESCRIPTION

This advance 3rd generation OTI crawler system is a result of many years of development couple withmany years of experiences working at the site. The range of crawlers we produced, can handle anominal pipe diameter from 6" (153mm) to 60" (1525mm). We manufactured 3 types of crawlersystem. Our smallest size crawler system can able to handle pipe sizes from 6" (155mm) to 16"(406mm) diameters, the medium size crawler can able to handle pipe sizes from 10” (254mm) to 60(1525mm) and the large size crawler can able to handle 24” (609mm) to 60” (1525mm)

UNIQUE DESIGN FEATURES

OTI crawler is of monocoque construction with all mechanical and electrical drives fitted on a subchassis for ease of maintenance. This particular design criteria was built with reliability, ease tomaintence and light weight.

The main drive from the DC permanent magnet motor drive the wheels. The motors that drive thewheels are light and powerful, with high starting torque characteristic.

Speed of motor are variable from 0 to 100% duty cycle when crawler acceleration, deceleration,inching and creeping. All this speeds is closely and accurately controlled by the powerful onboardfirmware ..

Our crawler’s power circuit are designed to improve the safety and reliability. Since, only one powercircuit is used, it is not possible for the drive motor to operate at the same time with the radiactionsource. This unique design feature is to ensures that accidentaly exposure by radiation source cannotbe happen while the crawler is being driven through the pipeline.

Page 24: Company Profile.pdf - MOGSC

OTI Crawler

Page 2 of 5

MICROPROCESSOR CONTROLLER

At the centre of the crawler logic is a power 68HC705B micro controller which is running at 4MHz.The operational firmware is carried inside the logic in a MCU itself. Various types of chopper areavailable to run different types of X-ray tube at their optimum performance point. Careful automaticcontrol of the X-ray tube switching wave forms ensures that the maximum X-ray output is obtainedfrom each type of tube whilst at the same time keeping the current drain from the battery pack to aminimum and prolongs the x-ray tube insert life.

The efficient management of the power systems in the controller extends the operational capabilities ofthe crawler. The external chopper system continuously monitors both the battery voltage and thecurrent being drawn by the power circuit. As the power available from the battery pack reduces duringoperation, the chopper system compensates by adjusting the power circuit control wave form tomaintain the X-ray output at the required level. This will maximise the number of radiographs beenradiograph by each full charged battery pack.

To prevent the battery pack from being damaged by deep discharge, usually caused by abusiveoperation, the Micro controller terminates the radiography process while there are still sufficientcharges remaining in the battery pack to drive the crawler out from the pipeline. This signal thecrawler operator that no further exposure is possible and need to drive out the crawler to replace orrecharge the battery pack.

KEY FEATURES AND BENEFITS.

1. RELIABILITY: The crawler is designed to withstand the rough area, minimise thebreakdown, repair time and at the same time to optimise the performanceand output.

2. MAINTAINABILITY: The monocoque construction ensures that maintenance can becarried out quickly, reducing machine downtime to the minimum.

3. OPERABILITY: The coded control signals system which transmit audible sound to theoperator, is to make operator aware the crawler system status and whathe should do next.

4. ADAPTABILITY: The whole crawler system is completely control by firmware andconfigured to activate external chopper system to provide full power toradiation source..

Page 25: Company Profile.pdf - MOGSC

OTI Crawler

Page 3 of 5

CRAWLER OPERATING INSTRUCTIONS.

The crawler logic unit is microprocessor controlled and is designed to position an x-ray source inside apipeline. All positioning and x-ray operation are software controlled and only a minimum number ofexternal controls are required.

By utilising an integrated power circuit design for both the motor and the x-ray are controlled by thesame unit. Since, the power is diverted by means of a relay to either the drive motor or the x-ray itshould not be possible for the crawler to emit x-rays while in the drive condition. This design featureis intended to protect personnel from the effects of a run-away crawler emitting x-ray.

GENERAL OPERATION.

The following descriptions assume that the user is familiar with the operation of pipeline crawlers andfurther assumes that the Controller has been installed correctly.

Following power up the crawlers' sounder will emit a short beep to indicate that the logic operationshave begun.

Following switch on the crawler is waiting for commands either in the form of a forward or reverseswipe by a radioactive tracer or from the manual inching control buttons.

Should the batteries be in a low state after about 60 seconds the sounder will emit a series of 3 beepsevery 2 seconds. In this state the crawler should not be put in a pipeline as no testing will be possible.

If it is required to halt any operations this may be done by pushing either of the forward and reversebuttons.

INCHING OPERATION

Two sets of inching buttons are provided at the front and rear of the crawler to allow the operator todrive the crawler into the pipeline. Only one inching button should be pushed at a time then eitherforwards or reverse inching operations at reduced speed will be carried out.

The inching speed is pre-set at 50% motor speed and the forward and reverse inching buttons controlthe crawler movement. Rapid operation by togging between forward and reverse should not beattempted as damage to the motor or drive train could result.

During detection and positioning operation a inching mode is used and this speed is adjustable by 25turn trimmer. This alternative speed may be observed by depressing either the forward and reverseinching buttons and 25 trimmer may be adjusted to achieve the desired inching speed for detectionoperations.

Page 26: Company Profile.pdf - MOGSC

OTI Crawler

Page 4 of 5

The above adjustment does not affect the normal inching operations which always take place at 50%motor speed.

FORWARD POSITIONING OPERATIONS.

If a tracer is swiped forwards over the Geiger Mueller (GM) detectors the processor will select theforward direction by operating the direction relay ad the drive motor speed will accelerate tomaximum.

When a signal is detected at the forward GM tube while motor in motion mode, the motor drive will gointo inching speed and stop when both Forward and Reverse GM tube had been detectedsimultaneously. This method of positioning has been adopted so that the crawler may drive atmaximum speed to the test site and then position accurately as quickly as possible.

When positioning operation have completed the crawler is primed to begin testing. Testing is initiatedby removing the tracer from the pipeline in a radial direction.

REVERSE OPERATIONS

If a reverse swipe is applied the direction relay (if not already de-energised), and travel in the reversedirection will commence. As before the drive will gradually accelerate to maximum.

When the first positioning signal is detected at GM2 the crawler again begins its detect and positioningoperation. The unit will continue inching until both GM1 of GM2 are detected. Once this conditionhas been reached the motor will stop .The reverse positioning sequence is identical to forward positioning sequence described previously.By this system the final rest position relative to the tracer is the same for both directions of travel.

Page 27: Company Profile.pdf - MOGSC

OTI Crawler

Page 5 of 5

EXPOSURE OF X-RAY SOURCE.

Unlike many conventional controllers which control the exposure by increasing the exposure time asthe batteries discharge, this external chopper controller compensates by monitoring the milliamperescurrent and voltage status being drawn by the tube. By this method exposure times are constant andduring operation the controller will maintain the current at its pre-set level. As the batteries begin todischarge the controller compensates by increasing the operating frequency and pulse width of the x-ray tube until the maximum specified frequency and minimum pulse width for the tube type is reached.Operation outside the manufacturers recommended parameters is not allowed not only for theprotection of the x-ray tube but also for the safe operation of the power controller.

Following positioning of the crawler testing may be triggered by removing the tracer from the pipe in aradial direction. When simultaneous loss of both GM1 and GM2 signals is detected the crawler willbegin its test sequence.

First the crawler will emit a 5 ( adjustable ) second pre-warning sound and this will be followed byactivation of the x-ray power source.

In very general terms the external chopper system will begin to drive the x-ray tube at its lowestoperating frequency and at its preset pulse width. This pulse width and frequecy controls the amountof current that is passed through the tube until specified period is reached.

This gives reduced power on the x-ray target and is done to warm-up the x-ray target before full poweris applied. One the test sequence has been completed the crawler waits for further command sequencesfrom the tracer.

Page 28: Company Profile.pdf - MOGSC

Page 1 of 23

COMPANY CURRENT & PAST PROJECT LISTONSHORE & OFFSHORE PROJECT

AUT SERVICES

Project : Provision of AUT Services for 28” x 280km EVA-NMB Gas Delivery System (ENGDS)Pipeline Installation Project for PCSB, Kelantan

Client : GOM Resources Sdn BhdYear : April 2014 – October 2014Details : Provision of AUT Services for 28” x 280km pipeline installation onboard Barge DLB-264

Project : North Malay Basin Integrated Gas Development Project, KelantanClient : GOM Resources Sdn BhdYear : March 2013 – May 2013Details : Provision of AUT Services for 16” x 52km pipeline installation onboard Barge DLB-264

Project : North Malay Basin Integrated Gas Development Project, Johor PortClient : GOM Resources Sdn BhdYear : February 2013 – March 2013Details : Provision of Standard NDT and AUT Services for WPQT / WQT

Project : Kebabangan Northern Hub Development Project – Zone 2, Pasir GudangClient : GOM Resources Sdn BhdYear : June 2012Details : Qualification and Validation of AUT Equipment

Project : 24” & 14” X 122.623km SOGT to KBB Platform for Kebabangan Northern HubDevelopment Project, offshore Sabah

Client : GOM Resources Sdn BhdYear : March 2012 – August 2012Details : Provision of AUT Services for 24” & 14” x 123km pipeline installation onboard Barge DLB-

264

Project : 24” & 14” X 122.623km SOGT to KBB Platform for Kebabangan Northern HubDevelopment Project, Pasir Gudang

Client : GOM Resources Sdn BhdYear : February 2012 – March 2012Details : Provision of Automatic Ultrasonic Testing Services for WQT

NDT SERVICES

Project : Provision of RT Services for Layang FPSO for PETRONAS Project, Pulau IndahClient : THHE Fabricators Sdn BhdYear : February 2016 – June 2016Details : Provision of Gamma Service

Project : Provision of Qualified Manpower and Equipment to carry out RT Services forLayang Mooring / Anchor Piles / Orwell Project, Pulau Indah

Client : THHE Fabricators Sdn BhdYear : January 2016 – February 2016Details : Provision of Gamma Service

Page 29: Company Profile.pdf - MOGSC

Page 2 of 23

Project : Additional Development Vasai East Project, IndiaClient : SapuraKencana TL Offshore Sdn BhdYear : December 2015 – May 2016Details : Provision of NDT Services for pipeline installation of 6” x 2.9km, 8” x 9.5km + 9.5km, 18” x

8.5km + 9.5km) and structural installation onboard Barge LTS 3000

Project : Additional Development Vasai East Project, JohorClient : SapuraKencana TL Offshore Sdn BhdYear : October 2015Details : Provision of NDT Services for WPQT / WQT (6” x 8.7mm & 18.3mm WT, 8” x 8.7mm &

17.5mm WT, 18” x 17.5mm & 25.4mm WT)

Project : NDT Services for Removal and Replacement of Gasoline Subsea Pipeline at PraiTerminal, Penang

Client : Alam Swiber Offshore (M) Sdn BhdYear : September 2015 – December 2015Details : Provision of NDT Services onboard Barge 1MAS300 and onshore

Project : Petronas FLNG-1 Ltd for Package FLNG – Mooring System Offshore InstallationWorks (Package 1), Bintulu, Sarawak

Client : Alam Swiber Offshore (M) Sdn BhdYear : July 2015 – September 2015Details : Provision of NDT Services for MPI Scope of Work onboard Barge 1MAS300

Project : CPOC Project, Tok Bali, KelantanClient : SapuraKencana TL Offshore Sdn BhdYear : July 2015 – October 2015Details : Provision of NDT Services for 18” Spool, Riser and Tie-in (CRA & CS) onboard Barge SK

900

Project : HESS, CPOC and H5 Projects, Tok Bali, Kelantan and VietnamClient : SapuraKencana TL Offshore Sdn BhdYear : June 2015 – July 2015Details : Provision of NDT Services for Structural Installation onboard Barge LTS 3000

Project : Garagol Deniz West Oil Development Pipeline Project, TurkmenistanClient : Sigur Ros Sdn BhdYear : June 2015 – March 2016Details : Provision of NDT Services for Pipeline and Structural Installation onboard Barge Armada

Installer

Project : CPOC Project, border Malaysia / ThailandClient : SapuraKencana TL Offshore Sdn BhdYear : July 2015 – November 2015Details : Provision of NDT Services for JDA B-17 & B-17-1 Pipeline Project Bulan C Project (18” x

18km, 7km, 7.5km 12.5km – CS and CRA) onboard Barge SK 1200

Project : Maharaja Lela South Project, BruneiClient : Shaw Pipeline Pte LtdYear : June 2015 – September 2015Details : Provision of Personnel and Equipment for Offshore Pipeline Installation onboard Barge

Sapura 3000

Page 30: Company Profile.pdf - MOGSC

Page 3 of 23

Project : TGT H5-WHP Topside & Pipeline Project Y2015, VietnamClient : SapuraKencana TL Offshore Sdn BhdYear : June 2015 – July 2015Details : Provision of NDT Services for Pipeline Installation (12” x 12.8km, 8” x 5.8km and 6” x

5.8km) onboard Barge SK 1200 and Riser, Spools and Tie-Ins onboard Barge KruezInstaller

Project : Booster Compression Project, border Malaysia / ThailandClient : Hyundai Heavy Industries Co., LtdYear : May 2015 – June 2015Details : Provision of NDT Services for Structural Installation onboard Barge Sapura 3000

Project : Dalak Rectification Works, Bintulu, SarawakClient : PBJV Group Sdn BhdYear : May 2015 – July 2015Details : Provision of NDT Services for pipeline installation onboard Barge KL-101

Project : PMO PL 6” Bea-Tia Pipeline Project, Lumut and KemamanClient : GOM Resources Sdn BhdYear : March 2015 – May 2015Details : Provision of NDT Services for WPQT / WQT at Lumut and pipeline replacement onboard

Barge SapuraKencana Constructor

Project : Provision of NDT Services for Thai Binh Project, VietnamClient : SapuraKencana TL Offshore Sdn BhdYear : January 2015 – April 2015Details : Provision of NDT Services for Structural and Pipeline Installation (12” x 25.4mm WT x

25km) onboard Barge SK 2000.

Project : PTTEP 2015 Campaign, ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : February 2015 – November 2015Details : Provision of NDT Services for Structural and Pipeline Installation onboard Barge K-2.

Project : NDT Services for SK316 Project, Bintulu / Miri, Sarawak, MalaysiaClient : Swiber Offshore Construction Pte LtdYear : March 2015 – April 2015 / August 2015Details : Provision of NDT Services for Structural Installation onboard Barge Kaizen 4000.

Project : Nong Yao Field Development Project, ThailandClient : Nippon Steel & Sumikin Engineering Co., Ltd.Year : February 2015 – April 2015Details : Provision of NDT Services for Pipeline and Structural Installation onboard Barge K-1.

Project : Transportation and Installation of Offshore Facilities for Diyarbekir Oil DevelopmentProject – Goragol Deniz West Pipeline, Nilai, Negeri Sembilan, Malaysia

Client : Sigur Ros Sdn BhdYear : January 2015 – April 2015Details : Provision of NDT Services for WPQT / WQT.

Project : NDT Services for Dalak Project, LabuanClient : PBJV Sdn BhdYear : December 2014 – February 2015Details : Provision of NDT Services for Pipeline and Structural Installation onboard Barge Viva 13

Page 31: Company Profile.pdf - MOGSC

Page 4 of 23

Project : PCC of Regasification Terminal 2 Pipeline Project (RGT2P), Pengerang, JohorClient : Axianergy (Malaysia) Sdn Bhd / CPM Construction Sdn BhdYear : October 2014 – April 2016Details : Provision of NDT Services for onshore pipeline of 36” dia. x 73km

Project : Nong Yao Field Development Project, BatamClient : Nippon Steel & Sumikin Engineering Co., Ltd.Year : October 2014 – February 2015Details : Provision of NDT Services for WPQT / WQT

Project : Provision of NDT Services for BG Mukhta-B Platform & Pipeline Project (Onshoreand Offshore), Pasir Gudang and India

Client : TL Offshore Sdn BhdYear : October 2014 – May 2015Details : Provision of NDT Services for 6” x 4km, 14” + 5” piggyback x 25km, 14” + 5” piggyback x

5km onboard Barge LTS 3000.

Project : SKO PL381 Project, Miri, SarawakClient : PBJV Group Sdn BhdYear : October 2014 – December 2014 / March 2015Details : Provision of NDT Services for pipeline installation for 10” x 11.1mm & 12.7mm x 21km

onboard Barge KL-101

Project : Provision of NDT Services for Nam Con Son 2 Project, Pasir Gudang and VietnamClient : TL Offshore Sdn BhdYear : September 2014 – October 2014Details : Provision of NDT Services for pipeline installation for 16” x 9.2km and 26” x 20km onboard

Barge LTS 3000

Project : EPCIC of JDA Gas Balancing Evacuation Project (EVA Project), offshore Kelantan,Malaysia

Client : TL Offshore Sdn BhdYear : July 2014 – October 2014Details : Provision of NDT Services for offshore pipeline of 24” dia. x 70km and structural

installation onboard Barge LTS3000

Project : Dalak Offshore Installation Project for PCSB, Bintulu, SarawakClient : PBJV Group Sdn BhdYear : July 2014 – February 2015Details : Provision of NDT Services for pipeline installation for 16” x 33km onboard Barge KL-101

Project : EPCIC of JDA Gas Balancing Evacuation Project (EVA Project), Pasir Gudang,Malaysia

Client : TL Offshore Sdn BhdYear : July 2014 – October 2014Details : Provision of NDT Services for WPQT / WQT

Project : Ichthys GEP Project (Australia), Kupang, IndonesiaClient : Saipem (Portugal) Comercio Maritimo – Australia BranchYear : June 2014 – December 2014Details : Provision of UT / MPI Technician and Welding Inspector

Project : Carigali Hess Bulan-C Project, ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : May 2014 – July 2014Details : Provision of NDT Services for CRA pipeline installation of 24” x 16.5km and structural

inspection onboard Barge K-2

Page 32: Company Profile.pdf - MOGSC

Page 5 of 23

Project : PTTEP Long Term Contracts of Bongkot Field Development (Bongkot 3M &Bongkot 4C) Project, Thailand

Client : Nippon Steel & Sumikin Engineering Co., LtdYear : May 2014 – November 2014Details : Provision of NDT Services for pipeline installation and structural installation onboard

Barge K-1

Project : Riser Guard Installation for PCSB, Bintulu, SarawakClient : PBJV Group Sdn BhdYear : April 2014 – July 2014Details : Provision of NDT Services for structural installation onboard Barge KL-101

Project : PTTEP Long Term Contracts of Bongkot Field Development (Bongkot 3M &Bongkot 4C) Project, Batam

Client : Nippon Steel & Sumikin Engineering Co., LtdYear : January 2014 – November 2014Details : Provision of NDT Services for WPQT / WQT

Project : PTTEP Bundled Phase (Arthit 2B and Arthit 2C) Project, ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : November 2013 – June 2014Details : Provision of NDT Services for pipeline installation and structural inspection onboard

Barges K-1 and K-2

Project : Provision of NDT Services for Permas and Bertam Projects, Pulau IndahClient : THHE Fabricators Sdn BhdYear : October 2013 – October 2014Details : Provision of Manual UT Services and MPI / DPI Services

Project : NDT Services for Manora Development Project, Johor Port and ThailandClient : TLO Offshore Sdn BhdYear : January 2014 – March 2014 / June 2014 – July 2014Details : Provision of NDT Services for WPQT for 8” and offshore pipeline of 8” dia. x 1.93km x 2

and structural installation of four-legged jacket onboard Barges SK2000 and SK3500

Project : Provision of NDT Services for Gorgon Heavy Lift and Tie-Ins, Johor PortClient : SapuraAcergy (Australia) Pty LtdYear : October 2013 – December 2013Details : Provision of NDT Services – MPI & UT onboard Barge Sapura 3000

Project : PTTEP Bundled Phase (Arthit 2C) Project, BatamClient : Nippon Steel & Sumikin Engineering Co., LtdYear : August 2013 – December 2013Details : Provision of NDT Services for WPQT / WQT

Project : Provision of Non-Destructive Test (NDT) Services for EVA-NMB Gas DeliverySystem (ENGDS), Paka, Terengganu

Client : PBJV Group Sdn BhdYear : August 2013 – October 2013Details : Provision of NDT Services for WPQT and beach pull pipeline installation

Project : Tukau – NDT Insepction Service, Offshore Terengganu and MiriClient : GOM Resources Sdn BhdYear : June 2013 – September 2013Details : Provision of NDT Services for WPQT, pipeline installation for 8” x 2km and riser

installation onboard Barge DLB-264

Page 33: Company Profile.pdf - MOGSC

Page 6 of 23

Project : EVA – NDT Insepction Service, Offshore TerengganuClient : GOM Resources Sdn BhdYear : June 2013 – September 2013Details : Provision of NDT Services for pipeline installation for 28” x 0.5km onboard Barge DLB-264

Project Provision of T&I for Offshore Facilities for Diamond Development Project, VietnamClient TL Offshore Sdn BhdYear June 2013 – November 2013 / April 2014Details Provision of NDT Services for pipeline installation for 10” x 18km and structural installation

onboard Barge SK 2000

Project : Carigali Hess Project (Bulan-B & Bumi-D), offshore Malaysia / ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : June 2013 – September 2013Details : Provision of NDT Services for CRA pipeline installation for 20” dia. pipe x 9.3km and

structural installation onboard K-1

Project : Diyarbekir Oil Development Project, TurkmenistanClient : Sigur Ros Sdn BhdYear : May 2013 – September 2013 / February 2014 – October 2014Details : Provision of NDT Services for pipeline installation for 18”, 14” and 4” totaling

approximately 30km onboard Barge Armada Installer

Project : Transportation and Installation of Offshore Pipelines and Facilities, KelantanClient : TL Offshore Sdn BhdYear : March 2013 – April 2013Details : Provision of NDT Services for Jacket and Topside installation for North Malay Basin Field

– Package-C (Hess) onboard Barge QP2000

Project : Transportation and Installation of Offshore Facilities – Bekok-A to Tiong-A 6”Pipeline Rectification for PCSB 2013 Work, Kemaman

Client : GOM Resources Sdn BhdYear : February 2013 – March 2013Details : Provision of NDT services for offshore pipeline installation onboard Barge DSV Crest

Odyssey-1

Project : Transportation and Installation of Offshore Pipelines and Facilities, MiriClient : TL Offshore Sdn BhdYear : February 2013 – March 2013Details : Provision of NDT Services for SSB F23DP-A Conductor Repair and Reinstatement

onboard Barge Petra Endeavour

Project : Transportation and Installation of Offshore Pipelines and Facilities, Johor PortClient : TL Offshore Sdn BhdYear : February 2013 – March 2013Details : WPQT / WQT for 8”, 10” and 16” x 12.7mm for MOC Projects

Project : PTTEP Bundled Phase (Arthit 2B, Bongkot 4B and Bongkot 3L), ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : February 2013 – November 2013Details : Provision of NDT Services for pipeline installation for two (2) 12” dia. Pipelines totalling

app 8km and seven (7) 16” dia. Pipelines totaling app. 62km and ten (10) WellheadPlatform structural installation onboard K-2

Page 34: Company Profile.pdf - MOGSC

Page 7 of 23

Project Carigali Hess Project (Bulan-B & Bumi-D), offshore Malaysia / ThailandClient : Nippon Steel & Sumikin Engineering Co., LtdYear : January 2013 – April 2013Details : Provision of NDT Services for CRA pipeline installation for 16” dia. pipe x 6.2km and

structural installation onboard K-1

Project : NDT Services for Bien Dong 2013 Project, Karimun and VietnamClient : Saipem (Portugal) Comercio MaritimoYear : January 2013 – June 2013Details : Provision of NDT Services for CRA pipeline installation for 12” dia. pipe onboard Barge

Semac-1 at Offshore Vietnam

Project NDT Services for Liwan Deepwater EPCI Project, KarimunClient : Saipem (Portugal) Comercio MaritimoYear : December 2012 – February 2013Details : Provision of NDT Services for CRA quad joint installation for 22” dia. pipe onboard Barge

Semac-1

Project : NDT Services for HUC (SHWE Field Development Project), MyanmarClient : Hyundai Heavy Industries Co., LtdYear : December 2012 – January 2013Details : Provision of NDT Services for offshore structural installation and piping onboard Barge

PW Natuna

Project : Transportation and Installation of Offshore Facilities – PMOPL73 Bekok-A to Tiong-A Pipeline, offshore Terengganu

Client : GOM Resources Sdn BhdYear : October 2012 – November 2012Details : Provision of NDT services for offshore pipeline installation and structural installation

onboard Barge DLB-264.

Project : SHWE Field Development Project, MyanmarClient : Hyundai Heavy Industries Co., LtdYear : October 2012 – December 2012Details : Provision of NDT services for 32” x 102km offshore pipeline installation and structural

installation onboard Barge HD-2500.

Project : Provision of NDT Services for Zawtika Field Development Project Phase 1A EPCICfor WP1, WP2, WP3 and Intrafield Sealines, Myanmar

Client : Larsen & Toubro LimitedYear : October 2012 – January 2013Details : Provision of NDT services for 18” x 21km offshore pipeline installation and three (3) jacket

& platform structural installation onboard Barge LTS 3000

Project : Kebabangan Northern Hub Development Project – Malikai, offshore SabahClient : GOM Resources Sdn BhdYear : September 2012 – October 2012Details : Provision of NDT services for offshore pipeline installation and structural installation

onboard Barge DLB-264.

Project : PTTEP Bundled Phase (Arthit 2B, Bongkot 4B and Bongkot 3L), BatamClient : Nippon Steel & Sumikin Engineering Co., LtdYear : September 2012 – February 2013Details : Provision of NDT services for WPQT / WQT

Page 35: Company Profile.pdf - MOGSC

Page 8 of 23

Project : BCOT Project, offshore MalaysiaClient : Alam Swiber Offshore (M) Sdn BhdYear : September 2012 – October 2012Details : Provision of NDT Services for pipeline installation onboard Barge 1Mas300

Project : CPOC Muda-E and Salamander Bravo Project, offshore Malaysia / ThailandClient : Nippon Steel Engineering Co., LtdYear : August 2012 – October 2012Details : Provision of NDT Services for pipeline Installation (18” dia. x 10.5km) and structural

installation for CPOC Muda-E Project and structural installation for Salamander BravoProject onboard Barge K-1

Project : NDT Services for Pipeline and Platform for Hui Su Trang (HST) and Hai Su Den(HSD) Project, Karimun Island and Vietnam

Client : Saipem LimitedYear : August 2012 – October 2012Details : Provision of NDT Services for 6” dia. x 17.6km (double lay joint) pipeline installation and

structural installation onboard Barge Semac-1.

Project : Transportation and Installation of Offshore Facilities – PMOPL73 Bekok-A to Tiong-A Pipeline, onshore Telok Kalong and offshore Terengganu

Client : GOM Resources Sdn BhdYear : July 2012 – September 2012Details : Provision of NDT services for onshore and offshore structural installation

Project : Transportation, Installation and Pre-Commissioning of 28” and 36” DiameterOnshore Pipeline (SOGT Project), Kimanis Sabah

Client : HSAP Sdn BhdYear : June 2012 – July 2012Details : Provision of NDT Services for onshore pipeline installation.

Project : Provision of NDT Services at Telok Gong, Kapar and Johor PortClient : GOM Resources Sdn BhdYear : June 2012 – September 2012Details : Provision of NDT Services

Project : Chess Phase II Project, offshore MalaysiaClient : TL Offshore Sdn BhdYear : June 2012 – September 2012Details : Provision of NDT Services for Riser Stalk-On and structural installation onboard Barge

PJW 3000.

Project : CPOC Muda-E: JDA Block B-17 Development Phase 2, BatamClient : Nippon Steel Engineering Co., LtdYear : May 2012 – August 2012Details : Provision of NDT Services for WPQT / WQT

Project : Transportation, Installation and Pre-Commissioning of SOGT Project, offshoreSabah

Client : Alam Swiber Offshore (M) Sdn BhdYear : May 2012 – September 2012Details : Provision of NDT Services for pipeline installation onboard Barges 1Mas300 & Swiber

Magnificent

Page 36: Company Profile.pdf - MOGSC

Page 9 of 23

Project : NDT Services for Bien Dong Project, Karimun Island and VietnamClient : Saipem LimitedYear : May 2012 – July 2012Details : Provision of NDT Services for 6” dia. x 2.7km, 8” dia. x 2.7km, 10” dia. x 8.8km and 16”

dia. x 2.7km pipeline installation and structural installation onboard Barge Castoro-8.

Project : Transportation, Installation Work and Pre-Commissioning of SOGT Project,offshore Bintulu

Client : Alam Swiber Offshore (M) Sdn BhdYear : April 2012 – September 2012Details : Provision of NDT Services for 28” dia. x 11.1km and 36” dia. x 9.32km pipeline installation

onboard Barge 1Mas-300

Project : SKO Pipeline Replacement Project, Crest Marine Base Johor and MiriClient : TL Offshore Sdn BhdYear : April 2012 – October 2012Details : Provision of NDT Services for 12” dia. x 12.3km and 18” dia. x 28.7km pipeline installation

and structural installation onboard Barge Norce Endeavour, 1Mas300 and Sea Horizon

Project : Provision of NDT Services for SSB for E8 and F13K Modules and Transportation,Installation Work and Pre-Commissioning of SOGT Project

Client : Alam Swiber Offshore (M) Sdn BhdYear : February 2012 – April 2012Details : Provision of NDT Services for WPQT / WQT

Project : Provision of NDT Services at Johor fro MNI2004 – Murphy Serendah / MMI2009Solidbend, Pasir Gudang

Client : Petrotechnical Inspection (M) Sdn BhdYear : February 2012 – March 2012Details : Provision of Radiographic Testing Services

Project : SHWE Onshore Pipeline & OGT Project Kyauk Phyu, MyanmarClient : Kunchong E&C Co., LtdYear : February 2012 – January 2013Details : Provision of NDT Services for 32” dia. x 4.8km onshore pipeline installation

Project : PTTEP Arthit & Bongkot Field Development Bundled Phases, ThailandClient : Nippon Steel Engineering Co., LtdYear : March 2012 – October 2012Details : Provision of NDT services for pipeline installation (12” dia. x 17km and 16” dia. x 34km)

and structural installation onboard Barge K-2

Project : 24” & 14” X 122.623km SOGT to KBB Platform for Kebabangan Northern HubDevelopment Project, Pasir Gudang

Client : Time Temasek Sdn BhdYear : February 2012 – March 2012Details : Provision of Standard NDT and AUT Services for WPQT / WQT

Project : CPOC Phase 2 Development of JDA Block B-17, offshore Malaysia / ThailandClient : Nippon Steel Engineering Co, LtdYear : February 2012 – March 2012Details : NDT Services for pipeline and structural installation onboard Barge K-2

Project : SHWE Field Development Project, MyanmarClient : Hyundai Heavy Industries Co., LtdYear : January 2012 – May 2012Details : Provision of NDT services for pipeline installation (32” dia. x 60km and 14” dia. x 12.7km)

onboard Barges HD-60.

Page 37: Company Profile.pdf - MOGSC

Page 10 of 23

Project : Gorgon Project, IndonesiaClient : PT Saipem IndonesiaYear : December 2011 – June 2013Details : Provision of NDT Level II Cross Checker

Project : SHWE Field Development Project, MyanmarClient : Hyundai Heavy Industries Co., LtdYear : December 2011 – March 2012Details : Provision of NDT services for pipeline installation (32” dia. x 45.8km and 14” dia. x 1.2km)

onboard Barges HD-2500.

Project : Mall 28, Baku, AzerbaijanClient : Pano Joint Stock CompanyYear : December 2011 – January 2012Details : Provision of NDT Services for skylight structure

Project : SHWE Field Development Project, BatamClient : Hyundai Heavy Industries Co., LtdYear : December 2011Details : Provision of NDT services for WPQT / WQT onboard Barges HD-2500 and HD-60

Project : PTTEP Arthit & Bongkot Field Development Bundled Phases, BatamClient : Nippon Steel Engineering Co., LtdYear : November 2011 – February 2012Details : Provision of NDT services for WPQT / WQT

Project : Beach Pull for Kebabangan 24” Gas & 14” Oil Export Line, Kota KinabaluClient : HSAP Sdn BhdYear : October 2011 – November 2011Details : Provision of NDT Services for onshore beach pull pipeline installation

Project : 24” and 14” Kebabangan Export Pipeline Shore Approach, Kota KinabaluClient : PBJV Group Sdn BhdaYear : September 2011 – October 2011Details : Provision of NDT services for pipeline installation (14” dia. x 0.7km and 24” dia. x 0.7km)

onboard Barge E3

Project : 24” KNAG to SOGT Shore Approach Pipeline, Kimanis SabahClient : Ombak Marine Group Sdn BhdYear : August 2011 – September 2011Details : Provision of NDT Services for shore approach pipeline installation

Project : Provision of NDT Services for Tinggi-A to Tiong-A Pipeline Project for Newfield,Kemaman and Terengganu

Client : Global Offshore (M) Sdn BhdYear : August 2011 – September 2011Details : Provision of NDT services for WPQT, offshore pipeline installation (10.75” dia. x 24.75km)

and structural installation onboard Barge DLB-264.

Project : J-Lay Tower Upgrade and Reburbishment, Pasir GudangClient : SapuraAcergy Sdn BhdYear : August 2011 – September 2011Details : Provision of NDT services – MPI & UT for the J-Lay Tower

Page 38: Company Profile.pdf - MOGSC

Page 11 of 23

Project : Turkmenistan Block 1 Gas Development Project, Installation and Pre-commissioning of Offshore Pipelines and Other Associated Civil Works,Turkmenistan

Client : Sigur Ros Sdn BhdYear : August 2011 – November 2011Details : Provision of NDT services for Gamma for topside on satellite platform

Project : Pipeline X-Ray Inspection Services for Petronas Melaka Refinery – Main OnshorePipeline, Melaka

Client : Care Ion Technologist Sdn BhdYear : July 2011 – February 2012Details : Provision of NDT services for onshore pipeline installation (30” dia. x 30km)

Project : WPQT / WQT 24” and 14” Kebabangan Export Pipeline Shore Approach, PakaTerengganu

Client : PBJV Group Sdn BhdaYear : July 2011 – August 2011Details : Provision of NDT services for WPQT / WQT

Project : Premier Oil Gajah Baru Project, IndonesiaClient : PT. Saipem IndonesiaYear : June 2011 – August 2011Details : Provision of NDT services for pipeline installation (16” dia. x 3km) and structural

installation onboard Barge Castoro-8

Project : Integrated Transportation and Installation of Offshore Facilities (Package A),offshore Malaysia

Client : Global Offshore Malaysia Sdn BhdYear : May 2011- July 2011Details : Provision of NDT services for riser and spool installation onboard Barge Nor Tigerfish

Project : Bach Ho Gas Pipeline Project, VietnamClient : Hyundai Heavy Industries Co., LtdYear : April 2011 – June 2011Details : Provision of NDT services for pipeline installation (12” dia. x 25.7km) and structural

installation onboard Barge HD-289

Project : Provision of 24” dia. ANDR-A / TCOT Shore Approach Pipeline Installation, offshoreKertih

Client : Alam Swiber Offshore (M) Sdn BhdYear : April 2011 – May 2011Details : Provision of transportation and installation of 24” dia. x 0.9km concrete pipeline for the

shore approach section from ANDR-A platform to Terengganu Crude Oil Terminal (TCOT)onboard Barge 1Mas-300

Project : NDT Services for Carigali Hess Project (CHOC Suriya B Malaysia), VietnamClient : Saipem Malaysia Sdn BhdYear : April 2011 – June 2011Details : Provision of NDT services for CRA pipeline installation (18” dia. x 6km) and structural

installation onboard Barge Castoro-8

Project : Integrated Transportation and Installation of Offshore Facilities (Package A),offshore Malaysia

Client : Global Offshore Malaysia Sdn BhdYear : April 2011 – September 2011Details : Provision of NDT services for pipeline installation and structural installation onboard Barge

DLB-264

Page 39: Company Profile.pdf - MOGSC

Page 12 of 23

Project : Integrated Transportation and Installation of Offshore Facilities (Package A), MasaiClient : Global Offshore Malaysia Sdn BhdYear : March 2011 – April 2011Details : Provision of NDT services for WQT

Project : 2011 Integrated Transportation and Installation of Offshore Pipelines and Facilities,offshore Malaysia

Client : TL Offshore Sdn BhdYear : March 2011 – August 2011Details : Provision of NDT Services for offshore structural installation onboard Barge QP 2000

Project : PTTEP Bongkot 3H4A (2011) and Arthit 1D, ThailandClient : Nippon Steel Engineering Co., LtdYear : February 2011 – June 2011Details : Provision of NDT Services for offshore pipeline & structural installation onboard Barge

DLB K-1 (12.75” dia. X 4km and 16” dia. X 23km)

Project : Suriya-B WHP Project for CHOC, BatamClient : Saipem Malaysia Sdn BhdYear : January 2011 – April 2011Details : Provision of NDT services for WPQT / WQT

Project : Baku Waste to Energy Project, Baku, AzerbaijanClient : Ustay Construction – Contracting and Trading Co.Year : January 2011 – PresentDetails : Provision of NDT Services for boiler piping, general piping and utility piping at Balaxani

Project Site

Project : PTTEP Arthit 1D Field Development, ThailandClient : Nippon Steel Engineering Co., LtdYear : January 2011 – February 2011Details : Provision of welding inspection for WPQT/WQP at Amara Yard TNS, Bangkok

Project : Chevron 2011 Installation Campaign, ThailandClient : Nippon Steel Engineering Co., LtdYear : January 2011 – June 2011Details : Provision of NDT Services for offshore pipeline installation onboard Barge DLB K-2 (6”

dia. X 4.511km and 10” dia. X 143.574km)

Project : Arthit Field Development Phase 1D & Bongkot Field Development Phase 4AProjects, Batam

Client : Nippon Steel Engineering Co., LtdYear : November 2010 – January 2011Details : Provision of NDT services and welding inspection for WPQT / WQT

Project : MHN Process Platform and Living Quarters Project and MHNRD-II 4 Well PlatformProject of ONGC, India

Client : L&T Sapura Offshore Pvt. LtdYear : November 2010 – June 2011Details : Provision of NDT services for the installation of four jackets and associated flare decks,

interconnecting bridges, deck crane pedestal and mooring buoy as well as four well headplatforms onboard Barge LTS 3000.

Project : Chim Sao Platforms and Pipelines Project, VietnamClient : Saipem (Portugal) Comercio MaritimoYear : August 2010 – October 2010Details : Provision of NDT services for structural installation onboard Barge Maersk Assister

Page 40: Company Profile.pdf - MOGSC

Page 13 of 23

Project : 2010 Integrated Transportation and Installation of Offshore Pipelines and Facilities,offshore Malaysia

Client : TL Offshore Sdn BhdYear : July 2010 – October 2010Details : Provision of NDT Services for offshore pipeline installation onboard Barge E3 (8” dia. X

3km)

Project : 2010 Integrated Transportation and Installation of Offshore Pipelines and Facilities,offshore Malaysia

Client : TL Offshore Sdn BhdYear : July 2010 – October 2010Details : Provision of NDT Services for offshore structural installation onboard Barge LTS 3000

Project : Provision of Survey & Barge Positioning Services for Carigali-Hess – MRU Project,Batam

Client : Global Offshore Malaysia Sdn BhdYear : June 2010 – July 2010Details : Provision of Onshore and Offshore NDT Services onboard Barge DLB Comanche

Project : 2010 Integrated Transportation and Installation of Offshore Pipelines and Facilities,offshore Malaysia

Client : TL Offshore Sdn BhdYear : June 2010 – October 2010Details : Provision of NDT Services for offshore structural installation onboard Barge QP 2000

Project : 2010 Integrated Transportation and Installation of Offshore Pipelines and Facilities,Pasir Gudang

Client : TL Offshore Sdn BhdYear : May 2010 – June 2010Details : Provision of NDT Services for WPQT / WQT for SSB

Project : Iwaki Platform Decommissioning Project, JapanClient : SapuraAcergy Sdn BhdYear : April 2010 – August 2010Details : Provision of NDT services for the decommissioning of the Iwaki Platform with topside

removal operations, subsea cutting operations, jacket lifting & lowering operation andjacket toppling operations

Project : Chevron 2010 Installation Campaign, ThailandClient : Nippon Steel Engineering Co., LtdYear : March 2010 – November 2010Details : Provision of NDT Services for offshore pipeline & structural installation onboard Barge

DLB K-2 (24” dia. X 36km, 20” dia. X 20.4km, 16” dia. X 28.8km, 18” dia. X 3.72km and10” dia. X 24km)

Project : Chim Sao Platforms and Pipelines Project, VietnamClient : Saipem (Portugal) Comercio MaritimoYear : March 2010 – July 2010Details : Provision of NDT services for pipeline installation (4” dia. X 1.85km, 8” dia. X 1.85km,10”

dia. X 1.85km x 2 lines & 10” dia. x 95.5km) onboard Barge Castoro-8

Project : Integrated Transportation and Installation of Offshore Facilities, Bintulu andTerengganu

Client : Global Offshore Malaysia Sdn BhdYear : March 2010 – September 2010Details : Provision of NDT services for pipeline installation (6” x 1.9km, 16” x 17.7km, 24” x 28.3km

and 24” x 52km), structural and riser installation onboard Barge DLB-264

Page 41: Company Profile.pdf - MOGSC

Page 14 of 23

Project : Turkmenistan Block 1 Gas Development Project, Installation and Pre-commissioning of Offshore Pipelines and Other Associated Civil Works,Turkmenistan

Client : Sigur Ros Sdn BhdYear : March 2010 – November 2011Details : Provision of NDT services for pipeline installation for 4” dia. X 81km, 12” dia. X 107km, 18”

dia. X 8km and 26” dia. X 73km onboard Barge Armada Installer

Project : Pipeline Replacement Programme for BP, IndonesiaClient : Cathem ConsortiumYear : January 2010 – June 2010Details : Provision of NDT services for 6” dia. and 10” dia. pipeline installation x 10km onboard

Barge Kalinda

Project : WPQT / WQT for Chim Sao Project, BatamClient : Saipem (Portugal) Comercio MaritimoYear : January 2010 – May 2010Details : Provision of NDT services for WPQT / WQT

Project : 2010 Integrated Transportation and Installation of Offshore Facilities (Sapura 3000 –Package C)

Client : TL Offshore Sdn BhdYear : February 2010 – April 2010Details : Provision of NDT services for structural installation onboard Barge Sapura 3000

Project : PTTEP Projects (Arthit 1B and Bongkot 3G, Bongkot 3H and 4A and Northern Arthit3N, Thailand

Client : Nippon Steel Engineering Co., LtdYear : January 2010 – September 2010Details : Provision of NDT Services for offshore pipeline & structural installation onboard Barge

DLB K-1 (12.75” dia. X 10.56km)

Project : Colombo Port Expansion Project, Sri LankaClient : Blue Marine Offshore Pte LtdYear : December 2009 – March 2010Details : Provision of NDT Services on 36” dia. X 9.8km offshore pipeline installation on board

Barge Arwana Satu (1)

Project : PTTEP Projects (Arthit 1B and Bongkot 3G, Bongkot 3H and 4A and Northern Arthit3N, Thailand

Client : Nippon Steel Engineering Co., LtdYear : November 2009 – March 2010Details : Provision of NDT Services for offshore pipeline & structural installation onboard Barge

DLB K-2 (8” dia. X 81.739km, 12.75” dia. X 4.258km, 16” dia. X 41.86km, 18” dia. X18.67km and 22” dia. X 35.98km)

Project : WPQT / WQT for Turkmenistan Gas Development Project, Pasir Gudang, Masai andPort Klang

Client : Sigur Ros Sdn BhdYear : November 2009 – January 2010Details : Provision of NDT services for WPQT / WQT

Project : J-Lay Tower Upgrade and Reburbishment, Pasir GudangClient : SapuraAcergy Sdn BhdYear : September 2009 – April 2010 / June 2010 – December 2010Details : Provision of NDT services – MPI & UT – for the J-Lay Tower prior to its installation onto

the Sapura 3000.

Page 42: Company Profile.pdf - MOGSC

Page 15 of 23

Project : WL-A to MCOT Pipeline Project – Onshore, MiriClient : Alam Maritim (M) Sdn BhdYear : September 2009 – November 2009Details : Provision of NDT services for onshore pipeline

Project : PTTEP Bongkot 3H & 4A (Phase-II), Batam & BangkokClient : Nippon Steel Engineering Co., LtdYear : August 2009 – November 2009Details : Provision of NDT services and welding inspection for WPQT / WQT

Project : 18” Crude Trunkline from WLP-A to MCOT, MiriClient : Alam Maritim (M) Sdn BhdYear : August 2009 – November 2009Details : Provision of NDT services for offshore pipeline installation onboard Barges Swiber

Conquest and Kalinda

Project : Labuan – Beaufort Water Pipeline, LabuanClient : Ombak-Wangi JV Sdn BhdYear : May 2009 – July 2009Details : Provision of NDT services for onshore and offshore water pipeline onboard Barge POE

PL-01

Project : Offshore Riser and Spool Installation, BintuluClient : Ombak-Wangi JV Sdn BhdYear : May 2009 – July 2009Details : Provision of NDT Services for riser and spool installation onboard Barge Safeena

Project : Pearl Development Project, VietnamClient : Saipem (Portugal) Comercio MaritimoYear : May 2009 – August 2009Details : Provision of NDT Services for offshore pipeline & structural installation onboard Barge

Castoro-8

Project : NDE for 2009 / 2010 Offshore Campaign Modification Hook-up / CommissioningUmm Shaif Project, Abu Dhabi

Client : Hyundai Heavy Industries Co., LtdYear : June 2009 – January 2010Details : Provision of NDT & AUT Services for structural installation onboard Barges Kawawa, Al-

Hyleh and Marinia

Project : CPOC B-17 Lateral Pipeline Development Project, offshore MalaysiaClient : Real Offshore Installation company Sdn BhdYear : May 2009 – July 2009Details : Provision of NDT Services on 24” x 2.9 km offshore pipeline onboard Barge Java

Constructor

Project : PTTEP Bongkot 3H & 4A, BatamClient : Nippon Steel Engineering Co., LtdYear : May 2009 – July 2009Details : Provision of NDT services and welding inspection for WPQT / WQT

Project : WPQT / WQT in Batam for Huizhou & Panyu Project, BatamClient : Saipem (Portugal) Comercio MaritimoYear : April 2009 – May 2009Details : Provision of NDT services and welding inspection for WPQT / WQT

Page 43: Company Profile.pdf - MOGSC

Page 16 of 23

Project : Batam Pipeline Load In / Out and Coating Inspection, BatamClient : Heerema Marine Contractors Nederland B.V.Year : March 2009 – March 2010Details : Provision of HSE / Safety Representative and Coating Inspector for the load-in / out in

Batam

Project : Welding Inspector for Semac-1, offshore ChinaClient : Saipem (Portugal) Comercio MaritimoYear : March 2009 – June 2009Details : Provision of Welding Inspector onboard Barge Semac-1

Project : Permanent Aviation Fuel Facility Project, Hong KongClient : Leighton Contractors (Asia) LimitedYear : February 2009 – May 2009Details : Provision of NDT Services of the submarine pipeline

Project : WPQT / WQT in Batam for Pearl Project, BatamClient : Saipem (Portugal) Comercio MaritimoYear : March 2009 – May 2009Details : Provision of NDT services and welding inspection for WPQT / WQT

Project : Umm Shaif Gas Injection Facilities Project (Phase 2), Abu DhabiClient : Hyundai Heavy Industries Co., LtdYear : February 2009 – January 2010Details : Provision of NDT Services for structural construction onboard Barge HD-1000

Project : Kuantan (Malaysia) Pipeline Load-in / Out & Coating Inspection, KuantanClient : Heerema Marine Contractors Nederland B/V.Year : January 2009 – December 2009Details : Provision of Coating Inspector for the load-in / out in Kuantan

Project : Mumbai High South Redevelopment Phase II Project, IndiaClient : SapuraAcergy Sdn BhdYear : January 2009 – April 2009Details : Provision of NDT Services for structural installation onboard Barge Sapura-3000

Project : WPQT / WQT in Batam for Ledong Project, BatamClient : Saipem (Portugal) Comercio MaritimoYear : January 2009 – February 2009Details : Provision of NDT services for WPQT / WQT

Project : Last Well Joint for CPC, TaiwanClient : Saipem (Portugal) Comercio MaritimoYear : January 2009 – February 2009Details : Provision of NDT services

Project : WPQT / WQT in for various projects, Pasir GudangClient : Serimax MalaysiaYear : January 2009 – December 2009Details : Provision of NDT services for WPQT / WQT conducted in Pasir Gudang

Project : Talisman PM-3 Bunga Orkid FSO Installation Project, offshore MalaysiaClient : Emas Offshore Construction and Production Pte LtdYear : December 2008 – March 2009Details : Provision of NDT Services for structural installation onboard Barge Lewek Champion

Page 44: Company Profile.pdf - MOGSC

Page 17 of 23

Project : Kambuna Offshore Installation Pipeline Project, IndonesiaClient : PT. Timas SuplindoYear : December 2008 – March 2009Details : Provision of NDT Services for pipeline construction onboard Barge POE-PL1

Project : Coating Inspection Services for Pipe Repair and Loadout (Surplus Pipes) at PPSCfor TTPP3 Project, Kuantan

Client : Saipem Asia Sdn BhdYear : October 2008Details : Provision of Coating Inspector

Project : Shanghai LNG Pipeline Project, ChinaClient : Hyundai Heavy Industries Co., LtdYear : October 2008 – December 2008Details : Provision of NDT Services for pipeline construction onboard Barge HD-289

Project : 12” dia. and 14” dia. Pipeline, Riser and Spool Installation Project for Shell SarawakBerhad, Miri

Client : TL Offshore Sdn BhdYear : August 2008 – September 2008Details : Provision of NDT Services for pipeline and structural installation onboard Barge Lewek

Champion

Project : Non-destructive Services for Offshore Riser and Spool Installation, BintuluClient : Offshore Subsea Works Sdn BhdYear : July 2008 – November 2008Details : Provision of NDT Services for riser fabrication (Onshore) and riser and spool installation

onboard Barge Perwira Perkasa

Project : Arthit North Gas FPSO Installation Project (P801), Pasir Gudang and ThailandClient : Emas Offshore Construction and Production Pte LtdYear : June 2008 – August 2008Details : Provision of MPI Services for structural installation onboard Barges Smit Borneo, Lewek

Toucan and Waldtrout

Project : Umm Shaif Gas Injection Facilities Project, Abu DhabiClient : Hyundai Heavy Industries Co., LtdYear : June 2008 – November 2008Details : Provision of NDT Services for structural installation onboard Barge Al-Hyleh

Project : JVPC Pipelaying and Construction for pipelines P11, P14, P15 and P16, VietnamClient : Global Industries Asia Pacific Pte LtdYear : May 2008 – September 2008Details : Provision of NDT Services for pipeline installation onboard Barge Comanche

Project : C8 Sea Trials for NDT Services, IndonesiaClient : Saipem (Portugal) Comercio MaritimoYear : April 2008 – May 2008Details : Provision of NDT Services for structural installation onboard Barge Castoro-8

Project : Installation of Stalk-On Risers for Block PM-3 CAA Northern Fields Developent,offshore Malaysia

Client : TL Offshore Sdn BhdYear : April 2008 – July 2008Details : Provision of NDT Services for pipeline construction onboard Barge Lewek Champion

Page 45: Company Profile.pdf - MOGSC

Page 18 of 23

Project : SK Crude Oil Unloading System relocation, KoreaClient : Hyundai Heavy Industries Co., LtdYear : Apr 2008 – July 2008Details : Provision of NDT Services for pipeline construction onboard Barge HD-289

Project : 36” Taichung-Tunghsiao-Tatan Project, Taiwan (Phase 2)Client : Saipem (Portugal) Comercio MaritimoYear : April 2008 – September 2008Details : Provision of NDT Services for pipeline construction onboard Barge Semac-1

Project : V/0038 – New Build Barge H-405, ChinaClient : Heerema Marine Contractors Nederland B.V.Year : April 2008 – May 2008Details : Provision of Painting & Coating Inspector

Project : V/0038 – New Build Barge H-405, ChinaClient : Heerema Marine Contractors Nederland B.V.Year : March 2008 – April 2008Details : Provision of UT Inspector

Project : Talisman Offshore Pipeline Installation, offshore MalaysiaClient : Swiber Offshore Construction Pte LtdYear : March 2008 – April 2008Details : Provision of NDT Services for offshore installation onboard Barge HD-60

Project : Semco Giant 5 Project, BatamClient : Swiber Offshore Construction Pte LtdYear : March 2008 – April 2008Details : Provision of Welding Inspector for fabrication of grillage / sea fastening

Project : Umm Shaif Gas Injection Facilities Project, Abu DhabiClient : Hyundai Heavy Industries Co., LtdYear : March 2008 – November 2008Details : Provision of NDT Services for structural construction onboard Barge HD-1000

Project : Umm Shaif Gas Injection Facilities Project, Abu DhabiClient : Hyundai Heavy Industries Co., LtdYear : March 2008 – November 2008Details : Provision of NDT Services for pipeline construction onboard Barge HD-2500

Project : Block Ravva Pipeline Installation, IndiaClient : Saipem (Portugal) Comercio MaritimoYear : February 2008 – May 2008Details : Provision of NDT Services for offshore installation onboard Barge Castoro-10

Project : Puteri Offshore Pipeline Installation, offshore MalaysiaClient : Swiber Offshore Construction Pte LtdYear : February 2008 – March 2008Details : Provision of NDT Services for offshore installation onboard Barge HD-60

Project : Galoc Philippine Project, PhilippinesClient : Emas Offshore Construction & Production Pte LtdYear : February 2008 – march 2008Details : Provision of NDT services for offshore installation onboard Barge Lewek Champion

Page 46: Company Profile.pdf - MOGSC

Page 19 of 23

Project : EMEPMI Guntung-F to Tapis –E Project, offshore MalaysiaClient : TL Offshore Sdn BhdYear : January 2008 – February 2008Details : Provision of NDT services for offshore installation onboard Barge Lewek Champion and

structural installation on Jerneh ‘B’ Platform.

Project : Kodeco-Merlasakti-PPP Jacket & Topside ProjectClient : Swiber Offshore Construction Pte LtdYear : January 2008 – February 2008Details : Provision of NDT services for offshore installation onboard Barge Dalihao

Project : GFI Bualang Field Project, ThailandClient : Emas Offshore Construction & Production Pte LtdYear : November 2007 – January 2008Details : Provision of NDT services for offshore installation onboard Barge Lewek Champion

Project : Sumandak ‘B’ Jacket Installation Project, offshore Labuan, MalaysiaClient : Swiber Offshore Construction Pte LtdYear : October 2007 – January 2008Details : Provision of NDT Services for structural installation onboard Barge Dalihao

Project : Total Peciko Field Development Project – Phase 5, IndonesiaClient : PT. Nippon Steel Construction Indonesia (Nisconi) / PT Radiant Utama InterinscoYear : August 2007 – September 2007Details : Provision of NDT and QC Work Services for offshore installation onboard Barge K-1

Project : Installation of Puteri Well Head Platform, offshore Terengganu, MalaysiaClient : Swiber Offshore Construction Pte LtdYear : August 2007 – September 2007Details : Provision of NDT Services for structural installation onboard Barge Dalihao

Project : Talisman & Newfield Offshore Installation Project, Offshore MalaysiaClient : Intraline Resources Sdn BhdYear : August 2007 – December 2007Details : Provision of NDT Services for pipeline installation onboard Barge Java Constructor

Project : Talisman & Newfield Offshore Installation Project, Offshore Malaysia / VietnamClient : Intraline Resources Sdn BhdYear : May 2007 – December 2007Details : Provision of NDT Services for pipeline installation onboard Barge HD-60

Project : Talisman & Newfield Onshore Johor PortClient : Intraline Resources Sdn BhdYear : May 2007 – December 2007Details : Provision of NDT Services for onshore pipe spool fabrication

Project : North Sea Project, NorwayClient : Shaw Pipeline ServicesYear : May 2007 – August 2007Details : Provision of Crawler Technician for the offshore pipeline installation

Project : Dung Quat Refinery Project, VietnamClient : JFE Engineering CorporationYear : May 2007 – July 2007Details : Provision of NDT Services for onshore pipeline project installation.

Page 47: Company Profile.pdf - MOGSC

Page 20 of 23

Project : Aramco Project, Saudi ArabiaClient : McDermott / Shaw Pipeline ServicesYear : May 2007 – July 2007Details : Provision of NDT Services for offshore pipeline installation

Project : CHOC Kencana Bumi Bulan & Suriya Gas Field Development Project, Malaysia /Thailand

Client : Saipem Luxembourg S.A.Year : June 2007 – October 2007Details : Provision of NDT Services for structural installation onboard Barge Castoro-8

Project : 36” Taichung-Tunghsiao-Tatan Project, TaiwanClient : Saipem (Portugal) Comercio MaritimoYear : June 2007 – August 2007Details : Provision of NDT Services for pipeline construction onboard Barge Semac-1

Project : CHOC Kencana Bumi Bulan & Suriya Gas Field Development Project, Malaysia /Thailand

Client : Saipem Luxembourg S.A.Year : May 2007 – August 2007Details : Provision of NDT Services for pipeline construction onboard Barge Castoro-10

Project : V/0038 – New Build Barge H-405, ChinaClient : Heerema Marine Contractors Nederland B.V.Year : May 2007 – May 2008Details : Provision of Welding Inspector

Project : QP Bul Hanine and Maydan Mahzam Development, QatarClient : Sime Darby Engineering Sdn BhdYear : April 2007 – December 2007Details : Provision of NDT Services for the EPCIC of BH-D05A, BH-MO4A and BH-IO3A Wellhead

Jackets, Topsides, Pipelines, Tie-Ins and Topsides Modifications

Project : Abu Cluster Phase II Project, Offshore MalaysiaClient : Apecs Offshore Pte LtdYear : January 2007 – April 2007Details : Provision of NDT services for pipeline and installation onboard barge DB Seminole

Project : Chevron 2007 Installation Campaign : Installation of Platforms and Pipelines,Thailand

Client : Nippon Steel Engineering Co., LtdYear : February 2007 – October 2007Details : Provision of NDT Services for offshore pipeline and structural installation onboard Barge

K-2.

Project : KJO McDermott Saudi Pipeline ProjectClient : McDermott / Shaw Pipeline ServicesYear : January 2007 – February 2007Details : Provision of NDT Services for offshore pipeline installation.

Project : Sisi Nubi Field Development Project, IndonesiaClient : Nippon Steel Engineering Co., LtdYear : January 2007 – May 2007Details : Provision of NDT services for the offshore structure installation onboard Barge K-1.

Page 48: Company Profile.pdf - MOGSC

Page 21 of 23

Project : Sisi Nubi Field Development Project, IndonesiaClient : Hyundai Heavy Industries Co., LtdYear : January 2007 – March 2007Details : Provision of NDT services on 16” dia. x 6.5km, 22” dia. x 15.2km and 26” dia. x 33km gas

pipeline onboard Barge HD-60.

Project : Jackson-Tarbot 10” Pipeline, Queensland, AustraliaClient : Global Technical ServicesYear : January 2007 – March 2007Details : Provision of NDT Services for onshore pipeline installation

Project : Dung Quat Refinery Project, VietnamClient : JFE Engineering CorporationYear : December 2006 – August 2007Details : Provision of Quality Control / Quality Assurance Manpower for the Dung Quat Refinery.

Project : Khursaniyah (Aramco) Project, Saudi ArabiaClient : McDermott / Shaw Pipeline ServicesYear : November 2006 – February 2007Details : Provision of NDT Services for offshore pipeline installation.

Project : BTIP – Onshore Facilities / Offshore Pipeline Project, NigeriaClient : Hyundai Heavy Industries Co., LtdYear : November 2006 – July 2007Details : Provision of NDT Services for the Bonny Terminal Integrated Project onboard Barge HD-

289.

Project : PGN, South Sumatra – West Java Gas Pipeline Project (Phase II)Client : Hyundai Heavy Industries Co., LtdYear : September 2006 – December 2006Details : Provision of NDT services on 32” dia. x 145km gas pipeline onboard Barge HD-60,

Indonesia

Project : Rong Doi Gas Development Project – Phase 1 and 2, VietnamClient : Hyundai Heavy Industries Co., LtdYear : August 2006 – October 2006Details : Provision of NDT services for Rang Doi Hook Up onboard Barge Hyundai Offshore-1 (HO-

1)

Project : Abu Cluster Field DevelopmentClient : Apecs Offshore Pte. LtdYear : August 2006 – September 2006Details : Provision of Welding Inspector on 6” and 8” dia. pipeline and structural installation for

Petronas Carigali, onboard Barge NTL 900, offshore Terengganu

Project : Abu Cluster Field DevelopmentClient : Apecs Offshore Pte. LtdYear : July 2006 – October 2006Details : Provision of NDT services on 6” and 8” dia. pipeline and structural installation for Petronas

Carigali, offshore Terengganu.

Project : Sakhalin Topside Project, Sakhalin Energy, RussiaClient : Saipem SpAYear : June 2006 – October 2006Details : Provision of QA/QC Supply Services onboard Castoro 8.

Page 49: Company Profile.pdf - MOGSC

Page 22 of 23

Project : Sakhalin II, Phase 2 – Offshore Pipelines & Cables, Sakhalin Energy, RussiaClient : Saipem SpAYear : June 2006 – October 2006Details : Provision of NDT services on 14” dia. x 95km offshore pipeline onboard Semac-1.

Project : Rong Doi Gas Development Project – Phase 1 and 2, VietnamClient : Hyundai Heavy Industries Co., LtdYear : April 2006 to October 2006Details : Provision of NDT services for 6” and 18” dia. pipeline and structural installation onboard

Barge HD-2500.

Project : South Sumatra – West Java (SSWJ) 32” dia. Pipeline Project, IndonesiaClient : Nippon Steel Corporation / PT. Radiant Utama InterinscoYear : February 2006 to May 2006Details : Provision of NDT services for Welder training WQT on 32” dia. pipe in Batam, Indonesia

Project : Premier West Lobe Wellhead Platform, IndonesiaClient : PT. Nippon Steel Construction Indonesia / PT. Radiant Utama InterinscoYear February 2006 to May 2006Details : Provision of NDT Services on 14” dia. offshore pipeline and structural installation

Project : Wangnoi Khaengkoi Project, ThailandClient : Nacap Thailand / Qualitech Co., LtdYear November 2005 to August 2006Details : Provision of NDT Services on 36” dia. X 73km onshore pipeline

Project : 3rd Transmission Pipeline Project, ThailandClient : CPP & TRC Joint Venture / Qualitech Co., LtdYear November 2005 to August 2006Details : Provision of NDT Services on 36” and 42” dia. onshore pipeline

Project : Petronas Gas Berhad Onshore Pipeline Project, Johor, MalaysiaClient : JFE Engineering (M) Sdn Bhd / Eastern Soldar Eng’rg & Const. Sdn BhdYear December 2005 to April 2006Details : Provision of NDT Services on 24” dia. X 1.5km onshore pipeline

Project : Singapore Gas Pipeline Offshore Project, Malaysia & SingaporeClient : JFE Engineering (M) Sdn BhdYear February 2006 to March 2006Details : Provision of NDT Services on 24” and 30” dia. X 4.2km offshore pipeline installation

Page 50: Company Profile.pdf - MOGSC

Page 23 of 23

UAV INSPECTION

Project : Unmanned Aerial Inspection Survey for offshore installations, offshore Kota Bharu,Malaysia

Client : Velosi / RepsolYear : May 2015Details : Provision of Unmanned Aerial Inspection survey on PM3 North & South platforms of

Flare/Vent/Telecom/Towers/Flare Anchoring points/Compressor Exhaust Ducts/Pipesupports etc.,– ahead of planned shutdowns in August.

Project : UAV & Thermal Imagery Inspection (Oil & Gas installations – Onshore & OffshoreSabah, Malaysia

Client : Petronas Carigali Sdn BhdYear : April 2015Details : Provision of Thermal Imagery and UAV Inspection of HP & LP flare tips, vent tips, flare

structures, flare booms, telecommunication towers, etc., in addition to thermal imagerysurvey for flare inconsistencies. Onshore installations inspected in Kota Kinabalu, Labuanand offshore at several locations. Allowed engineering staff to plan and prepare forshutdown in advance of works.

Project : UAV Inspection of Talisman South Angsi “A” Platform, Offshore Terengganu,Malaysia

Client : Velosi Specialised Inspection / Talisman EnergyYear : July 2014Details : Provision of UAV Inspection of flare tips, crane boom, MOAB, wellhead structure,

conductor guide frames, riser and underdeck as well as thermal survey checking forleakage and lagging damage