Commitment Text Source Reference Timeframe (Project Phase) Status Accountable Lead Comments Enbridge will provide to the NEB, no later than July 15, 2016, a preliminary Enbridge Environment Protection Plan (“EPP”) that includes mitigation measures for pipeline and related facilities construction, as well as decommissioning of the existing pipeline, as committed to in Enbridge’s Application [NEB Filing ID: A74506 and A74508]. The preliminary EPP will be posted on the NEB website and will be available to the public for review. NEB Filing ID: A77228- 2, PDF Page 41 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] Enbridge’s Enbridge Environment Guidelines for Construction (“EGC”) are used, in part, to develop the project-specific preliminary EPP, which will be filed with the NEB and provided to you no later than July 15, 2016. Applicable EGC content is incorporated into the preliminary EPP, which may be modified as necessary to ensure Enbridge Environment mitigation is specific to the scope of the Project. The preliminary EPP is the project-specific document that will be used and referenced for Enbridge Environment mitigation during construction. NEB Filing ID: A77228- 2, PDF Page 41 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] A listing of Restricted Activity Periods ("RAPs") and associated species will be provided in the preliminary EPP that will be filed with the NEB no later than July 15, 2016. NEB Filing ID: A77227- 2, PDF Page 66 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] For the displacement, cleaning, and general construction activities, all waste water will be treated and/or disposed of according to applicable local laws, regulations, and Enbridge Operations and Maintenance Manuals (“OMMs”). Water with parameters that exceed applicable provincial or federal guidelines will be treated until it can be released to the environment, or disposed of at an approved waste facility. Mitigation for wastewater management will be included in the preliminary Project Enbridge EPP to be filed with the NEB no later than July 15, 2016. In addition, Enbridge’s Waste Management Plan (2014) will be adhered to in order to avoid contaminant introduction during Project activities. NEB Filing ID: A77227- 2, PDF Page 8 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] Schedule construction activities near residential areas, community facilities (e.g., golf courses, parks), or privately owned businesses during the period from 7:00 am to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions. Note that some construction activities, once started, must continue on a 24hour basis (e.g., an horizontal directional drill ("HDD") may be continuous until completion). In the event of afterhours noise during construction (e.g., potential use of generators at HDD sites), Enbridge will ensure affected landowners are notified in advance and any required approvals are obtained. NEB Filing ID: A77228- 2, PDF Page 54 Pre-Construction In Progress Enbridge Construction/Enbridge Land Services Initial measures in place, management of the commitment is ongoing. Pipeline construction activities on the right-of-way ("ROW") or temporary workspace will not have direct disruption to any golf course based on the routing presented to the NEB within the application. Enbridge will manage secondary effects such as traffic disruption, noise, and dust using the mitigation measures that follow. (Schedule construction activities near privately owned businesses during the period from 7:00 am to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions.) NEB Filing ID: A77227- 2, PDF Page 63 Pre-Construction In Progress Enbridge Construction Initial measures in place, management of the commitment is ongoing. A detailed list (including start and end kilometer posts) of the pipeline sections (portions), based on terrain, water, road and railway crossings, as well as current and potential land use along the entire ROW of the Replaced Segment will be provided when these details have been finalized. Note: This commitment has been supersceded by response to NEB IR#3.1.a where the detailed information in this commitment will be included in the Decommissioning Enbridge Environment Technical Report to be submitted to the NEB on August 15, 2016. NEB Filing ID: A77227- 2, PDF Page 2 Pre-Construction Completed Enbridge Environment NEB Filing ID: A78683-2, PDF Page 1 and 2 An assessment of the biophysical and socio-economic elements for deviations that are greater than 50 meters from the center line of Enbridge’s proposed route is anticipated to be filed on August 15, 2016. It is anticipated that the Enbridge Environment and Socio-economic Assessment ("ESA") conditions for these route deviations are similar to those previously described in the ESA [NEB Filing ID: A74508-2], given that the route deviations are relatively short and close to the proposed replacement pipeline route. As such, it is further anticipated that significance conclusions of the ESA will remain unchanged for potential Project effects and cumulative effects. NEB Filing ID: A77227- 2, PDF Page 42 Pre-Construction Completed Enbridge Environment ESA Filed on August 15, 2016 [NEB Filing ID: A78970] Enbridge commits to the monitoring of provincial and federal species at risk listings and updates to federally-identified critical habitat for wildlife potentially affected by the Project, and providing updates if necessary to the NEB during the hearing process. NEB Filing ID: A77227- 2, PDF Page 54 Pre-Construction; Construction In Progress Enbridge Environment Ongoing Enbridge Pipelines Inc. Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017 Condition 11 - Commitments Tracking Table Filed October 13, 2017 Page 1 of 3
3

Commitment Text Source Reference Timeframe (Project Phase ...

Jan 02, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Commitment Text Source Reference Timeframe (Project Phase ...

Commitment Text Source Reference Timeframe (Project Phase) Status Accountable Lead Comments

Enbridge will provide to the NEB, no later than July 15, 2016, a preliminary Enbridge Environment

Protection Plan (“EPP”) that includes mitigation measures for pipeline and related facilities

construction, as well as decommissioning of the existing pipeline, as committed to in Enbridge’s

Application [NEB Filing ID: A74506 and A74508]. The preliminary EPP will be posted on the NEB

website and will be available to the public for review.

NEB Filing ID: A77228-

2, PDF Page 41

Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]

Enbridge’s Enbridge Environment Guidelines for Construction (“EGC”) are used, in part, to develop

the project-specific preliminary EPP, which will be filed with the NEB and provided to you no later

than July 15, 2016. Applicable EGC content is incorporated into the preliminary EPP, which may be

modified as necessary to ensure Enbridge Environment mitigation is specific to the scope of the

Project. The preliminary EPP is the project-specific document that will be used and referenced for

Enbridge Environment mitigation during construction.

NEB Filing ID: A77228-

2, PDF Page 41

Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]

A listing of Restricted Activity Periods ("RAPs") and associated species will be provided in the

preliminary EPP that will be filed with the NEB no later than July 15,

2016.

NEB Filing ID: A77227-

2, PDF Page 66

Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]

For the displacement, cleaning, and general construction activities, all waste water will be treated

and/or disposed of according to applicable local laws, regulations, and Enbridge Operations and

Maintenance Manuals (“OMMs”). Water with parameters that exceed applicable provincial or federal

guidelines will be treated until it can be released to the environment, or disposed of at an approved

waste facility. Mitigation for wastewater management will be included in the preliminary Project

Enbridge EPP to be filed with the NEB no later than July 15, 2016. In addition, Enbridge’s Waste

Management Plan (2014) will be adhered to in order to avoid contaminant introduction during

Project activities.

NEB Filing ID: A77227-

2, PDF Page 8

Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]

Schedule construction activities near residential areas, community facilities (e.g., golf courses,

parks), or privately owned businesses during the period from 7:00 am to 7:00 pm, or in

accordance with applicable noise bylaws or approval conditions. Note that some construction

activities, once started, must continue on a 24‑hour basis (e.g., an horizontal directional drill

("HDD") may be continuous until completion). In the event of afterhours noise during construction

(e.g., potential use of generators at HDD sites), Enbridge will ensure affected landowners are

notified in advance and any required approvals are obtained.

NEB Filing ID: A77228-

2, PDF Page 54

Pre-Construction In Progress Enbridge Construction/Enbridge Land Services Initial measures in place, management of the commitment is ongoing.

Pipeline construction activities on the right-of-way ("ROW") or temporary workspace will not have

direct disruption to any golf course based on the routing presented to the NEB within the

application. Enbridge will manage secondary effects such as traffic disruption, noise, and dust using

the mitigation measures that follow.

(Schedule construction activities near privately owned businesses during the period from 7:00 am

to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions.)

NEB Filing ID: A77227-

2, PDF Page 63

Pre-Construction In Progress Enbridge Construction Initial measures in place, management of the commitment is ongoing.

A detailed list (including start and end kilometer posts) of the pipeline sections (portions), based on

terrain, water, road and railway crossings, as well as current and potential land use along the entire

ROW of the Replaced Segment will be provided when these details have been finalized.

Note: This commitment has been supersceded by response to NEB IR#3.1.a where the detailed

information in this commitment will be included in the Decommissioning Enbridge Environment

Technical Report to be submitted to the NEB on August 15, 2016.

NEB Filing ID: A77227-

2, PDF Page 2

Pre-Construction Completed Enbridge Environment NEB Filing ID: A78683-2, PDF Page 1 and 2

An assessment of the biophysical and socio-economic elements for deviations that are greater than

50 meters from the center line of Enbridge’s proposed route is anticipated to be filed on August 15,

2016. It is anticipated that the Enbridge Environment and Socio-economic Assessment ("ESA")

conditions for these route deviations are similar to those previously described in the ESA [NEB

Filing ID: A74508-2], given that the route deviations are relatively short and close to the proposed

replacement pipeline route. As such, it is further anticipated that significance conclusions of the

ESA will remain unchanged for potential Project effects and cumulative effects.

NEB Filing ID: A77227-

2, PDF Page 42

Pre-Construction Completed Enbridge Environment ESA Filed on August 15, 2016 [NEB Filing ID: A78970]

Enbridge commits to the monitoring of provincial and federal species at risk listings and updates to

federally-identified critical habitat for wildlife potentially affected by the Project, and providing

updates if necessary to the NEB during the hearing process.

NEB Filing ID: A77227-

2, PDF Page 54

Pre-Construction; Construction In Progress Enbridge Environment Ongoing

Enbridge Pipelines Inc.

Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017

Condition 11 - Commitments Tracking Table Filed October 13, 2017

Page 1 of 3

Page 2: Commitment Text Source Reference Timeframe (Project Phase ...

Commitment Text Source Reference Timeframe (Project Phase Status Accountable Lead Comments

In the event that watercourse construction activities need to occur within the instream restricted

activity timing windows, a qualified fish biologist, in consultation with the appropriate regulatory

authority, will determine appropriate mitigation measures. These may include assessing the

crossing location for the presence of fish and mussels prior to construction work beginning,

conducting fish and mussel salvage from the work site, and relocating fish and mussels to suitable

nearby habitat. In addition, Enbridge will reduce instream work duration by ensuring all equipment

and supplies are on site prior to commencement to the extent feasible, completing work in as little

time as possible, and maintaining the natural volume of stream flow at all times. All activities will be

in accordance with approvals from the appropriate regulatory authorities. A qualified fish biologist

will be available, as needed, during instream construction activities to provide advice to reduce

impacts and ensure compliance with regulatory approvals.

NEB Filing ID: A77227-

2, PDF Page 67

Pre-Construction; Construction In Progress Enbridge Environment Ongoing

The most current watercourse listing for the project was filed with the Board in the preliminary

project EPP on July 15, 2016 [NEB filing: A78552] in Appendix O, Table

2. However, further updates will be added to the table for the Electrical Transmission Corridor

Route (once field data is summarized) and for any subsequent reroutes that may affect

watercourses. Updates will be submitted to the Board prior to the commencement of construction.

NEB Filing ID: A79404-

2, PDF Page 7

Pre-Construction Completed Enbridge Environment An updated watercourse crossing list was filed with the Board in compliance with

Condition 7 [NEB Filing ID: A83623]

Enbridge is committed to restoring irrigation systems affected by pipeline construction to their

preconstruction condition (or equivalent) based upon consultation/agreements with individual

landowners and site specific conditions.

NEB Filing ID: A77228-

2, PDF Page 48

Post-Construction Scheduled Enbridge Construction This will be reviewed post-construction.

The proposed mitigation for the Project will avoid vegetation clearing during the pre-volant period

when bats are less resilient to disturbance. Sensory disturbance as a result of construction activities

will be temporary. The proposed mitigation to avoid operation of heavy equipment between dusk

and dawn will reduce potential for sensory disturbance of roosting bats.

NEB Filing ID: A79569-

2, PDF Page 13

Pre-Construction; Construction Completed Enbridge Environment Complete

Enbridge commits to offsetting any impacts to identified critical bat habitat. Enbridge is committed

to installing bat boxes to mitigate habitat loss. Enbridge commits to putting the information in the

Enbridge Environment protection plan and on the alignment sheets to avoid and maintain bat

maternity roosting habitat to the extent possible.

NEB Filing ID: A80119-

1, PDF Page 16, 17

Pre-construction; Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]

Enbridge will consult with the appropriate government agencies, including Environment and Climate

Change Canada ("ECCC"), as warranted, if red-headed woodpeckers, eastern whip-poor-wills or

any other migratory bird species at risk listed under Schedule 1 of the Species at Risk Act is

identified that has not previously been identified and is considered to potentially be impacted by

the Project. Additionally, if proposed mitigation measures to reduce potential effects to those

species change from described in the application or are determined to be unsuccessful, Enbridge

will consult with the appropriate agencies.

NEB Filing ID: A79569-

2, PDF Page 15

Pre-Construction; Construction In Progress Enbridge Environment Ongoing

Ensure that test water withdrawn from one regional watershed will not enter into another regional

watershed. The location of regional watersheds along the pipeline route are identified on the

Enbridge Environment Alignment Sheets and

include:

• Grand River Regional Watershed;

• Hamilton Region Watersheds; and

• Niagara Peninsula Region Watersheds.

NEB Filing ID: A78552-

2, PDF Page 49

Construction Scheduled Enbridge Environment The project will use municipal water for the mainline hydrotest and the disposal will

be directed to the City of Hamilton sanitary sewer.

Environmental supplemental studies to be completed in spring 2017

include:

• Rare plant surveys (spring and summer);

• Weed surveys;

• Amphibian breeding surveys;

• Jefferson Salamander pond suitability studies;

• Bobolink/Eastern Meadowlark surveys;

• Breeding bird surveys; and,

• Crepuscular bird surveys.

The results from these surveys will be summarized and provided to

the NEB after the 2017 Spring surveys have been completed.

NEB Fiing ID: A79858-

2, PDF Page 7

Construction In Progress Enbridge Environment The updated survey results are expected to be filed in October, 2017

Enbridge Pipelines Inc.

Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017

Condition 11 - Commitments Tracking Table Filed October 13, 2017

Page 2 of 3

Page 3: Commitment Text Source Reference Timeframe (Project Phase ...

Commitment Text Source Reference Timeframe (Project Phase Status Accountable Lead Comments

Updates to the EPP and EAS will be made prior to construction based on the results of field surveys

along the Electrical Transmission Corridor Route ("ETCR"), including the resource-specific mitigation

measures and locations.

NEB Filing ID: A79406-

8, PDF Page 11

Pre-Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]

Enbridge will identify areas on the final Enbridge Environment alignment sheets noted in Reference

i) (i.e., ornamental trees, shelterbelts, windbreaks) where mitigation measures will be applied and

include a description of how the mitigation options will be applied.

NEB Filing ID: A79404-

2, PDF Page 14

Pre-Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]

Enbridge commits to retaining Six Nations of the Grand River ("Six Nations") monitors to participate

in construction monitoring for the purpose of monitoring effects on resource uses important to Six

Nations.

NEB Filing ID: A80075-

1, PDF Page 78 ; NEB

Filing ID: A80119-

1, PDF Page 37, 64

Pre-Construction Completed Legal and Regulatory The Aboriginal Monitoring Plan was filed with the Board on June 15,

2017 [NEB Filing ID: A84446]

Enbridge to confirm crossing methods and provide to Niagara Peninsula Conservation Authority

("NPCA"). Monitoring Plan and EPP to be shared with NPCA. A field visit during construction to be

offered to NPCA Staff.

NEB Filing ID: A78970-

2, PDF Page 21

Pre-Construction Scheduled Enbridge Environment Ongoing

To date Enbridge has not consulted on noise levels associated with HDD activities to directly

affected landowners. Once construction drilling rig specifications are finalized including anticipated

noise levels, Enbridge will further consult with directly affected landowners within 200 m of the

HDD location on the noise levels and appropriate mitigations as previously outlined in Enbridge’s IR

No.2 response

2.26 a.3, as well Section 6.0 of the Preliminary Enbridge Environment Protection

Plan [NEB Filing ID A5D8Y1].

NEB Filing ID: A79404-

2, PDF Page 26

Pre-Construction In Progress Enbridge Land Services Enbridge has undertaken HDD consultation with all landowners within 1000m of

the HDD drill locations. All directly affected landowners with residences within

150m of the HDD entry and exit points shall receive a form of compensation to

mitigate impacts associated with increased construction traffic and noise levels

during the HDD drilling activities. Landowner concerns raised during HDD activity

will be addressed and mitigation measures from the EPP will be utilized.

Prior to HDD activity, an Enbridge representative will make reasonable efforts to contact the

landowner a minimum of seven days in advance of startup. We will then work with the landowner

to discuss access, estimated compensation for potential impacts, determine a preferred work

schedule, review Enbridge Environment and safety considerations provide Enbridge contact

information, and address any questions and property-specific concerns.

NEB Filing ID: A79404-

2, PDF Page 27

Pre-Construction In Progress Enbridge Land Services Pre-construction meetings were held with all directly affected landowners to review

consultation materials, answer questions and to discuss any questions or concerns

prior to commencing construction. Any landowner commitments made have been

documented and provided to the construction contractor. HDD Consultation was

undertaken with all directly affected landowners within 1000m proximity to the

HDD drill exit and entry points. Seven days prior to the HDD activity beginning,

Enbridge representatives made reasonable efforts to provide reminder notifications

of the upcoming activity.

Butternut trees at one location were assessed on July 6, 2016 by a Butternut Health Assessor. The

assessment of the additional trees that may be impacted will occur in the fall of 2016. The results

of these assessments will be submitted to the Ministry of Natural Resources and Forestry ("MNRF")

after the results have been determined and will be included in a Supplemental Enbridge

Environment and Socio- economic Impact Assessment and/or Enbridge Environment Protection

Plan, as appropriate.

NEB Filing ID: A79404-

2, PDF Page 18

Pre-Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]

Enbridge has committed to complete pre-construction water well sampling (and monitoring for all 9

tracts of land to ensure water wells are not adversely affected by construction of the project.

NEB Filing ID: A79889-

5, PDF Page 1

Pre-Construction Completed Enbridge Environment Sampling was completed in 2016.

Enbridge committed to installing a wall of hay bales along the edge of the construction footprint to

minimize dust and noise from construction activities. (Landowner Consultation on 1 tract)

NEB Filing ID: A79889-

5, PDF Page 2

Pre-Construction Cancelled Enbridge Construction Landowner agreed to alternative dust control meassures as required.

Enbridge will be in contact with they city of Hamilton as well as the local school board to inform

them of upcoming construction activities in order to determine the appropriate mitigation to ensure

school bus routes are not negatively impacted by construction.

NEB Filing ID: A79889-

5, PDF Page 2

Pre-Construction Ongoing Enbridge Public Affairs Ongoing

Enbridge commits to follow up beyond the five year timeframe of post-construction monitoring to

ensure wetland regeneration has taken place. (Condition 30)

NEB Filing ID: A80119-

1, PDF Page 37

Operations Scheduled Enbridge Environment Scheduled

Enbridge Pipelines Inc.

Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017

Condition 11 - Commitments Tracking Table Filed October 13, 2017

Page 3 of 3