Commitment Text Source Reference Timeframe (Project Phase) Status Accountable Lead Comments Enbridge will provide to the NEB, no later than July 15, 2016, a preliminary Enbridge Environment Protection Plan (“EPP”) that includes mitigation measures for pipeline and related facilities construction, as well as decommissioning of the existing pipeline, as committed to in Enbridge’s Application [NEB Filing ID: A74506 and A74508]. The preliminary EPP will be posted on the NEB website and will be available to the public for review. NEB Filing ID: A77228- 2, PDF Page 41 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] Enbridge’s Enbridge Environment Guidelines for Construction (“EGC”) are used, in part, to develop the project-specific preliminary EPP, which will be filed with the NEB and provided to you no later than July 15, 2016. Applicable EGC content is incorporated into the preliminary EPP, which may be modified as necessary to ensure Enbridge Environment mitigation is specific to the scope of the Project. The preliminary EPP is the project-specific document that will be used and referenced for Enbridge Environment mitigation during construction. NEB Filing ID: A77228- 2, PDF Page 41 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] A listing of Restricted Activity Periods ("RAPs") and associated species will be provided in the preliminary EPP that will be filed with the NEB no later than July 15, 2016. NEB Filing ID: A77227- 2, PDF Page 66 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] For the displacement, cleaning, and general construction activities, all waste water will be treated and/or disposed of according to applicable local laws, regulations, and Enbridge Operations and Maintenance Manuals (“OMMs”). Water with parameters that exceed applicable provincial or federal guidelines will be treated until it can be released to the environment, or disposed of at an approved waste facility. Mitigation for wastewater management will be included in the preliminary Project Enbridge EPP to be filed with the NEB no later than July 15, 2016. In addition, Enbridge’s Waste Management Plan (2014) will be adhered to in order to avoid contaminant introduction during Project activities. NEB Filing ID: A77227- 2, PDF Page 8 Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552] Schedule construction activities near residential areas, community facilities (e.g., golf courses, parks), or privately owned businesses during the period from 7:00 am to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions. Note that some construction activities, once started, must continue on a 24‑hour basis (e.g., an horizontal directional drill ("HDD") may be continuous until completion). In the event of afterhours noise during construction (e.g., potential use of generators at HDD sites), Enbridge will ensure affected landowners are notified in advance and any required approvals are obtained. NEB Filing ID: A77228- 2, PDF Page 54 Pre-Construction In Progress Enbridge Construction/Enbridge Land Services Initial measures in place, management of the commitment is ongoing. Pipeline construction activities on the right-of-way ("ROW") or temporary workspace will not have direct disruption to any golf course based on the routing presented to the NEB within the application. Enbridge will manage secondary effects such as traffic disruption, noise, and dust using the mitigation measures that follow. (Schedule construction activities near privately owned businesses during the period from 7:00 am to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions.) NEB Filing ID: A77227- 2, PDF Page 63 Pre-Construction In Progress Enbridge Construction Initial measures in place, management of the commitment is ongoing. A detailed list (including start and end kilometer posts) of the pipeline sections (portions), based on terrain, water, road and railway crossings, as well as current and potential land use along the entire ROW of the Replaced Segment will be provided when these details have been finalized. Note: This commitment has been supersceded by response to NEB IR#3.1.a where the detailed information in this commitment will be included in the Decommissioning Enbridge Environment Technical Report to be submitted to the NEB on August 15, 2016. NEB Filing ID: A77227- 2, PDF Page 2 Pre-Construction Completed Enbridge Environment NEB Filing ID: A78683-2, PDF Page 1 and 2 An assessment of the biophysical and socio-economic elements for deviations that are greater than 50 meters from the center line of Enbridge’s proposed route is anticipated to be filed on August 15, 2016. It is anticipated that the Enbridge Environment and Socio-economic Assessment ("ESA") conditions for these route deviations are similar to those previously described in the ESA [NEB Filing ID: A74508-2], given that the route deviations are relatively short and close to the proposed replacement pipeline route. As such, it is further anticipated that significance conclusions of the ESA will remain unchanged for potential Project effects and cumulative effects. NEB Filing ID: A77227- 2, PDF Page 42 Pre-Construction Completed Enbridge Environment ESA Filed on August 15, 2016 [NEB Filing ID: A78970] Enbridge commits to the monitoring of provincial and federal species at risk listings and updates to federally-identified critical habitat for wildlife potentially affected by the Project, and providing updates if necessary to the NEB during the hearing process. NEB Filing ID: A77227- 2, PDF Page 54 Pre-Construction; Construction In Progress Enbridge Environment Ongoing Enbridge Pipelines Inc. Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017 Condition 11 - Commitments Tracking Table Filed October 13, 2017 Page 1 of 3
3
Embed
Commitment Text Source Reference Timeframe (Project Phase ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Commitment Text Source Reference Timeframe (Project Phase) Status Accountable Lead Comments
Enbridge will provide to the NEB, no later than July 15, 2016, a preliminary Enbridge Environment
Protection Plan (“EPP”) that includes mitigation measures for pipeline and related facilities
construction, as well as decommissioning of the existing pipeline, as committed to in Enbridge’s
Application [NEB Filing ID: A74506 and A74508]. The preliminary EPP will be posted on the NEB
website and will be available to the public for review.
NEB Filing ID: A77228-
2, PDF Page 41
Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]
Enbridge’s Enbridge Environment Guidelines for Construction (“EGC”) are used, in part, to develop
the project-specific preliminary EPP, which will be filed with the NEB and provided to you no later
than July 15, 2016. Applicable EGC content is incorporated into the preliminary EPP, which may be
modified as necessary to ensure Enbridge Environment mitigation is specific to the scope of the
Project. The preliminary EPP is the project-specific document that will be used and referenced for
Enbridge Environment mitigation during construction.
NEB Filing ID: A77228-
2, PDF Page 41
Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]
A listing of Restricted Activity Periods ("RAPs") and associated species will be provided in the
preliminary EPP that will be filed with the NEB no later than July 15,
2016.
NEB Filing ID: A77227-
2, PDF Page 66
Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]
For the displacement, cleaning, and general construction activities, all waste water will be treated
and/or disposed of according to applicable local laws, regulations, and Enbridge Operations and
Maintenance Manuals (“OMMs”). Water with parameters that exceed applicable provincial or federal
guidelines will be treated until it can be released to the environment, or disposed of at an approved
waste facility. Mitigation for wastewater management will be included in the preliminary Project
Enbridge EPP to be filed with the NEB no later than July 15, 2016. In addition, Enbridge’s Waste
Management Plan (2014) will be adhered to in order to avoid contaminant introduction during
Project activities.
NEB Filing ID: A77227-
2, PDF Page 8
Pre-Construction Completed Enbridge Environment The EPP was filed with the Board on July 15, 2016 [NEB Filing ID: A78552]
Schedule construction activities near residential areas, community facilities (e.g., golf courses,
parks), or privately owned businesses during the period from 7:00 am to 7:00 pm, or in
accordance with applicable noise bylaws or approval conditions. Note that some construction
activities, once started, must continue on a 24‑hour basis (e.g., an horizontal directional drill
("HDD") may be continuous until completion). In the event of afterhours noise during construction
(e.g., potential use of generators at HDD sites), Enbridge will ensure affected landowners are
notified in advance and any required approvals are obtained.
NEB Filing ID: A77228-
2, PDF Page 54
Pre-Construction In Progress Enbridge Construction/Enbridge Land Services Initial measures in place, management of the commitment is ongoing.
Pipeline construction activities on the right-of-way ("ROW") or temporary workspace will not have
direct disruption to any golf course based on the routing presented to the NEB within the
application. Enbridge will manage secondary effects such as traffic disruption, noise, and dust using
the mitigation measures that follow.
(Schedule construction activities near privately owned businesses during the period from 7:00 am
to 7:00 pm, or in accordance with applicable noise bylaws or approval conditions.)
NEB Filing ID: A77227-
2, PDF Page 63
Pre-Construction In Progress Enbridge Construction Initial measures in place, management of the commitment is ongoing.
A detailed list (including start and end kilometer posts) of the pipeline sections (portions), based on
terrain, water, road and railway crossings, as well as current and potential land use along the entire
ROW of the Replaced Segment will be provided when these details have been finalized.
Note: This commitment has been supersceded by response to NEB IR#3.1.a where the detailed
information in this commitment will be included in the Decommissioning Enbridge Environment
Technical Report to be submitted to the NEB on August 15, 2016.
NEB Filing ID: A77227-
2, PDF Page 2
Pre-Construction Completed Enbridge Environment NEB Filing ID: A78683-2, PDF Page 1 and 2
An assessment of the biophysical and socio-economic elements for deviations that are greater than
50 meters from the center line of Enbridge’s proposed route is anticipated to be filed on August 15,
2016. It is anticipated that the Enbridge Environment and Socio-economic Assessment ("ESA")
conditions for these route deviations are similar to those previously described in the ESA [NEB
Filing ID: A74508-2], given that the route deviations are relatively short and close to the proposed
replacement pipeline route. As such, it is further anticipated that significance conclusions of the
ESA will remain unchanged for potential Project effects and cumulative effects.
NEB Filing ID: A77227-
2, PDF Page 42
Pre-Construction Completed Enbridge Environment ESA Filed on August 15, 2016 [NEB Filing ID: A78970]
Enbridge commits to the monitoring of provincial and federal species at risk listings and updates to
federally-identified critical habitat for wildlife potentially affected by the Project, and providing
updates if necessary to the NEB during the hearing process.
NEB Filing ID: A77227-
2, PDF Page 54
Pre-Construction; Construction In Progress Enbridge Environment Ongoing
Enbridge Pipelines Inc.
Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017
Condition 11 - Commitments Tracking Table Filed October 13, 2017
Page 1 of 3
Commitment Text Source Reference Timeframe (Project Phase Status Accountable Lead Comments
In the event that watercourse construction activities need to occur within the instream restricted
activity timing windows, a qualified fish biologist, in consultation with the appropriate regulatory
authority, will determine appropriate mitigation measures. These may include assessing the
crossing location for the presence of fish and mussels prior to construction work beginning,
conducting fish and mussel salvage from the work site, and relocating fish and mussels to suitable
nearby habitat. In addition, Enbridge will reduce instream work duration by ensuring all equipment
and supplies are on site prior to commencement to the extent feasible, completing work in as little
time as possible, and maintaining the natural volume of stream flow at all times. All activities will be
in accordance with approvals from the appropriate regulatory authorities. A qualified fish biologist
will be available, as needed, during instream construction activities to provide advice to reduce
impacts and ensure compliance with regulatory approvals.
NEB Filing ID: A77227-
2, PDF Page 67
Pre-Construction; Construction In Progress Enbridge Environment Ongoing
The most current watercourse listing for the project was filed with the Board in the preliminary
project EPP on July 15, 2016 [NEB filing: A78552] in Appendix O, Table
2. However, further updates will be added to the table for the Electrical Transmission Corridor
Route (once field data is summarized) and for any subsequent reroutes that may affect
watercourses. Updates will be submitted to the Board prior to the commencement of construction.
NEB Filing ID: A79404-
2, PDF Page 7
Pre-Construction Completed Enbridge Environment An updated watercourse crossing list was filed with the Board in compliance with
Condition 7 [NEB Filing ID: A83623]
Enbridge is committed to restoring irrigation systems affected by pipeline construction to their
preconstruction condition (or equivalent) based upon consultation/agreements with individual
landowners and site specific conditions.
NEB Filing ID: A77228-
2, PDF Page 48
Post-Construction Scheduled Enbridge Construction This will be reviewed post-construction.
The proposed mitigation for the Project will avoid vegetation clearing during the pre-volant period
when bats are less resilient to disturbance. Sensory disturbance as a result of construction activities
will be temporary. The proposed mitigation to avoid operation of heavy equipment between dusk
and dawn will reduce potential for sensory disturbance of roosting bats.
NEB Filing ID: A79569-
2, PDF Page 13
Pre-Construction; Construction Completed Enbridge Environment Complete
Enbridge commits to offsetting any impacts to identified critical bat habitat. Enbridge is committed
to installing bat boxes to mitigate habitat loss. Enbridge commits to putting the information in the
Enbridge Environment protection plan and on the alignment sheets to avoid and maintain bat
maternity roosting habitat to the extent possible.
NEB Filing ID: A80119-
1, PDF Page 16, 17
Pre-construction; Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]
Enbridge will consult with the appropriate government agencies, including Environment and Climate
Change Canada ("ECCC"), as warranted, if red-headed woodpeckers, eastern whip-poor-wills or
any other migratory bird species at risk listed under Schedule 1 of the Species at Risk Act is
identified that has not previously been identified and is considered to potentially be impacted by
the Project. Additionally, if proposed mitigation measures to reduce potential effects to those
species change from described in the application or are determined to be unsuccessful, Enbridge
will consult with the appropriate agencies.
NEB Filing ID: A79569-
2, PDF Page 15
Pre-Construction; Construction In Progress Enbridge Environment Ongoing
Ensure that test water withdrawn from one regional watershed will not enter into another regional
watershed. The location of regional watersheds along the pipeline route are identified on the
Enbridge Environment Alignment Sheets and
include:
• Grand River Regional Watershed;
• Hamilton Region Watersheds; and
• Niagara Peninsula Region Watersheds.
NEB Filing ID: A78552-
2, PDF Page 49
Construction Scheduled Enbridge Environment The project will use municipal water for the mainline hydrotest and the disposal will
be directed to the City of Hamilton sanitary sewer.
Environmental supplemental studies to be completed in spring 2017
include:
• Rare plant surveys (spring and summer);
• Weed surveys;
• Amphibian breeding surveys;
• Jefferson Salamander pond suitability studies;
• Bobolink/Eastern Meadowlark surveys;
• Breeding bird surveys; and,
• Crepuscular bird surveys.
The results from these surveys will be summarized and provided to
the NEB after the 2017 Spring surveys have been completed.
NEB Fiing ID: A79858-
2, PDF Page 7
Construction In Progress Enbridge Environment The updated survey results are expected to be filed in October, 2017
Enbridge Pipelines Inc.
Line 10 Westover Segment Replacement Project Commitments Tracking Table for the period ending September 30, 2017
Condition 11 - Commitments Tracking Table Filed October 13, 2017
Page 2 of 3
Commitment Text Source Reference Timeframe (Project Phase Status Accountable Lead Comments
Updates to the EPP and EAS will be made prior to construction based on the results of field surveys
along the Electrical Transmission Corridor Route ("ETCR"), including the resource-specific mitigation
measures and locations.
NEB Filing ID: A79406-
8, PDF Page 11
Pre-Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]
Enbridge will identify areas on the final Enbridge Environment alignment sheets noted in Reference
i) (i.e., ornamental trees, shelterbelts, windbreaks) where mitigation measures will be applied and
include a description of how the mitigation options will be applied.
NEB Filing ID: A79404-
2, PDF Page 14
Pre-Construction Completed Enbridge Environment The updated EPP and EAS were filed on May 31, 2017 [NEB Filing ID: A84069]
Enbridge commits to retaining Six Nations of the Grand River ("Six Nations") monitors to participate
in construction monitoring for the purpose of monitoring effects on resource uses important to Six
Nations.
NEB Filing ID: A80075-
1, PDF Page 78 ; NEB
Filing ID: A80119-
1, PDF Page 37, 64
Pre-Construction Completed Legal and Regulatory The Aboriginal Monitoring Plan was filed with the Board on June 15,
2017 [NEB Filing ID: A84446]
Enbridge to confirm crossing methods and provide to Niagara Peninsula Conservation Authority
("NPCA"). Monitoring Plan and EPP to be shared with NPCA. A field visit during construction to be