Commissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1 st May 2014
14

Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Mar 25, 2018

Download

Documents

vutruc
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Commissioning and Test Plans

Generator CommissioningProcess Workshop

Presenter: Kevin WronskiDate: 1st May 2014

Page 2: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Where they sit within a Project:

Design Build Commission/Test

Jointly AssessAsset

Capability

Risks?Performance

Requirements?

Prepare andagree Plans

Commission/Test

tt –2+ years t –1+ year t – 6 mths

Page 3: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Commissioning Plan

CommissioningPlan

Appendix 1Eng Test Plans

Week AheadSchedule

Appendix 2Operational Test

Plans

Day Aheadschedule

Page 4: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Typical (Minimum) Timelines

CommissioningPlan

Appendix 1Eng Test Plans

Week AheadSchedule

Appendix 2Operational Test

Plans

Day Aheadschedule

8 – 10 Week prior

6 – 8 Week prior

2 - 3Week prior

Page 5: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Commissioning vs Test Plans

A few terms used in our presentations are oftenunderstood differently depending on thecircumstances.• A “Commissioning Plan ” is what is needed to

connect a new or refurbished asset to the gridfor the first time

• A “Test Plan” is what is needed when the assetis to be tested whilst connected to the grid

Page 6: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Things that need to be included• A place to note the agreement of both the Asset

Owner and the System Operator to the plan• A timetable containing the sequence of events

necessary to connect the assets to the grid andconduct any proposed system tests; and

• Protection and control settings to be appliedbefore livening of the assets

Page 7: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Things that have proved very useful

• Communications Protocols to be used;• Summary of any Risk Assessments;• Confirmation of Protection sign-off;• Confirmation that SCADA will be available;• Acknowledgement of any specific “Trading

Arrangements” that need to be implemented

Page 8: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Test Plan

• Should be prepared by the Asset Owner inconsultation with the system operator– required for tests carried out whilst connected

to the power system– standard template available

http://www.systemoperator.co.nz/sites/default/files/bulk-upload/documents/FM-EA-010_Test_Plan.pdf

– high MW tests need more time for analysis[as a guide > 100 MW (north island) > 60 MW (south island)]

Page 9: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Test Plan Template

Page 10: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Test Plan Template

Page 11: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Both Commissioning and TestPlans allow for:

• Declaration of any additional risk that may beneeded for the unit under test

• Agreement for release from performance relatedobligations during the period that the plan covers(or a subset of it)

Page 12: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

“Engineering” Test Plans

• Detail the purpose of the test• Lists special requirements of the test• Lists data points / signals to be recorded

and sampling rates• Review of Engineering Test Plans by the

System Operator can help ensure testingis carried out in the most appropriatemanner to achieve agreed outcomes

Page 13: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Week Ahead Plans

• Give an overview of MW and MVArschedules

• List any particular items of interest forwitnessing or risks that need mitigating

• Submitted once every 7 days, rather thana rolling week plan submitted daily

Page 14: Commissioning and Test Plans - Transpower · PDF fileCommissioning and Test Plans Generator Commissioning Process Workshop Presenter: Kevin Wronski Date: 1st May 2014

Day Ahead Plans

• Best estimate MW and MVAr schedules• Submitted daily, 7 days a week