2/30
Commercial Heat Pump 1. Components
Manifold Kit (Optional)
Manifold tube
Branch Assembly(Gate or Ball Valve Only)
End cap
Threaded reducer
8/12/2019 Commercial Heat Pump Installation - Sample
3/30
Commercial Heat Pump 1. Components
Components
Storage tanksHeat p ump
8/12/2019 Commercial Heat Pump Installation - Sample
4/30
Commercial Heat Pump 2. Clearances
Heat pump requires 900mm
service clearance at each end.
8/12/2019 Commercial Heat Pump Installation - Sample
5/30
Commercial Heat Pump 3. Mark out position of pipes and tanks
Mark out position of
all pipes on wall.
Mark out position of
storage tanks on floor.Manifold tube
T Piece
Copper pip e
Elbows
Manifold tub e
Manifold tube
Manifold tube
Manifold tube
Manifold tube
Coldwater inlet train
8/12/2019 Commercial Heat Pump Installation - Sample
6/30
Commercial Heat Pump 4. Connect pipes
Solder all joints as required.
Manifold tubes
End cap
T Piece
Copper pipe
End cap
Elbows
Secure all pipes to wall with
pipe clamps as required.
Coldwater inlet train
Hot Water Supply Out
End cap
8/12/2019 Commercial Heat Pump Installation - Sample
7/30
Commercial Heat Pump 5. Connect cold water inlet train
Cold water inlet train.
Drain line must terminate
at least 1 metre away from tank.
(AS/NZS 3500.4)
Copper Inlet Pipe
Pressure Limiting
Valve (If Required)
Isolation Valve
Expansion Control
Valve (if required)
No Return Valve
8/12/2019 Commercial Heat Pump Installation - Sample
8/30
Commercial Heat Pump 6. Position storage tanks
Place storage tanks in position.
8/12/2019 Commercial Heat Pump Installation - Sample
9/30
Commercial Heat Pump 7. Connect reducer fittings
Connect reducer fittings.
Repeat for all inlets/outlets on each
storage tank.
8/12/2019 Commercial Heat Pump Installation - Sample
10/30
Commercial Heat Pump 8. Fit branch assemblies
Check position of tanks
inlets/outlets must be parallel to wall.
Fit the branch assembly to manifold
and storage tank.
Solder connections as required.
Compression nut,
Flared pipe end or
similar
NB: Gate valve or ball valve ONLY to
be used in branches
DO NOT install non-return valves
or loose jumper valves
Solder connection here
Isolation Valve
8/12/2019 Commercial Heat Pump Installation - Sample
11/30
Commercial Heat Pump 8. Fit branch assemblies
Repeat fitting of branch assemblies
to all required inlets/outlets.
8/12/2019 Commercial Heat Pump Installation - Sample
12/30
Commercial Heat Pump 9. Connect TPR valves
Connect TPR valves to each tank.
8/12/2019 Commercial Heat Pump Installation - Sample
13/30
Commercial Heat Pump 9. Connect TPR valves
Fit drain lines to each
TPR valve.
TPR Valves can drain into a
common tundish.
Terminate drain lines at least
1 metre away from tanks.
Drain line must terminate
at least 1 metre away from t ank.
(AS/NZS 3500.4)
Tundish
8/12/2019 Commercial Heat Pump Installation - Sample
14/30
Commercial Heat Pump 10. Position Heat Pump
Position Heat Pump.
Note alignment of inlet and outlet pipes
8/12/2019 Commercial Heat Pump Installation - Sample
15/30
Commercial Heat Pump 11. Connect cold water inlet pipe
Connect primary flow to heat pump.
Note: non return valve is not required
after primary pump.
Connect to Heat
Pump inletPrimary Pump
Isolation Valve
8/12/2019 Commercial Heat Pump Installation - Sample
16/30
Commercial Heat Pump 12. Connect hot water return line
Connect the primary hot
water return line.
Connect to outlet
Isolation Valve
8/12/2019 Commercial Heat Pump Installation - Sample
17/30
Commercial Heat Pump 12. Connect hot water return line
Connect the drain line to
the pressure relief valve.
Drain line must termin ate at least
1 metre away from Heat Pump
and Tank(s). (AS/NZS 3500.4)
8/12/2019 Commercial Heat Pump Installation - Sample
18/30
Commercial Heat Pump 13. Connect main power
Remove the front cover panel.
8/12/2019 Commercial Heat Pump Installation - Sample
19/30
8/12/2019 Commercial Heat Pump Installation - Sample
20/30
Commercial Heat Pump 13. Connect main power
Connect the 3 Phase power cable.
Secure wires with screws provided
in the Terminal Block.
Observe correct phase rotation.
Tighten firmly.
8/12/2019 Commercial Heat Pump Installation - Sample
21/30
Commercial Heat Pump 13. Connect main power
Secure the conduit to heat pump
using brackets.
Tighten screws firmly.
Do not obstruct cover panel opening.
8/12/2019 Commercial Heat Pump Installation - Sample
22/30
Commercial Heat Pump 14. Connect wiring to primary pump
Connect primary circulation
pump wiring to heat pump.
8/12/2019 Commercial Heat Pump Installation - Sample
23/30
Commercial Heat Pump 14. Connect wiring to primary pump
Connect primary pump wiring to heat pump.
8/12/2019 Commercial Heat Pump Installation - Sample
24/30
8/12/2019 Commercial Heat Pump Installation - Sample
25/30
Commercial Heat Pump 14. Connect wiring to primary pump
Remove pump cover screw. Remove pump cover.
8/12/2019 Commercial Heat Pump Installation - Sample
26/30
Commercial Heat Pump 14. Connect wiring to primary pump
Connect wiring to primary pump using push-fit
connectors on the terminal block.
Push retaining lug down and insert wire
8/12/2019 Commercial Heat Pump Installation - Sample
27/30
Commercial Heat Pump 14. Connect wiring to primary pump
Replace pump cover and screw.
If outdoors affix a suitable weather
cover over the primary pump.
8/12/2019 Commercial Heat Pump Installation - Sample
28/30
Commercial Heat Pump 15. Fit tank sensor
Remove the protective cap from one of the tanks.
Remove the threaded plug.
Insert the sensor well into the tank and tighten firmly.
8/12/2019 Commercial Heat Pump Installation - Sample
29/30
Commercial Heat Pump 16. Replace heat pump cover panel
Replace Heat Pump cover panel. Secure conduit.
Do not obstruct control panel opening.
8/12/2019 Commercial Heat Pump Installation - Sample
30/30
Commercial Heat Pump 17. Commissioning
Refer to instructions for commissioning the unit.