Top Banner

of 23

Commercial Context of Project Management

Apr 03, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 Commercial Context of Project Management

    1/23

    2013

    David Aime Masvosvere

    Student ID: 1113855

    3/24/2013

    The Commercial Context

    Module: BS3353

    Assignment

    Case Study: Proposed Thames

    Estuary Airport Hub Project

  • 7/28/2019 Commercial Context of Project Management

    2/23

    2 | P a g e

    EXECUTIVE SUMMARY

    Calls for a new airport for London and the UK have been heard for decades. Each time a proposal has

    been made alternative measures to avoid building an airport in the London Thames estuary have

    been sought. Now however, cries to have this airport structure in the Thames have been voiced ever

    more loudly by London mayor Boris Johnson, Lord Foster and a few others.

    The main issue of contention with the project has been the sketchy financials along with

    environmental concerns. These environmental concerns despite having been echoed by many a

    British politician pale in comparison to the financiability and logistical matter. As will be noted in this

    document in quotes and extracts from BBC articles, Government literature and consultancy reports

    by economist firms among others, presently this project is just too risky and lacks detail in areas

    where necessary.

    A report prepared for the House of Commons Transport Select Committee deals a hugeblow to the project, claiming it would be a risky investment.

    It says that because the value of the investment is significantly negative an investor wouldbe likely not to touch the project.

    A public subsidy of 10-30 billion would be needed to get the airport built, the report by

    economics consultancy Oxera suggests.

    The reports authors have calculated the value of a new airport at 15.6 billion bycalculating revenues from passenger charges and taking out operating costs.

    In todays money it would have costs of 43.7 billion, leaving a significant gap that would

    need to be made up.

    If Heathrow were to close as the result of a Thames Estuary airport being built, the final

    compensation bill could be as high as 20 billion.

    Thomas of Foster + Partners, the architects behind plans for the worlds biggest airport on

    the Isle of Grain, will answer questions on the proposal, which has an estimated cost of 50

    billion.1

    1http://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspx

  • 7/28/2019 Commercial Context of Project Management

    3/23

    3 | P a g e

    CONTENTS

    EXECUTIVE SUMMARY2

    TABLES AND FIGURES USED..4

    PART A..5

    1. Overview.5

    2. COSTS ...7

    3. AIRPORT VALUE.8

    4. AIRPORT COST9

    5. ARR..9

    6. IRR9

    7. NPV.10

    8. PAYBACK PERIOD11

    PART B.12

    1. PURCHASING AND SUPPLY12

    2. COMMERCIAL ISSUES AND RELATED RISKS IN THE TENDERING AND CONTRACT PHASES...16

    2.1 IDENTIFYING NEED AND PLANNING PURCHASE.16

    2.2 SELECTING TENDERER..17

    2.3 CONTRACT MANAGEMENT...17

    CONCLUSIONS.20

    RECOMMENDATIONS21

    REFERENCES21

    BIBLIOGRAPHY OF SOURCES CONSULTED BUT NOT DIRECTLY REFERRED TO WITHIN THE

    WORK...22

  • 7/28/2019 Commercial Context of Project Management

    4/23

    4 | P a g e

    TABLES AND FIGURES USED

    Constrained and unconstrained Demand

    Cost estimate

    Airport value

    Cost forecast

    NPV

    Cash flow Model

    Procurement Cycle

    Procurement process

    The city of London in 2009 proposed to have the following structure for procurement

    Procurement Strategy

  • 7/28/2019 Commercial Context of Project Management

    5/23

    5 | P a g e

    PART A

    1. Overview

    In assessing whether a new hub airport would be commercially feasible, the first deliberation is the

    extent of future demand from passengers and freight. Forecasts estimate the revenue that could be

    earned from a new airport, and hence the expected cash flows. The UK Department for Transport

    (DfT) published official projections in January 2013 of constrained and unconstrained future UK

    aviation demand.

  • 7/28/2019 Commercial Context of Project Management

    6/23

    6 | P a g e

    As seen above forecasts for traffic have been lowered substantially since 2007.

    Also it is worth noting that on top of providing services to presently constrained traffic, if all traffic

    that would otherwise have used Heathrow Airport were to be moved to a new airport, there would be

    an additional 85m passengers per annum (mppa) available for the new hub in 2050 that is with the

    assumption that a 100% transfer, from Heathrow happens.

    Economics consultancy firm Oxeras analysis, scenarios where Heathrow closed assume 100% from

    Heathrow to the Thames Airport hub, whereas if Heathrow remains open no transfer is assumed.

    It is also likely that abstraction from Gatwick and Stansted Airports is a concern, which jointly is

    projected to provide 70mppa in 2050, though full abstraction is improbable. It is important to notethat, Oxeras base-case scenario has been to assume that there is no abstraction from these airports

    and, in a high-case scenario, that there is abstraction of traffic from full-service carriers at Gatwick

    (30%) and Stansted (3%) that will transfer to the new hub. These assumptions should cover the fullrange of likely outcomes, with the outturn level of traffic transfer likely to be somewhere in

    between.2

    2http://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdf

  • 7/28/2019 Commercial Context of Project Management

    7/23

    7 | P a g e

    2. COSTS

    It is pertinent to note that due to the number of proposal with varying specification (i.e. number of

    runways etc) costs estimates vary. Oxera collated cost estimates from a few proposals adjusting for

    inflation where necessary as is seam below.

    As seen above a new airport in the Thames Estuary would probably cost in the range of 20 billion to

    50 billion. The reason for a wide range of cost estimates comes primarily from conflicting estimateswith regard to surface access costs. As most of the proposals outlined are indicative only, it remains

    unclear whether this accounts for optimism bias. Repercussions of optimism bias on cost projections

    are a great concern as they can result in cost overruns in the order of 50% to 100% for major

    infrastructure Projects

    Oxeras analysis assumes that a new UK hub airportwould open and be fully functional in

    around 2025, which, from the proposals to date, appears to be a reasonable base case,although it is likely that a staged opening would occur in practice.3

    An important aspect that most miss to mention and Oxera also noted, was the lack of details on

    compensation in the event that Heathrow is closed, this was not addressed in many of the proposals.

    With the current value of Heathrows regulatory asset base (RAB) around 13 billion, with pastestimates having suggested that total compensation for the closure of Heathrow could be as high as

    20 billion taking into account compensation to airlines, this is a major aspect in regard to the

    Thames airport project cost worth noting. The Thames Estuary proposal will not have location

    compensation to worry about but there is a prospect for the incurrence of environmental costs as

    many have opposed the project on an environmental basis.

    3http://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdf

  • 7/28/2019 Commercial Context of Project Management

    8/23

    8 | P a g e

    3. AIRPORT VALUE

    According to Oxera the resulting figure came about by estimating revenues from forecast passengers

    with the assumption that each paid the forecast charges net of operating costs. After this, revenues

    are then calculated using todays money with a discount factor reflecting the time value of money

    between now and the period when the airport is operational. Then result of this calculation is 15.6

    billion.

  • 7/28/2019 Commercial Context of Project Management

    9/23

    9 | P a g e

    4. AIRPORT COSTUsing data from the same Economic consultancy firm the following was discovered. With use of acomparable basis the calculation takes a cost estimate for a four-runway hub which is slated above

    70 billion inclusive of compensation, this cost is then calculated in todays money using a discount

    factor. If an assumption of an investment programme over time duration of ten years till 2025, with

    compensation after the new airport becomes operational, the resultant cost is 43.7 billion.

    5. ACCOUNTING RATE OF RETURN (ARR )This is an appraisal technique that considers a simple estimate of a project's or investment's

    profitability, subtracting money invested from returns without regard to interest accrual or

    applicable taxes. This method is widely used for investment appraisals and capital

    budgeting decisions. How to reach a decision is simple, one easy way is to accept projects with an

    accounting rate of return that is higher than the cost of capital and reject those that do not.

    With regard to the Thames project using ARR is difficult due to the uncertainty of the financials. Theexpected returns and capital investment required are yet to be determined. However it would be a

    more than competent technique for a project of this magnitude.

    6. INTERNAL RATE OF RETURN (IRR)

    This method of appraisal works along with Net Present Value (NPV) as it is the discount rate at

    which the NPV of costs of the investment equals the net present value of the of the investment. Hence

    it is a method of capital budgeting which can calculate IRR and compare it with cut off rate for

    selecting any project. NPV and IRR have been used together as appraisal tools and given good results.

    As far as the Thames Airport project is concerned, after looking at the financial forecasts and in

    particular the hugely negative NPV it is my assumption that the IRR is lower than Cost of Capitaltherefore is a bad investment.

    http://www.investinganswers.com/financial-dictionary/investing/investment-4904http://www.investinganswers.com/financial-dictionary/economics/money-5074http://www.investinganswers.com/financial-dictionary/tax-center/taxes-4567http://en.wikipedia.org/wiki/Discount_ratehttp://en.wikipedia.org/wiki/Net_present_valuehttp://en.wikipedia.org/wiki/Net_present_valuehttp://en.wikipedia.org/wiki/Net_present_valuehttp://en.wikipedia.org/wiki/Net_present_valuehttp://en.wikipedia.org/wiki/Discount_ratehttp://www.investinganswers.com/financial-dictionary/tax-center/taxes-4567http://www.investinganswers.com/financial-dictionary/economics/money-5074http://www.investinganswers.com/financial-dictionary/investing/investment-4904
  • 7/28/2019 Commercial Context of Project Management

    10/23

    10 | P a g e

    7. NPVThis appraisal technique takes into account the present value of net cash inflows generated by aproject including salvage value, if any, less the initial investment on the project. This methods

    reliability in capital budgeting is based on accounting for time value of money with the use

    discounted cash inflows.

    The Net Present Value (NPV) of this project is negative taking into account that subtracting costsfrom the airport value when cost is higher than the airport value renders a negative figure. From a

    finance standpoint a based on this NPV value an investor would be unlikely to embark on the

    investment. This then implies that the collective investment in a new airport in addition to related

    infrastructure is improbable as a commercial investment. However it may still be possible to finance

    the projectin the new airport infrastructure of around 20 billion alone, but only through injection

    of substantial levels of public subsidy and investment for the surface access and compensation, which

    would comprise around 6075% of the total investment cost.4

    4http://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdf

    http://accountingexplained.com/related/tvm/http://accountingexplained.com/related/tvm/
  • 7/28/2019 Commercial Context of Project Management

    11/23

    11 | P a g e

    Cash flow Model

    8. PAYBACK PERIOD

    This appraisal technique is one of the simplest and takes into account the time in which the initial

    cash outflow of an investment is expected to be recovered from the cash inflows generated by the

    investment.

    According to the House of Commons, The ambitious and wide-ranging set of developments intendedto fix Britains creaking infrastructure would cost in the region of 50 billion (20 billion for the

    airport and 30 billion for the other infrastructure improvements), though the authors claimed that if

    implemented the plan could generate 150 billion - 35bn from the airport, 35bn from road and

    rail; 2bn from environmental management and 75bn from growth in the Thames Hub area.5

    The main issue with a lot of contention is the time frame needed to recoup the funding and begin

    experiencing profitability here. Giving the planning and construction timetables its highly unlikely anew airport could be operational within 25 years. Given the pressing needs of the UK economy to

    meet the current demand for international travel, inaction over this period would be highly

    detrimental to recovery and growth.6

    5http://www.parliament.uk/briefing-papers/SN04920.pdf6 http://eandt.theiet.org/magazine/2013/03/debate.cfm

    http://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdf
  • 7/28/2019 Commercial Context of Project Management

    12/23

    12 | P a g e

    PART B

    3. PURCHASING AND SUPPLY

    Purchasing and supply can be defined as the acquisition or rendering of goods, services or works. It is

    complimentary that the goods, services or works are appropriate and that they are availed at the best

    possible cost, quality, quantity, time, and location. It important to note that Corporations and publicbodies often define processes intended to uphold fair and open competition for their business while

    reducing contact to racketeering and conspiracy.

    Due to the magnitude of this project the essential success criterion is the well-timed, precise to excellence

    and gainful delivery of supplies, systems and amenities. There are many stakeholders, contractors and

    suppliers involved in this kind of project, not forgetting consulting firms. Due to this procurement

    methodologies and processes are fundamental to ensuring that project resources are delivered as

    requisite.

    Procurement Cycle

    http://en.wikipedia.org/wiki/Total_cost_of_ownershiphttp://en.wikipedia.org/wiki/Total_cost_of_ownership
  • 7/28/2019 Commercial Context of Project Management

    13/23

    13 | P a g e

    The Procurement Process

  • 7/28/2019 Commercial Context of Project Management

    14/23

    14 | P a g e

    The city of London in 2009 proposed to have the following structure for procurement.

    As far as Strategy goes I looked at the Just in time strategy used mostly in Japan and despite it being

    comprehensive I was not convinced it would serve this project well. As will be seen below I have a

    diagram with a strategy proposed in New South Wales that I believe would be suitable to the Thames

    project.

  • 7/28/2019 Commercial Context of Project Management

    15/23

    15 | P a g e

    7 http://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProcurementStrategy.pdf

  • 7/28/2019 Commercial Context of Project Management

    16/23

    16 | P a g e

    4. COMMERCIAL ISSUES AND RELATED RISKS IN THE TENDERING AND CONTRACT PHASES

    2.1 IDENTIFYING NEED AND PLANNING PURCHASE

    Potential Risk Probable Effect of risk Action required to Counter Effects

    Understatement of the need Purchase of unsuitableproduct or service

    Money wasted

    Need not satisfied

    Analyse need accurately

    Overstatement of the need Greater expense

    Poor competition

    Analyse need accurately

    Use functional and performance

    requirements

    Misinterpretation of user

    needs

    Totally unacceptable

    purchase or not most suitable

    product or service

    Time lost

    Increased costs

    Possible downtime

    Improve consultation with users

    Obtain clear statement of work and

    definition of need

    Insufficient funding Delay in making the purchase

    Additional costs for re-tender

    Obtain appropriate approvals before

    undertaking process

    Improve planning

    Impractical timeframe Inadequate responses from

    tenderers

    Reduced competitionDelivery schedule not met

    Improve forecasting, planning and

    consultation with users

    Improve communication with potentialtenderers

    Probity issues Increased procurement costs

    Misuse of resources

    Most suitable product notobtained

    Unethical conduct

    Implement best practice policies,

    guidelines and practices

    Maintain ethical environment

    Improve training of personnel

    Put suitable controls and reviews in place

    Consider using a probity adviser

    Improve communication with potential

    tenderers

  • 7/28/2019 Commercial Context of Project Management

    17/23

    17 | P a g e

    2.2 SELECTING TENDERER

    Potential Risk Probable Effect of risk Action required to Counter Effects

    Selecting an inappropriate

    supplier

    Failure to fulfil the contract Provide staff with appropriate tender

    evaluation, financial and technical skills

    training and commercial expertise

    Improve evaluation procedures

    Improve evaluation criteria and clearly

    identify them to tenderers in tender

    documents

    Reject unacceptable offers

    Perform financial, technical and company

    evaluations before awarding contract

    Procurement Review Committee to

    review tender and selection process prior

    to awarding contract

    Selecting inappropriate

    productFailure to meet the clientsneed

    Ensure users are involved in the

    evaluation/selection process

    Improve technical evaluation procedures

    and train staff as appropriate

    Procurement Review Committee to

    review tender and selection process prior

    to awarding contract

    2.3 CONTRACT MANAGEMENT

    Potential Risk Probable Effect of risk Action required to Counter Effects

    Variations in price and foreign

    exchange

    Cost overruns Agree on prices and the basis of prices

    Agree on a formula for calculating

    variations

    Unwillingness of the supplier

    to accept the contract

    Delays in delivery

    Need to restart procurement

    Seek legal redress if non-acceptance

    causes loss

    Negotiate but retain integrity of thecontract

    Failure of either party to fulfil

    the conditions of the contract

    Contract disputes

    Failure to satisfy needs

    Delays in delivery

    Downtime

    Legal action

    Ensure good contract administration and

    performance management

    Hold regular inspections / meetings and

    ensure progress reports

    Ensure all staff know responsibilities and

    conditions

    Ensure good record keeping and

  • 7/28/2019 Commercial Context of Project Management

    18/23

    18 | P a g e

    Potential Risk Probable Effect of risk Action required to Counter Effects

    documentation

    Inadequately administering

    the contract

    Cost increases

    Failure of contract

    Full benefits not achieved

    Delivery of unsatisfactory

    product

    Contract/supply disputes

    Maintain up-to-date agency procedures

    and practices

    Ensure all staff are suitably trained andexperienced in contract planning and

    management

    Commencement of work by

    the supplier before contract is

    exchanged or letter of

    acceptance issued

    Potential liability to pay for

    unauthorised work

    Possibility of legal action for

    perceived breach of contract

    Confirm verbal acceptance of contract

    with written advice

    Accept all contracts in writing

    Ensure approvals are received before

    allowing work to start

    Unauthorised increase inscope of work

    Unanticipated cost increases

    Contract disputes

    Ensure all contract amendments areissued in writing

    Record all discussions and negotiations

    Confirm instructions in writing

    Loss of intellectual property Loss of commercial

    opportunity

    Unwarranted reliance on

    supplier for product support

    Ensure suitable clauses are included in

    the contract

    Failure to meet liabilities of

    third parties (eg. royalties orthird party property

    insurance)

    Legal action

    Damage to the agencysprofessional reputation

    Check that all obligations are covered in

    the contractAgree on responsibilities

    Implement appropriate safety standards

    and programs

    Loss or damage to goods in

    transit

    Delays in delivery

    Downtime

    Liability disputes

    Include appropriate packaging

    instructions in specification

    Agree on insurance cover for supplier to

    provide

    Accept delivery only after inspection

    Know when title of goods is transferredto buyer

    Fraud Misuse of resources

    Legal action

    Disruption to procurement

    activities

    Maintain an ethical environment

    Follow and maintain fraud control

    procedures

  • 7/28/2019 Commercial Context of Project Management

    19/23

    19 | P a g e

    Potential Risk Probable Effect of risk Action required to Counter Effects

    Key personnel not available Progress on project disrupted

    Less expertise

    Include requirement in specification and

    ensure compliance in post-tender

    negotiation

    Know the market

    Accept risk and manage possible delay

    Acknowledgment: This checklist is an adaptation of information derived by consultation with a

    checklist developed by NSW Department of Public Works and Services.8

    8http://www.nswprocurement.com.au/psc/Tendering-Manual/Appendix-3A.aspx

  • 7/28/2019 Commercial Context of Project Management

    20/23

    20 | P a g e

    CONCLUSIONS

    Based on the appraisal techniques used it is evident that the project leaves a lot of financial

    uncertainties. Based on this reason I do not believe it is a wise investment. The NPV and IRR are a big

    factor in this realization as they do not project long term financial viability. It is important to also

    note that due to the nature of the project size not all areas have been forecast by the office of MayorBoris Johnson. It can be then concluded that there is a lot of optimism bias with little fact to back up.

    As far as the contract and tender phases as outlined in the document, it is very important that these

    areas be managed closely as improprieties will prove costly not only financially but time wise and

    politically as well as this is highly controversial project.

    RECOMMENDATIONS

    1. Government regulation to reduce tax improving returns2. Attract investment from development banks that seek returns other than the financial

    3. Issuing government guaranteed or backed debt to raise financing changes to the cost structure toreduce cash outflows4. Having supplier credit as it is a good way to improve project performance because one does notpay suppliers immediately freeing up cash for other uses

    5. Having strict contract and tender practices that are closely monitored and evaluated6. Having strict in house and outsourced audit systems to reduce improprieties

    Word Count (2488)

    REFERENCES

  • 7/28/2019 Commercial Context of Project Management

    21/23

    21 | P a g e

    1. http://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspx

    2. http://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdf

    3. http://www.parliament.uk/briefing-papers/SN04920.pdf

    4. http://eandt.theiet.org/magazine/2013/03/debate.cfm

    5. http://www.gowerpublishing.com/isbn/9781409425151,http://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-

    Author.pdf

    6. http://www.nswprocurement.com.au/psc/Tendering-Manual/Appendix-3A.aspx

    7. http://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProcurementStrategy.pdf

    8. Baily, P., Farmer, D., Croker, B., Jessop, D., Jones D. (2008) Procurement Principles andManagement,10th Edn. London, FT Prentice Hall (Financial Times). Recommended By The

    Chartered Institute Of Purchasing And Supply

    7. http://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdf

    8. http://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdf

    9. http://archive.treasury.gov.uk/pub/html/docs/cup/cup39.pdf

    All references accessed between Thursday, January 24 2013 and Friday March 22 2013

    http://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://eandt.theiet.org/magazine/2013/03/debate.cfmhttp://eandt.theiet.org/magazine/2013/03/debate.cfmhttp://www.gowerpublishing.com/isbn/9781409425151http://www.gowerpublishing.com/isbn/9781409425151http://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-Author.pdfhttp://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-Author.pdfhttp://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-Author.pdfhttp://www.nswprocurement.com.au/psc/Tendering-Manual/Appendix-3A.aspxhttp://www.nswprocurement.com.au/psc/Tendering-Manual/Appendix-3A.aspxhttp://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProcurementStrategy.pdfhttp://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProcurementStrategy.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://archive.treasury.gov.uk/pub/html/docs/cup/cup39.pdfhttp://archive.treasury.gov.uk/pub/html/docs/cup/cup39.pdfhttp://archive.treasury.gov.uk/pub/html/docs/cup/cup39.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cityoflondon.gov.uk/business/tenders-and-procurement/Documents/Procurement%20strategy.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.cips.org/Documents/Resources/Knowledge%20Now/What%20is%20purchasing%20and%20supply%20management.pdfhttp://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProcurementStrategy.pdfhttp://www.nswprocurement.com.au/psc/Tendering-Manual/Appendix-3A.aspxhttp://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-Author.pdfhttp://www.gowerpublishing.com/pdf/SamplePages/Managing-Project-Supply-Chains-Author.pdfhttp://www.gowerpublishing.com/isbn/9781409425151http://eandt.theiet.org/magazine/2013/03/debate.cfmhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.oxera.com/Oxera/media/Oxera/downloads/Agenda/A-new-UK-hub-airport.pdf?ext=.pdfhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspx
  • 7/28/2019 Commercial Context of Project Management

    22/23

    22 | P a g e

    BIBLIOGRAPHY OF SOURCES CONSULTED BUT NOT DIRECTLY REFERRED TO WITHIN THE

    WORK

    1. http://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdf

    2. http://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdf

    3. http://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdf

    4. http://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspx

    5. http://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdf

    6. http://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdf

    7. www.parliament.uk/briefing-papers/SN04920.pdf

    8. http://www.bbc.co.uk/news/uk-politics-16606212

    9. http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6

    10.http://www.bbc.co.uk/news/uk-england-kent-15473914

    11.http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/

    12.http://www.bbc.co.uk/news/uk-england-london-15817520

    13.http://www.bbc.co.uk/news/uk-england-london-20317321

    14.http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/

    15.http://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdf

    http://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.bbc.co.uk/news/uk-politics-16606212http://www.bbc.co.uk/news/uk-politics-16606212http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.bbc.co.uk/news/uk-england-kent-15473914http://www.bbc.co.uk/news/uk-england-kent-15473914http://www.bbc.co.uk/news/uk-england-kent-15473914http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://www.bbc.co.uk/news/uk-england-london-15817520http://www.bbc.co.uk/news/uk-england-london-15817520http://www.bbc.co.uk/news/uk-england-london-15817520http://www.bbc.co.uk/news/uk-england-london-20317321http://www.bbc.co.uk/news/uk-england-london-20317321http://www.bbc.co.uk/news/uk-england-london-20317321http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://thamesestuaryairport.com/pdf/THAMES%20ESTUARY%20AIRPORT%20for%20web.pdfhttp://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.archdaily.com/339271/foster-partners-to-submit-thames-hub-airport-proposal-to-airport-commission/http://www.bbc.co.uk/news/uk-england-london-20317321http://www.bbc.co.uk/news/uk-england-london-15817520http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://media.aerosociety.com/aerospace-insight/2012/09/07/londons-thames-airport-plans-deja-vu-all-over-again/7288/http://www.bbc.co.uk/news/uk-england-kent-15473914http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.purchasing.tas.gov.au/buyingforgovernment/getpage.jsp?uid=07CC4222E4F10F00CA256C8D007F9FC6http://www.bbc.co.uk/news/uk-politics-16606212http://www.parliament.uk/briefing-papers/SN04920.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.ciltuk.org.uk/Portals/0/Documents/ProSectors/Aviation/CILT_response_to_DfT_aviation_policy.pdfhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.kentonline.co.uk/medway_messenger/news/2013/january/24/thames_estuary_airport.aspxhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.publications.parliament.uk/pa/cm201213/cmselect/cmtran/writev/aviation/m103.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdfhttp://www.parliament.uk/documents/commons-committees/transport/Would_a_new_hub_airport_be_commercially_viable.pdf
  • 7/28/2019 Commercial Context of Project Management

    23/23

    23 | P a g e

    16.http://thamesestuaryairport.com/masterplan.html

    17.http://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.html

    18.www.fosterandpartners.com/core/pdf/news/?id=494

    19.http://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.html

    20.http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/

    21.http://www.tfl.gov.uk/assets/downloads/corporate/a-new-airport-for-london-part1.pdf

    22.http://www.london.gov.uk/sites/default/files/Anewairportforlondon_part2.pdf

    All sources accessed between Thursday, January 24 2013 and Friday March 22 2013

    THE END

    http://thamesestuaryairport.com/masterplan.htmlhttp://thamesestuaryairport.com/masterplan.htmlhttp://thamesestuaryairport.com/masterplan.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.fosterandpartners.com/core/pdf/news/?id=494http://www.fosterandpartners.com/core/pdf/news/?id=494http://www.fosterandpartners.com/core/pdf/news/?id=494http://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.tfl.gov.uk/assets/downloads/corporate/a-new-airport-for-london-part1.pdfhttp://www.tfl.gov.uk/assets/downloads/corporate/a-new-airport-for-london-part1.pdfhttp://www.tfl.gov.uk/assets/downloads/corporate/a-new-airport-for-london-part1.pdfhttp://www.london.gov.uk/sites/default/files/Anewairportforlondon_part2.pdfhttp://www.london.gov.uk/sites/default/files/Anewairportforlondon_part2.pdfhttp://www.london.gov.uk/sites/default/files/Anewairportforlondon_part2.pdfhttp://www.london.gov.uk/sites/default/files/Anewairportforlondon_part2.pdfhttp://www.tfl.gov.uk/assets/downloads/corporate/a-new-airport-for-london-part1.pdfhttp://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.fosterandpartners.com/news/thames-hub-team-welcomes-consideration-of-thames-estuary-airport-and-re-states-its-vision/http://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.telegraph.co.uk/finance/newsbysector/epic/bba/9022146/New-Thames-Estuary-airport-could-be-built-in-six-years.htmlhttp://www.fosterandpartners.com/core/pdf/news/?id=494http://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://www.dailymail.co.uk/news/article-2088376/New-London-airport-Thames-Estuary-favoured-Government-says-Boris-Johnson.htmlhttp://thamesestuaryairport.com/masterplan.html