Cold Operation of a Recirculating CO 2 System at Aachen Lutz Feld, Waclaw Karpinski, Jennifer Merz , Michael Wlochal RWTH Aachen University, 1. Physikalisches Institut B 10.02.2010 CMS Upgrade Cooling and Mechanics Meeting
Jan 02, 2016
Cold Operation of aRecirculating CO2 System
at Aachen
Lutz Feld, Waclaw Karpinski, Jennifer Merz, Michael Wlochal
RWTH Aachen University, 1. Physikalisches Institut B
10.02.2010 CMS Upgrade Cooling and Mechanics Meeting
Outline
2Jennifer Merz
Description of CO2 test system in Aachen
Specifications of new chiller
Dryout measurements at room temperature
First measurement at low temperature
Conclusion and outlook
CO2 Test System Aachen - Specs
3Jennifer Merz
Goals:
- Gain experience with a recirculating (closed) CO2 cooling system
- Find the lowest possible operating temperature
- Determine ideal operating conditions ( stable operation)
depending on heat load and coolant temperature
Specifications:
Maximum heat load: 500W
Coolant temperature at detector: -45°C - +20°C
Precise temperature control and flow measurement
Continous operation
Safe operation (maximum pressure 100bar)
Schematic of Test System
4
Expansion Vessel: Filled with saturated mixture of CO2-liquid and -vapour
CO2 Pump
Flow Meter
Vacuum Pump
CO2 Bottle
Chiller 2: Heat removal
Heat Exchanger 2
Heat Exchanger 1
Detector:500 W heat load
Heat Exchanger 2:- Removes heat from the system- Cools incoming CO2 down to about
-50°C
4
6
3
1
4
5
2
-45°C
-50°C
Heat Exchanger 1:- Heats liquid CO2 to appropriate
temperature- Partial condensation of returning CO2
1 4
ΔQ
ΔQ
56
32
Chiller 1: Chiller temperature vapour pressure system temperature
Burst Disk
Burst Disk
Burst Disk
CO2-FlascheCO2-Bottle
Vacuum-Pump
CO2 Cooling Test System
5Jennifer Merz
Heat Exchanger 1
Expansion Vessel
Detector
CO2 Bottle
CO2-Flasche
Vacuum-Pump
Cooling of Expansion Vessel
6Jennifer Merz
Copper piping replaced by copper shell
Improvement of thermal contact
Reduction of flow resistance
CO2-FlascheCO2-Bottle
Vacuum-Pump
CO2 Cooling Test System
7Jennifer Merz
- 6m long stainless steel pipe with 1.5mm
outer diameter, in insulated box
- 14 thermistors to measure temperature
distribution over pipe
- Electrical connections to simulate heat load
CO2-FlascheCO2-Bottle
Chillers: unistat 815
8Jennifer Merz
- Originally ordered chiller had to be replaced; cooling power was not sufficient
- New chiller was damaged during transport
- “Old” chiller had to be repaired by company
- Chillers now achieve required low temperatures
Delay in commissioning,
system is fully operational since
end of January
Chiller specifications: (both chillers identical)
unistat 815
- Company: Peter Huber Kältemaschinenbau,
Offenburg, Germany
- Temperature range: -85°C to 250°C
- Cooling power: 1.5kW @ -20°C1.4kW @
-40°C1.2kW @
-60°C- Pump: max. 40 l/min, max. 0.9bar
Heat load: 70W - Vary revolutions per minute of CO2 pump
variation of CO2 flow- Keep heat load constant- Determine when temperature rises over
certain level
Dryout Measurement at Room Temp.
9
Dryout: Pipe walls not in touch with liquid anymore no power dissipation by evaporating CO2
temperature rises
Liquid Gas
Heat load: 70W
2468101214
1357 91113
Vacuum-Pump
Dryout Measurement at Room Temp.
10Jennifer Merz
30W40W50W60W70W
The lower the flow, the earlier a rise
in temperature is observed The higher the heat load,
the more flow is needed
Vacuum-Pump
First Measurement at Low Temperature
11Jennifer Merz
- Expansion vessel at -27°C- Chiller 2 at -44°C
No stable operation Fast variations in CO2 flow Beginning of dryout visible System behaviour not yet
understood
Operation at low temperatures possible (down to -45°C) if bypass is open; nearly no flow through detector pipe
Chillers work fine (see also next slide) Flow resistance too high? More investigation and measurements needed
Vacuum-Pump
Chiller Performance
Both chillers show excellent performanceLow temperatures Stable operation
Nominal Temp.Internal Temp.Temp. at Exp. Vessel
Nominal Temp.Internal Temp.
Chiller 1
Chiller 2
Conclusions and Outlook
13Jennifer Merz
- CO2 test system in Aachen is finally fully operational
- First measurements show that system works in principal
- New chillers manage to reach low temperatures
- No stable operation at low temperatures possible yet
Investigate how to bring low temperature to detector
Install filter to avoid water and other disturbing particles in system
Determine pressure drop and temperature distribution for different
pipe routings and diameter
CO2 Enthalpy-Pressure Diagram
15Enthalpy, kJ/kg
Pre
ssu
re,
bar
liquid
gas
liquid + gas
Design of cooling plant in p-H-digramEnthalpy:H = U + pV “internal energy + expansion work”ΔH is exchanged heat at constant pressure
CO2 Enthalpy-Pressure Diagram
16Enthalpy, kJ/kg
Pre
ssu
re,
bar
liquid
gas
liquid + gas
Design of cooling plant in p-H-digramEnthalpy:H = U + pV “internal energy + expansion work”ΔH is exchanged heat at constant pressure
Re-Circulating System(closed system)
41 6 5
32
ΔQ
ΔQ
Detector load (4-5)
CO2 Cooling System
17Jennifer Merz
Power consumption with DC-DC converters: 84W per petal- Including 18.8W power loss of converters, due to converter efficiency of 80%- One aluminium cooling block per converter implemented to dissipate converter
power loss
CO2 : low density small contribution to material budget Operation at high pressures small pipe diameter Low temperatures (-45°C) good for sensor performance
Current tracker (C6F14) vs. tracker with DC-DC converters cooled with CO2
TEC Cooling
TEC Total Material Budget
Current tracker with C6F14
Layout with DC-DC converters with CO2
A total reduction of 14.3% seems possible with CO2 cooling and DC-DC conversion.
-38.5% -14.3%
Advantages: