Top Banner
Coherent Web Sustaining Engineering Plan 1
5

Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

Dec 16, 2015

Download

Documents

Russell Melton
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

Coherent Web Sustaining Engineering Plan

1

Page 2: Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

The Coherent Web team will:• Utilize two-week development “sprints” to plan and track implementation activities. • Perform weekly reviews of newly submitted NCRs

• NCR priority is assigned based on submitter request and CW Team analysis.• If possible, a target version will be designated.

• Categorize NCR into two categories:• “Milestone Activities” – new features that are included in Coherent Web milestones.• “Sustaining Engineering” – internally or externally submitted enhancements and fixes.

• As needed, work with the Advisory Group to coordinate schedule and testing

The Coherent Web users will: •Submit enhancement requests or bug reports to the Coherent Web Team

• Currently: All items submitted to the Coherent Web Team via email (esdis-

[email protected])• Future: Items submitted through the Coherent Web Trouble Ticket Tool (Milestone 2)

• Include a requested priority (see subsequent slide) with request• Include a need-by date (optional) with request

2

Coherent Web Sustaining Engineering Overview

Page 3: Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

Translating Priority into Development Start Date• Critical CMS items worked immediately• Critical & Severe Content items worked immediately• All other items will be planned in a subsequent Coherent Web sprint.

All enhancements have the same priority• Enhancements will be reviewed to determine if they will be implemented and in

which version

3

NCR Priorities

Page 4: Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

Sprint Timeline

NCR Testing & Deployment• When possible, items will be immediately applied to the operational website. • Some items, such as “Milestone Development” activities, will require a staged deployment. In these

instances, changes will be applied to the Earthdata UAT environment. The CW Team, issue submitter, and/or Advisory Group, will then perform the necessary user acceptance testing prior to Operational deployment

4

Page 5: Coherent Web Sustaining Engineering Plan 1. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities.

Proposed 2011 Sprints• Sprint “2011-1“ - 10/3 – 10/14• Sprint “2011-2“ - 10/17 – 10/28• Sprint “2011-3“ - 10/31 – 11/11• Sprint “2011-4“ - 11/14 – 12/2 (Extended due to Thanksgiving)• Sprint “2011-5“ - 12/5 – 12/16• Sprint “2011-6“ - 12/19 – 12/30

Notifications regarding issue completion will come either from the CW Team or the CW Ticket Tracking tool. • Until a tool is developed, all communications will come from the CW

Team.

Each sprint plan will be published to the informational page on the Earthdata website for historical referencing and planning purposes.

5

Sprint Scheduling