Top Banner
Cogeneration at UC July 18, 2013
39

Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Dec 26, 2015

Download

Documents

Elfreda Nichols
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Cogeneration at UC July 18, 2013

Page 2: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

2

Welcome

Page 3: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

3

Transformation of thePower Plant

POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007

Page 4: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

4

Power Plant Site transformedCampus Recreation Center

POWER PLANT SITE OF REC CENTER CAMPUS RECREATION CENTER

Page 5: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Investing for the future

• $84,000,000 Construction of Central Utility Plant 2004• $6,000,000 Solar Turbine Maintenance contract 2004 - 2011• $6,000,000 Construction of Thermal Storage System 2011 • $7,000,000 Construction of New Substation

• Total Investment of Over $100,000,000

5

Page 6: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Central Utility Plant

Page 7: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Childrens Hospital Medical Center Shriners Hospital for Children

Veterans HospitalUniversity Hospital Hoxworth Blood Bank

Holmes Hospital

Hospitals Served by UC Utilities

Page 8: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

8

University of Cincinnati Consolidated Utilities

• UC and 6 Hospitals• 100 buildings• 12 million square feet

• Two Utility Production Plants

• Piping/Tunnel System• 100% distribution

Page 9: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

9

• Electric production 47MW• Steam Production

• 610,000 pounds-per-hour capacity-coal, gas, oil, interruptible gas

• Chilled Water Production • 34,000 tons capacity• natural gas and electric chillers

• Thermal Energy Storage• 2.8 million gallons of chilled water East Campus• 4.0 million gallons of chilled water West Campus

Consolidated Utilities Operations Capacity

Page 10: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

10

• Steam Pipes - 35,509 Linear Feet• Chilled Water Pipes - 32,889 Linear Feet• Tunnels - 13,947 Linear Feet

Utilities Distribution System

Page 11: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Central Utility Plant

Page 12: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.
Page 13: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

• 2 Solar Titan Combustion Turbines• 12.47 kV• 13,400 kVA

State of the Art Electric Production Equipment

Page 14: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

• 2 ERI HRSGs• 600 PSIG• 40,000 #/hr • 120,000 #/hr with burners

Heat Recovery From Cogen Increases Efficiency

•Overall efficiency is double the efficiency of a large utility plant

Page 15: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

• Use for campus heat in winter• Use for more electricity in summer• 20 MW steam turbine generator• 12.47 kV

Additional Electric Production Equipment

Page 16: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Cogen Benefits

• Increased Reliability• “Free” Steam• $2,590,000 per year

of savings• Lower Emissions•No transmission and distribution losses

Certified Emission Monitoring System

Cogen Benefits

Page 17: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

17

Electric Monitoring

Page 18: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

• Duke Energy Ohio regulated

• DERS non regulated supply

• Both depend on PJM 5 CP

• 5 CP is determined by regional transmission operator

• 5 CP stands for top 5 highest coincident peaks in PJM total territory

Peak Load Is Main Priority

Page 19: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Weather in DC,

Philadelphia, New

Jersey, or Chicago

Could affect total

Peak load

PJM Service Territory

Page 20: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

PJM Historical Coincident Peak Hours

Year Date_Time Year Date_Time2006 8/2/2006 17:00 2009 8/10/09 17:002006 8/1/2006 17:00 2009 8/18/09 16:002006 7/17/2006 17:00 2009 8/17/09 17:002006 7/31/2006 17:00 2009 8/11/09 17:002006 8/3/2006 16:00 2009 8/20/09 17:002007 8/8/2007 17:00 2010 7/7/2010 17:002007 8/7/2007 17:00 2010 7/6/2010 17:002007 7/9/2007 17:00 2010 7/23/2010 17:002007 8/2/2007 17:00 2010 8/10/2010 17:002007 6/27/2007 16:00 2010 8/11/2010 17:002008 6/9/2008 17:00 2011 7/22/2011 15:002008 7/17/2008 17:00 2011 7/21/2011 17:002008 7/18/2008 17:00 2011 7/20/2011 17:002008 7/21/2008 17:00 2011 7/19/2011 17:002008 6/10/2008 17:00 2011 6/8/2011 17:00

• Look at the trend• Peak is almost always

hour ending 17:00• Only 4 of 25 hours were

not hour ending 5PM and they were close

20

Page 21: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

DATE HOUR PEAK TIME

Meter - 105014030

(kw)

Meter - 106156664

(kw)

Meter - 106995461

(kw)

Meter - 108026022

(kw)

Meter - 108026025

(kw) Total (kw)PeakAverag

(kw)70512 15:00-16:00 1530 0 0 0 0 57.6 57.6 28.870612 16:00-17:00 1615 0 0 0 0 0 0 071612 16:00-17:00 1615 0 0 0 0 0 0 071712 16:00-17:00 1615 0 0 0 0 57.6 57.6 14.471812 14:00-15:00 1445 0 0 0 0 57.6 57.6 14.4

Average 11.52

Last Year’s 5 Peak days

These results are excellent and avoided millions of dollars of additional demand charges on our electric bill

•Electric Bill would be additional $380,000 per month higher

Page 22: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

CTG Performance

Page 23: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Simple Fuel Operation

• We use 600 cfm more gas to produce additional 5,000 kW

• This is equal to 36 MCF per hour

• $4 per MCF = $144/5,000kWh = $0.0288/kWh

• $5 per MCF = $180/5,000kWh = $0.036/kWh

• $6 per MCF = $180/5,000kWh = $0.0432/kWh

• $7 per MCF = $180/5,000kWh = $0.0504/kWh

• $10 per MCF = $180/5,000kWh = $0.072/kWh

Page 24: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

O& M Costs

• 4 Additional Operators

• Full Service Contract with Solar

• $1,500,000 per year fixed cost

• $0.01/kWh

Page 25: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Debt Costs

• Tax Exempt Bonds

• Low Interest rates

• $40,000,0000

• $3,600,000/ yr

• $0.02/kWh

• Could be less if you needed more capacity

Page 26: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Gas is still low but climbing

Page 27: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

EFFICIENCY RESULTS

Page 28: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Energy use per student down 30% over last 9 years

Page 29: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

City water usage down 43% over last 9 years

Page 30: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

GF Adjusted Utility Budget Compared to PUCO Historical Commercial &

Industrial Rates for Cincinnati

Page 31: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Award Winning Operations

Page 32: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Energy Conservation• Saves money • Reduces carbon footprint• Over $2,500,000 of rebates• Promotes sustainability• Duke Power Partner Award

Page 33: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Awards and Honors• 2012 International Thinking Buildings Award • 2011 EPA Combined Heat and Power Award• 2010 EPA Combined Heat and Power Award• 2009 EPA Combined Heat and Power Award• 2005 Energy Project of the Year, Association of Energy Engineers (AEE)• 2005 System of the Year, International District Energy Association (IDEA)• 2005 CHP Certificate of Recognition, U.S. EPA • 2005 Governor’s Award for Excellence in Energy, State of Ohio • 2003 Ohio Governor’s Award for Excellence, highest award in the Ohio Award for Excellence competition • 2001 Corporate Energy Management of the Year, Association of Energy Engineers (AEE) • 2001 Award for Excellence in Facilities Management, Association of Higher Education Officers (APPA) • 2000 Governor’s Award for Excellence in Energy Efficiency, State of Ohio • 2000 Facilities Management Excellence Award, Association for Facilities Engineers • 1999 Facility Management Achievement Award, International Facilities Management Association (IFMA) • 1997 Greenlights Partner, U.S. Environmental Protection Agency (EPA)

33

Page 34: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Additional Benefits

• Improved Reliability

• Voltage Sags reduced

• Reduced carbon footprint

• Less transmission and distribution losses

• Good Publicity

Page 35: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Additional Concerns

• Increased Fuel Volatility

• Increased Operational Complexity

• Additional regulatory issues

• PJM Interconnect may be needed

• Increased Staff may be needed

• Additional environmental permitting, monitoring, and reporting

Page 36: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Summary

• Great technology, but it is not for everyone

• Need a medium - large summer steam load and year round need for power

• Adds complexity to operations

• Capital and regulatory intensive

• Works great with low gas prices

Page 37: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Other Sources of Information

• http://www.midwestcleanenergy.org/

• DOE’s Federal Energy Management Program (FEMP) has issued a Notice of Intent (NOI) to provide grants for capital projects to Federal Agencies through a Funding Opportunity Announcement (FOA) entitled, "Assisting Federal Facilities with Energy Conservation Technologies (AFFECT)." CHP projects will be eligible for direct funding.

Page 38: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

Questions?

Page 39: Cogeneration at UC July 18, 2013. 2 Welcome 3 Transformation of the Power Plant POWER PLANT CENTER OF CAMPUS CENTRAL UTILITY PLANT 2007.

39

• For more information contact• Joe Harrell (513)-558-4635• [email protected]

Summary