CO2 cooling and IBL interface meeting
Tooling cooling line at PP1
Didier LaporteCNRS – LPNHE Paris
06 février 2014EDMS IN2P3 : I-036854 – V2
Assembling tooling
First cooling line
• Montage splitter box,• Début montage des lignes, soudure
6/8 lines on tools
Fitting stoppers
Ready to install
In the pit, on scaffolding
• LPSC table
Mainframe
Elcom 20x20
Z table (axis)
• Elcom
Final position
Same operation for the 6 lines
Final position
To do list :
• Update of the lines (6 / 8 ), LAPP• Design side A, LPNHE• Splitter box interface, LAPP• Escargot interface, LAPP• Protection for travel, LPNHE• Connection links at PP1 (for tests), LPNHE• Command to do (Elcom), LAPP/LPNHE