Top Banner
05 Sept 2006 CNGS Overview presented by K. Elsener to NBI2006 1 CNGS Overview Konrad Elsener
25

CNGS Overview Konrad Elsener

Jan 16, 2016

Download

Documents

Hansel

CNGS Overview Konrad Elsener. OUTLINE 1. The CNGS beam 2. Schedule 3. Status 4. Summary. 1. The CNGS beam – main components. 10 cm long graphite rods. Helium tanks. 400 GeV protons from SPS, fast extracted ( 2 x 10.5 m s, D t=50 ms). 50 ms. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

1

CNGS Overview

Konrad Elsener

Page 2: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

2

OUTLINE

1. The CNGS beam2. Schedule3. Status4. Summary

Page 3: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

3

400 GeV protons from SPS,fast extracted ( 2 x 10.5 s, t=50 ms)

10 cm long graphite rods

1.The CNGS beam – main components

Helium tanks

Page 4: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

4

150 kA

180 kA

Helium tanks

1. The CNGS beam – main components

50 ms

Page 5: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

5

= 2.45 m steel tube, t = 18 mmsurrounded by 50 cm concrete;- NO COOLING -vacuum 1 mbarentrance window 3 mm Tiexit window 50 mm steel

Helium tanks

1. The CNGS beam – main components

Page 6: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

6

V = 1 litre air-filled ionisation chambers

(17->37 fixed + 1 moveable detector in both muon detection chambers)

800 m 100 m 1000m 67 m

Helium tanks

TBID(SEM monitor)

1. The CNGS beam – main components

Page 7: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

7

Page 8: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

8

2. Schedule

10 July 2006

Page 9: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

9

3. Status

construction:completed

commissioning:done

CNGS operational !

Page 10: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

10

3. Status

construction:completed

commissioning:done

CNGS operational !

Page 11: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

11

3a. Status

BPM: not o.k.BTV: ? not aligned ?target: not aligned w/beam not aligned w/hornhorns: polarity wrong, timing wrong, alarm (conductivity)data logging: missing spillsdecay tube pumps: one “dead”ventilation: not o.k.smoke detection: problems.... ....

Page 12: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

12

- Hardware commissioning / cold check-outBeam instrumentations Feb. – April 2006Power suppliesMagnets (incl. polarities)Vacuum system(April / May: Target / Horn exchange excercises “real”)

- “Dry runs” April – May 2006TimingControls InterlocksBeam permitMagnets (current & polarities)

- Commissioning with beam 2006: weeks 28, 30 and 33

3. Status

Page 13: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

13

3c. Status

week 28 week 30 week 33

1x1013

total number of protons used: 7.8x1015

(equivalent to 1 hour of CNGS running with nominal beam)

Page 14: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

14

how did we use these “few” protons ?

... answers throughout this workshop ...

3. Status

Page 15: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

15

• Put some plots here, ex. Horn current vs. time, or ex. T40 temp. vs. time

3. Status

week 33M

D -

cy

cle

ch

an

ge

d

MD

– n

o b

eam

acc

es

s

operation

horn current extraction 1

Page 16: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

16

MD

– n

o b

eam

acc

es

s

horn current extraction 1

Page 17: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

17

PRELIMINARYmore on Friday, 8 Sept. (Edda’s talk)

Quality check – muon monitors(example: Pit 1 - horizontal plane)

data <> Fluka

3. Status

Page 18: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

18

... other problems ... (construction)

February 2006: safety shutter -> not on safe power (!)decay tube air-inlet “local controls”

March 2006: helium purity BAD (weather changed...)

30 June 2006: hadron stop water leak (flowmeters)

... more problems ... (commissioning)

MKE kickers not working reliably – fixed “last minute”

beam availability from the PS + SPS (PS septum change, etc.)

radioactive cooling water from the TED (beam dump in extr. line)

two out of 4 air-cooling units in the service gallery have a fault

details of TBID readout still need to be understood (electronics?)

3. Status

Page 19: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

19

... on the sunny side: “everything works”!

-> was wonderful to see how smoothly the proton beam came on

-> impressive (to me) to see the tools at work for proton beam analysis

-> little trouble moving/turning the target

-> horn + reflector are working reliably

-> beam interlock system is a success

-> controls systems were rarely a cause of trouble (“dry runs” paid off!)

-> it was great to get so many additional muon monitors in week 29 !

3. Status

Page 20: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

20

4. Summary

CNGS project was approved in December 1999

Civil Engineering – Equipment design – production- installation phases lasted 6 years

CNGS completed on budget and within the 2002 schedule.

two of our “main worries” at NBI2005 are gone (target / horns ready and installed in time)

the two other “main worries” remain(target chamber heating/cooling calculations,

decay tube heating + stresses )

CNGS is operational – but the toughest part is still ahead !

Lesson learned: hardware commissioning for “services” !!!

Page 21: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

21

Page 22: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

22

Page 23: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

23

Page 24: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

24

Page 25: CNGS Overview Konrad Elsener

05 Sept 2006 CNGS Overviewpresented by K. Elsener to NBI2006

25

1.3E+13

1.35E+13

1.4E+13

1.45E+13

1.5E+13

1.55E+13

1.6E+13

1.65E+13

1.7E+13

1.75E+13

1.8E+13

8/25/20060:00:00.000

8/25/200612:00:00.000

8/26/20060:00:00.000

8/26/200612:00:00.000

8/27/20060:00:00.000

8/27/200612:00:00.000

8/28/20060:00:00.000

8/28/200612:00:00.000

8/29/20060:00:00.000

148600

148700

148800

148900

149000

149100

149200

149300

149400

149500

149600

p.o.t. (1st extr.) horn current [A]