Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States' practical experience © Dr. Norbert Heller, Verwaltungsbehörde,
12

Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

Mar 27, 2015

Download

Documents

Emily Ramos
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

Click to edit Master title style

© Dr. Norbert Heller – Verwaltungsbehörde -

Preparation of the certified statement of final

expenditure:

Member States' practical experience

© Dr. Norbert Heller, Verwaltungsbehörde,

Page 2: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

Click to edit Master title style

© Dr. Norbert Heller – Verwaltungsbehörde -

Saxony-Anhalt

Page 3: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 3

Structural Funds Period• Marriage for a time

– Euphoria of programming period

• Variety of implementation

• Winding up period

organizing steps to closure in time

Page 4: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 4

Certificate of final application• Total amount of expenditures

• Problem: number + financial amount of projectse.g. Saxony-Anhalt– ERDF 15 000– ESF 15 000– EAGGF 35 000

organization and electronic data based system

(ca. 2.0 bn € - total 9.0 bn €)

(ca. 0.7 bn € - total 1.5 bn €)

(ca. 0.7 bn € - total 2.0 bn €)

Page 5: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 5

Organization

Page 6: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 6

Documents of paying authorityDeclaration of expenditure of paying authority

Payment application of paying authority

Certification of paying authority

Page 7: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 7

Adaptation of plan

• OP level: until 06-12-31• PC level: until 08-12-31 / 09-04-30

• Rule of flexibility „2 %“

Page 8: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 8

Deadlines

06-12-31 09-04-30Grants non Art. 87 Grants according to Art. 87

Payments

Payments

09-02-28 09-06-30

Input

Input

10-07-31

Clousure Documents

Closure Auditing

Page 9: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 9

Definition of a project to close: granting

– expenditure

+ repayment

= 0

Don‘t forget:Prove that sufficient article 4 on-the- spot-checks are done !

Page 10: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 10

List of open projects• Decisions to close projects, e.g.

– Not yet finished investments– Open minor amounts– Insolvency– Administrative or Legal proceedings– etc.

• Reporting tasks – two years after closure! • Irregularities

Page 11: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 11

What customer What customer explainedexplained

What What project managerproject manager understood understood

What analyst What analyst outlinedoutlined

How it has been How it has been supportedsupported

What programmer What programmer programmed programmed

What consultant What consultant recommendedrecommended

How project is How project is documenteddocumented

How it has beenHow it has been installed installed

What has been What has been charged to customercharged to customer

What customerWhat customer had needed had needed

Page 12: Click to edit Master title style © Dr. Norbert Heller – Verwaltungsbehörde - Preparation of the certified statement of final expenditure: Member States'

© Dr. Norbert Heller - Verwaltungsbehörde - 12

Thanks for your attention!