Page 1
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
Version 03 - in effect as of: 22 December 2006
CONTENTS
A. General description of the small scale project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring Information
Page 2
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
2
Revision history of this document
Version
Number
Date Description and reason of revision
01 21 January
2003
Initial adoption
02 8 July 2005 The Board agreed to revise the CDM SSC PDD to reflect
guidance and clarifications provided by the Board since
version 01 of this document.
As a consequence, the guidelines for completing CDM SSC
PDD have been revised accordingly to version 2. The latest
version can be found at
<http://cdm.unfccc.int/Reference/Documents>.
03 22 December
2006
The Board agreed to revise the CDM project design
document for small-scale activities (CDM-SSC-PDD), taking
into account CDM-PDD and CDM-NM.
Page 3
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
3
SECTION A. General description of small-scale project activity
A.1 Title of the small-scale project activity:
Reduction of Heavy Fuel Oil usage for Power Generation at Lucky Cement, Pezu, Pakistan
Version No. 1
Date: 19/03/2010
A.2. Description of the small-scale project activity:
Lucky Cement Limited, a part of Yunus Brothers Group (YB Group), started production in 1996 with a
daily production capacity of 4,200 tonnes per day. It is presently a 21,000 tonnes per day, dry process
Cement Plant having production facilities at Pezu (Production capacity: 10,800 Tons per day) and
Karachi (Production capacity: 9,000 Tons per day)1.
Lucky Cement’s – Pezu plant, is in the process of retrofitting its existing heavy fuel oil (HFO) based
Wartsila generators to operate in dual fuel mode, with natural gas (NG) as the primary fuel and an option
to use HFO in case of gas unavailability. The electricity generated, from the generators, is used to meet
the electricity demand for in house cement manufacturing process. Diesel is consumed as a support fuel
during both NG and HFO operation.
The purpose of the project activity is to reduce greenhouse gas (GHG) emission for electricity generation,
by replacement of a higher carbon intensive fossil fuel mix with a lower carbon intensive fossil fuel mix.
In the pre project scenario (also the baseline scenario), the generators were based on approximately 100%
HFO (~0.04% Diesel oil consumption). Under the project scenario the generators would be based on an
average fuel mix of approximately 35% HFO and 65% NG. Thus, the project results in lower emissions
for generation of equivalent amount of power during the project scenario as compared to the baseline.
In the pre project scenario, the power requirement for the cement manufacturing process was being met by
10 numbers HFO (and very low percentage of diesel oil) based Wartsila generators of total capacity
69.358 MW. As part of project activity, these generators have been modified to operate on dual fuel
(Natural gas (NG), Heavy fuel oil (HFO) and very low percentage of diesel oil as support fuel) mode. The
de-rated capacity of the generator post modification is around 65.87 MW (on NG mode).
Contribution of project activity to sustainable development of host country:
As per Ministry of Environment (DNA-Pakistan), a project contributes to sustainable development of
Pakistan, under the following criteria:
In view of project proponent, the proposed CDM project activity results in sustainable development in
the following ways:
1 http://www.lucky-cement.com/
Page 4
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
4
1. General criteria:
a. The project activity is consistent with all the national laws and regulations.
b. The project would not result in any further obligation apart from the CERs generated, to
any other party outside of Pakistan
2. Environmental criteria:
a. The proposed project activity is replacing high carbon intensive fossil fuel mix with a
lower carbon intensive fossil fuel mix, for generating same units of electricity. This
results in lower quantity of net CO2 emission.
3. Social criteria:
a. The project activity would create job opportunities for localities to be recruited as skilled
and unskilled workers for data monitoring and during the installation and conversion
procedure.
b. These new job opportunities would help in poverty alleviation of the local region
c. Natural gas transportation pipelines setup and maintaince would result in more economic
activities in the region.
d. The project would create awareness about global warming impacts and mitigation by use
of environment friendly energy sources.
e. Since HFO is brought in heavy tankers, the reduction in HFO in the project situation
shall prevent degradation of local roads by heavy transport vehicles.
4. Economic criteria:
a. The project would reduce the dependence on HFO as well as provide new and diversified
methods of energy generation.
b. The project will reduce the dependence of Pakistan on HFO which is mainly imported
thus saving a lot of revenue for the country.
c. The project would bring revenues in the form of CER. These revenues would result in
economic development of the country.
d. The local people would be employed for various jobs which would bring economic
development in the region.
e. Pakistan would become one of the favoured destinations of CDM project activity and
would bring in investments by Annex I parties which would result in further sustainable
development.
5. Technological criteria:
a. The technical know-how of using natural gas to generate power will be available for use
by other industries in the NWFP
Page 5
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
5
A.3. Project participants:
Name of Party involved
(host) indicates a host
Party
Private and/ or public entity(ies)
project participants
(as applicable)
Kindly indicate if
the Party involved
wishes to be
considered as
project participant
(Yes/ No)
Pakistan (Host party) Private Entity:
Lucky Cement Limited
No
Pakistan (Host party) Private Entity:
Carbon Services (Private) Limited
No
Switzerland First Climate (Switzerland) AG No
A.4. Technical description of the small-scale project activity:
A.4.1. Location of the small-scale project activity:
A.4.1.1. Host Party(ies):
Pakistan
A.4.1.2. Region/State/Province etc.:
Province: North-West Frontier
District: Lakki Marwat
A.4.1.3. City/Town/Community etc:
Town: Pezu
A.4.1.4. Details of physical location, including information allowing
the unique identification of this small-scale project activity :
Geographical coordinates of the site2: 32.32.4º (N), 70.73.2º (E)
Indicative map:
2 http://www.wikimapia.org/#lat=32.3242756&lon=70.7327271&z=10&l=0&m=a&v=2
Page 6
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
6
3
4
A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:
With reference to “Appendix B to the simplified modalities and procedures for small scale CDM project
activities” the project activity falls under the Type III: Other Project Activities and Category AH.
In the pre-project scenario, Lucky cement used the following 10 numbers HFO based generators to meet
its electricity demands:
Generator Number of generators Capacity of each generator in
MW
Wartsila 18V32 7 Nos. 5.594
Wartsila 12V46 3 Nos. 10.09
Conversion of generators from HFO to natural gas based has resulted in a de-rating of these generators.
The de-rated capacities of the retrofitted generators are as follows:
Generator Number of generators Capacity of each generator in
MW
Wartsila 18V32 (Retrofitted) 7 Nos. HFO – 5.584
NG – 5.39
Wartsila 12V46 (Retrofitted) 3 Nos. HFO – 10.09
NG – 9.38
3 www.mapsofindia.com
4 http://www.lucky-cement.com/
Page 7
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
7
The modifications to the existing generators were carried out by Wartsila Corporation – Finland. The
major components changed were complete cylinder head, button end bearing, WIOS and WECS, starting
system, turning gear unit, fuel system, turbocharger unit.
Based on availability trend of NG in Pakistan (NG is unavailable during most part of winter season), it is
envisaged that the generators would operate for 65% of the annual operating time on NG mode and
remaining 35% of the time on HFO mode. This converts to an annual average fuel mix of approximately
35% HFO and 65% NG.
A.4.3 Estimated amount of emission reductions over the chosen crediting period:
Years Estimation of annual emission reductions in
tonnes of CO2e
1st Sep 2010 – 30
th Aug 2011 34,342
1st Sep 2011 – 30
th Aug 2012 34,342
1st Sep 2012 – 30
th Aug 2013 34,342
1st Sep 2013 – 30
th Aug 2014 34,342
1st Sep 2014 – 30
th Aug 2015 34,342
1st Sep 2015 – 30
th Aug 2016 34,342
1st Sep 2016 – 30
th Aug 2017 34,342
1st Sep 2017 – 30
th Aug 2018 34,342
1st Sep 2018 – 30
th Aug 2019 34,342
1st Sep 2019 – 30
th Aug 2020 34,342
Total estimated reductions
(tonnes of CO2e)
343,420
Total number of crediting years 10
Annual average of the estimated reductions
over the crediting period
34,342
A.4.4. Public funding of the small-scale project activity:
There is no public funding involved in the project activity.
A.4.5. Confirmation that the small-scale project activity is not a debundled component of
a large scale project activity:
Reference to Appendix C to the simplified modalities and procedures for the small scale CDM project
activities:
Further reference to Compendium of guidance on the debundling for SSC project activities (EB 36,
Annex 27):
As per paragraph 2:
Page 8
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
8
A proposed small-scale project activity shall be deemed to be a debundled component of a large project
activity if there is a registered small-scale CDM project activity or an application to register another
small-scale CDM project activity:
(a) With the same project participants Applicable:
The same project participants have applied for
registration of another CDM project
(b) In the same project category and
technology/measure
Not applicable:
The project participant has applied for registration
of a Waste heat recovery based power generation
project, which is based on a different
technology/measure as compared the proposed
CDM project activity, which is fuel switch
measures at captive generators.
(c) Registered within the previous 2 years Not applicable:
The project participant has not registered any other
project activity at the time of start of validation of
the project.
(d) Whose project boundary is within 1 km of the
project boundary of the proposed small scale
activity at the closest point?
Not applicable:
The project participant has not registered any other
project activity at the time of validation of the
project.
Thus it can be concluded that the project activity is not a debundled component of a large scale project
activity.
Page 9
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
9
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
With reference to UNFCCC CDM website, the approved baseline and monitoring methodology applied
to the project activity is:
Methodology No: AMS III AH
Title: Shift from high carbon intensive fuel mix ratio to low carbon intensive fuel mix ratio
Version no.: 01
B.2 Justification of the choice of the project category:
Referring to the applicability criteria as given in paragraphs 1 to 11 of the methodology, the justification
of the choice of methodology is presented here-below:
Paragraph
No.
Applicability criteria as given in
AMS III AH
Applicable (Not applicable) to project
activity with justification
1 This methodology comprises of activities that
result in increased share of low GHG
intensive fossil fuel in an element process of
an industrial, residential, commercial, and
institutional or electricity generation
application that uses a mix of fossil fuel. For
example, shift from high carbon intensive fuel
mix ratio to low carbon intensive fuel mix
ratio on an annual basis in power generation
Applicable and fulfilled:
The project activity involves shift in fossil
fuel mix, from higher carbon intensive
mix to lower carbon intensive mix, for
electricity generation application. This
result in lower CO2 emission per unit of
electricity generated.
2 This methodology is applicable for retrofit or
replacement of existing installations. Cases
involving Greenfield projects and capacity
additions are not eligible under this
methodology.
Applicable and fulfilled:
The project activity involves retrofit of the
existing HFO based generator units.
3 Switching of fuel mix ratio may also result in
energy efficiency improvements of the facility,
thus both the project activities with or without
energy efficiency improvements are eligible
under this category. Project activities for
implementation of energy efficiency measures
not-related to the switch of energy sources
shall apply Type II SSC methodologies.
Not applicable:
The project activity is primarily aimed at
fuel switch and not aimed at achieving
energy efficiency improvement.
4 The requirements for demonstration of the
remaining lifetime of the equipment replaced
Applicable and fulfilled:
The remaining lifetime of the retrofitted
Page 10
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
10
shall be met as described in the general
guidance. If the remaining lifetime of the
plant increases due to the project activity, the
crediting period shall be limited to the
estimated remaining lifetime, i.e., the time
when the existing equipment of the element
process would have been replaced in the
absence of the project activity.
equipment does not increase due to
project activity implementation. The
generators would have had a remaining
lifetime of around 15 years, in absence of
the project activity.
5 This methodology is not applicable to project
activities that propose switch from fossil fuel
use in the baseline to renewable biomass,
biofuel or renewable energy in the project
scenario. This methodology is not applicable
to project activities utilizing waste gas or
energy; these project activities may consider
applying AMS-III.Q.
Not applicable:
The project activity does not involve
switching from fossil fuel to renewable
biomass.
6 This category is applicable to project
activities where it is possible to directly
measure and record the energy use (e.g.,
electricity or heat) and consumption (e.g.,
fossil fuel) within the project boundary.
Applicable and fulfilled:
Meters installed at the generator end
records the amount of power generated
from the project boundary. The natural
gas consumed in the generators would
come through dedicated pipelines and
measured through gas flow meters, while
liquid fuels feeding into the generators,
would be metered from buffer tanks.
7 Heat or electricity produced under the project
activity shall be for on-site captive use and/or
export to other facilities included in the
project boundary. In case energy produced by
the project activity is delivered to another
facility or facilities, to displace more carbon
intensive energy source than the project fuel
mix, within the project boundary, a contract
between the supplier and consumer(s) of the
energy will have to be entered into specifying
that only the facility generating the energy can
claim emission reductions from the fuel
switch.
Applicable and fulfilled:
Net electricity generated under the project
activity, would be completely used for on-
site captive use.
8 Export of electricity to a grid is not eligible
under this category. That is, the project
activity may physically connect to a grid but
emission reduction cannot be claimed by
exporting electricity to the grid.
Not applicable:
As mentioned above, net electricity
generated would be completely used for
on-site captive consumption and no
surplus power would be sent to the grid.
9 Measures are limited to those that result in
emission reductions of less than or equal to
Applicable and fulfilled:
The project activity would result in
Page 11
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
11
60 kt CO2 equivalent annually. emission reductions of 34342 t CO2
equivalents.
10 Regulations do not constrain the facility from
using the energy sources cited in paragraph 1
before the fuel switch. Regulations do not
require the use of low carbon energy source
(e.g., natural gas or any other fuel) in the
element processes.
Applicable and fulfilled:
No government regulation in Pakistan
restricts the use of HFO for electricity
generation in generator sets.
11 The project activity does not result in
integrated process change. The purpose is to
exclude measures that affect other
characteristics of the process besides switch
of energy sources e.g., operational conditions,
type of raw material processed, use of non-
energy additives, change in type or quality of
products manufactured etc.
Not applicable:
The project activity does not result in any
integrated process change.
Thus, the project activity meets all the applicability criteria of the methodology. The selection of the
methodology is thus justified.
B.3. Description of the project boundary:
As per paragraph 12 of the methodology, “the project boundary is the physical, geographical site where
the switching of energy source takes place. It includes all installations, processes or equipment affected
by the switching. The boundary also extends to the industrial, commercial or residential facilities
consuming energy generated by the system.”
Natural Gas
HFO
Power
Lucky Cement - Pezu
Generator sets
(MW)
Cement manufacturing
unit
Page 12
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
12
B.4. Description of baseline and its development:
The baseline scenario to the project activity is the continuation of pre project scenario, which is use of
HFO (and very small percentage of diesel as support fuel) as fuel for electricity generation in generator
sets.
As per paragraph 13 of the methodology, “historical information (detailed records) on the use of fossil
fuels and the element process output (e.g., heat or electricity) from at least three years prior to project
implementation shall be used in the baseline calculations”
For the project activity historical data for HFO consumption, diesel consumption and power generated
during the last 3 years (2004 – 2006) is available and presented below:
Particulars Unit Year
2004 2005 2006
HFO consumption by 7 No.
18V32 Wartsila generators
Tonne 37,068 38,878 31,584
Electricity generated by 7 No. of
18V32 Wartsila generators
MWh 164,459 171,625 140,722
Diesel consumption by 7 No.
18V32 Wartsila generators
Litre 20,459 16,832 19,535
HFO consumption by 3 No.
12V46 Wartsila generators
Tonne 0 9,390 35,709
Electricity generated by 3 No.
12V46 Wartsila generators
MWh 0 47,326 179,225
Diesel consumption by 3 No.
12V46 Wartsila generators
Litre 0 1,000 11,200
As per paragraph 14 of the methodology, “during the crediting period, if there is a restricted
availability of a particular baseline fuel on account of local regulations this has to be considered by
adjusting the baseline emissions ex post for the period where the baseline fuel is not available. The
adjustment is done in a conservative manner i.e., if the restriction results in downward adjustment of
baseline emissions it shall be taken into account5 and on the other hand upward adjustment of baseline
emissions are not eligible.”
During the crediting period, it is expected that there would be no restriction to availability of baseline
fuels (HFO and diesel). In fact, there may be restricted availability of the project fuels (NG). However,
the availability of both the baseline fuels is being monitored during the crediting period and in case of
restricted availability baseline emission would be adjusted accordingly.
Page 13
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
13
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
As per the decision 17/cp.7 paragraph 43, “a CDM project activity is additional if anthropogenic emissions of
greenhouse gases by sources are reduced below those that would have occurred in the absence of the
registered CDM project activity.”
According to Attachment A to Appendix B of the simplified modalities and procedures for small scale CDM
project activity categories, the project participants are required to provide an explanation to show that the
project activity would not have occurred anyway due to at least one of the below mentioned barriers
Investment barrier
Technological barrier
Barriers due to prevailing practice or
Other barriers..
In the project the investment would not have happened due to the existence of investment barriers: Option (a),
investment barrier is chosen to demonstrate the financial attractiveness of the project activity. The Internal Rate
of Return (IRR) for the project activity has been evaluated and demonstratred to be lower than the benchmark
return (which also corresponds to the minimum opportunity cost of capital invested in the project activity), and
the project IRR surpasses the benchmark return with additional revenue stream from sale of Certified Emission
Reductions (CER) generated under the project activity.
For calculating the project’s IRR, following data parameters and assumptions were used:
Sl.
No.
Parameter Value applied Unit Source of value
Investment cost – Generator
change 7x18V32 1,731,063,036
PKR Feasibility study report
Debt component 100 % Feasibility study report
Equity component 0 % Calculated
Loan period 7 years Feasibility study report
Grace period 5 years Feasibility study report
Base rate (KIBOR) 10.33 % Feasibility study report
Risk premium 2 % Feasibility study report
Technical lifetime of the
project
15 years Feasibility study report
Depreciation cost 6.67 % Feasibility study report
Tax rate 35 % Feasibility study report
Crediting period 10 years Feasibility study report
CER price 1264 PKR/CER Feasibility study report
Price of HFO 19350 PKR/t Feasibility study report
Price of natural gas 9.35 PKR/ Nm3 Feasibility study report
Price of diesel 31.5 PKR/l Feasibility study report
Price of O&M in baseline 0.18 PKR/kWh Feasibility study report
Price of O&M in project 0.22 PKR/kWh Feasibility study report
Cost of major overhaul
every 5th
year
10,000,000 PKR Feasibility study report
Page 14
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
14
Yearly electricity generated
(Net)
300,000,000 kWh Feasibility study report
Electricity generation by
HFO in baseline
100 % Feasibility study report
Electricity generation by
NG in baseline
0 % Feasibility study report
Electricity generation by
HFO in project
35 % Feasibility study report
Electricity generation by
NG in project
65 % Feasibility study report
Average specific HFO
consumption of generators
0.21 kg/kWh Feasibility study report
Specific NG consumption
of generators
0.26 Nm3/kWh Feasibility study report
Specific diesel
consumption
6 g/kWh Feasibility study report
Cost of un-for-seen diesel
consumption due to
generator mall operation
0.03 PKR/kWh Feasibility study report
The investment analysis is done in line with the “Guidance on the Investment Analysis”5.
Referring to guidance provided by document, fulfillment of this guidance by the proposed project
activity’s investment analysis is shown below:
Guidanc
e
Number
Guidance text Explanation related to fulfillment of
guidance by the below presented
Investment Analysis
General issues in presentation and calculation
3 The period of assessment should not be limited to
the proposed crediting period of the CDM project
activity. Both project IRR and equity IRR
calculations shall as a preference reflect the period
of expected operation of the underlying project
activity (technical lifetime), or - if a shorter period
is chosen - include the fair value of the project
activity assets at the end of the assessment period.
In general a minimum period of 10 years and a
maximum of 20 years will be appropriate. The IRR
calculation may include the cost of major
maintenance and/or rehabilitation if these are
expected to be incurred during the period of
assessment. Project participants are requested to
Applicable and fulfilled:
The period of assessment is taken as
15 years (which is not limited to the
10 years crediting period for the
project activity). The project is using
project IRR to demonstrate investment
barrier.
The same is reflected in the IRR
spreadsheet.
5 http://cdm.unfccc.int/EB/051/eb51_repan58.pdf
Page 15
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
15
justify and DOEs are requested to validate the
appropriateness of the period of assessment in the
context of the underlying project activity, without
reference to the proposed
CDM crediting period.
4 The fair value of any project activity assets at the
end of the assessment period should be included as
a cash inflow in the final year. The fair value should
be calculated in accordance with local accounting
regulations where available, or international best
practice. It is expected that such fair value
calculations will include both the book value of the
asset and the reasonable expectation of the potential
profit or loss on the realization of the assets.
Applicable and fulfilled:
The fair value of assets at the end of
assessment period is included as cash
inflow in the final year. The same is
reflected in the IRR spreadsheet.
5 Depreciation, and other non-cash items related to
the project activity, which have been deducted in
estimating gross profits on which tax is calculated,
should be added back to net profits for the purpose
of calculating the financial indicator (e.g. IRR,
NPV). Taxation should only be included as an
expense in the IRR/NPV calculation in cases where
the benchmark or other comparator is intended for
post-tax comparisons.
Applicable and fulfilled:
Depreciation, which is a non cash item
was deducted to calculate tax, and was
added back to calculate post tax cash
flows. Taxation has been included as
an expense because the IRR calculated
is post tax IRR. The same is reflected
in the IRR spreadsheet.
6 Input values used in all investment analysis should
be valid and applicable at the time of the investment
decision taken by the project participant. The DOE
is therefore expected to validate the timing of the
investment decision and the consistency and
appropriateness of the input values with this timing.
The DOE should also validate that the listed input
values have been consistently applied in all
calculations.
Applicable and fulfilled:
All variables and assumptions in the
IRR is based on values presented in
the FSR which was drafted at the time
of decision making. The same is
reflected in the IRR spreadsheet.
7 In the case of project activities for which
implementation ceases after the commencement and
where implementation is recommenced due to
consideration of the CDM the investment analysis
should reflect the economic decision making
context at point of the decision to recommence the
project. Therefore capital costs incurred prior to the
revised project activity start date can be reflected as
the recoverable value of the assets, which are
limited to the potential reuse/resale of tangible
assets.
Not Applicable:
For the project activity CDM was
considered from the decision making
and the same was followed up with
raise of purchase order.
8 Project participants should supply spreadsheet
versions of all investment analysis. All formulas
Applicable and fulfilled:
Spreadsheet versions of all investment
Page 16
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
16
used in this analysis be readable and all relevant
cells be viewable and unprotected. The spreadsheet
will be made available to the Executive Board,
UNFCCC secretariat and others contracted to
assess the request for registration on behalf of the
Board including assigned members of the
Registration and Issuance Team. In cases where the
project participant does not wish to make such a
spreadsheet available to the public an exact read-
only or PDF copy shall be provided for general
publication. In case the PP wishes to black-out
certain elements of the publicly available version, a
clear justification for this shall be provided to the
UNFCCC secretariat by the DOE when requesting
registration.
analysis would be provided to the DoE
and UNFCCC EB.
Specific Guidance on the calculation of project IRR and Equity IRR
9 The cost of financing expenditures (i.e. loan
repayments and interest) should not be included in
the calculation of project IRR.
Applicable and fulfilled:
Loan repayment is not considered in
the IRR analysis. Interest payment is
considered only for tax computation
purpose and has been added back
again. The same is reflected in the IRR
spreadsheet.
10 In the calculation of equity IRR only the portion of
investment costs which is financed by equity should
be considered as the net cash outflow, the portion
of the investment costs which is financed by debt
should not be considered a cash outflow.
Not Applicable:
Project IRR is calculated.
11 Due to the impact of loan interest on income tax
calculations it is recommended that when a project
IRR is calculated to demonstrate additionality a pre-
tax benchmark be applied. In cases where a post-tax
benchmark is applied the DOE shall ensure that
actual interest payable is taken into account in the
calculation of income tax. In such situations interest
should be calculated according to the prevailing
commercial interest rates in the region, preferably
by assessing the cost of other debt recently acquired
by the project developer and by applying a debt-
equity ratio used by the project developer for
investments taken in the previous three years.
Applicable and fulfilled:
Project IRR is calculated to
demonstrate additionality and has been
compared against commercial lending
rate in Pakistan. The same is reflected
in the IRR spreadsheet.
Selection and validation of appropriate benchmark
12 In cases where a benchmark approach is used the
applied benchmark shall be appropriate to the type
of IRR calculated. Local commercial lending rates
Applicable and fulfilled:
Project IRR is calculated to
demonstrate additionality and has been
Page 17
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
17
or weighted average costs of capital (WACC) are
appropriate benchmarks for a project IRR.
Required/expected returns on equity are appropriate
benchmarks for equity IRR. Benchmarks supplied
by relevant national authorities are also appropriate
if the DOE can validate that they are applicable to
the project activity and the type of IRR calculation
presented.
compared against local commercial
lending rate in Pakistan. The same is
reflected in the IRR spreadsheet.
13 In the cases of projects which could be developed
by an entity other than the project participant the
benchmark should be based on publicly available
data sources which can be clearly validated by the
DOE. Such data sources may include local lending
and borrowing rates, equity indices, or benchmarks
determined by relevant national authorities. The
DOE.s validation of such benchmarks shall also
include its opinion of the suitability of the
benchmark applied in the context of the underlying
project activity.
Applicable and fulfilled:
The proposed project activity is fuel
switch at existing generators from
higher carbon intensive fossil fuel mix
to lower carbon intensive fossil fuel
mix, which can be developed by
entities other than the project
participant too. Thus, KIBOR which is
a publicly available data is used as
benchmark.
14 Internal company benchmarks/expected returns
(including those used as the expected return on
equity in the calculation of a weighted average cost
of capital - WACC), should only be applied in
cases where there is only one possible project
developer and should be demonstrated to have been
used for similar projects with similar risks,
developed by the same company or, if the company
is brand new, would have been used for similar
projects in the same sector in the country/region.
This shall require as a minimum clear evidence of
the resolution by the company’s Board and/or
shareholders and will require the validating DOE to
undertake a thorough
assessment of the financial statements of the project
developer - including the proposed WACC - to
assess the past financial behavior of the entity
during at least the last 3 years in relation to similar
projects.
Not Applicable:
The proposed project activity is fuel
switch at existing generators from
higher carbon intensive fossil fuel mix
to lower carbon intensive fossil fuel
mix, which can be developed by
entities other than the project
participant too. Thus, KIBOR which is
a publicly available data is used as
benchmark.
15 Risk premiums applied in the determination of
required returns on equity shall reflect the risk
profile of the project activity being assessed,
established according to national/international
accounting principles. It is not considered
reasonable to apply the rate general stock market
returns as a risk premium for project activities that
Not Applicable:
Project IRR is used for additionality
demonstration.
Page 18
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
18
face a different risk profile than an investment in
such indices.
Investment Comparison Analysis and Benchmark Analysis
16 If the proposed baseline scenario leaves the project
participant no other choice than to make an
investment to supply the same (or substitute)
products or services, a benchmark analysis is not
appropriate and an investment comparison analysis
shall be used. If the alternative to the project
activity is the supply of electricity from a grid this is
not to be considered an investment and a benchmark
approach is considered appropriate.
Not Applicable:
The baseline scenario to the project
activity does not creates a situation
where the project proponent is left
with no other choice but to make an
investment in any other kind of power
plant.
Sensitivity Analysis
17 Only variables, including the initial investment cost,
that constitute more than 20% of either total project
costs or total project revenues should be subjected
to reasonable variation (all parameters varied need
not necessarily be subjected to both negative and
positive variations of the same magnitude), and the
results of this variation should be presented in the
PDD and be reproducible in the associated
spreadsheets.. Where a DOE considers that a
variable which constitute less than 20% have a
material impact on the analysis they shall raise a
corrective action request to include this variable in
the sensitivity analysis
Applicable and fulfilled:
Only parameters which would
contribute to more than 20% of total
project cost or total project revenues
have been varied in a range of +10% to
-10%, and sensitivity has been
conducted. The same is reflected in the
IRR spreadsheet.
18 The DOE should assess in detail whether the range
of variations is reasonable in the project context.
Past trends may be a guide to determine the
reasonable range. As a general point of departure
variations in the sensitivity analysis should at least
cover a range of +10% and .10%, unless this is not
deemed appropriate in the context of the specific
project circumstances. In cases where a scenario
will result in the project activity passing the
benchmark or becoming the most financially
attractive alternative the DOE shall provide an
assessment of the probability of the occurrence of
this scenario in comparison to the likelihood of the
assumptions in the presented investment analysis,
taking into consideration correlations between the
variables as well as the specific socio-economic and
policy context of the project activity.
Applicable and fulfilled:
Parameters which would contribute to
more than 20% of total project cost or
total project revenues have been varied
in a range of +10% to -10%, and
sensitivity has been conducted. The
same is reflected in the IRR
spreadsheet.
Page 19
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
19
In the light of above figures and assumptions, the project IRR comes to 10.15% without considering
revenues from CDM.
The applied benchmark for the project IRR is local commercial lending rates. In the case of the project
activity this is the Risk added KIBOR Rate which is at 12.33%.
Results of Sensitivity Analysis:
The parameters considered for the Sensitivity Analysis are the project investment, the fuel prices, the
O&M cost under the project and the load factor of Natural Gas in a range of +/- 10%. For the fuel prices,
the fact that the natural gas and the HFO prices are highly correlated with 98.10%6 leads to the
conclusion that a variation in the natural gas price will implicate a comparable variation in the HFO
prices and therefore the sensitivity analysis does consider the variation of all fuel prices in a similar
range.
A +/- 10% variation of the project investment would lead to a corresponding variation of the IRR
between 8.57% and 12.05%. A variation of the fuel prices would lead to the project IRR between 7.96%
and 12.28% while the variation of the O&M cost of the project activity would implicate an IRR between
9.69% and 10.62%. A change in the load factor would bring the IRR to a range between 8.98% and
11.31%. All these changes would result below the benchmark of 12.33% and therefore the Sensitivity
Analysis does confirm that the project is not economically viable without CER revenues.
6 Detailed information was provided to the DOE.
Page 20
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
20
The project IRR was recalculated considering CDM revenues into the assessment and the new IRR was
13.07%, which is higher than the required benchmark return of 12.33, making the project feasible with
CDM revenues in consideration. Thus, CDM helps in removing the barrier to the project activity.
Prior CDM consideration:
Sl Date Project
Implementation
Sl Date Action for
securing CDM
status for the
project
1 07/04/2006 Offer from
Wartsila for
conversion of 7 x
18V32 generators
1 03/02/2007 Letter from
Carbon Services,
Pakistan to LCL
about possible
benefits from
CDM for fuel
switch.
2 19/02/2007 Extract from
Minutes of
meeting of the
Board about
Investment
2 19/02/2007 Extract from
Minutes of
meeting of the
Board about
Investment
Page 21
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
21
decision with
CDM
consideration
decision with
CDM
consideration
3 13/04/2007 Purchase Order to
Wartsila for
conversion of 6 x
18V32 Wartsila
generators.
3 28/05/2007 E mail from
Carbon Services
Pakistan to LCL
with CDM
contract.
4 19/07/2007 Offer from
Wartsila for
conversion of 3 x
12V46 generators
4 19/09/2008 Date for
stakeholder notice
5 30/10/2007 Contract signed
with SNGPL for
gas supply
5 18/11/2008 Date of
stakeholder
meeting
6 03/04/2008 Commissioning
of gas facilities by
SNGPL
6 25/06/2008 Date of contract
signing between
Verde Consulting
Pvt. Ltd. and First
Climate AG for
development of
PDD.
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
Baseline emission:
As per paragraph 13 of the methodology, “historical information (detailed records) on the use of fossil
fuels and the element process output (e.g., heat or electricity) from at least three years prior to project
implementation shall be used in the baseline calculations, e.g., information on coal use and heat output
by a district heating plant, liquid fuel oil use and electricity generated by a generating unit (records of
fuel used and output can be used in lieu of actual collecting baseline validation data). For facilities that
are less than three years old, all historical data shall be available (a minimum of one year data would
be required). In case of project activity exporting to other facilities included in the project boundary, the
above historical information from the recipient plants are required.”
Historical information for historic three years (year 2004 – 2006, already presented in section B.4 of the
PDD) is available and has been used for calculation of baseline emission.
As per paragraph 14 of the methodology, “during the crediting period, if there is a restricted
availability of a particular baseline fuel on account of local regulations this has to be considered by
adjusting the baseline emissions ex post for the period where the baseline fuel is not available. The
adjustment is done in a conservative manner i.e., if the restriction results in downward adjustment of
Page 22
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
22
baseline emissions it shall be taken into account and on the other hand upward adjustment of baseline
emissions are not eligible.”
The baseline fuel is HFO, which would be available in abundance, during the crediting period. The
availability of baseline fuel is monitored during the crediting period. The same is included under section
B.7.1 of the PDD.
Baseline emissions are calculated based on paragraph 15 of the methodology as follows:
, , 2,( * * )j
y BL j y j CO jBE FC NCV EF ______________________________________(1)
Where:
BEy tCO2 Baseline emission during year y
FCBL,j,y kt Amount of fuel j consumed during the year y operating at the baseline
energy scenario
NCVj TJ/kt Net calorific value of the fuel type j
EFCO2,j tCO2/TJ CO2 emission factor of the fuel type j
As per paragraph 15 of the methodology, “the amount of each fuel type j consumed is calculated ex-post
using the total monitored energy output of the element process i during year y and the share of each
energy source in the identified baseline scenario”
There is a single element process, making the use of “i” unnecessary.
, , 3, ,
, , ,
**(3.6*10 )
*
PJ y j BLBL j y
BL j BL cofire HFO DI
EG aFC
NCV Eff
________________________________
______(2)
Where:
FCBL,j,y kt Amount of fuel j consumed during the year y operating at the baseline
energy scenario
EGPJ,y MWh Total monitored electricity during the year y
aj,BL ratio Share of fuel j in the total input energy for the identified baseline
scenario
EffBL,cofire,HFO+D
I
% Conversion efficiency of the element process when operating with
fuel mix of HFO + DI in the baseline scenario. The baseline scenario
is a cofired scenario.
NCVBL,j TJ/kt Net calorific value of the baseline fuel type j
Project activity emissions:
As per paragraph 18 of the methodology, “project activity emissions consist of those related to use of
fossil fuel in the element processes i during the crediting period.”
Page 23
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
23
There is a single element process, making the use of “i” unnecessary.
Project emission is calculated using the following equation:
, , , , 2,* *y PJ j y PJ j PJ CO j
j
PE FC NCV EF __________________________________________(3)
Where:
PEy tCO2 Project emissions during the year y
FCPJ,j,y kt or Nm3 Quantity of fuel type j combusted during the year y
NCVPJ,j TJ/kt or
TJ/Nm3
Net calorific value of the fuel type j
EFPJ,CO2,
j
tCO2/TJ CO2 emission factor of the fuel type j
Leakage emission:
As per paragraph 19 of the methodology, “no leakage calculation is required.”
Emission Reduction:
As per paragraph 20 of the methodology, “The emission reduction achieved by the project activity will
be calculated as the difference between the baseline emissions and the project emissions” as follows:
y y yER BE PE _____________________________________________________________(4)
Where:
ERy tCO2 Emission reduction in the year y
BEy tCO2 Baseline emissions during the year y
PEy tCO2 Project emissions during the year y
B.6.2. Data and parameters that are available at validation:
Data / Parameter: EFPJ,CO2,NG
Data unit: tCO2/TJ
Description: CO2 emission factor for natural gas
Source of data used: IPCC 2006 Report, Vol 2 Ch 1
Value applied: 56.1
Justification of the
choice of data or
description of
measurement methods
and procedures actually
IPCC report is an authentic source of data
Page 24
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
24
applied :
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: EFPJ,CO2,HFO, EFCO2,HFO
Data unit: tCO2/TJ
Description: CO2 emission factor for HFO
Source of data used: IPCC 2006 Report, Vol 2 Ch 1
Value applied: 77.4
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
IPCC report is an authentic source of data
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: EFPJ,CO2,DI, EFCO2,DI
Data unit: tCO2/TJ
Description: CO2 emission factor for Diesel oil
Source of data used: IPCC 2006 Report, Vol 2 Ch 1
Value applied: 74.1
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
IPCC report is an authentic source of data
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: aHFO,BL
Data unit: ratio
Description: Share of HFO in the total input energy for the identified baseline scenario
Source of data used: Historic plant records(for the years 2004, 2005, 2006)
Value applied: Derived value (Refer table 7 under Annex 3 of the PDD):
0.9996
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
This value is derived based on following historic data:
Sum of HFO consumption during the last 3 years: 107,530 tonne
Diesel consumption during the last 3 years: 45,099 tonne
NCV of HFO: 40.4 TJ/kt
NCV of diesel: 43 TJ/kt
Any comment: The value would be archived for a period of 10 + 2 years from the start of
Page 25
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
25
crediting period
Data / Parameter: aDI,BL
Data unit: ratio
Description: Share of diesel oil in the total input energy for the identified baseline scenario
Source of data used: Historic plant records (for the years 2004, 2005, 2006)
Value applied: Derived value (Refer to Table 7 under Annex 3 of the PDD):
0.0004
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
This value is derived based on following historic data.
Sum of HFO consumption during the last 3 years: 107,530 tonne
Diesel consumption during the last 3 years: 45,099 tonne
NCV of HFO: 40.4 TJ/kt
NCV of diesel: 43 TJ/kt
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: EffBL,cofire,HFO+DI
Data unit: %
Description: Conversion efficiency of the element process when operating with fuel mix of
HFO + DI in the baseline scenario. The baseline scenario is a cofired scenario.
Source of data used: Maximum value of efficiency provided by two manufacturers
Value applied: 44.59
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
As per paragraph 16 (b) of the methodology, “Highest of the efficiency values
provided by two or more manufacturers for units with similar specifications,
using the baseline fuel,” is acceptable.
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: DDI
Data unit: kg/l
Description: Density of diesel oil
Source of data used:
Value applied: 0.86
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
IOCL specification is an authentic source of data
Any comment: The value would be archived for a period of 10 + 2 years from the start of
Page 26
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
26
crediting period
Data / Parameter: DNG
Data unit: kg/Nm3
Description: Density of natural gas
Source of data used: Specification sheet as per www.engineeringtoolbox.com7
Value applied: 0.65
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
The source of data used is a public domain data and is authentic
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: DHFO
Data unit: kg/l
Description: Density of HFO
Source of data used: Specification sheet as per www.engineeringtoolbox.com8
Value applied: 0.93
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
The source of data used is a public domain data and is authentic
Any comment: The value would be archived for a period of 10 + 2 years from the start of
crediting period
B.6.3 Ex-ante calculation of emission reductions:
Baseline emission:
Table No. 1
Equation no. 1 under section B.6.1 of the PDD
, , 2,( * * )j
y BL j y j CO jBE FC NCV EF
BEy tCO2 Baseline emission during year y 301,859 Using equation no. 1
under section B.6.1
7 http://www.engineeringtoolbox.com/specific-gravities-gases-d_334.html
8 http://www.engineeringtoolbox.com/fuels-densities-specific-volumes-d_166.html
Page 27
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
27
of the PDD
FCBL,HFO,
y
kt Amount of HFO consumed during the
year y operating at the baseline energy
scenario
96.493 From table no. 2
under section B.6.3
of the PDD
NCVHFO TJ/kt Net calorific value of HFO 40.4 IPCC Report 2006,
Vol 2 Ch 1
EFCO2,HFO tCO2/TJ CO2 emission factor of HFO 77.4 IPCC Report 2006,
Vol 2 Ch 1
FCBL,DI,y kt Amount of diesel oil consumed during
the year y operating at the baseline
energy scenario
0.0399 From table no. 2
under section B.6.3
of the PDD
NCVDI TJ/kt Net calorific value of diesel oil 43 IPCC Report 2006,
Vol 2 Ch 1
EFCO2,DI tCO2/TJ CO2 emission factor of diesel oil 74.1 IPCC Report 2006,
Vol 2 Ch 1
Table no. 2
Equation no. 2 under section B.6.1 of the PDD:
, , 3, ,
, , ,
**(3.6*10 )
*
PJ y j BLBL j y
BL j BL cofire HFO DI
EG aFC
NCV Eff
FCBL,HFO,y kt Amount of HFO consumed during the
year y operating at the baseline energy
scenario
96.493 Using equation no.
2 under section
B.6.1 of the PDD
FCBL,DI,y kt Amount of diesel oil consumed during
the year y operating at the baseline
energy scenario
0.0399 Using equation no.
2 under section
B.6.1 of the PDD
EGPJ,y MWh Total monitored electricity during the
year y
483,053 Please refer to
Table 5 under
Annex 3of the PDD
for details
aHFO,BL ratio Share of HFO in the total input energy
for the identified baseline scenario
0.9996 Based on historical
data. Please refer to
Table 7 under
Annex 3 of the
PDD for details.
EffBL,cofire,
HFO+DI
% Conversion efficiency of the element
process when operating with fuel mix
of HFO + DI in the baseline scenario.
The baseline scenario is a cofired
scenario.
44.59 Maximum value of
efficiency provided
by two suppliers of
similar equipments
NCVBL,HF
O
TJ/kt Net calorific value of the baseline HFO 40.4 IPCC 2006 Report,
Vol 2 Ch 1
aDI,BL Ratio Share of diesel oil in the total input
energy for the identified baseline
0.0004 Based on historical
data. Please refer to
Page 28
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
28
scenario table 7 under Annex
3 of the PDD for
details.
EffBL,cofire,
HFO+DI
% Conversion efficiency of the element
process when operating with fuel mix
of HFO + DI in the baseline scenario.
The baseline scenario is a cofired
scenario.
44.59 Maximum value of
efficiency provided
by two suppliers of
similar equipments
NCVBL,DI TJ/kt Net calorific value of the baseline
diesel oil
43 IPCC 2006 Report,
Vol 2 Ch 1
Project activity emissions:
Table No. 3
Equation no. 3 under section B.6.1 of the PDD
, , , , 2,* *y PJ j y PJ j PJ CO j
j
PE FC NCV EF
PEy tCO2 Project emissions during the year y 267,517 Using equation no.
3 under section
B.6.1 of the PDD
FCPJ,NG,y Nm3 Quantity of NG combusted during the
year y
85,322,265 Please refer to Table
6 under Annex 3 of
the PDD
NCVPJ,NG TJ/Nm3 Net calorific value of NG 0.0000312 Derived from NCV
of NG as per IPCC
2006 Report, Vol 2,
Ch 1 and density of
NG as per The
Engineering Tool
Box.
EFPJ,CO2,NG tCO2/TJ CO2 emission factor of NG 56.1 IPCC 2006 Report,
Vol 2, Ch 1
FCPJ,HFO,y kt Quantity of HFO combusted during the
year y
37.757 Please refer to Table
6 under Annex 3 of
the PDD
NCVPJ,HFO TJ/kt Net calorific value of HFO 40.4 IPCC 2006 Report,
Vol 2, Ch 1
EFPJ,CO2,HF
O
tCO2/TJ CO2 emission factor of HFO 77.4 IPCC 2006 Report,
Vol 2, Ch 1
FCPJ,DI,y kt Quantity of diesel oil combusted
during the year y
0.034 Please refer to Table
6 under Annex 3 of
the PDD
NCVPJ,DI TJ/kt Net calorific value of diesel oil 43 IPCC 2006 Report,
Vol 2, Ch 1
EFPJ,CO2,DI tCO2/TJ CO2 emission factor of diesel oil 74.1 IPCC 2006 Report,
Page 29
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
29
Vol 2, Ch 1
Emission Reduction:
Table no. 4
Equation no. 4 under section B.6.1 of the PDD
y y yER BE PE
ERy tCO2 Emission reduction in the year y 34,342 Using equation no.
4 under section
B.6.1 of the PDD
BEy tCO2 Baseline emissions during the year y 301,859 Using information
from Table 1 under
section B.6.3 of the
PDD
PEy tCO2 Project emissions during the year y 267,517 Using information
from Table 3 under
section B.6.3 of the
PDD
B.6.4 Summary of the ex-ante estimation of emission reductions:
Year Estimation of
project activity
emission
(tCO2e)
Estimation of baseline
emission
(tCO2e)
Estimation of
leakage
(tCO2e)
Estimation of
overall emission
reductions
(tCO2e)
Year 1 267,517 301,859 0 34,342
Year 2 267,517 301,859 0 34,342
Year 3 267,517 301,859 0 34,342
Year 4 267,517 301,859 0 34,342
Year 5 267,517 301,859 0 34,342
Year 6 267,517 301,859 0 34,342
Year 7 267,517 301,859 0 34,342
Year 8 267,517 301,859 0 34,342
Year 9 267,517 301,859 0 34,342
Year 10 267,517 301,859 0 34,342
Total 2,675,170 3,018,590 0 343,420
Page 30
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
30
B.7 Application of a monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Data / Parameter: EGPJ,y
Data unit: MWh
Description: Total monitored electricity during the year y
Source of data to be
used:
Plant records (Generator room log book)
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
483,053 (Ex-ante value. Please refer to Table 5 under Annex 3 of the PDD)
This value is estimated based on the following:
Technical specification sheet of the generators
Assumed PLF for generators
Assumed annual working hours
Description of
measurement methods
and procedures to be
applied:
The electricity generated would be monitored by electricity meter installed at
generator outlet.
Frequency: Daily
QA/QC procedures to
be applied:
The meters would be calibrated regularly as per manufacturer’s specification. In
absence of manufacturer’s specification, national calibration standard would be
used.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: FCPJ,NG,y
Data unit: Nm3
Description: Quantity of NG combusted during the year y
Source of data to be
used:
Plant records (Generator room log book)
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
85,322,265 (Ex-ante value. Please refer to Table 6 under Annex 3 of the PDD)
This value is estimated based on the following:
Energy generated by the generators
Percentage input energy contribution of NG, in the project scenario
NCV of NG
Terminal heat rate of generators on NG operation
Description of
measurement methods
and procedures to be
applied:
Digital gas flow meter installed by SNGPL
Frequency: Daily
QA/QC procedures to The meter would be calibrated regularly by SNGPL
Page 31
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
31
be applied:
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: FCPJ,HFO,y
Data unit: kt
Description: Quantity of HFO combusted during the year y
Source of data to be
used:
Plant records (Generator room log book)
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
37.757 (Ex-ante value. Please refer to Table 6 under Annex 3 of the PDD)
This value is estimated based on the following:
Energy generated by the generators
Percentage input energy contribution of HFO, in the project scenario
NCV of HFO
Terminal heat rate of generators on HFO operation
Description of
measurement methods
and procedures to be
applied:
Volume of HFO consumed would be monitored by checking the level of dip
from a standard surface area storage tank. The consumption figure would be
multiplied by density (provided ex-ante) to obtain mass of HFO consumed.
Frequency: Every 12 hours
QA/QC procedures to
be applied:
Internal calibration is done by Operations department. External calibration is
done by stores/auditors.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: FCPJ,DI,y
Data unit: kt
Description: Quantity of diesel oil combusted during the year y
Source of data to be
used:
Plant records (Generator room log book)
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
0.034 (Ex-ante value. Please refer to Table 6 under Annex of the PDD)
This value is estimated based on the following:
Energy generated by the generators
Percentage input energy contribution of diesel oil, in the project
scenario
Description of
measurement methods
and procedures to be
applied:
Volume of diesel consumed would be monitored by checking the level of dip
from a standard surface area storage tank. The consumption figure would be
multiplied by density (provided ex-ante) to obtain mass of diesel consumed.
Frequency: Every 12 hours
QA/QC procedures to
be applied:
Internal calibration is done by Operations department.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Page 32
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
32
Data / Parameter: NCVPJ,NG
Data unit: TJ/Nm3
Description: Net calorific value for Natural gas
Source of data to be
used:
Laboratory test reports
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
0.0000312 (Ex-ante value. Derived value – This value is based on the
following:
NCV of NG as per IPCC 2006 Report, Vol 2 Ch 1
Density of NG (at NTP) as per The Engineering Tool Box)
Description of
measurement methods
and procedures to be
applied:
The NCV of fuel would be measured at laboratory
Frequency: Annually
QA/QC procedures to
be applied:
The laboratory is accredited by relevant statutory authority.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: NCVPJ,HFO, NCVBL,HFO
Data unit: TJ/kt
Description: Net calorific value for HFO
Source of data to be
used:
Laboratory test report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Will be monitored ex-post.
77.4 (Ex-ante value. This value is taken from IPCC 2006 Report, Vol 2 Ch 1)
Description of
measurement methods
and procedures to be
applied:
The NCV of fuel would be measured at laboratory
Frequency: Annually
QA/QC procedures to
be applied:
The laboratory is accredited by relevant statutory authority.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
Data / Parameter: NCVPJ, DI, NCVPJ, DI
Data unit: TJ/kt
Description: Net calorific value for Diesel oil
Source of data to be
used:
Laboratory test reports
Value of data applied
for the purpose of
Will be monitored ex-post.
43 (Ex-ante value. This value is taken from IPCC 2006 Report, Vol 2 Ch 1)
Page 33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
33
calculating expected
emission reductions in
section B.5
Description of
measurement methods
and procedures to be
applied:
The NCV of fuel would be measured at laboratory
Frequency: Annually
QA/QC procedures to
be applied:
The laboratory is accredited by relevant statutory authority.
Any comment: The data would be archived for a period of 10 + 2 years from the start of
crediting period
B.7.2 Description of the monitoring plan:
Parameter
Hourly
Data
Collection
Daily Data
Log
Preparation
Initial Data
Verification
Final Data
Verification
Data Auditing
Designatio
n Frequency
Fuel
Consumption
by Generators
12 Hourly
by Engine
Room
Operator
By Shift
Engineer
By
Operation
Manager
By Senior
Manager,
verification
every day
Stores,
Accounts &
Power
Generation
Department
Monthly
Electricity
Generation
12 Hourly
by
Operator
or Shift
Supervisor
By Shift
Engineer
(Electrical)
By
Operation
Manager
By Senior
Manager,
verification
every day
Power
Generation
Department
Monthly
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
Date of completion: 19th
Mar, 2010.
Responsible entity:
First Climate (India) Pvt. Ltd.
3C, Camac Street, Camac Tower, 9th Floor,
Kolkata – 700 016, India
Phone – Direct: +91 33 4022 3456
Fax: +91 33 4005 6615
Website: www.firstclimate.com
First Climate (India) Pvt. Ltd. is not a project participant.
Page 34
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
34
SECTION C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
As per Glossary of CDM terms, “The starting date of a CDM project activity is the earliest date at
which either the implementation or construction or real action of a project activity begins (CDM
Glossary of Terms, Version 03). As per EB 41, in light of the above definition, the start date shall be
considered to be the date on which the project participant has committed to expenditures related to the
implementation or related to the construction of the project activity. This, for example, can be the date
on which contracts have been signed for equipment or construction/operation services required for the
project activity. For this CDM project activity, date of release of first purchase order can be taken as
the project activity start date.”
The start date is: (13/04/2007). This corresponds to the first purchase order release date.
C.1.2. Expected operational lifetime of the project activity:
15 years
C.2 Choice of the crediting period and related information:
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
Fixed crediting period is chosen
C.2.1.2. Length of the first crediting period:
Fixed crediting period is chosen
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
01/09/2010 or project registration date, whichever is later.
C.2.2.2. Length:
10 years 0 months
Page 35
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
35
SECTION D. Environmental impacts
>>
D.1. If required by the host Party, documentation on the analysis of the environmental impacts
of the project activity:
According to the host country regulations, the project activity had to receive an Environmental Approval
from the Environment Protection Department of the local government, upon submission of an Initial
Environmental Examination (IEE) Report by the project proponent.
The IEE points out that the project will be beneficial to the environment as utilization of NG, less carbon
intensive fossil fuel, is made possible by the proposed technology. No negative environmental impacts are
to be considered, as the technology to be adopted is mature and safe, once appropriate operation and
maintenance procedure are in place.
The environmental analyses conducted by Lucky Cement Limited for the project are consistent in
demonstrating that the project activity is expected to remain fully compliant with NEQS (National
Environmental Quality Standards). In fact, it is expected that pollutant emissions (both of local concern
and global concern, such as CO2) will reduce from the current levels.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an
environmental impact assessment undertaken in accordance with the procedures as required by
the host Party:
Neither the project participants nor the host Party have any concern about negative environmental impacts
associated with the project activity, given that project activity aims at reducing the local and global
environmental impacts of the industrial site where the project activity is to be implemented.
IEE Report (Initial Environmental Examination Report) and the accompanying approval request letter
were submitted on 10/11/2008. Approval letter was issued on 12/11/2008. The approval letter does not
raise any particular issue with regard to the environmental impact of the project.
Page 36
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
36
SECTION E. Stakeholders’ comments
>>
E.1. Brief description how comments by local stakeholders have been invited and compiled:
The stakeholders to the project activity are local farmers, chowkidaar(security personnels), driver and a
teacher. They were notified about the project through a newspaper advertisement9. The stakeholders were
invited for a meeting at the plant10
. The stakeholders provided their views about the project in writing11
.
E.2. Summary of the comments received:
The comments received from the stakeholders were favourable and supportive of the project activity. The
comments are about the project’s contribution to:
Pollution reduction
Utilization of natural resources
Employment generation
Cleaner environment
Improved road condition
The comments received from stakeholders have been tabulated below:
Stakeholders’ Comments Translation for Lucky Cement Generator Change Project at Pezu Plant:
Com
ment
N.
Stakeholder’s
Name
Designation/
Profession
Qualification Address Comments/Views about
the Project
1 Muhammad
Saleem
Farmer Under Matric Pezu, P/O
Pezu.
Tehsil &
District
Lakki
Marwat
Natural gas based operation
will not only reduce
pollution but will also result
in a better utilization of
national resources.
2 Mr. Zaki Khan Farmer Under Matric Wanda
Ahmed
Khan teh &
Distt. Lakki
Marwat
1. Installation of gas plant
will result in abatement
of environmental
pollution.
2. The project will result
9 The local language version of the newspaper advertisement is present in Annex 6. Also an English version of the
same has been provided.
10 Snapshots of the meeting would be provided to the DOE during validation
11 All copies of written comments by invited stakeholders would be provided to the DOE during validation.
Page 37
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
37
in increased
employment
opportunities.
3 Shah Nawaz Chowkidar Primary Wanda
Ahmed
Khan teh &
Distt. Lakki
Marwat
1. People will get jobs.
2. The air will be cleaner
and the environment
more pleasant.
4 Fida
Muhammad
Driver Primary Pezu P/O
Pezu
District
Lakki
Marwat
1. Gas based electricity
generation will cause
less pollution to the
environment.
2. New Job opportunities
will add to the
prosperity of this
region.
5 Inayatullah Driver Primary Wanda
Ahmed
Khan P/O
Pezu Tehsil
Distt Lakki
Marwat
1. Installation of a new
pipe line would result in
new employment
opportunities
2. Road condition will
improve.
6 Abadullah
Khan
Farmer Under Metric Wanda Jogi
P/O Pezu
Tehsil
Lakki
Marwat
1. Pollution will decrease
due to switching of
plant to gas.
2. New job opportunities
will result in over all
betterment of the area.
7 Noor Shah Teacher M.A Pezu P/O
Pezu, Lakki
Marwat
1. Gas based electricity
generation would result
in less import of crude
oil.
2. National economy will
improve
3. Pollution will decrease.
8 Muhammad
Nazir
Farmer SSC Pezu P/O
Pezu, Lakki
Maewat
1. General climate of the
area will improve.
2. New job opportunities
will be created.
Page 38
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
38
9 Raza
Muhammad
Farmer Primary Wanda Jogi
P/O Pezu
Tehsil &
Distt Lakki
Marwat
1. This project will result
in abatement of
environmental pollution.
2. Number of oil tankers
on the road will
decrease resulting in
less wear an tear on the
road.
E.3. Report on how due account was taken of any comments received:
No adverse comments to the project activity have been received. All comments received during
stakeholder consultation will be made available to DOE during validation. The project would be put up
for international stakeholder consultation in the UNFCCC site as a part of validation.
Page 39
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
39
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: Lucky Cement Ltd.
Street/P.O.Box: A.Aziz Hashim Taba Street
Building: 6-A M.Ali Housing Society
City: Karachi
State/Region: Sindh
Postcode/ZIP:
Country: Pakistan
Telephone: 092 21-111 786 555
FAX: 092 21 3453 4302
E-Mail: [email protected]
URL: www.lucky-cement.com
Represented by:
Title: Director Power Generation
Salutation:
Last name: Haqqi
Middle name: Haq
First name: Intisar ul Haq
Department: Power Generation
Mobile: 0092-03008550883
Direct FAX: +92-969-580122
Direct tel: +92-969-580121
Personal e-mail: [email protected]
Organization: Carbon Services Private Limited
Street/P.O.Box: 19 Davis Road
Building: 2nd Floor, Al Maalik,
City: Lahore
State/Region: Punjab
Postfix/ZIP:
Country: Pakistan
Telephone: +92-42-36313235 / 36313236
FAX: +92-42-36312959
E-Mail:
URL: www.carbon.com.pk
Represented by: Mr. Omar M. Malik
Title: Director
Salutation: Mr
Last Name: Malik
Page 40
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
40
Middle Name: M
First Name: Omar
Department:
Mobile: +92-300-8463743
Direct FAX: +92-42-36312959
Direct tel: +92-42-36313235 / 36313236
Personal E-Mail: [email protected]
Organization: First Climate (Switzerland) AG
Street/P.O.Box: Stauffacherstr.45
Building:
City: Zurich
State/Region: Zurich
Postcode/ZIP: 8004
Country: Switzerland
Telephone: +41-44-298 2800
FAX: +41 44-298 2899
E-Mail: [email protected]
URL: www.firstclimate.com
Represented by:
Title: Managing Partner
Salutation:
Last name: Lüchinger
Middle name:
First name: Alexander
Department:
Mobile:
Direct FAX: +41 44-298 2899
Direct tel: +41-44-298 2807
Personal e-mail: [email protected]
Page 41
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
41
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
This section has been intentionally left blank
Page 42
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
42
Annex 3
BASELINE INFORMATION
Electricity generated by the generators under project scenario:
Table no. 5
Parameter Unit Value Remarks
Electricity generated under HFO operation
The equations used are:
Electricity generated by 7 No. of 18V32 generators = {(De-rated capacity of each 18V32 Wartsila
generator on HFO) x (Number of 18V32 Wartsila generator) x (Annual operating hours for generator) x
(Percentage of time for which the generators would operate on HFO) x (PLF for
generators)}__________________________________________________________________(A)
Electricity generated by 3 No. of 12V46 generators = {(De-rated capacity of each 12V46 Wartsila
generator on HFO) x (Number of 12V46 Wartsila generator) x (Annual operating hours for generator) x
(Percentage of time for which the generators would operate on HFO) x (PLF for
generators)}__________________________________________________________________(B)
De-rated capacity of each 18V32 Warsila
generator (On HFO) MW 5.584
Technical specification:
Appendix 1.3_18V32
Number of 18V32 Wartsila generators No 7
Information provided by
LCL
De-rated capacity of each 12V46 Warsila
generator (On HFO) MW 10.09
Technical specification:
Appendix 1.4_12V46
Number of 12V46 Wartsila generators No 3
Information provided by
LCL
Annual operating hours for generator hours/yr 8,000
Assumed value. Industry
standard.
Percentage of time for which the generators
would operate on HFO % 35
Estimated based on annual
gas availability
PLF for generators % 90
Assumed value. Industry
standard.
Electricity generated by 7 No. 18V32
generators on HFO MWh/yr 98,501
Estimated using equation
no. A under table no. 5 of
Annex 3 of the PDD.
Electricity generated by 3 No. 12V46
generators on HFO MWh/yr 76,280
Estimated using equation
no. B under table no. 5 of
Annex 3 of the PDD.
Electricity generated on NG operation
The equations used are:
Electricity generated by 7 No. of 18V32 generators = {(De-rated capacity of each 18V32 Wartsila
Page 43
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
43
generator on NG) x (Number of 18V32 Wartsila generator) x (Annual operating hours for generator) x
(Percentage of time for which the generators would operate on NG) x (PLF for
generators)}__________________________________________________________________(C)
Electricity generated by 3 No. of 12V46 generators = {(De-rated capacity of each 12V46 Wartsila
generator on NG) x (Number of 12V46 Wartsila generator) x (Annual operating hours for generator) x
(Percentage of time for which the generators would operate on NG) x (PLF for
generators)}___________________________________________________________________(D)
De-rated capacity of each 18V32 Warsila
generator (On NG) MW 5.39
Technical specification:
Appendix 1.3_18V32
Number of 18V32 Wartsila generators No 7
Information provided by
LCL
De-rated capacity of each 12V46 Warsila
generator (On NG) MW 9.38
Technical specification:
Appendix 1.4_12V46
Number of 12V46 Wartsila generators No 3
Information provided by
LCL
Annual operating hours for generator hours/yr 8,000
Assumed value. Industry
standard.
Percentage of time for which the generators
would operate on NG % 65
Estimated based on annual
gas availability
PLF for generators % 90
Assumed value. Industry
standard.
Electricity generated by 7 No. 18V32
generators on NG MWh/yr 176,576
Estimated using equation
no. A under table no. 5 of
Annex 3 of the PDD.
Electricity generated by 3 No. 12V46
generators on NG MWh/yr 131,695
Estimated using equation
no. B under table no. 5 of
Annex 3 of the PDD.
Total electricity generated
Total electricity generated during the year y = {( Electricity generated by 7 No. 18V32 generators on
HFO) + (Electricity generated by 3 No. 12V46 generators on HFO) + (Electricity generated by 7 No.
18V32 generators on NG) + (Electricity generated by 3 No. 12V46 generators on
NG)}___________________________________________________________________(E)
Total electricity generated during the year y Mwh 483,053
Estimated using equation
no. E under table no. 5 of
Annex 3 of the PDD.
Electricity generated by 7 No. 18V32
generators on HFO MWh/yr 98,501
Electricity generated by 3 No. 12V46
generators on HFO MWh/yr 76,280
Electricity generated by 7 No. 18V32
generators on NG MWh/yr 176,576
Electricity generated by 3 No. 12V46 MWh/yr 131,695
Page 44
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
44
generators on NG
Fuel consumption under project scenario:
Table no. 6
Parameter Unit Value Remarks
HFO consumption under project scenario
The equations used are:
HFO consumption by 7 Nos. of 18V32 generators = [{(Electricity generated by 7 No. 18V32 generators
on HFO) x (Terminal heat rate for 18V32 Wartsila generators on HFO)} / (NCV of
HFO)]____________________________________________________________________(F)
HFO consumption by 3 Nos. of 12V46 generators = [{(Electricity generated by 3 No. 12V46 generators
on HFO) x (Terminal heat rate for 12V46 Wartsila generators on HFO)} / (NCV of
HFO)]_____________________________________________________________________(G)
Total HFO consumption by 10 No. generators = {( HFO consumption by 7 Nos. of 18V32 generators) +
(HFO consumption by 3 Nos. of 12V46 generators)}__________________________________(H)
Electricity generated by 7 No. 18V32
generators on HFO MWh/yr 98,501
Taken from Table no. 5
under Annex 3 of the PDD
Terminal heat rate for 18V32 Wartsila
generator (on HFO) KJ/kWh 8,710
Technical specification:
Appendix 1.3_18V32
NCV of HFO TJ/kt 40.4
IPCC 2006 report, Vol 2,
Ch 1
HFO consumption by 7 Nos. of 18V32
generators tonne/yr 21,236
Using equation no. F under
table 6 of Annex 3 of the
PDD.
Electricity generated by 3 No. 12V46
generators on HFO MWh/yr 76,280
Taken from Table no. 5
under Annex 3 of the PDD
NCV of NG
Technical specification:
Appendix 1.4_18V32
Terminal heat rate for 12V46 Wartsila
generators (on HFO) kJ/kWh 8,750
IPCC 2006 report, Vol 2,
Ch 1
HFO consumption by 3 Nos. of 12V46
generators tonne/yr 16,521,
Using equation no. G under
table 6 of Annex 3 of the
PDD.
Total HFO consumption by 10 No
generators tonne/yr 37,758
Using equation no. H under
table 6 of Annex 3 of the
PDD.
NG consumption under project scenario
The equations used are:
Page 45
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
45
NG consumption by 7 Nos. of 18V32 generators = [{(Electricity generated by 7 No. 18V32 generators on
NG) x (Terminal heat rate for 18V32 Wartsila generators on NG)} / (NCV of
NG)]____________________________________________________________________(F)
NG consumption by 3 Nos. of 12V46 generators = [{(Electricity generated by 3 No. 12V46 generators on
NG) x (Terminal heat rate for 12V46 Wartsila generators on NG)} / (NCV of
NG)]_____________________________________________________________________(G)
Total NG consumption by 10 No. generators = {( NG consumption by 7 Nos. of 18V32 generators) +
(NG consumption by 3 Nos. of 12V46 generators)}____________________________________(H)
Electricity generated by 7 No. 18V32
generators on NG MWh/yr 176,576
Taken from Table no. 5
under Annex 3 of the PDD
Terminal heat rate for 18V32 Warsila
generator (on NG) KJ/kWh 8,990
Technical specification:
Appendix 1.3_18V32
NCV of NG TJ/kt 56
IPCC 2006 report, Vol 2,
Ch 1
NG consumption by 7 Nos. of 18V32
generators tonne/yr 33,071
Using equation no. F under
table 6 of Annex 3 of the
PDD.
Electricity generated by 3 No. 12V46
generators on NG MWh/yr 131,695
Taken from Table no. 5
under Annex 3 of the PDD
Terminal heat rate for 12V46 Wartsila
generators (on NG) KJ/kWh 8,160
Technical specification:
Appendix 1.4_18V32
NCV of NG TJ/kt 56
IPCC 2006 report, Vol 2,
Ch 1
NG consumption by 3 Nos. of 12V46
generators tonne/yr 22,388
Using equation no. G under
table 6 of Annex 3 of the
PDD.
Total NG consumption by 10 No generators tonne/yr 55,459
Using equation no. H under
table 6 of Annex 3 of the
PDD.
Density of NG kg/Nm3 0.65 The Engineering Tool Box
Total NG consumption by 10 Generators Nm3/yr 85,322,265
Based on NG consumption
in tonne and density of NG
Diesel consumption under project scenario
The equation used is:
Total energy input by diesel = [{(Total HFO consumption by 10 No generators) x (NCV of HFO)} +
{(Total NG consumption by 10 No generators) x (NCV of NG)}] x {( Share of diesel oil in total energy
input) / (Share of fuels other than diesel in total energy input)}_______________________________(J)
Total diesel consumption = (Total energy input by diesel) / (NCV of diesel)_______________(K)
Page 46
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
46
Total HFO consumption by 10 No.
generators tonne/yr 22,388
Taken from above (same
table)
NCV of HFO TJ/kt 40.4 IPCC 2006, Vol 2 Ch 1
Total NG consumption by 10 No. generators tonne/yr 55,459
Taken from above (same
table)
NCV of NG TJ/kt 48 IPCC 2006, Vol 2 Ch 1
Share of fuels other than diesel in total
energy input % 99.96
Assuming equal % share of
energy input
of diesel on HFO and NG
operation
Share of diesel oil in total energy input % 0.04
Assuming equal % share of
energy input
of diesel on HFO and NG
operation
Total energy input by Diesel TJ/yr 1.47
Using equation no. J under
table 6 of Annex 3 of the
PDD
NCV of diesel TJ/kt 43
IPCC 2006 report Vol 2 Ch
1
Total diesel consumption by 10 No.
generators tonne/yr 34.3
Using equation no. K under
table 6 of Annex 3 of the
PDD
Historical data
Table 7:
Parameter Unit Value Remarks
18V32 generators
HFO consumption by 7 No. 18V32 Wartsila
generators in 2004 tonne 37,068
Historic operational data
HFO consumption by 7 No. 18V32 Wartsila
generators in 2005 tonne 38,878
Historic operational data
HFO consumption by 7 No. 18V32 Wartsila
generators in 2006 tonne 31,584
Historic operational data
Total HFO consumption by 7 No. 18V32
Wartsila generators during 2004 - 2006 tonne 107,530
Historic operational data
Electricity generated by 7 No. of 18V32
Wartsila generators in 2004 MWh 164,459
Historic operational data
Electricity generated by 7 No. of 18V32
Wartsila generators in 2004 MWh 171,625
Historic operational data
Electricity generated by 7 No. of 18V32
Wartsila generators in 2004 MWh 140,722
Historic operational data
Total electricity generated by 7 No. of
18V32 Wartsila generators during 2004 -
2006 MWh 476,806
Historic operational data
Page 47
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
47
Diesel consumption by 7 No. 18V32
Wartsila generators in 2004 Litre 20,459
Historic operational data
Diesel consumption by 7 No. 18V32
Wartsila generators in 2005 Litre 16,832
Historic operational data
Diesel consumption by 7 No. 18V32
Wartsila generators in 2006 Litre 19,535
Historic operational data
Total diesel consumption by 7 No. 18V32
Wartsila generators during 2004 - 2006 Litre 56,826
Historic operational data
12V46 generators
HFO consumption by 3 No. 12V46 Wartsila
generators in 2004 tonne 0
Not installed
HFO consumption by 3 No. 12V46
Wartsila generators in 2005 tonne 9,390
Historic operational data
HFO consumption by 3 No. 12V46 Wartsila
generators in 2006 tonne 35,709
Historic operational data
Total HFO consumption by 3 No. 12V46
Wartsila generators during 2004 – 2006 tonne 45,099
Historic operational data
Electricity generated by 3 No. 12V46
Wartsila generators in 2004 MWh 0
Not installed
Electricity generated by 3 No. 12V46
Wartsila generators in 2004 MWh 47,326
Historic operational data
Electricity generated by 3 No. 12V46
Wartsila generators in 2004 MWh 179,225
Historic operational data
Total electricity generated by 3 No. 12V46
Wartsila generators during 2004 - 2006 MWh 226,551
Historic operational data
Diesel consumption by 3 No. 12V46
Wartsila generators in 2004 Litre 0
Not installed
Diesel consumption by 3 No. 12V46
Wartsila generators in 2005
Litre 1,000
Historic operational data
Diesel consumption by 3 No. 12V46
Wartsila generators in 2006
Litre 11,200
Historic operational data
Total diesel consumption by 3 No. 12V46
Wartsila generators during 2004 - 2006 Litre 12,200 Historic operational data
Analysis of historical data
The equations used are:
Total energy input by HFO during 2004 - 2006 = [{(Total HFO consumption by 7 No. 18V32 Wartsila
generators during 2004 – 2006) + (Total HFO consumption by 3 No. 12V46 Wartsila generators during
2004 – 2006)} x (NCV of HFO)]____________________________________________________(L)
Total energy input by diesel during 2004 - 2006 = [{(Total diesel consumption by 7 No. 18V32 Wartsila
generators during 2004 – 2006) + (Total diesel consumption by 3 No. 12V46 Wartsila generators during
2004 – 2006)} x (NCV of diesel)]___________________________________________________(M)
Percentage share of HFO in total energy input during 2004 – 2006 = (Total energy input by HFO during
Page 48
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
48
2004 - 2006) / {( Total energy input by HFO during 2004 - 2006) + (Total energy input by diesel during
2004 - 2006)}___________________________________________________________________(N)
Percentage share of diesel in total energy input during 2004 – 2006 = (Total energy input by diesel
during 2004 - 2006) / {( Total energy input by HFO during 2004 - 2006) + (Total energy input by diesel
during 2004 - 2006)}_____________________________________________________________(P)
Total HFO consumption by 7 No. 18V32
Wartsila generators during 2004 - 2006 Tonne 107,530
Historic operational data
Total HFO consumption by 3 No. 12V46
Wartsila generators during 2004 – 2006 Tonne 45,099
Historic operational data
NCV of HFO TJ/kt 40.4
IPCC 2006 Report, Vol 2
Ch 1
Total energy input by HFO during 2004 -
2006 TJ 6,166
Using equation no. L under
table 7 of Annex 3 of the
PDD
Total diesel consumption by 7 No. 18V32
Wartsila generators during 2004 - 2006 Litre 56,826
Historic operational data
Total diesel consumption by 3 No. 12V46
Wartsila generators during 2004 - 2006 Litre 12,200 Historic operational data
Density of diesel kg/l 0.86 IOCL specification
NCV of diesel TJ/kt 43
IPCC 2006 Report, Vol 2
Ch 1
Total energy input by diesel during 2004 -
2006 TJ 2.55
Using equation no. M
under table 7 of Annex 3 of
the PDD
Percentage share of HFO in total energy
input during 2004 - 2006 % 99.96
Using equation no. N under
table 7 of Annex 3 of the
PDD
Percentage share of HFO in total energy
input during 2004 - 2006 % 0.04
Using equation no. P under
table 7 of Annex 3 of the
PDD
Page 49
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM – Executive Board
49
Annex 4
MONITORING INFORMATION
This section has been left blank.