Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

Feb 17, 2019

Download

Documents

vonhan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes
Page 2: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

Clean Air Act 101Module 5 – Title V Operating Permits

Marcia L. SpinkAssociate Director for Policy & Science

Air Protection Division EPA Region 3

& The Office of Air Quality Planning and Standards

Page 3: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

Overview of the Title V

Operating Permit Program

Page 4: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

33

What is the Title V What is the Title V Operating Permit Program?Operating Permit Program?

Established by the Established by the Clean Air Act Amendments of 1990

One source - One Title V Permit

Permit expires after 5 years

Title V pays for itself – Permit fees

Page 5: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

44

Benefits of the Title V Operating Permit Program

Satisfies the need for a uniform and comprehensive permit system that implements the Clean Air Act.

Increased Public Access– Permit Review Process– Compliance Data and Reports

Page 6: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

55

Benefits of the Title V Operating Permit Program

continued

Improved compliance due to consolidation of requirements

Improved implementation

Page 7: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

66

Who is the Title V Permitting Who is the Title V Permitting AuthorityAuthority

The CAA envisioned that State and Local air The CAA envisioned that State and Local air pollution agencies would issue Title V permits. pollution agencies would issue Title V permits.

States become the Title V permitting authority upon final approval by EPA of its Title V Program consisting of regulations to satisfy 40CFR Part 70.

Until that happens, EPA is the permitting authority under 40 CFR Part 71.

Page 8: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

77

Who Needs a Title V Permit?Who Needs a Title V Permit?

Major Sources - any stationary source that exceeds potential-to-emit (PTE) thresholds for regulated pollutants.

Regulated Pollutant Thresholds– Criteria Pollutants: >100 tpy PTE– HAPs: >10 tpy (1 HAP) or >25 tpy (HAPs)

Page 9: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

88

Who Needs a Title V Permit?Who Needs a Title V Permit?continuedcontinued

Facilities subject to (regardless of size):– New Source Performance Standards (NSPS) – National Emission Standards for Hazardous Air

Pollutants (NESHAPs) aka– Maximum Achievable Control Technology (MACT)

Standards

Facilities subject to major New Source Review (NSR) including Prevention of Significant Deterioration (PSD)

Sources subject to the Title IV Acid Rain program.

Page 10: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

99

Who Does Not Need a Title V Permit?

Minor Sources– Natural Minors– Synthetic Minors

Exempted Area Sources under Section 112 (MACT Standards) e.g. drycleaners

Page 11: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1010

How are Title V Permits Different From Preconstruction

Permits?

Title V does not establish any new Federal requirements for a facility.

Preconstruction permits are required for most new facilities or new/modified units at existing facilities.

Title V permits will contain most preconstruction permit conditions.

Page 12: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1111

What Does a Title V Permit Look Like?

Identification of Units and Boilerplate

Emission Unit and Facility-wide Groups

Federal and State-only Enforceable Sections

Statement of Basis/Fact Sheet/TSD

Page 13: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1212

Title V Permit

Title I

Nonattainment

Title IIIAir Toxics

Title IV

Acid Rain

Exis

ting

SIP

Requ

irem

ents

State PermitPrograms

Title VII

Enforcement

What Goes into a Title V Permit?

Page 14: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1313

What Goes into a Title V Permit?Continued

Applicable Requirements– SIP Requirements– Major NSR/PSD Permits– Other Federally Enforceable Permits– NSPS and 111(d) Plans– NESHAPs/MACT- 40 CFR Parts 61 and 63– Acid Rain Permits (Title IV)– Stratospheric Ozone (Title VI)– Other

Page 15: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1414

What Goes into a Title V Permit?continued

Emission Limits, Operational Restrictions, Work Practice Standards

Monitoring and Testing

Recordkeeping and Reporting

Any Compliance Schedules

Page 16: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1515

Why is Title V Important?

A more useful permit for everyone

More compliance information

Expanded legal rights/requirements

Page 17: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1616

SIPS & Title V Permits

Title V permits “house” existing SIP requirements (and all other applicable federal and state requirements).

SIPs are required under Title I of the CAA and must stand complete on their own.

Title V permits are required under Title V of the CAA.

Page 18: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1717

SIPS & Title V Permits

Title V permits may not be used to “create” or “fix” or “fill-in” SIP requirements.

The issue is NOT federal enforceability.

Nothing is made part of the SIP until and unless it goes through the state and federal processes required to codify it in 40 CFR Part 52 pursuant to Section 110.

Page 19: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1818

SIPS & Title V Permits

SIP requirements cannot be open-ended with the “details” to be set in the Title V permit.

SIP revision requests to approve documents or regulations with expiration or sunset dates pose approvability problems.

Page 20: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

1919

Title V Contacts at EPA Region 1 - Ida McDonnell Region 2 - Steve Riva Region 3 - Kathleen Anderson Region 4 - Gregg Worley Region 5 - Pamela Blakley Region 6 - Jeff Robinson Region 7 - Mark Smith Region 8 - Carl Daly Region 9 - Gerald Rios Region 10 - Nancy Helm OAQPS - Juan Santiago

Page 21: Clean Air Act 101 Operating Permits - EPA Archives | US EPA · Clean Air Act 101 Module 5 – Title V Operating Permits ... Nothing is made part of the SIP until and unless it goes

2020

END OF Clean Air Act 101 MODULE 5 – Title V