Class 24: Chapter 15: Materials Requirements Planning •Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam •90% of the 30 questions will come from earlier exams • 9 Am time and date •10:30 time and date •1:30 time and date •4:00 time and date •News of Note –GM IPO •An Overview of Chapter 15
13

Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Dec 22, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Class 24: Chapter 15: Materials Requirements Planning

Class 24: Chapter 15: Materials Requirements Planning

• Class 24 Agenda–Review Deliverables Due Dates–Review Final Exam

•90% of the 30 questions will come from earlier exams•9 Am time and date•10:30 time and date•1:30 time and date•4:00 time and date

• News of Note–GM IPO

• An Overview of Chapter 15

Page 2: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Requirments Planning Requirments Planning

• Independent Demand: demand created by customers

• Dependent Demand: demand is driven by demand of another item

• MRP: computes demand for dependent items

• DRP: computes demand for finished goods in the distribution system

• CRP: determines if sufficient resources are available

15–15–22

Page 3: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP and DRP in the Supply Chain MRP and DRP in the Supply Chain

Figure 15-1 15–15–33

Page 4: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP Process MRP Process

Figure 15-3 15–15–44

Page 5: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP InputsMRP Inputs

• Bill of Materials (BOM): detailed listing of all materials needed to make an ‘end item;

Figure 15-5 15–15–55

Page 6: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

ActivityActivity

• Select one of the items below and develop a product structure BOM:

–Chair

–Desk

– 2 dozen cupcakes

–Set of golf clubs

–Product of your choice

15–15–66

Page 7: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP InputsMRP Inputs

• Master Production Schedule (MPS): schedule for building finished products

–Time Bucket: time periods for planning

–Planning Horizon: entire time period covered by the MPS

–Available to Promise (ATP): planned production not already committed to a customer

–Rough-cut Capacity Planning: estimates the critical resources needed to build MPS

• Inventory Records: contains information about inventory including amount on hand

15–15–77

Page 8: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP ProcessMRP Process

• Gross Requirements: total amount of an end item that is required

• Requirements Explosion: determines how many additional units are needed

• Net Requirements: minimum amount needed in a time period

• Planned Order Receipt: amount of an item planned to arrive in a time period

• Planned Order Release: amount of an item planned to be ordered in time period

15–15–88

Page 9: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

MRP Inputs and Outputs MRP Inputs and Outputs

15–15–99

Page 10: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Capacity Requirements Planning (CRP) Capacity Requirements Planning (CRP)

• Capacity Requirements Planning (CRP): an estimate of capacity needed

• Infinite Loading: assumption of infinite capacity

• Load Profile: comparison of capacity needs to what is needed

15–15–1010

Page 11: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Advances in Planning Systems Advances in Planning Systems

• Enterprise Requirements Planning (ERP): software that consolidates all business planning systems and data

• Advanced Planning and Scheduling (APS): combines MRP and CRP into one system

15–15–1111

Page 12: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

CustomerRelationship

Mgt

QualityMgt

ERP Systemsand Add-ons

SupplyChain Mgt

Facility Mgt

Project Mgt

Pricing andOrder

Mgt

HumanResource

Mgt

Life Cycle Mgt

FinancialPlanning

Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)

Inventory Data

MRPEngine

PurchaseOrders

ProductionOrders

Original MRP‘little mrp’

15–15–1212

Page 13: Class 24: Chapter 15: Materials Requirements Planning Class 24 Agenda –Review Deliverables Due Dates –Review Final Exam 90% of the 30 questions will come.

Material & Resource Planning SummaryMaterial & Resource Planning Summary

1. Dependent demand is for raw materials, parts, and subassemblies.

2. MRP inputs include MPS, BOM and inventory records.

3. MRP determines how much and when to order

4. MRP outputs include reports for operations planning

5. DRP applies MRP logic to the distribution network

6. MRP plans must be balanced with available capacity using CRP

7. Technology is streamlining the planning process