Top Banner
CIVL 4121: Embankment Dams: 1 GEOTECHNICAL & GEOENVIRONMENTAL ENGINEERING CIVL 4121 Embankment Dams
11
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CIVL4121

CIVL 4121: Embankment Dams: 1

GEOTECHNICAL & GEOENVIRONMENTAL ENGINEERING CIVL 4121

Embankment Dams

Page 2: CIVL4121

CIVL 4121: Embankment Dams: 2

Embankment dams

• Types of embankment dams – earth fill, rock fill• Site Choice – site selection, site investigation, geology• Materials• Clayey core materials

• clay mineralogy• dispersivity• compaction

• Filter requirements• Drain calculations – flow nets• Scour Protection• Tailings Dams

Page 3: CIVL4121

CIVL 4121: Embankment Dams: 3

Some dam types

Page 4: CIVL4121

CIVL 4121: Embankment Dams: 4

Worsley Alumina Refinery, CollieRefinery Catchment Lake Dam

Weathered granite foundation – clays, silts, sands

Page 5: CIVL4121

CIVL 4121: Embankment Dams: 5

Harvey Dam (Collie, WA)

Typical earth embankment dam used in WA. Spillway shown on left. Below is the

downstream slope

Page 6: CIVL4121

CIVL 4121: Embankment Dams: 6

Mundaring Dam, WA (water for the Goldfields)

Page 7: CIVL4121

CIVL 4121: Embankment Dams: 7

Itaipu Dam (Brazil, Paraguay)Largest Hydro-Electric Power Station in the World

(until 3 Gorges Dam in China becomes fully operational)

Page 8: CIVL4121

CIVL 4121: Embankment Dams: 8

The different colored soils correspond to the upstream shell (left side), core (darkest), filter, and drain zone (lightest), and downstream shell.

Page 9: CIVL4121

CIVL 4121: Embankment Dams: 9

The downstream filter and drain zones are the lighter-colored soils in the middle of this photo.

Page 10: CIVL4121

CIVL 4121: Embankment Dams: 10

This photo shows a cross section through a rockfill dam in Norway that was constructed with an asphalt core only one meter thick. Norwegian engineers have developed this technology because

at some sites in Norway there is no clay available from which to make the core. Very high quality control is necessary for such a thin core.

Page 11: CIVL4121

CIVL 4121: Embankment Dams: 11

Here the asphalt core is under construction. The core and the adjacent transition zones are constructed to very exacting standards.